Yogesh Mehra vs Vaayu Infrastructure Llp & Ors

National Company Law Appellate Tribunal11 February 2022

Ratio decidendi

The rule this decision rests on

The Adjudicating Authority, in admitting a Section 7 petition and dismissing an application for stay or recall, is bound to consider the provisions of Rules 37, 49 and 150 of the NCLT Rules, 2016; an order passed without regard to those provisions, where the corporate debtor was denied a fair opportunity to be heard, is liable to be set aside and the matter remitted for fresh consideration.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

NATIONAL COMPANY LAW APPELLATE TRIBUNALPRINCIPAL BENCH, NEW DELHICompany Appeal (AT) (Insolvency) No. 1069-1070 of 2019

[Arising out of orders dated 30.08.2019 in CP No. 1951/ IBC/ NCLT/ MB/ MAH/ 2019 and 16.09.2019 in MA 2984/2019 & MA 3061/2019 in C.P. 1951(IB) (MB)/2019 passed by the Ld. Adjudicating Authority (National Company Law Tribunal), Mumbai Bench.]

IN THE MATTER OF:

Yogesh Mehra Partner of Vaayu Infrastructure LLP (Powers Suspended) 201, Hare Krishna Presidency Society North South Road No. 8 JVPD Scheme; Vile Parle (West) Mumbai - 400049, Maharashtra ...... Appellant.

Versus

1. Vaayu Infrastructure LLP Through Resolution Professional Mr. Shailen Shah 1102(2), 11th Floor, Fortune Terrace New Link Road, Andheri (West) Mumbai - 400053, Maharashtra. ....... Respondent No. 1.

2. Vejas Power Projects Ltd. IL&FS, Financial Centre Plot No. C-22, G Block Bandra Kurla Complex Bandra (East) Mumbai - 400051, Maharashtra. ...... Respondent No. 2.

3. Union of India Through Secretary, Ministry of Corporate Affairs 5th Floor, 'A' Block, Shastri Bhawan, New Delhi - 110001. ....... Respondent No. 3. 2

4. Infrastructure Leasing and Financial Services Ltd. IL&FS, Financial Service Centre Plot No. C-22, G Block Bandra Kurla Complex Bandra (East) Mumbai. ...... Respondent No. 4.

5. Radhika Mehra 201, Hare Krishna Presidency Society North South Road No. 8 JVPD Scheme; Vile Parle (West) Mumbai - 400049, Maharashtra. ........ Respondent No. 5. Present: For Appellant: Mr. Abhinav Vasisht, Sr. Advocate with Ms. Varsha Banerjee and Mr. Kumar Anurag Singh and Mr. Palash Singhai, Advocates. For Respondents: Mr. Satendra K. Rai and Mr. Pravar Veer Mishra Advocates for R-1. Mr. R. Sudhinder, Ms. Ekta Bhasin, Mr. Ranjit Shetty, Ms. Priyanka Shetty and Mr. Samar Kachwaha, Advocates for R-2. Mr. Rahul Kumar, Advocate for R-4. Mr. Abhijeet Sinha, Aditya Shukla and Mr. Saikat Sarkar, Advocates for R-5.

JUDGMENT

(11th February, 2022)

Justice Anant Bijay Singh;

This Appeal has been preferred by the Appellant - Yogesh Mehra,

Partner of Vaayu Infrastructure LLP (Powers Suspended) being aggrieved and

dissatisfied by the orders dated 30.08.2019 in CP No. 1951/ IBC/ NCLT/ MB/

MAH/ 2019 and 16.09.2019 in MA 2984/2019 & MA 3061/2019 in C.P.

1951(IB) (MB)/2019 passed by the Adjudicating Authority (National Company

Law Tribunal), Mumbai Bench wherein the Application filed by the

Respondent No. 2 herein (Financial Creditor) - 'Vejas Power Projects Ltd.'

under Section 7 of the Insolvency and Bankruptcy Code, 2016 (for short IBC)

Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019 3

against the 'Vaayu Infrastructure LLP' (Corporate Debtor) was allowed and

further Application filed by the Corporate Debtor for staying the operation of

Insolvency proceeding was rejected.

2. The facts giving rise to this Appeal are as follows:

i) The IL&FS Financial Services Ltd. (IL&FS) had provided Wind World

Wind Farms (MP) Private Limited (for short WWWFPL) with financial

assistance for an amount of Rs. 100,00,00,000/- (Facility 1) and Rs.

110,00,00,000/- (Facility 2) vide Facility Agreements dated 27.06.2014 and

24.09.2014 respectively.

ii) The IL&FS had assigned its debt in favour of the Financial Creditor

herein pursuant to the Assignment Agreement dated 30.12.2015. The

Corporate Debtor is the guarantor of WWWFPL for it had executed irrevocable

and unconditional guarantees in respect of the Facilities granted to the

WWWFPL.

iii) The Financial Creditor in its Form 1 mentioned that amounts under

Facility 1 and facility 2 are disbursed on different dates which are given

hereunder:

Facility 1- Rs. 100,00,00,000/- Facility 2- Rs. 110,00,00,000/-

Date Amount Disbursed Date Amount Disbursed

30.06.2014 42,00,00,000 27.06.2014 45,00,00,000

11.07.2014 25,00,00,000 29.09.2014 40,00,00,000

08.08.2014 10,00,00,000 30.09.2014 25,00,00,000

26.08.2014 23,00,00,000

Total 100,00,00,000 Total 110,00,00,000

Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019 4

iv) The Financial Creditor contends that an amount of Rs.

1,26,24,68,685/- is due and payable in respect of Facility 1 and an amount of

Rs. 1,42,63,76,004/- is due and payable in respect of Facility 2.

v) The Loan facilities are secured by hypothecation of various movable

properties, the Corporate Guarantee given by the Corporate Debtor vide letters

of Guarantee dated 27.06.2014 and 24.09.2014 for the two facilities

respectively, the Corporate Guarantee given by the Vish Wind Infrastructure

LLP vide letters of Guarantees of Mr. Ajay Mehra and Mr. Yogesh Mehra.

vi) The Financial Creditor issued a recall notice dated 29.01.2018 to the

WWWFPL for an outstanding amount of Rs. 254,72,62,584/- as on

28.01.2018 but nothing fructified. The Financial Creditor, thereafter, issued a

letter dated 07.02.2018 to the Corporate Debtor for invocation of guarantee

issued to the Financial Creditor for the debt of WWWFPL in respect of the

default committed in repayment.

vii) Further case is that the Corporate Debtor has not appeared before the

Ld. Adjudicating Authority despite opportunities being given. Notices for

intimation of dates of hearing have also been sent and affidavit of service has

been produced on record by the Financial Creditor. The Corporate Debtor has

nowhere denied his liability to pay the amount claimed.

viii) After hearing the parties, the Ld. Adjudicating Authority has given

finding that the Corporate Debtor has defaulted in repayment of debt and the

Financial Creditor has made out its case with ample evidences for his claim,

so the debt and default has been admitted in terms of Section 5 (8) of the IBC

and Section 3 (12) of the IBC and Mr. Shailen Shah appointed as Interim

Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019 5

Resolution Professional to conduct the Corporate Insolvency Resolution

Process. Being aggrieved, the Appellant has filed the present Appeal.

Submissions on behalf of the Appellant

3. The Learned Senior Counsel for the Appellant during the course of

argument and in his memo of Appeal along with Written Submissions

submitted that the Appellant herein being one of the Partner of Corporate

Debtor - 'Vaayu Infrastructure LLP' is aggrieved by the impugned orders dated

30.08.2019 and 16.09.2019 which are bad in law as the same had been

passed by the Ld. Adjudicating Authority without even considering the

relevant provisions of law and in grave violation of principles of natural justice.

The Appellant as well as the Corporate Debtor were denied an opportunity to

be heard and file its reply before the Ld. Adjudicating Authority, which lead to

wrongful initiation of proceedings under Section 7 of the IBC.

4. It is further submitted that the initiation of Corporate Insolvency

Resolution Process against the Corporate Debtor is non-est and the impugned

orders initiating the same had been passed on the sham and fraudulent

transactions portrayed as loan/debt by the Financial Creditor (Respondent

No. 2) and the Ld. Adjudicating Authority without providing any opportunity

to the Corporate Debtor to counter the said facts on merits proceeded ex-parte

in a hastened manner on 28.08.2019 and purportedly pronounced impugned

order on 30.08.2019 without even listing the same for the said purpose.

5. It is further submitted that the Appellant seeks liberty of this Hon'ble

Tribunal to reproduce chronology of the events passed by the Ld. Adjudicating

Authority which are hereunder:

27.05.2019 Respondent Financial Creditor sent a copy of the Application to the Corporate Debtor vide letter dated Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019 6

27.05.2019. It is pertinent to mention herein that the date of hearing was not mentioned in the letter dated 27.05.2019 addressed by the advocate for the Financial Creditor. This was merely an advance notice of the Petition without any intimation of date of hearing.

24.07.2019 The Ld. Adjudicating Authority passed an order wherein due to the fact that no notice was served upon the Appellant, the Appellant could not remain present before the AA on 24.07.2019.

31.07.2019 Financial Creditor addressed a letter dated 31.07.2019 to the Corporate Debtor which was received by the Corporate Debtor on 06.08.2019. In the said letter, the advocates for the Financial Creditor informed the Corporate Debtor for the first time that the matter is listed on 27.08.2019 (at page 119, Vol. I of the Appeal).

27.08.2019 As an abundant caution, on 27.08.2019, the Appellant though its representative instructed its lawyer to appear before Ld. Adjudicating Authority on 28.08.2019 (at page 107-108, Vol. I of the Appeal) and seek time to file reply so that it could establish that the petition preferred by the Financial Creditor is a frivolous petition.

28.08.2019 The Ld. Adjudicating Authority rejected the prayer of granting time to file vakalatnama and reply and proceeded to hear the matter ex parte. Further, Ld. Adjudicating Authority reserved its order on the same date.

30.08.2019 The Ld. Adjudicating Authority purportedly pronounced its order and admitted Company Petition bearing CP No. 1951/IBC/NCLT/MB/MAH/2019 preferred under Section 7 of IBC by the Financial Creditor and appointed Mr. Shailen Shah, having registration No. IBBI/IPA-001/IP P00408/2017-18/10724, as Interim Resolution

Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019 7

Professional ("IRP"). This order came to the knowledge of the Appellant only on 10.09.2019(at page 89-90, Vol. I of the Appeal).

03.09.2019 The Appellant immediately after the hearing order dated 28.08.2019 filed an application being CA No. 2984 of 2019 (at page 102, Vol. I of the Appeal).

05.09.2019 The Appellant through its counsel mentioned the aforesaid application and Ld. Adjudicating Authority allowed the circulation of the said application to 24.09.2019 and directed the Appellant to give a notice of hearing to the Financial Creditor.

10.09.2019 In the interregnum, the order dated 30.08.2019 admitting the CIRP came to the knowledge of the Appellant and was uploaded on the official website of the Ld. Adjudicating Authority on 10.09.2019.

11.09.2019 The Appellant filed another application bearing No. 3061 of 2019 under Section 424 of the Companies Act, 2013 and Section 60(5) of the IBC seeking stay of order dated 30.08.2019 passed by the Adjudicating Authority till the time MA No. 2984 of 2019 was heard and disposed of by Ld. Adjudicating Authority (at page 88, Vol. I of the Appeal).

12.09.2019 In light of the order dated 30.08.2019 initiating CIRP in the case of the Corporate Debtor, the Appellant mentioned its pending application being MA No. 2984 of 2019 and sought urgent hearing of the said application. The matter was accordingly, listed on 16.09.2019.

13.09.2019 The application as preferred by the Appellant seeking stay of the order dated 30.08.2019 was mentioned on

13.09.2019, wherein the Adjudicating Authority rejected the interim say as sought by the Appellant on account of

Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019 8

pendency of MA No. 2984 of 2019 which was listed for hearing on 16.09.2019.

16.09.2019 The Ld. Adjudicating Authority after hearing the counsels without providing any opportunity to place on record the reply on merits to Application under Section 7 of IBC, reserved its order.

27.09.2019 Order dated 16.09.2019 was uploaded on the official website of the Adjudicating Authority on 27.09.2019.

6. It is further submitted that the finding of the Ld. Adjudicating Authority

below is premised on the wrong interpretation of the law and provisions of the

IBC as the Ld. Adjudicating Authority failed to exercise the power and

jurisdiction vested upon it by the legislature which has caused grave prejudice

to the interest of the Corporate Debtor as well Appellant.

7. It is further submitted that the Ld. Adjudicating Authority failed to

provide reasonable opportunity to the Corporate Debtor of being heard which

is in violation of principles of natural justice and not followed the due process

and procedure as stipulated under Rule 150 of NCLT Rules and also failed to

consider that the alleged transactions reflected as loan/debt is a sham

transaction and in the absence of any reply the same could not be adjudicated

upon.

8. It is further submitted that the Ld. Adjudicating Authority in a hasten

manner proceeded with the matter ex-parte on 28.08.2019 and inspite of the

presence of Authorised Representative of Corporate Debtor which is evident

from Reply Affidavit of Respondent No. 2 (Para 6, at page 3 of the Reply) as

well as observation of Ld. Adjudicating Authority at para 6 of the order dated

16.09.2019 (at page 84 of the Appeal). It is noteworthy to mention that no Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019 9

daily order or record of proceeding dated 28.08.2019 is available, which

makes it further clear that due process and procedure was not followed by

the Ld. Adjudicating Authority while adjudicating the matter and the order

suffers from grave infirmity which makes it non est in the eyes of law. The

Rule 49 of NCLT Rules is reproduced hereunder:

" Rule 49:

(1) Where on the date fixed for hearing the petition or application or on any other date to which such hearing may be adjourned, the applicant appears and the respondent does not appear when the petition or the application is called for hearing, the Tribunal may adjourn the hearing or hear and decide the petition or the application ex parte."

9. It is further submitted that the Corporate Debtor being aggrieved by

order dated 28.08.2019 passed by the Ld. Adjudicating Authority, filed CA No.

2489 of 2019 for recall of the said order dated 28.08.2019. In the interregnum

on 10.09.2019, the Corporate Debtor became aware of the fact that the Ld.

Adjudicating Authority without listing the matter for pronouncement and

uploaded the impugned order dated 30.08.2019 which is again in

contravention to Rule 150 of NCLT Rules.

10. It is further submitted that Corporate Debtor upon coming to know

about impugned order dated 30.08.2019 filed MA No. 3061 of 2019 seeking

stay on impugned order dated 30.08.2019 till CA No. 2498 of 2019 is

adjudicated by the Ld. Adjudicating Authority. The Ld. Adjudicating Authority

on 16.09.2019 heard both the Applications of Corporate Debtor and without

application of mind passed the impugned order dated 16.09.2019 which is

premised on wrong understanding and interpretation of law. Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019 10

11. It is further submitted that the impugned order dated 16.09.2019 is

premised on the wrong understanding and interpretation of law as the Ld.

Adjudicating Authority failed to consider the power and jurisdiction vested

upon NCLT in terms of Rule 49(2) of NCLT Rules, wherein NCLT is well within

its jurisdiction to recall any ex parte order upon the sufficient cause being

shown by the party. The Rule 49(2) of NCLT Rules read as hereunder:

" 49(2): Where a petition or an application has been heard ex parte against a respondent or respondents, such respondent or respondents may apply to the Tribunal for an order to set it aside and if such respondent or respondents satisfies the Tribunal that the notice was not duly served or that he or they were prevented by any sufficient cause from appearing (when the petition or the application was called) for hearing, the Tribunal may make an order setting aside the ex parte hearing as against him or them upon such terms as it thinks fit: Provided that where the ex parte hearing of the petition or application is of such nature that it cannot be set aside as against one respondent only, it may be set aside as against all or any of the other respondents also."

12. The Learned Senior Counsel for the Appellant placed reliance upon two

judgments passed by this Appellate Tribunal in the case of "AKJ Fincap

Limited Vs. Bank of India, Company Appeal (AT) (Insolvency) No. 178 of

2021 and Bhasker Vs. Sai Precious Traexim Pvt. Ltd., Company Appeal

(AT) (Insolvency) No. 531 of 2020" wherein it is categorically observed that

the Ld. Adjudicating Authority has power in terms of Rule 49(2) of NCLT Rules,

2016 to recall any ex-parte order if sufficient cause is shown. Further this

Appellate Tribunal is such circumstances when the Ld. Adjudicating Authority

Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019 11

failed to exercise jurisdiction as per Rule 49(2) and initiated the CIRP, has

released the Corporate Debtor from the rigours of CIRP by declaring all the

actions taken so far by Resolution Professional, Committee of Creditors as

illegal and remanded the matter to the Ld. Adjudicating Authority for

adjudication. Based on these submissions the impugned orders be set aside

and the matter be remanded to the Ld. Adjudicating Authority for passing

appropriate orders.

Submissions on behalf of the Respondent No. 1

13. The Learned Counsel for the Respondent No. 1 during the course of

argument and in his short Reply submitted that vide order dated 30.08.2019

passed by Ld. Adjudicating Authority under which the Ld. Adjudicating

Authority initiated Corporate Insolvency Resolution Process and appointed

Mr. Shailen Shah as the Interim Resolution Professional, the Respondent No.

1. Pursuant to the order dated 30.08.2019 he has taken charge of the

Corporate Debtor. Further, this Appellate Tribunal in its order dated

17.10.2019 has directed the IRP to ensure that the Corporate Debtor is

maintained as a going concern.

14. It is further submitted that the Respondent No. 1 after taking charge,

certain expenses in relation to the CIRP of the Corporate Debtor have been

incurred including cost and expenses of the IRP. The Respondent No. 1 prays

that in the event the instant Appeal is allowed by this Appellate Tribunal and

the order initiating the CIRP of the Corporate Debtor is set aside, then this

Appellate Tribunal be pleased to pass appropriate orders directing the

Appellant to pay the expenses and costs incurred in respect of the IRP, IRP

entity, IRP team and IRP advisors and any other CIRP expenses, if any, from

Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019 12

the date of the IRP taking charge of the Corporate Debtor till the date of

disposal of the instant Appeal.

Submissions on behalf of the Respondent No. 2

15. The Learned Counsel for the Respondent No. 2 during the course of

argument and in his Reply Affidavit along with Written Submissions

submitted that on 24.07.2019 the matter was listed before the Ld.

Adjudicating Authority wherein it was recorded that Company Petition was

served to Appellant/Corporate Debtor but there is no response also non-

attendance at the time of hearing and further it was recorded that this is a

high-stake case which is required to be taken on priority basis. The

Respondent No. 2/Financial Creditor was directed to serve notice upon the

Appellant/Corporate Debtor as a last chance to make a representation in the

matter.

16. It is further submitted that on next date i.e. 28.08.2019, when the case

matter was called before the Ld. Adjudicating Authority, an Advocate appeared

for the Corporate Debtor without a Vakalatnama or an authority letter and

requested for further time. Since the matter was being heard after three

months of filing of the Company Petition and ample time was given to the

Appellant/Corporate Debtor, the Ld. Adjudicating Authority proceeded to hear

the matter and eventually reserved the matter for orders. Thereafter, the Ld.

Adjudicating Authority pronounced the order and admitted the Company

Petition.

17. It is further submitted that the Appellant/Corporate Debtor have further

tried to made out a case that the order was not pronounced in open Court and

it was not mentioned in the Cause List. Further reliance is placed on Rule 151

Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019 13

of the NCLT Rules, 2016. The said Rule Directory in nature and further,

reliance is placed on the Judgment passed by the Hon'ble Madras High Court

in the case of "Shaji Purushothaman Vs. Union of India & Ors., W.P. No.

1926 of 2020 and W.M.P. No. 2253 of 2020" decided on 19.03.2020,

wherein para 55 and 56 read as hereunder:

"55. Now coming to the mandatory nature of NCLT Rules, 2016 more particularly Rules 150 and 153, in the light of the settled legal position that consequences that may arise on account of the non-adherence to the time line/procedure have not been indicated in the said Rules, it can be considered to be only directory.

56. The Division Bench judgment of the Bombay High Court in Kamal K. Singh V. Union of India [MANU/MH/3538/2019] is distinguishable for the reason that the legal position as laid down by the Hon'ble Apex Court in the various pronouncements as to the directory/mandatory nature of Statutory Rules have not been dealt with in the said judgment. It is a settled legal dictum that "when a public functionary is required to perform a public function within a time frame, the same will be held to be directory unless the consequences there for are specified". Admittedly, the consequences that may emanate as to the non-adherence/infraction of the Rules have not been indicated in the Statutory Rules. Hence, the impugned common order cannot be set aside on the ground."

18. It is further submitted that the Appellant has placed reliance on Rule

49 of the NCLT Rules, which is completely erroneous as the date of hearing

which was already fixed on 28.08.2019 by the order dated 24.07.2019 making

abundantly clear to the effect that the same would be its "last chance" to

Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019 14

represent the matter. Therefore, the Rule 49(2) will not be applicable in this

case. Based on these submissions there is no merit in the Appeal, the Appeal

is fit to be dismissed.

Submissions on behalf of the Respondent No. 4

19. The Learned Counsel for the Respondent No. 4 during the course of

argument and in his Reply Affidavit submitted that the Respondent No. 4 has

no connection whatsoever with the present matter. The Appellant/Corporate

Debtor is seeking to drag Respondent No. 4 in the present mater by alleging

some sort of connection between the transaction which forms the subject

matter of the petition and a set of completely distinct transactions which are

the subject matter of another Corporate Insolvency Resolution Process

ongoing before the Ld. NCLT, Ahmedabad Bench.

20. It is further submitted that the CIRP is ongoing before the Ld. NCLT,

Ahmedabad is in respect of Wind World (India) Limited whereas Jogihali Wind

Energy Private Limited, Mahidad Wind Energy Private Limited, Sipla Wind

Energy Private Limited have submitted their claims to the Resolution

Professional. Jogihali, Mahidad and Sipla are subsidiaries of IL&FS Energy

Development Company Limited.

21. It is further submitted that the dispute in the present Appeal is between

the Appellant/Corporate Debtor and the Respondent No. 2/Financial Creditor.

The Respondent No. 4 is not privy to the contract between the Appellant and

Respondent No. 2. There are no grounds or reasons to implead Respondent

No. 4 and hence the Respondent No. 4 should not be impleaded in the present

proceedings. Further, Respondent No. 4 is not required to adjudicate the

Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019 15

dispute under Section 7 of the IBC filed by the Financial Creditor against

Corporate Debtor.

Submissions on behalf of the Respondent No. 5

22. The Learned Counsel for Respondent No. 5 during the course of

argument and in his Written Submissions submitted that the Respondent No.

5 was granted liberty to impugn the orders dated 30.08.2019 and 16.09.2019

in terms of the order dated 06.01.2020 (at page 11 of I.A. No. 1021 of 2021)

passed by the Hon'ble High Court of Bombay. Thereafter, the Respondent No.

5 joined the proceedings and supported the case of the Appellant herein.

FINDINGS

23. After hearing the parties and having gone through the pleadings made

on behalf of the parties, we are of the considered view that the Ld. Adjudicating

Authority passed the order dated 30.08.2019 in CP No.

1951/IBC/NCLT/MB/MAH/2019 and admitted the petition filed by the

Respondent No. 2 herein (Financial Creditor) - 'Vejas Power Project Ltd.' under

Section 7 of the Insolvency and Bankruptcy Code, 2016 against the Appellant

herein (Corporate Debtor) - 'Vaayu Infrastructure LLP' and further while

dismissing the Application filed by the Appellant herein vide order dated

16.09.2019 in MA 2984/2019 & MA 3061/2019 in C.P. 1951(IB) (MB)/2019,

the Ld. Adjudicating Authority has not considered the provisions of Rules 37,

49 and 150 of the NCLT Rules. In view of the above, the impugned orders

dated 30.08.2019 and 16.09.2019 are hereby set aside and the matter is

remitted back to the Ld. Adjudicating Authority (National Company Law

Tribunal), Mumbai Bench with a request to hear the parties including the

Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019 16

Appellant herein and Respondent No. 1 herein about his fee and expenses for

the period he has worked as IRP and pass appropriate orders within six weeks

from the date of receipt of this judgment.

24. Registry to upload the Judgment on the website of this Appellate

Tribunal and send the copy of this Judgment to the Ld. Adjudicating Authority

(National Company Law Tribunal), Mumbai Bench, forthwith.

[Justice Anant Bijay Singh] Member (Judicial)

[Ms. Shreesha Merla] Member (Technical)

New Delhi 11th February, 2022 R. Nath.

Company Appeal (AT) (Insolvency) No. 1069-1070 of 2019

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free