Vishal Vijay Kalantri vs Dbm Geotechnics & Constructions Pvt. ...
- CitationCompany Appeal (AT) (Insolvency) No. 139 of 2018
Ratio decidendi
The rule this decision rests on
The Appellate Tribunal will not examine the existence of a pre-existing dispute in an appeal against an admission order under Section 9 where the matter has been prolonged for over a year and a half, the operational default is admitted, and admitting the appeal would regenerate fresh proceedings and expose the corporate debtor to liquidation, so that the admission order is not interfered with. Where the Committee of Creditors has approved a resolution plan by a voting share of 99.68% and the plan is pending before the Adjudicating Authority under Section 31, the Appellate Tribunal cannot sit in appeal over the commercial wisdom of the Committee of Creditors, in accordance with the principle laid down in Committee of Creditors of Essar Steel India Limited v. Satish Kumar Gupta.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
NATIONAL COMPANY LAW APPELLATE TRIBUNAL, NEW DELHI
Company Appeal (AT) (Insolvency) No. 139 of 2018 [ arising out of Order dated 25th March, 2018 by NCLT, Mumbai Bench, Mumbai in CP(IB) No. 1382/I&BC/2017 ]
IN THE MATTER OF:
Vishal Vijay Kalantri, S/o Mr. Vijay Kalantri, R/o Flat No. 2, Wahedna CHS Ltd., 75, Hill Road, Bandra (W), Mumbai 400 051 .... Appellant
Vs
1. DBM Geotechnics & Construction Pvt. Ltd. B/301, Centaur House, Shantinagar Industrial Estate, Vakola, Santacruz (E), Mumbai - 400 055.
2. Dighi Port Ltd., New Geotechnics & Constructions Pvt. Ltd., New Excelsior Building, 6th Floor, A.K. Nayak Marg, Fort, Mumbai - 400 001. .... Respondents
Present: For Appellant: Mr. Amit S. Chadha, Senior Advocate with Ms. Neeha Nagpal, Ms. Srishti Govil, Mr. Akshay Sharma, Mr. Vishvendra Tomar, Mr. Rohan Jaitley, and Ms. Sanya Ahluwalia, Advocates.
For Respondents: Mr. Gourab Banerji, Senior Advocate with Ms. Aditi Sharma, Mr. Raka Chatterjee, Advocate for Committee of Creditors.
Mr. Kunal Vajani, Mr. Varun Ahuja and Mr. Paras Anand, Advocates for Resolution Professional. Mr. Niraj Kumar, Mr. Satendra K. Rai and Ms. Tejali, Advocates for Resolution Professional.
Mr. Abhishek Puri and Ms. Surbhi Gupta, Advocates for Maharashtra Maritime Board.
With 2
Company Appeal (AT) (Insolvency) No. 697 of 2019
[ arising out of Order dated 8th May, 2019 by NCLT, Mumbai Bench, Mumbai in M.A. No. 529/2019, MA. No. 761/2019 and MA No. 1147/2019 IN CP(IB) No. 1382/I&BC/NCLT/MAH/2017]
IN THE MATTER OF:
Adani Ports and Special Economic Zone Ltd., Adani House, Mithakhali, Six Road, Navrangpura, Ahmedabad, Gujarat .... Appellant
Vs 1. Mr. Shailen Shah, Resolution Professional of Dighi Port Ltd., BBSR & Co., 5th Floor, Lodha Excelus, Apollo Mill Compound, NM Joshi Marg, Mahalaxmi Mumbai - 400 011
2. Committee of Creditors of Dighi Port Limited, Through lead Bank - Bank of India, Oriental Building, Esplanade Road, Mumbai - 400 001.
3. The Board of Trustees of the Jawaharlal Nehru Port Trust, Administration Building, Sheva, Talukauran, Navi Mumbai - 400 707 .... Respondents
Present: For Appellant: Mr. Arun Kathpalia, Senior Advocate with Ms. Diksha Gupta, Mr. Mahesh Agarwal, Mr. M.S. Ananth and Mr. Rajeev Kumar, Advocates
For Respondents: Mr. Gourab Banerji, Senior Advocate with Ms. Aditi Sharma, Advocate for Committee of Creditors.
Mr. Kunal Vajani, Mr. Varun Ahuja and Pranav Vyas, Advocates for Resolution Professional. Mr. Niraj Kumar, Mr. Satendra K. Rai, Mr. Nirav Shah and Ms. Tejali, Advocates for Resolution Professional.
Company Appeal (AT) (Insolvency) Nos. 139 of 2018; 697 of 2019; 698 of 2019 and 722 of 2019 3
Mr. Abhishek Puri, Advocate for Maharashtra Maritime Board.
With
Company Appeal (AT) (Insolvency) No. 698 of 2019
[ arising out of Order dated 27th May, 2019 by NCLT, Mumbai Bench, Mumbai in CP(IB) No. 1382/I&BC/2017 ]
IN THE MATTER OF:
Adani Ports and Special Economic Zone Ltd. .... Appellant
Vs
Mr. Shailen Shah, RP of Dighi Port Ltd. & Ors. .... Respondents
Present: For Appellant: Mr. Arun Kathpalia, Senior Advocate with Ms. Diksha Gupta, Mr. Mahesh Agarwal, Mr. M.S. Ananth and Mr. Rajeev Kumar, Advocates
For Respondents: Mr. Gourab Banerji, Senior Advocate with Ms. Aditi Sharma, Advocate for Committee of Creditors.
Mr. Kunal Vajani, Mr. Varun Ahuja Advocates for Resolution Professional. Mr. Niraj Kumar, Mr. Satendra K. Rai and Ms. Tejali, Advocates for Resolution Professional.
Mr. Abhishek Puri, Advocate for Maharashtra Maritime Board.
With Company Appeal (AT) (Insolvency) No. 722 of 2019
[ arising out of Order dated 8th May, 2019 by NCLT, Mumbai Bench, Mumbai in M.A. No. 529/2019, MA. No. 761/2019 and MA No. 1147/2019 IN CP(IB) No. 1382/I&BC/NCLT/MAH/2017 ]
IN THE MATTER OF: Mr. Vishal Vijay Kalantri, Former Director and Shareholder of Dighi Port Limited, R/o Flat No. 2, Wahedna CHS Ltd., 75, Hill Road, Bandra (W), Mumbai - 400 051. .... Appellant
Company Appeal (AT) (Insolvency) Nos. 139 of 2018; 697 of 2019; 698 of 2019 and 722 of 2019 4
Vs
1. Dighi Port Ltd., Corporate Debtor, New Excelsior Building, 6th Floor, A.K. Nayak Marg, Fort, Mumbai - 400 001.
2. Jawaharlal Nehru Port Trust, The Resolution Applicant, New Excelsior Building, A.K. Nayak Marg, Fort, Mumbai - 400 001. .... Respondents
Present: For Appellant: Mr. Amit Chadha, Senior Advocate with Ms. Neeha Nagpal, Ms. Srishti Govil and Mr. Vishvendra Tomar and Ms. Sanya Ahluwalia, Advocates.
For Respondents: Mr. Gourab Banerji, Senior Advocate with Ms. Aditi Sharma, Advocate for Committee of Creditors.
Mr. Kunal Vajani, Mr. Varun Ahuja Advocates for Resolution Professional. Mr. Niraj Kumar, Mr. Satendra K. Rai and Ms. Tejali, Advocates for Resolution Professional.
Mr. Abhishek Puri, Advocate for Maharashtra Maritime Board.
JUDGMENT
SUDHANSU JYOTI MUKHOPADHAYA, J.
'DBM Geotechnics and Constructions Pvt. Ltd.' moved an application
under Section 9 of the 'Insolvency and Bankruptcy Code, 2016 ('I&B Code',
for short) for initiation of the 'Corporate Insolvency Resolution Process'
against 'Dighi Port Limited' (Corporate Debtor). The Adjudicating Authority
by impugned order dated 25th march, 2018 admitted the application.
Company Appeal (AT) (Insolvency) Nos. 139 of 2018; 697 of 2019; 698 of 2019 and 722 of 2019 5
2. Mr. Vishal Vijay Kalantri (Director and Shareholder of the Corporate
Debtor) initially challenged the impugned order on one of the ground that
there is an 'existence of dispute'. The notice was issued on Respondents
pursuant to which the Respondent (DBM Geotechnics and Constructions Pvt.
Ltd. - Operational Creditor) appeared. The learned counsel for the Appellant
sought time to settle the dispute, which was agreed upon by the learned
counsel for the Respondent as recorded on 12th July, 2018, which is :
"12.07.2018: The appeal was preferred
against order of initiation of Corporate Insolvency
Resolution Process under Section 9 of the Insolvency
and Bankruptcy Code, 2016. The matter was taken
up and ultimately the senior counsel for the
Appellant sought for time to settle the dispute, which
was agreed by learned senior counsel for the
Respondent (Operational Creditor).
Today, learned senior counsel for the
Appellant again sought for some more time to ensure
settlement. Learned senior counsel appearing on
behalf of Respondent (Operational Creditor) agreed
to negotiate, if the Appellant approach.
In these circumstances, adjourn the case. If no
settlement is made, the court may proceed with the
appeal on merit.
Mr. Gourab Banerji, learned senior counsel
alongwith Mr. I. P. A. Oberoi, Advocate submits that
Company Appeal (AT) (Insolvency) Nos. 139 of 2018; 697 of 2019; 698 of 2019 and 722 of 2019 6
he wants to intervene on behalf of the CoC, as the
Resolution Process is on-going.
We allow him to file an Intervention
Application within a week and make it clear that we
have not stayed the Resolution Process, therefore,
the Resolution Professional, Committee of Creditors
and the Adjudicating Authority, in the meantime,
may proceed in accordance with law.
Place the case 'for orders' on 1st August,
2018."
3. However, the matter was not finally settled between the Appellant -
'Vishal Vijay Kalantri' and the Respondent - 'DBM Geotechnics and
Constructions Pvt. Ltd.' (Operational Creditor). The Appellant sought time to
move an application under Section 12A of the 'I&B Code'. Therefore, the
'Company Appeal (AT) (Insolvency) No. 139 of 2018' remained pending and
during the pendency of the Appeal, 'Corporate Insolvency Resolution Process'
continued.
4. 'Resolution Plan' by 'Adani Ports and Special Economic Zone Limited'
('APSEZL', for short) was declared as the highest evaluated compliant
resolution plan and the same was put to the vote of 'Committee of Creditors'
on 31st January, 2019 and was rejected by 99.38% of votes by the 'Committee
of Creditors'. Subsequently, the 'Jawaharlal Nehru Port Trust' ('JNPT' for
short) resolution plan being the second highest resolution plan as per the
scoring was put to the vote on 1st February, 2019 which was approved by
99.38% of the requisite majority of the 'Committee of Creditors'. The
Company Appeal (AT) (Insolvency) Nos. 139 of 2018; 697 of 2019; 698 of 2019 and 722 of 2019 7
Adjudicating Authority (National Company Law Tribunal), Mumbai Bench by
impugned order dated 8th May, 2019 approved the resolution plan of 'JNPT',
'Government of India Undertaking' with certain conditions. The said order
has been challenged by 'Adani Ports and Special Economic Zone Limited', one
of the resolution applicant and also by 'Vishal Vijay Kalantri' - a shareholder
of the 'Corporate Debtor' in their respective 'Company Appeal (AT) (Insolvency)
No. 697 of 2019' and 'Company Appeal (AT) (Insolvency) No. 722 of 2019' . At
the relevant point of time, the proposal under Section 12A of the 'I&B Code'
was submitted by 'Vishal Vijay Kalantri' which was rejected by the 'Committee
of Creditors'. Subsequently, the 'Successful Resolution Applicant' (JNPT)
sought additional time of 30 days for filing the affidavit for acceptance or
rejection of the modifications in terms of the order dated 8th May, 2019. In
the said application, it was contended that it was very critical for JNPT to fully
understand and holistically evaluate the impact of modifications directed in
the JNPT's resolution plan before taking any decision in this respect and for
this additional time of at least 30 days was required for filing the affidavit
regarding its acceptance or rejection in terms of order dated 8th May, 2019.
5. It was further stated that 'JNPT' being the Government of India
Undertaking is required to follow certain procedure for obtaining appropriate
internal approvals, including from the Ministry of Shipping before proceeding
further on the 'resolution plan' because it has financial implications, which
may also require consultation with the Ministry of Finance. In this
background the Adjudicating Authority by impugned order dated 27th May,
2019 allowed 30 days' time for filing an additional affidavit, as the last
opportunity. The said order has been challenged by 'Adani Ports and Special
Company Appeal (AT) (Insolvency) Nos. 139 of 2018; 697 of 2019; 698 of 2019 and 722 of 2019 8
Economic Zone Limited' as another 'resolution applicant' in 'Company Appeal
(At) (Insolvency) No. 698 of 2019'.
6. When the matter was taken up, the learned counsel appearing on behalf
of the 'Resolution Professional' submitted that in 19th meeting of the
'Committee of Creditors', it was decided that the 'resolution plans' from all the
three 'resolution applicants' and the 'settlement proposal' of 'Vishal Vijay
Kalantri' and other promoters of the 'Corporate Debtor' be called and received
on or before 4th September, 2019. Such meeting was held pursuant to the
direction as was given on 21st August, 2019 by this Appellate Tribunal as
JNPT was not agreed to proceed with the modified resolution plan as was
approved. The 'Committee of Creditors' decided that the 'Resolution
Professional' will write to the existing three resolution applicants i.e. (a)
'Jawaharlal Nehru Port Trust (JNPT); (b) 'Adani Ports and Special Economic
Zone Limited (APSEZL') and (c) 'Veritas India Limited and UV Asset
Reconstruction Company Limited ('Veritas Consortium') calling for the
revised/improved/revalidated resolution plans. The 'Committee of Creditors'
also requested the Appellant to submit the 'Promoters' Settlement Proposal'
under Section 12A within the time limits.
7. On 4th September, 2019 at the 20th Meeting of the 'Committee of
Creditors', the Resolution Professional placed before the 'Committee of
Creditors' [i] the term sheet received from the promoters regarding their
Settlement Proposal, and [ii] the revised/ improved/revalidated Resolution
Plans from APSEZ and Veritas Consortium. At the said meeting, the Appellant
was invited to explain the Promoters Settlement Plan in detail to the
'Committee of Creditors'.
Company Appeal (AT) (Insolvency) Nos. 139 of 2018; 697 of 2019; 698 of 2019 and 722 of 2019 9
8. Thereafter, the 21st Meeting of the 'Committee of Creditors' was held
on 9th September, 2019 whereat the 'Committee of Creditors' discussed and
deliberated upon the Resolution Plans submitted by 'APSEZL' and 'Veritas
Consortium' and called upon the Resolution Applicant(s) to give a
presentation on their Resolution Plans. At the said meeting, the Resolution
Professional requested 'APSEZL' and Veritas Consortium to provide certain
clarifications in light of the amendments made in Section 39(2)(b) of the I&B
Code. Accordingly, 'APSEZL' and 'Veritas Consortium' agreed to comply with
the same. Further, the 'Committee of Creditors' fixed the deadline of 12th
September, 2019 for the Promoters of the Corporate Debtor to submit EMD of
20% of the Settlement Proposal along with further
details/clarifications/information as sought by the Forensic Auditor/
Evaluation Advisor.
9. Pursuant to the aforesaid, 'APSEZL' and 'Veritas Consortium' submitted
the addendums inter alia to clarify on compliances with the Amendments
made in Section 30(2)(b) of the I&B Code.
10. Thereafter, on 13th September, 2019, the 22nd Meeting of the
'Committee of Creditors' was held whereat the 'Committee of Creditors'
decided that the Proposal for Settlement received from the Promoters under
Section 12A of the I&B Code also seeking withdrawal of the 'corporate
insolvency resolution process' be put to vote. It is pertinent to record that at
the said Meeting, the 'Committee of Creditors' took note that EMD of 20% of
the Settlement Proposal along with further details/clarifications/information
as were previously sought were not received. The Resolution Professional also
apprised the 'Committee of Creditors' that the relevant form FA and the Bank
Company Appeal (AT) (Insolvency) Nos. 139 of 2018; 697 of 2019; 698 of 2019 and 722 of 2019 10
Guarantee as prescribed under Regulation 30A of the Insolvency and
Bankruptcy Board of India (Insolvency Resolution Process for Corporate
Persons) Regulations 2016 [" CIRP Regulations"], had also not been received.
However, on the basis of the directions of this Hon'ble Appellate Tribunal, the
'Committee of Creditors' proposed to put the withdrawal resolution under
Section12A of the I&B Code for voting by the members of the 'Committee of
Creditors'. The 'Committee of Creditors' further decided that, if in case the
withdrawal is not approved by the requisite percentage of votes by the
'Committee of Creditors', then the Resolution Plan received from 'APSEZL' be
put to vote immediately thereafter.
11. The voting on the resolution for approval of Settlement Proposal under
Section 12A of the I&B Code proposed at the 'Committee of Creditors' Meeting
held on 13th September, 2019 was concluded on 17th September, 2019. From
the results of the voting, it was noted that the resolution for withdrawal of
'corporate insolvency resolution process' under Section 12A of the I&B Code
was rejected by the members of the 'Committee of Creditors' by 99.68% voting
shares and 'Committee of Creditors' members having the remaining 0.3%
voting shares abstained from voting. As such, it is unequivocally clear that
the resolution for withdrawal of 'corporate insolvency resolution process'
under Section 12A of the 'I&B Code' came to be rejected by the members of
the 'Committee of Creditors' as the same could not muster the requisite 90%
voting share
12. It is pertinent to mention that the said Resolution Plan of the 'APSEZL'
was found to be in compliance with Section 30(2) of the I&B Code and
Regulation 38 of the CIRP Regulations. Since, the withdrawal resolution
Company Appeal (AT) (Insolvency) Nos. 139 of 2018; 697 of 2019; 698 of 2019 and 722 of 2019 11
under Section 12A of the I&B Code stood rejected by the members of the
'Committee of Creditors', as per the instructions of the 'Committee of
Creditors' in its 22nd Meeting, the Resolution Professional put the Resolution
Plan submitted by 'APSEZL' for voting by the members of the 'Committee of
Creditors'. The voting on the same commenced on 17th September, 2019 and
concluded on 19th September, 2019.
13. On 19th September, 2019, the voting results were received which
revealed that the Resolution Plan submitted by APSEZ was approved by the
members of the 'Committee of Creditors' with 99.68% votes.
14. It was submitted that that Hon'ble NCLT vide its Order dated 15th
January, 2020 in the 'Company Petition [C.P.(I.B.) No. 1382 (MB) of 2017]'
has reserved Judgement on the Application filed by the 'Resolution
Professional' under Sections 30 and 31 of the I&B Code, inter alia, seeking
approval of the Resolution Plan of 'APSEZL' which has been approved by
99.68% [voting share] of the 'Committee of Creditors'. Therefore, the
determination/adjudication as to whether the Resolution Plan is in
compliance to the provisions of the I&B Code and Regulations framed
thereunder is sub judice before the NCLT i.e. Adjudicating Authority being
the court of first instance. It is further submitted that the Settlement Proposal
of the Appellant under Section 12A of the I&B Code has been rejected by
99.68% [voting share] of the 'Committee of Creditors'. Furthermore, almost
2[two] years have elapsed since passing of the Admission Order and in the
event this Appellate Tribunal interferes with the Admission Order, this would
result in one of the creditors filing a fresh application before the NCLT and
'corporate insolvency resolution process' of the 'Corporate Debtor' would have
Company Appeal (AT) (Insolvency) Nos. 139 of 2018; 697 of 2019; 698 of 2019 and 722 of 2019 12
to be recommenced. It is imperative to record that in the event the 'corporate
insolvency resolution process' of the Corporate Debtor is interfered with, the
same would result in a risk of the Maharashtra Maritime Board cancelling the
Concession Agreement granted to the Corporate Debtor for the purpose of
operating the port. Consequently, none of the lenders/stake holders would
receive their dues from the subsequent 'corporate insolvency resolution
process' of the Corporate Debtor and the Corporate Debtor would eventually
be subjected to nothing but liquidation.
15. From the record, we find that after the 'corporate insolvency resolution
process' was initiated on 25th March, 2018 and number of claims were filed
by different 'financial creditors' and the 'operational creditors', the claims
amounting to Rs.3000 crores. In view of the said position, the Appellant -
'Vishal Vijay Kalantri' on behalf of the 'Promoter' sought time to settle the
claim under Section 12A.
16. Now at the time of hearing, the learned counsel for the Appellant wanted
to highlight the merit to suggest that there is a 'pre-existence of dispute'.
However, as more than one and a half year has passed and as the matter
remains pending since long because of the Appellant - 'Vishal Vijay Kalantri',
the 'Promoter' would have settled the matter with the creditors and also
sought time, we are not inclined to determine the initial issue whether there
was a 'pre-existing dispute' or not. Even if, the proceedings is quashed on the
'pre-existing dispute', as admittedly there is a default of payment and it will
regenerate other proceedings, which is not desirable. Admittedly, the
'Committee of Creditors' now approved the plan as submitted by the APSEZL'
with 99.68% voting share and approved on 19th September, 2019. The matter
Company Appeal (AT) (Insolvency) Nos. 139 of 2018; 697 of 2019; 698 of 2019 and 722 of 2019 13
is pending before the Adjudicating Authority for passing the order under
Section 31(1) of the 'I&B Code'. In terms of the 'Committee of Creditors of
Essar Steel India Limited vs. Satish Kumar Gupta & Ors. - (2019) SCC
Online SC 1478', the Adjudicating Authority or the National Company Law
Tribunal or this Appellate Tribunal cannot sit in appeal on commercial
wisdom of the 'Committee of Creditors'.
17. In the circumstances, we are not interfering with the impugned order
dated 25th March, 2018 passed by the Adjudicating Authority (National
Company Law Tribunal), Mumbai Bench and dismiss the appeals preferred
by 'Vishal Vijay Kalantri' and declare both the appeals preferred by 'APSEZL'
as infructuous. The matter stands remitted to the Adjudicating Authority to
pass appropriate order under Section 31 of the I&B Code in accordance with
law.
In the result, the 'Company Appeal (AT) (Insolvency) No. 139 of 2018'
and 'Company Appeal (AT) (Insolvency) No. 722 of 2019' is dismissed and the
'Company Appeal (AT) (Insolvency) Nos. 697 of 2019' and 'Company Appeal
(AT) (Insolvency) No. 698 of 2019' is declared infructuous.
[Justice S. J. Mukhopadhaya] Chairperson
[Justice Bansi Lal Bhat] Member (Judicial) New Delhi
12th March, 2020
//ns//
Company Appeal (AT) (Insolvency) Nos. 139 of 2018; 697 of 2019; 698 of 2019 and 722 of 2019 14
12.03.2020:
N.B. After the Judgment was delivered, learned counsel appearing on
behalf of 'Adani Ports and Special Economic Zone Ltd.' and counsel for the
'Resolution Professional' brought on record one order dated 5th March, 2020
by which the Adjudicating Authority (National Company Law Tribunal),
Mumbai Bench, Mumbai, has approved the 'Resolution Plan' submitted by
'Adani Ports and Special Economic Zone Ltd.'.
The order dated 5th March, 2020 be kept on record.
[Justice S. J. Mukhopadhaya] Chairperson
[Justice Bansi Lal Bhat] Member (Judicial)
/ns/
Company Appeal (AT) (Insolvency) Nos. 139 of 2018; 697 of 2019; 698 of 2019 and 722 of 2019
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free