Recording of proceedings before the Tribunal is not permissible as of right; under the Administrative Order and Revised SOP, it may be allowed only on a prior order of the Court concerned, granted upon a request showing "special reasons" for recording after an opportunity is given to the other side. An applicant seeking video-recording of proceedings must, to meet the "special reasons" requirement, identify specific and particular grounds warranting the recording; generalised assertions that fraud has occurred in the underlying proceedings do not suffice.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
NATIONAL COMPANY LAW APPELLATE TRIBUNAL PRINCIPAL BENCH, NEW DELHI Company Appeal (AT) (Ins) No. 642 - 644 of 2023 & I.A. No. 2116 of 2025 IN THE MATTER OF: Vir Jai Khosla ...Appellants Versus Nemo ...Respondents
Present:
For Appellant : Mr. Deepak Khosla, Advocate. For Respondents : Dr. Abhishek Manu Singhvi, Sr. Advocate with Ms. Ruby Singh Ahuja, Mr. Ashim Sood, Mr. Vishal Gehrana, Ms. Aakriti Vohra, Mr. Devang Kumar, Mr. Amit Bhandari, Mr. Varun Khanna, Mr. Prateek Kundu, Ms. Isha Khurana, Advocates for AMNS.
ORDER
(Hybrid Mode)
IA No. 2116 of 2025 has been filed in Company Appeal (AT)(Ins.) No. 642-
644 of 2023 by Mr. Vir Jai Khosla-Applicant under Rule 11 of the NCLAT Rules
for video recording of the proceedings in the above appeals.
2. To put things in their chronological perspective, in the CIRP of Essar
Steel India Ltd. (ESIL), the resolution plan of Arcelor Mittal India Pvt. Ltd.
(AMIPL) (now merged with Arcelor Mittal Nippon Steel India Pvt. Ltd.) was
approved by the Adjudicating Authority on 08.03.2019 and affirmed by this
Tribunal on 04.07.2019. This plan was further upheld by the Hon'ble Supreme
Court on 15.11.2019 in Committee of Creditors Vs Satish Kumar Gupta & Ors. (2020) 8 SCC 531. Another entity, Odisha Slurry Pipeline Infrastructure
Ltd. (OSPIL) also came under the rigours of CIRP following which AMIPL in this
case too submitted a resolution plan which was approved by the Adjudicating
Authority on 02.03.2020; affirmed by this Tribunal on 18.01.2022 and further
upheld by the Hon'ble Supreme Court on 10.11.2022.
3. Subsequently, IA No. 832 of 2022, was filed before the Adjudicating
Authority by M/s Srei Multiple Asset Investment Trust (SMAIT) against several
Respondents seeking to initiate proceedings under the provisions of IPC;
Section 195 of CrPC and other provisions of law for abetting perjury for filing
false affidavits making false declaration vesting the title of the slurry pipeline
with ESIL though the dispute about the title of the said pipeline was still
pending in Civil Court at Sealdah, West Bengal. The Adjudicating Authority on
21.02.2023 rejected IA No. 832 of 2022 after taking notice that the alleged
dispute surrounding the title of the slurry pipeline was not raised by SMAIT
before it when the resolution plan of ESIL was taken up for consideration. It is
pertinent to note that until this stage, Mr. Vir Jai Khosla, the present Applicant
was not a party to the proceedings.
4. Aggrieved by the above order of the Adjudicating Authority in IA No. 832
of 2022, a recall application vide IA No. 283 of 2022 was filed by SREI
Infrastructure Finance Ltd. (SIFL) and present applicant, Mr. Vir Jai Khosla as
a shareholder in SIFL under Section 44 of the Indian Evidence Act, 1872
seeking recall of the order dated 21.02.2023. After satisfying itself that the
2 of 7 CA (AT) (Ins) No. 642 - 644 of 2023 & I.A. No. 2116 of 2025 order dated 21.02.2023 was not based on any fraudulent statement, this recall
application was rejected by the Adjudicating Authority on 17.03.2023.
5. The present Applicant has now filed Company Appeal No. 642-644 of
2023 against the orders of the Adjudicating Authority dated 21.02.2023 and
17.03.2023 respectively in IA No. 832 of 2022 and IA No. 283 of 2023 in C.P.(IB)
No. 40 of 2017. IA No. 2130 has been filed by the Applicant under Order-I (Rule
8A) of the CPC alongwith the Company Appeals praying for formal orders that
the present appeal be heard and decided ex-parte.
6. However, when the Company Appeals came up for hearing before us on
15.04.2025, the Learned Counsel for the Applicant vehemently insisted that
before the Company Appeals are considered, hearing should commence in the
first instance on IA No. 2116 of 2025 which has been filed under Rule 11 of the
NCLAT Rules for video recording of the proceedings in the above appeals.
7. During the hearing held on 15.04.2025, Learned Counsel for the
Applicant dilated at length upon the rationale for insisting on capturing the
proceedings by video recording and for this purpose relied on an order of the
Hon'ble Supreme Court in Orbit Electricals Pvt. Ltd vs Deepak Kishan
Chhabria & Ors. in Contempt Petition (C) No.1195/2023 dated 30.10.2023
and order of this Tribunal in Standard Chartered Bank vs Satish Kumar
Gupta in IA Nos 2853 and 2854 of 2023 of CA(AT)(Ins)No. 242 of 2019.
Attention was also adverted to the orders passed by the Hon'ble Delhi High
Court on 03.07.2024 while disposing W.P.(C) 8580 of 2024 in Gujarat
Operational Creditors Association Vs National Company Law Tribunal,
3 of 7 CA (AT) (Ins) No. 642 - 644 of 2023 & I.A. No. 2116 of 2025 New Delhi & Ors. and the consequential Administrative Order issued by this
Tribunal on 22.11.2024 which provides scope for video-recording of
proceedings. It was urged that the proceedings in the Company Appeals need
to be recorded since the whole matter smacks of fraudulent statements made
by certain entities/persons. It is the case of the Applicant that the impugned
orders of 21.02.2023 and 17.03.2023 having been obtained by fraud, it is
necessary to have video-recording to help in recording of arguments in a
verifiable form with accuracy so as to ensure the accountability of all the actors
in these proceedings.
8. At this juncture, it may be useful to refer to the relevant portions of the
aforesaid Administrative Order in the context of recording of proceedings as
envisaged under the extant Revised Standard Operating Procedure devised by
this Tribunal for virtual mode hearing under its auspices which is as extracted
below:
"15. We have already noticed Revised SOP issued by the NCLAT where recording and use in any manner of the proceedings of the hearing through VC is strictly prohibited. In view of what has been noted above, on viability of the directions sought in the writ petition concerning recordal of proceedings, following is directed:-
(i) The recordal of proceedings in an Appeal/Application pending before the NCLAT is permissible only on prior order obtained by any of the parties to the proceedings from the Court concerned.
(ii) The permission for recording of the proceedings can be granted by Court concerned after looking into the special reason for recording as claimed by Applicant after giving an opportunity to other side.
(iii) On direction issued by the Court, as made above, Registry shall make all necessary arrangements for recording of the proceedings
4 of 7 CA (AT) (Ins) No. 642 - 644 of 2023 & I.A. No. 2116 of 2025 which shall confine to the recording of the proceedings in the nature and manner as directed by the Court.
(iv) The proceedings recorded by the Registry as per the direction of the Court shall be separately kept and shall be used and provided to the parties in the manner as directed by the Court."
9. From a plain reading of Para 15 of the above Administrative Order it
becomes clear that recording of proceedings is not to be ordinarily resorted to
but has to be permitted by the Court concerned, on a request so made, subject
to meeting the criterion of "special reason" warranting such recording.
10. Given this backdrop and without commenting on the locus of the
Applicant, we now like to dwell upon the request of the Applicant to allow video-
recording of the proceedings. When we look back at the sequence of events, it
is an undisputed fact that both the resolution plans of ESIL and OSPIL have
met the approval of the Adjudicating Authority as also of this Tribunal and
most importantly that of the Hon'ble Apex Court. Both the resolution plans of
ESIL and OSPIL have also been fully implemented. It is also apparent from
material on record that the present Applicant did not participate in the CIRP
proceedings of ESIL or OSPIL not being a party therein. It would not be off the
mark for us to take the view that till the stage of plan approval, this Applicant
was nowhere in the picture. Therefore, the question of the Applicant having
agitated their cause on account of their interests having been adversely touched
or affected, either substantially or marginally, either at the stage of CIRP
proceedings of ESIL or OSPIL or until approval of the plan clearly does not
arise. The Applicant came into the lis directly for the first time as late as in
2023 when it filed a recall application vide IA No. 283 of 2022 seeking recall of
5 of 7 CA (AT) (Ins) No. 642 - 644 of 2023 & I.A. No. 2116 of 2025 the order of Adjudicating Authority dated 22.02.2023. It is also pertinent to
note that the Applicant has filed IA No. 2130 as mentioned at para 5 above in
which IA a prayer has been made to the effect that the Company Appeal be
adjudicated ex-parte without granting any opportunity of audience/
hearing/reply to certain Respondents who have been classified by the Applicant
as "Prospective Accused". In such peculiar circumstances, this Bench was of
the view that the Applicant ought to proceed with making its submissions in
the Appeal to make good its request for recording of proceedings. The Applicant
was also repeatedly persuaded to give up their misapprehensions and be rest
assured that this Bench would take utmost care to take note of each and every
argument canvassed and contentions raised. It was also explained that the
Applicant will also have the liberty of filing written submissions wherein it can
adequately and sufficiently highlight all questions of law and fact and other
related contentions in the matter which would suffice for meeting the ends of
justice. However, the Applicant insisted on hearing of IA No 2116 by reiterating
in generalised terms that a colossal fraud had occurred in the events leading
up to the approval of the resolution plans. The pre-requisite conditions of
indicating "special reasons" required to be met under Para 15(ii) of the
Administrative Order does not stand fulfilled. We, therefore, do not do not find
any exceptional grounds or compelling consideration which warrants the need
to record the proceedings.
6 of 7 CA (AT) (Ins) No. 642 - 644 of 2023 & I.A. No. 2116 of 2025
11. In result, we are not in a position to accede to the request of the Applicant
for video-recording of the hearing. IA No. 2116 of 2025 is disposed of in the
above terms. No costs.
[Justice Ashok Bhushan] Chairperson
[Barun Mitra] Member (Technical)
Place: New Delhi Date: 14.07.2025
Abdul/Harleen
7 of 7 CA (AT) (Ins) No. 642 - 644 of 2023 & I.A. No. 2116 of 2025
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free