Where a judgment of the Tribunal has fixed the rate of interest after weighing the facts, including repayments made during the insolvency proceedings, a later application seeking modification of that rate to the contractual default rate, filed under the liberty of a Supreme Court order that permitted only an application for modification, is not a rewriting of the contract but an attempt to reopen a concluded adjudication; the Tribunal will decline it where the contractual rate would enlarge the liability disproportionately to the already-discharged principal and defeat the corporate-resolution objectives of the Code. Liberty granted by the Supreme Court to seek modification of an interest rate does not by itself entitle the applicant to the relief sought; the applicant must establish legal or factual grounds warranting modification of the final judgment, such as a factual error or an omission in the record, and absent any such showing the Tribunal will not alter the rate it had previously fixed on the same facts. Proceedings under the Insolvency and Bankruptcy Code are not a substitute for recovery of contractual interest; where the principal has been discharged and only a dispute over the quantum of interest remains, the creditor's remedy for enhanced contractual interest lies before a competent forum under the loan agreement, not in the insolvency proceedings.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
IN THE MATTER OF: Vinodkumar Mahasukhbhai Thaker ...Appellant(s)
Versus
M/s Kurlon Limited & Anr. ...Respondent(s)
Present:
For Appellant : Mr. Santosh Paul, Sr. Adv., with Ms. Ekta Mehta, Mr. Antarik Chakroborti, Ms. Aditi Rai & Mr. Aditya Sonawane, Advocates.
For Respondents : Mr. Gaurav Mitra, Sr. Advocate, Ms. Honey Satpal, Mr. Nipun Singhvi, Mr. Akash Agarwalla & Mr. Aman, Advocates.
ORDER
(Hybrid Mode)
INDEVAR PANDEY, MEMBER (T)
This Interlocutory Application No. 2832 of 2025 has been filed by M/s.
Kurlon Limited, presently known as M/s. Kanara Consumer Products
Limited/Respondent No.1 in CA (AT) (Ins.) No. 03 of 2024, being the
Financial Creditor, invoking Rule 11 of the National Company Law Appellate
Tribunal Rules, 2016, pursuant to the liberty granted by the Hon'ble Supreme
Court vide its order dated 07.04.2025 in Civil Appeal No. 4338 of 2025.
2. A Company appeal, CA (AT) (Ins.) No. 03 of 2024 preferred by Mr.
Vinodkumar Mahasukhbhai Thaker, Member of the Suspended Board of
Directors of India Green Reality Limited was disposed of by this Appellate Tribunal on 31.01.2025, whereby the order of the Adjudicating Authority
admitting the Corporate Debtor into the Corporate Insolvency Resolution
Process was set aside. While allowing the appeal, this Tribunal directed the
Appellant to pay the balance financial debt, after adjustment of
Rs.65,00,000/-, together with interest payable on it @ 9% per annum.
Aggrieved by the aforesaid order, the Respondent No.1/Financial Creditor
approached the Hon'ble Supreme Court, which dismissed the Civil Appeal,
with liberty reserved to Applicant to seek modification of the interest
component before this Tribunal. In pursuance thereof, the present
Interlocutory Application has been preferred seeking modification of the rate
of interest awarded in the judgment dated 31.01.2025.
Brief Facts of the case
3. The facts of the case relevant to deciding this Application are given
below:
i. M/s. Kurlon Limited, presently known as M/s. Kanara Consumer
Products Limited (Respondent No.1/Applicant herein) had advanced a
financial facility of Rs.52,50,000/- to India Green Reality Limited
(Corporate Debtor). The transaction was governed by the Loan
Agreement dated 25.04.2017, under which the facility was to remain
outstanding for the period from 24.04.2017 to 23.04.2019 and carried
interest at 1.75% per month.
ii. The Loan Agreement further provided that, in case of delay in
repayment, the borrowers would be liable to pay interest at 2% per Page 2 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 month on a pro-rata basis together with additional interest of 1% per
month on a pro-rata basis, resulting in a contractual default interest of
3% per month. Respondent No.1/Financial Creditor relies upon these
contractual terms for seeking modification of the rate of interest
awarded by this Tribunal.
iii. The underlying insolvency proceedings arose from the default in
repayment of the aforesaid financial debt, pursuant to which
proceedings under Section 7 of The Insolvency and Bankruptcy Code,
2016 (hereinafter referred to as the 'Code') were initiated by the
Financial Creditor. The CP (IB) No. 195 of 2019 was admitted by the
Adjudicating Authority on 22.12.2023 for a claimed amount of Rs.
71,61,091/-. The said order was challenged by Mr. Vinodkumar
Mahasukhbhai Thaker, the suspended member of Board of Directors of
Corporate Debtor in Company Appeal (AT) (Insolvency) No. 03 of 2024.
iv. During the pendency of the insolvency proceedings, an amount of
Rs. 65,00,000/- was paid by the Appellant/corporate Debtor, and the
dispute before this Tribunal was ultimately concerned, inter alia, the
adjustment of the said payment against the debt forming the subject
matter of CP (IB) No. 195 of 2019. This Appellate Tribunal set aside the
order admitting the Corporate Debtor into CIRP and directed that the
amount remaining after deduction of Rs.65,00,000/- from Rs.
71,61,091/- be paid by the Appellant/Corporate Debtor to Respondent
No.1/Financial Creditor, together with interest payable on it @ 9% per
Page 3 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 annum from the date the amount became due to be paid until the actual
payment, within two months from the date of the order.
v. Respondent No.1/Financial Creditor, being aggrieved by the
determination of interest @ 9% per annum, preferred Civil Appeal No.
4338 of 2025, before the Hon'ble Supreme Court, contending that the
contractual rate of interest stipulated in the Loan Agreement had not
been given effect to.
vi. The Hon'ble Supreme Court, by order dated 07.04.2025, declined to
interfere with the matter and dismissed Civil Appeal No. 4338 of 2025,
while specifically reserving liberty in favour of the Financial Creditor
who is the Applicant in the present IA, to seek modification of the rate
of interest determined by the NCLAT. The order of Hon'ble SC is
extracted below :-
"O R D E R
We have heard learned senior counsel for the appellant and learned senior counsel for the respondents- Caveators.
2. We are not inclined to interefer in the matter.
3. The appeal is hence dismissed.
4. However, liberty is reserved to the appellant herein to seek modification of the rate of interest that has been determined by the National Company Law Appellate Tribunal.
Pending application(s), if any, shall stand disposed of.
New Delhi April 07, 2025"
Page 4 of 25
I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 vii. Pursuant to the aforesaid order, Applicant/ Financial Creditor has
preferred the present Interlocutory Application in IA No. 2832 of 2025
invoking Rule 11 of the NCLAT Rules, 2016, seeking modification of the
interest component in the judgment dated 31.01.2025. It is contended
that, since the Loan Agreement provides for 3% interest per month upon
default, the award of interest at 9% per annum is contrary to the agreed
contractual terms and that the contractual stipulation ought not to be
ignored or rewritten.
viii. Applicant/Financial Creditor has further stated that the direction
dated 31.01.2025 requiring payment within two months has not been
complied with. After adjustment of the payment of Rs.65,00,000/-
against the debt in CP (IB) No. 195 of 2019, Respondent No.1 claims
that Rs.1,31,84,877/- remains payable, calculated on the basis of the
contractual rate of 3% interest per month.
ix. The present IA accordingly seeks modification of the order dated
31.01.2025 to the extent of interest component as granted in
accordance with the terms of the Loan Agreement at 3% per month,
along with a direction to the Appellant to pay the outstanding amount
expeditiously.
Submissions of Applicant/Financial Creditor
4. The Ld. Counsel for the Applicant/Financial Creditor submitted that
while this Tribunal directed payment of the outstanding amount with interest
at 9% per annum, the parties had expressly agreed under the Loan Agreement Page 5 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 dated 25.04.2017, that in an event of default, interest would be payable at
the contractual rate of 3% per month on a pro-rata basis. It was submitted
that the Tribunal ought to enforce the contractual terms agreed between the
parties and modify the rate of interest accordingly.
5. He submitted that the Loan Agreement dated 25.04.2017 had expressly
provided for payment of interest @ 1.75% per month during the currency of
the loan and, in the event of default, interest at 2% per month together with
additional interest at 1% per month, thereby making the contractual rate of
default interest 3% per month on a pro-rata basis. The Appellant voluntarily
entered into the agreement and accepted all its terms and conditions. At no
stage during the ensuing proceedings under Section 7 of the Code did the
Appellant dispute either the execution of the Loan Agreement or the
contractual rate of interest stipulated therein.
6. Ld. Counsel further submitted that a contract freely entered into
between parties cannot be rewritten by a judicial forum upon its judicial
interference, merely because one party subsequently considers its terms to be
onerous. Where the contractual terms are clear, unambiguous and mutually
accepted particularly when exhausted its binding effect, the Court is bound
to give effect to the agreed intention of the parties as per contract. He placed
reliance on Rajasthan State Industrial Development and Investment
Corporation & Anr. v. Diamond and Gem Development Corporation Ltd.
& Anr., (2013) 5 SCC 470, wherein the Hon'ble SC held that courts cannot
rewrite the terms of a commercial contract. By reducing the contractual rate
Page 6 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 of interest to 9% per annum, this Tribunal effectively altered the bargain
between the parties, which is contrary to settled principles of contract law.
7. He submitted that this very issue formed one of the principal grounds
before the Hon'ble SC in the Civil Appeal, which ultimately had resulted in
the matter, being remanded for reconsideration of the rate of interest. The
Corporate Debtor's (CD) contention in the present proceedings had been that
the contractual rate is exorbitant, unfair or unreasonable this plea is an
afterthought, as no such objection was ever raised, when the Section 7
application was adjudicated. Having accepted the Loan Agreement and after
having defaulted in repayment, the CD remains bound to honour the agreed
contractual rate of interest of 3% per month on the outstanding dues.
8. The Ld. Counsel submitted that the amount of Rs.71,61,091/- claimed
in the application under Section 7 of the Insolvency and Bankruptcy Code,
2016 represented the outstanding dues only up to the date of filing of the
application i.e. till February 2019. The said amount was never intended to be
the final liability of the Appellant, as the debt continued to remain unpaid
throughout the pendency of the proceedings. Since the Appellant failed to
discharge its repayment obligations despite the admitted default, interest
continued to accrue on the outstanding amount in accordance with the terms
of the Loan Agreement until actual payment.
9. It was submitted that there was a considerable gap of nearly six years
between the filing of the Section 7 application and the judgment of this
Appellate Tribunal dated 31.01.2025. During this entire period, the Appellant
remained in continuous default and consequently became liable to pay Page 7 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 contractual interest for the entire duration of such default. The
Applicant/Financial Creditor, therefore, cannot be deprived of the benefit of
the agreed contractual interest merely because adjudication of the
proceedings consumed considerable time, for a fault which was not
attributable to applicant i.e; Financial Creditor.
10. The Ld. Counsel further submitted that, it is a settled principle
governing financial transactions that any payments received from a borrower
are first to be appropriated towards the interest component before being
adjusted against the principal amount. After giving due credit to all payments
made by the Appellant, in terms of the judgment dated 31.01.2025, the
outstanding liability as on 31.07.2025 works out to Rs.1,30,64,877/-. The
said amount represents the dues payable after adjustment of all payments
and is computed strictly in accordance with the contractual terms agreed
between the parties.
11. Accordingly, he submitted that the Respondent is legally entitled to
recover the outstanding amount together with interest at the contractual rate,
as the continued accrual of interest is solely attributable to the Appellant's
prolonged default in repayment of the loan and not to any overt act or
omission on the part of the Respondent.
12. The Ld. Counsel submitted that the CD's objection that the present
application amounts to a fresh recovery proceeding or constitutes a separate
lis is wholly misconceived and devoid of merit. The present application neither
seeks recovery of any new claim nor raises any issue requiring fresh
adjudication. It has been filed only for modification of the rate of interest Page 8 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 awarded by this Appellate Tribunal from 9% per annum to the contractual
rate agreed between the parties.
13. It was submitted that the entitlement of the Applicant/Financial
Creditor to receive interest on the outstanding dues was an issue which
already stands adjudicated by this Tribunal in its judgment dated
31.01.2025. The Appellant did not challenge the aspect of grant of interest
before any higher forum. The only issue requiring consideration is whether
such interest ought to be awarded at the contractual rate, instead of the
reduced rate fixed by this Tribunal. Therefore, the present application is
confined to modification of an existing direction and does not involve
adjudication of any fresh dispute between the parties.
14. Ld. Counsel submitted that Hon'ble SC gave liberty to Respondent, to
approach this Tribunal for modification of the rate of interest, and no
objection regarding maintainability was raised by the Appellant before the
Hon'ble Supreme Court. Consequently, the Appellant cannot now at this
matured stage of proceedings contend that the present proceedings are not
maintainable, as the application is fully supported by the order of the Hon'ble
Supreme Court and is confined to the limited issue for which liberty was
granted, as regards to payability of interest and at what rate.
15. He further submitted that the present application is a legitimate
invocation of the inherent powers of this Tribunal under Rule 11 of the
National Company Law Appellate Tribunal Rules, 2016. The application does
not seek recovery of any independent contractual claim or initiation of a fresh
Page 9 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 proceeding, but is confined to securing complete justice by seeking
modification of the rate of interest awarded in the judgment dated 31.01.2025,
in accordance with the contractual terms which was inter-se binding upon
the parties.
16. It was submitted that where the statutory framework by itself does not
expressly provide a procedural mechanism to address a particular situation,
this Appellate Tribunal is empowered to exercise its inherent jurisdiction to
secure the ends of justice and prevent miscarriage of justice. The Respondent
has approached this Tribunal only after obtaining express liberty from the
Hon'ble SC and, therefore, the present application squarely falls within the
scope of Rule 11. Reliance was placed on Glass Trust Co. LLC v. Byju
Raveendran, (2025) 3 SCC 625, wherein the Hon'ble SC recognised that the
inherent powers of the Tribunal may be exercised where no express provision
exists to meet the ends of justice. Accordingly, he prayed that the present
application be allowed and the rate of interest awarded in the judgment dated
31.01.2025 be modified to the contractual rate stipulated in the Loan
Agreement.
Submissions of Appellant / Corporate Debtor
17. Ld. Counsel for Corporate Debtor submitted that the present
Application is liable to be dismissed as it is, in substance, an attempt to seek
review of the judgment dated 31.01.2025, a jurisdiction which this Tribunal
does not possess under the realms of the Code. It was submitted that while
deciding the appeal, this Tribunal had consciously exercised its judicial
discretion in directing payment of the remaining amount with interest at 9% Page 10 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 per annum after taking note of the fact that the entire principal amount and
a substantial portion of the interest had already been repaid by the Corporate
Debtor. The Applicant now seeks to substitute the said rate with the
contractual default rate of 3% per month (36% per annum), thereby
converting an outstanding amount of Rs.6,61,091/- into an alleged liability
of Rs.1,31,84,877/-. Such a prayer is, in effect, a re-hearing of a concluded
issue under the guise of modification. It was further submitted that Rule 11
of the National Company Law Appellate Tribunal Rules, 2016 does not confer
any power of review and merely preserves the inherent powers of this Tribunal
any provision of law vesting inherent power will not be inclusive of power of
review, which has to be otherwise independently conferred to the Tribunal
under a statute. The liberty granted by the Hon'ble SC only permitted the
Applicant to approach this Tribunal and did not direct or warrant modification
of the interest awarded.
18. He submitted that the Applicant's claim for interest at the rate of 3%
per month is wholly exorbitant, arbitrary and contrary to settled law. In this
regard, reliance was placed upon the Constitution Bench judgment of the
Hon'ble SC in Central Bank of India v. Ravindra & Ors., (2002) 1 SCC
367, wherein it was held that the award of pendente lite and post-decree
interest is a matter of judicial discretion and not a mechanical enforcement
of the contractual rate. The Hon'ble SC further held that penal interest cannot
be capitalised or compounded and that charging interest upon penal interest
is opposed to public policy.
Page 11 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024
19. It was submitted that although the Corporate Debtor has already repaid
the entire principal amount of Rs.52,50,000/-, and that the Applicant has
compounded penal interest year after year and inflated its claim to
Rs.1,31,84,877/-. Such a claim is directly contrary to the principles laid down
in Central Bank of India v. Ravindra & Ors (supra) and is also inconsistent
with Sections 50 and 51 of the Code, which empower the Adjudicating
Authority to avoid extortionate credit transactions. Accordingly, the direction
of this Tribunal awarding interest @ 9% per annum constitutes a fair and
proper exercise of judicial discretion.
20. Ld. Counsel submitted that no subsisting financial debt survives for
adjudication under the Code, as even though the Applicant had filed Company
Petition (IB) No. 195 of 2019 claiming an amount of Rs.71,61,091/, during
the pendency of the proceedings, the Corporate Debtor had repaid
Rs.65,00,000/-, thereby discharging the entire principal amount of
Rs.52,50,000/- along with a substantial portion of the interest. It was
precisely on account of this substantial repayment that this Tribunal, by its
judgment dated 31.01.2025, held the admission of the Section 7 application
to be a patent error and consequently set aside the admission order.
Therefore, the Applicant cannot continue to repeatedly invoke the insolvency
jurisdiction merely for recovery of an alleged differential amount of penal or
contractual interest after the principal debt itself stands fully discharged.
21. Ld. Counsel further submitted that the Applicant has taken
contradictory stand before different judicial forums regarding the amount
allegedly due to be payable towards interest. It was pointed out that in the
Page 12 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 proceedings pending before the Court of Small Causes (C.C. No. 0050156
of 2019), the Applicant's own counsel recorded on 20.06.2025 that, after
adjustment of the amounts already paid, only approximately Rs.11,00,000/-
remained payable towards interest. However, in the present Interlocutory
Application, the Applicant seeks to recover an exorbitant amount of
Rs.1,31,84,877/- allegedly payable towards interest in respect of the very
same loan transaction. Such inconsistent stands clearly demonstrate that the
Applicant is blowing hot and cold before different judicial forums and has not
approached this Tribunal with clean hands. Consequently, the Applicant is
not entitled to any relief.
22. It was further submitted that the Applicant cannot attribute any delay
in payment to the Corporate Debtor, since instead of accepting the benefit of
the judgment dated 31.01.2025 and permitting the compliance to be ensured,
within the period granted by this Tribunal to expire, the Applicant itself
preferred Civil Appeal No. 4338 of 2025 before the Hon'ble SC on 10.03.2025,
even before expiry of the two-month period granted for compliance. Having
itself challenged the judgment before the Hon'ble SC, the Applicant cannot
subsequently allege non-compliance by the Corporate Debtor.
23. Ld. Counsel submitted that the Code is intended to facilitate insolvency
resolution and not to serve as a mechanism for recovery of disputed
contractual dues. In support of this submission, reliance was placed upon the
judgment of the Hon'ble SC in Transmission Corporation of Andhra
Pradesh Limited v. Equipment Conductors and Cables Limited & Anr.,
(2019) 12 SCC 697, wherein it was categorically held that the Code is not a
Page 13 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 substitute for debt recovery proceedings. Reliance was also placed upon the
decision of this Appellate Tribunal in Ranjeet Singh v. Karan Motors
Private Limited, Company Appeal (AT) (Insolvency) No. 693 of 2020,
wherein it was observed that if a creditor seeks recovery of interest for delayed
payment, the appropriate remedy is before a competent civil court and not by
initiating or continuing insolvency proceedings. Similar reliance was placed
upon Amier Hamsa Ali Abbas Rawther (Liquidator) v. Chairman-cum-
Managing Director, NLC India Limited, Company Appeal (AT) (CH)
(Insolvency) No. 213 of 2025, wherein this Tribunal reiterated that
proceedings under the Code cannot be utilised as recovery proceedings for
disputed contractual claims. It was therefore the case of Appellant that any
residual claim regarding enhanced contractual interest can only be
adjudicated before the competent civil court or through arbitration,
particularly when the Loan Agreement dated 25.04.2017 itself contains an
arbitration clause.
24. It was submitted that during the hearing of the present Application, the
Appellant relied only upon those judgments, which had already been cited in
the reply and served upon the Applicant well in advance. Consequently, the
Applicant's request to file further written submissions on the ground that it
had no opportunity to examine those judgments is wholly untenable and
deserves to be rejected.
25. Ld. Counsel finally submitted that once the application under Section
7, admission had been set aside on account of substantial repayment, the
Applicant cannot indirectly convert the insolvency proceedings into a debt
Page 14 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 recovery mechanism by seeking enhancement of the rate of interest through
the present Application. The judgment dated 31.01.2025 conclusively
determined the issue by directing payment of the balance amount along with
interest at 9% per annum, and the present Application is nothing but an
attempt to reopen a concluded adjudication under the guise of modification.
It was case of the Appellant, that if the Applicant is genuinely aggrieved by
the contractual rate of interest, its remedy lies before the competent civil court
or in arbitration in accordance with the Loan Agreement and not before this
Tribunal exercising jurisdiction under the Code. Summing up his arguments,
Ld. Counsel prayed that this Appellate Tribunal may be pleased to dismiss IA
No. 2832 of 2025 with costs and maintain the rate of interest at 9% per
annum, as awarded by this Tribunal vide judgment dated 31.01.2025.
Analysis and Findings
26. We have gone through the documents available on record and heard
the parties.
27. The present Application has been filed pursuant to the liberty granted
by the Hon'ble Supreme Court while dismissing the Civil Appeal preferred
against the Judgment dated 31.01.2025. The only question which restrictively
arises for our consideration is whether the direction contained in the said
judgment awarding interest at the rate of 9% per annum deserves to be
modified and substituted with the contractual rate of interest provided under
the Loan Agreement.
28. The Loan Agreement dated 25.04.2017 clearly provides that in case of
default, the borrower is liable to pay interest at the rate of 2% per month
Page 15 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 together with an additional 1% per month, amounting to 3% per month. The
Appellant never disputed this contractual stipulation at any stage of the
proceedings. It is the case that once the parties had consciously agreed to
such rate of interest, the same ought to have been given effect to and the
award of interest at 9% per annum amounts to rewriting the contract. It is
further submitted that the amount claimed in the Section 7 Application
represented the dues only up to February 2019 and that interest continued
to accrue thereafter until payment. The Applicant also argues that the present
Application is not in the nature of a review, but merely seeks modification of
the rate of interest in terms of the liberty granted by the Hon'ble Supreme
Court.
29. The Corporate Debtor, on the other hand, submits that the present
Application seeks to reopen a final judgment under the guise of modification.
It is argued that while deciding the appeal on 31.01.2025, all the facts,
including the terms of the Loan Agreement, were before this Tribunal. After
considering those facts, interest at 9% per annum was consciously awarded
as part of the final relief. It is further submitted that during the pendency of
the insolvency proceedings, the Corporate Debtor had already repaid the
entire principal amount of Rs.52.50 lakh along with a substantial part of the
interest by paying Rs.65 lakh, and it was primarily on account of these
repayments that the admission of the Corporate Debtor into CIRP was set
aside. According to the Corporate Debtor, permitting contractual default
interest at 3% per month at this stage would enlarge the liability to more than
Rs.1.31 crore, despite the principal having already been discharged, which
Page 16 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 would be wholly disproportionate. It is also contended that Rule 11 does not
confer any power to review a final judgment and that proceedings under the
Insolvency and Bankruptcy Code cannot be converted into proceedings for
recovery of penal contractual interest.
30. Having noticed the rival submissions, we shall now examine whether
the Applicant has been able to show any legal or factual ground which would
justify modification of the judgment dated 31.01.2025.
31. At the outset, it is necessary to examine the nature of the Judgment
sought to be modified. The Judgment dated 31.01.2025 was not an interim
order passed during the pendency of the proceedings. It was rather a final
adjudication by which the appeal itself was finally disposed of after
considering the pleadings, documents and submissions advanced by both
sides. While deciding the appeal, this Tribunal took note of the fact that
during the pendency of the insolvency proceedings, the Corporate Debtor had
already repaid Rs.65 lakh, thereby clearing the entire principal amount of
Rs.52.50 lakh and also paying a substantial portion of the interest claimed
by the Financial Creditor. Keeping these facts in view, the admission of the
Corporate Debtor into Corporate Insolvency Resolution Process was held to
be unsustainable and was accordingly set aside. However, at the same time,
this Tribunal directed the Corporate Debtor to pay the remaining balance
together with interest at 9% per annum from the date the amount became
due till its payment. Thus, the rate of interest was not fixed casually or
without consideration. It formed part of the final relief granted after
Page 17 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 appreciating the overall facts and circumstances of the case, founded upon
the factual rationality.
32. The principal submission of the Applicant is that since the Loan
Agreement specifically provides for payment of interest at the rate of 3% per
month in the event of default, this Tribunal ought to have awarded interest
strictly in accordance with the contract. According to the Applicant, once the
parties had voluntarily agreed to such terms, there was no occasion for this
Tribunal to substitute the agreed rate with interest at 9% per annum.
33. We are unable to accept this submission in the manner canvassed by
the Applicant for the reasons which have been discussed in subsequent paras.
34. There can be no dispute that parties are ordinarily bound by the terms
of the contract voluntarily entered into between them. Equally, Courts and
Tribunals do not ordinarily rewrite commercial contracts merely because one
party subsequently finds the terms to be onerous. However, that principle
cannot be applied in isolation without considering the nature of the
proceedings before the Court and the relief that is ultimately granted. Once a
dispute reaches a judicial forum, the Court is required not merely to read the
contract, but also to mould the relief in accordance with law after considering
the conduct of the parties, the surrounding facts and to ensure justice within
the framework of law. The framework here being the Insolvency and
Bankruptcy Code. Therefore, while contractual terms undoubtedly constitute
an important factor, they are not the only factor governing the relief to be
granted by the Court.
Page 18 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024
35. In the present case, the direction awarding interest at 9% per annum
did not arise because this Tribunal ignored the terms of the Loan Agreement.
Rather, it was passed after taking into consideration the subsequent
developments which had taken place during the pendency of the proceedings.
By the time the appeal was finally decided, the Corporate Debtor had already
discharged the entire principal amount and had also paid a substantial
amount towards interest. It was precisely because of these subsequent
payments that this Tribunal found the continuation of CIRP to be unjustified.
Therefore, the award of interest at 9% per annum was a conscious exercise of
judicial discretion while balancing the equities between the parties after the
principal liability had been discharged.
36. The Applicant has also argued that interest continued to accrue after
filing of the Section 7 Application and, therefore, the contractual rate ought
to be applied till the date of actual payment. It is true that the loan transaction
and the contractual obligations between the parties continued to subsist.
However, it is equally important to notice that the present proceedings arise
under the Code. The object of the Code is to determine whether insolvency
proceedings deserve to continue against the Corporate Debtor. It is not
intended to function as a forum for recovery of every contractual claim or for
enforcing every term of a commercial agreement irrespective of the stage of
the dispute.
37. The facts of the present case demonstrate this distinction. The Section
7 Application was originally filed on the basis of an alleged financial debt of
Rs.71,61,091/-. During the pendency of the proceedings, however, the
Page 19 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 Corporate Debtor paid Rs.65 lakh, thereby wiping out the entire principal
amount and substantially reducing the outstanding liability. It was these very
repayments which persuaded this Tribunal to hold that the admission of the
Corporate Debtor into insolvency proceedings was a patent error. Once the
insolvency proceedings themselves were found to be unsustainable because
of substantial repayment, the remaining dispute essentially became one
relating to the quantum of interest payable between the parties.
38. At this stage, the Applicant seeks to substitute the judicially awarded
rate of 9% per annum with contractual default interest of 3% per month,
which, according to its own calculations, would increase the outstanding
claim to more than Rs.1.31 crore. We find that such relief cannot be examined
merely by looking at the contractual clause in isolation. The consequence of
granting such prayer must also be kept in view. The principal amount of the
loan already stands repaid. The insolvency proceedings have already been set
aside. What survives is only a dispute regarding the extent of interest payable.
If, despite these circumstances, contractual default interest at the rate of 36%
per annum is permitted to be enforced through modification of the earlier
judgment, the liability would increase manifold solely on account of penal
interest. Such a consequence would substantially alter the very basis on
which the appeal had earlier been decided which could not be done under the
garb of modification by even partially revisiting the judgments on merits. The
objective of the Code is the resolution of corporate insolvency and not the
recovery of claimed amount. Once it was held that CIRP proceedings against
the CD would not survive and it's also a going concern, awarding such
Page 20 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 usurious rates of interest, would lead to corporate debtor actually slipping
into insolvency, which would be against the objectives of the Code.
39. We also find considerable force in the submission of the Corporate
Debtor that the liberty granted by the Hon'ble Supreme Court cannot, by
itself, be read as an approval of the Applicant's claim. The order of the Hon'ble
Supreme Court merely granted liberty to approach this Tribunal for seeking
modification of the rate of interest. Therefore, the burden still lies upon the
Applicant to establish that modification of the final judgment was at all
warranted on legal as well as factual grounds. Mere grant of liberty cannot
automatically entitle the Applicant to the relief sought.
40. We also cannot lose sight of the fact that while passing the Judgment
dated 31.01.2025, this Tribunal had already exercised its discretion after
considering the complete factual matrix before it. The Applicant has not
pointed out any factual error, inadvertent omission or circumstance which
was not within the knowledge of this Tribunal while deciding the appeal. The
terms of the Loan Agreement were already part of the record. The repayments
made by the Corporate Debtor were also fully known. After considering all
these facts, this Tribunal consciously awarded interest at 9% per annum. The
present Application, therefore, substantially seeks a different conclusion on
the very same set of facts.
41. We further take note of the terms and conditions of the Loan Agreement
in case of default. The last para of the Loan Agreement dated 25.04.2017
provides for arbitration and the same is extracted below:
Page 21 of 25
I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 "In the event of any claim(s), dispute(s) or difference(s) arising directly or indirectly out of this Agreement, or the interpretation thereof or anything done or omitted to be done pursuant thereto or the performance or non-performance, defaults, breaches, of this Agreement ("Dispute(s)"), such Dispute(s) shall be referred to the sole arbitrator appointed by the Lender. The seat of arbitration shall be at Mumbai, India and the arbitration shall be governed by the provisions of the Arbitration and Conciliation Act, 1996 or any statutory amendments thereof or any statute enacted for the replacement therefore. The language of the arbitration proceedings shall be English. The expenses of the arbitration shall be borne in such manner as the arbitrator or arbitral tribunal, as the case may be, may determine. The award including interim award(s) of the arbitral tribunal shall be final, conclusive and binding on all the parties concerned. The arbitral tribunal may, from time to time, lay down the procedure to be followed in conducting the arbitration proceedings and shall conduct the arbitration proceedings in such manner as it considers appropriate."
42. The Applicant has relied upon Rajasthan State Industrial
Development and Investment Corporation & Anr. v. Diamond and Gem
Development Corporation Ltd. & Anr., (2013) 5 SCC 470, particularly
paragraph 23, to submit that the terms of a contract must be given their
actual meaning and that a Court cannot make a new contract for the parties.
There is no dispute with this general principle. However, in the present case,
we are not changing, rewriting or re-interpreting the Loan Agreement. The
clause providing for 2% interest per month plus an additional 1% per month
in case of default, making it 3% per month, is clear and its existence is not in
dispute. The question before us is different: whether, after considering the
facts of the case, we should modify the 9% per annum interest already
awarded by us in our final Judgment dated 31.01.2025. At the time of passing
Page 22 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 that judgment, the entire principal amount of Rs.52.50 lakh had already been
paid, and the Corporate Debtor had paid Rs.65 lakh, which included the
entire principal and a substantial part of the interest. These payments were
taken into account while setting aside the admission of the Corporate Debtor
into CIRP and while directing payment of the remaining amount with interest
at 9% per annum. The matter before us was for adjudication under the
Insolvency and Bankruptcy Code for corporate insolvency resolution. The
objective of the Code is to keep the corporate debtor as a going concern. The
interest rate allowed was keeping in mind this objective of the Code. The code
could not be used as recovery forum as a separate mechanism for recovery of
its claims was available to the lender.
43. In Central Bank of India v. Ravindra, (2002) 1 SCC 367, the
Constitution Bench of the Hon'ble Supreme Court held that grant of interest
after a matter reaches the Court is not automatic and need not always follow
the contractual rate. The Court can award a lower rate where, considering the
facts of the case, the contractual interest is disproportionate to the principal
amount. Such discretion, however, has to be exercised fairly and for proper
reasons. The Hon'ble Supreme Court also held that penal interest cannot be
capitalised, and further interest cannot be charged upon the penal interest.
In these proceedings, the Corporate Debtor had paid Rs.65 lakh, which
covered the entire principal and a substantial part of the interest. Despite
this, the Applicant's computation results in a claim of about Rs.1.31 crore by
continuing to apply the contractual default rate. Therefore, the issue before
us is not whether the contractual clause exists, but whether that rate should
Page 23 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 be applied in the present circumstances. Having regard to the substantial
payment already made, the repayment of the entire principal and the fact that
this Tribunal had already awarded interest at 9% per annum. The principle
laid down in Ravindra supports the exercise of judicial discretion rather than
mechanically applying the contractual rate of 36% per annum.
44. The decisions in Transmission Corporation of A.P. Ltd. v.
Equipment Conductors & Cables Ltd., (2019) 12 SCC 697, Ranjeet Singh
v. Karan Motors Pvt. Ltd., and Amier Hamsa Ali Abbas Rawther
(Liquidator) v. CMD, NLC India Ltd., Company Appeal (AT)(CH)(Ins.) No.
213 of 2025, also help us understand the limited purpose of proceedings
under the Insolvency and Bankruptcy Code. The Hon'ble Supreme Court has
made it clear that the IBC is not a substitute for an ordinary recovery
proceeding. The same principle has been followed by this Tribunal, including
in cases where the dispute essentially concerns delayed payment or a
contractual claim for interest. What remains between the parties is essentially
a dispute regarding the amount of interest payable under the Loan
Agreement. The Applicant now seeks to apply the contractual default rate of
3% per month or 36% per annum to this remaining liability. In these
circumstances, permitting the present insolvency proceedings to be used for
recovery of enhanced contractual interest would, in substance, turn the
proceedings into a recovery proceeding. We are therefore of the view that while
the Applicant may pursue such contractual claim before a forum competent
to decide it, as provided in the Loan Agreement, the same cannot be used as
Page 24 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024 a basis to reopen the final judgment passed in the insolvency proceedings and
substitute the rate of interest already fixed by us.
45. Viewed from this perspective, we find that the direction awarding
interest at 9% per annum strikes a fair balance between the competing rights
of the parties. It ensures that the Financial Creditor is compensated for the
delayed payment, while at the same time recognising the undisputed fact that
the Corporate Debtor had already repaid the entire principal amount together
with a substantial portion of the interest even before the appeal was finally
decided. Replacing that rate with contractual default interest of 3% per month
would convert the corporate insolvency resolution proceedings which have
been closed by this Tribunal, into a recovery proceeding, which would be
contrary to the objectives of the Code.
46. Accordingly, we do not find any rationale to modify the interest rate
which was fixed at 9% per annum on the balance amount in the Judgment
dated 31.01.2025. The IA No. 2832 of 2025 is dismissed. No order as to costs.
[Justice Sharad Kumar Sharma] Member (Judicial)
[Arun Baroka] Member (Technical)
[Indevar Pandey] Member (Technical) Place: New Delhi Dated: 24.08.2026
Harleen Pragya (LRA)
Page 25 of 25 I.A. No. 2832 of 2025 in Company Appeal (AT) (Ins.) No. 03 of 2024
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free