Union Of India vs Infrastructure Leasing And Financial ...
- CitationCompany Appeal (AT) No. 346 of 2018
Ratio decidendi
The rule this decision rests on
The Tribunal will not decide, in an interlocutory application, whether a termination notice was issued on sufficient grounds; such a factual dispute is to be pursued through the remedies available under the concession agreement, not in those proceedings. An interim restraint order passed in the appeal, which directed the authority not to cancel any agreement with the companies in question, is confined to the order in which it was made and is not continued by a later order that refers to it only for a different purpose or that does not expressly continue it; the restraint therefore does not operate in perpetuity and does not bar the authority from issuing a termination notice thereafter.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
Union of India ...Appellant
Vs
Infrastructure Leasing and Financial Services Ltd. & Ors. ...Respondents
IN THE MATTER OF:
West Gujarat Expressway Limited ...Applicant
Vs.
National Highways Authority of India ...Respondent
Present:
For Appellant: Mr. Ramji Srinivasan, Senior Advocate with Mr. Raunak Dhillon, Mr. Adarsh Saxena, Mr. Vikash Kumar Jha, Mr. Hariharan Kumar, Ms. Isha Malik, Ms. Drishti Das, Ritu Anand Vishwakarma, Mr. Nihaad Dewan, Advocates for Applicant in I.A No. 2908 of 2021.
Mr. Sanjay Shorey, Director Legal, MCA for Appellant
For Respondents: Mr. Shailesh Suman, NHPC Mr. Puneet Taneja, Ms. Laxmi Kumari, Mr. Manmohan Singh, Advocates for Intervenor for GAIL
Mr. Ramesh Babu, Ms. Manisha Singh, Jagriti Bharti, Advocates for RBI Advocate
Interlocutory Application No.2908 of 2021 in Company Appeal (AT) No. 346 of 2018 1 Ms. Gunjan Sinha, Respondent in IA 2908 of 2021
Mr. Sanjay Kapur, Ms. Megha Karnwal, Mr. Arjun Bhatia, Advocates for SBI
Mr. Anil Seth, Mr. Prateek, Udit Seth, Advocates for Intervenor.
Mr. Rajiv S Roy, Aurojyoti Chatterjee, Mr. Satyam Saxena, Advocates for Canara and UCO Bank.
Mr. Manish Paliwal, Mr. Vikas Kumar, for Intervenor
Mr. Ashwin Kumar Nair, Mr. Kunal Verma, Intervenor
Mr. Vishnu Sharma, Ms. Anupma Sharma, Mr. Amar Jyoti Sharma, Advocates for Noida Authority Mr. Parag Maini, Mr. Abhimanyu Chopra, Advocates for SIB.
Mr. Abhinav Vashisht, Sr. Advocate with Manmeet Singh, Ishaan Duggal, Shatakshi Tripathi, Intervenor
JUDGMENT
ASHOK BHUSHAN, J.
This Application has been filed by West Gujarat Expressway Limited,
an entity, which is part of the Infrastructure Leasing & Financial Services
Group ("IL&FS Group") praying for quashing the Termination Notice dated
21st December, 2021 issued by National Highways Authority of India
("NHAI").
Interlocutory Application No.2908 of 2021 in Company Appeal (AT) No. 346 of 2018 2
2. The Applicant entered into a Concession Agreement on 22nd March,
2005 with the NHAI for conversion of Jetput-Gondal-Rajkot bypass section
of NH-8B into access controlled four lane highway with service lanes along
certain sections and strengthening of the existing lanes from km 1117 to
km 143.0 and improvement to Gondol-Rajkot section (km 143.0 to km 175)
falling in the State of Gujarat, on BOT Basis, having a concession period of
20 years. The Applicant completed the construction work in the year 2008
for which Completion Certificate was issued on 14th August, 2008.
3. After issuance of Completion Certificate, the Project Highway was to
be maintained by the Applicant - Concessionaire as per the provisions of
the Concession Agreement. The NHAI issued various notices to the
Applicant regarding compliance of safety provisions envisaged in the
Concession Agreement and to rectify the default observed from time to time.
A Cure Notice followed by Preliminary Notice dated 16th July, 2021 was
issued by the NHAI to the Applicant and subsequent notices were also
issued. By the impugned notice dated 21st December, 2021, the NHAI
observing that Concessionaire has committed Concessionaire Events of
Default in terms of Concession Agreement, hence, termination notice was
issued in accordance with Clause 32.1.2 of the Concession Agreement and
the NHAI by virtue of the Termination Notice, deemed to have taken
possession and control of the Project Highway forthwith.
4. The IA No.2908 of 2021 is filed by the Applicant praying for quashing
the Notice dated 21st December, 2021. On 23rd December, 2021, this
Tribunal directed the Application to be taken up on 4th January, 2022 and
Interlocutory Application No.2908 of 2021 in Company Appeal (AT) No. 346 of 2018 3 till then it was directed that Applicant shall not be dispossessed in
pursuance of the Termination Notice dated 21st December, 2021. The
interim order passed on 23rd December, 2021 was extended by this
Tribunal. The NHAI has filed its reply on 25th February, 2022, to which
rejoinder affidavit has also been filed by the Applicant on 10th March, 2022.
The Application was heard by this Tribunal and is being disposed of by this
order.
5. Shri Ramji Srinivasan, learned Senior Counsel appearing for the
Applicant submits that this Tribunal vide order dated 8th April, 2019 has
already directed the NHAI not to take any step to cancel any agreement
with any of the companies in question, hence, as per order dated 8th April,
2019, Termination Notice dated 21st December, 2021 could not be issued
and it is clear breach of the said order. It is further submitted that the
Resolution Process for Resolution of various subsidiaries of IL&FS
including the Applicant is at crucial stage of its Final Resolution and
Termination Notice at this stage will severally prejudice the Applicant and
also impact the overall Resolution of IL&FS Group. It is submitted that
Applicant has liability towards its lenders and on the basis of collections
made from Toll, the Applicant was discharging its debt having been
categorized as 'Green entity'. The termination at this stage shall hamper
the capacity of the Applicant to serve its debt. The learned Senior Counsel
for the Applicant also cites subsequent order dated 23rd October, 2019
passed in IA No.3320 of 2019 to support the submission. It is submitted
that to the Cure Notice issued by the NHAI, on 2nd April, 2021 Applicant
Interlocutory Application No.2908 of 2021 in Company Appeal (AT) No. 346 of 2018 4 has submitted appropriate reply and further to the Preliminary Termination
Notice dated 16th July, 2021, Applicant has submitted reply and there was
no default on the part of the Applicant, so as to invoke the power of
termination under the Concession Agreement.
6. The learned Counsel appearing for the NHAI refuting the
submissions of learned Senior Counsel for the Applicant contends that
NHAI is not party to the present Appeal in this Tribunal, nor was heard
before passing the order dated 8th April, 2019. The order dated 8th April,
2019 is not an order, which was continued by this Tribunal by its
subsequent orders, including the final order passed on 12th March, 2020.
It is submitted that due to Concessionaire default a portion of the retaining
wall of Ch. 180 in the Project Highway collapsed on 8th June, 2020 causing
death of two persons. Inquiry into the incident culminated into a Report
and NHAI vide its order dated 9th March, 2021 debarred the Promoter of
the Applicant, that is IL&FS. The NHAI was not provided the copy of the
order dated 8th April, 2019 prior to 21st December, 2021. The learned
Counsel for the Respondent submits that if the Applicant is so aggrieved by
the Termination Notice, it is open for him to invoke dispute resolution
process as envisaged by Clause 39 of the Concession Agreement through
Arbitration and Conciliation proceedings. It is further submitted that as per
Clause 32.3 of the Concession Agreement, it provides that upon
termination by NHAI on account of occurrence of Concessionaire Event of
Default, the NHAI shall pay to the Concessionaire by way of Termination
payment of an amount equal to 90% of the debt due less insurance claims,
Interlocutory Application No.2908 of 2021 in Company Appeal (AT) No. 346 of 2018 5 if any. It is submitted that Concession Agreement has nothing to do with
Resolution of the applicant. The Applicant has miserably failed in
honouring the obligation under the Concession Agreement. The NHAI was
left with no remedy except to terminate the Agreement. It is submitted that
public safety and maintenance of Project Highway cannot be compromised.
7. Mr. Abhinav Vashisht, learned Senior Counsel has appeared on
behalf of the lenders of the Applicant and has also supported the
submissions of the Applicant. It is submitted that on termination of the
Agreement, lenders shall suffer a loss and shall not be able to recover their
debt.
8. We have considered submissions of learned Counsel for the parties
and have perused the record.
9. In the order dated 8th April, 2019, on which reliance has been placed
by the Applicant, paragraph 10 of the same is to the following effect:
"Pursuant to the earlier order, a supplementary affidavit has been filed by the Appellant - Union of India, but it has not been filed in a format as the Appellate Tribunal wanted. The Appellate Tribunal wanted to understand with regard to each Amber Entity the amount due to one or the other 'Financial Creditor' or the 'Operational Creditor'. The learned Counsel will handover the same on 16.04.2019 at least with regard to the four Amber Entities in question. They will also try to prepare a similar chart with regard to rest of the nine Amber Entities by the same date. The 'Financial Creditor' and the 'Operational Creditor' of these four companies will also handover
Interlocutory Application No.2908 of 2021 in Company Appeal (AT) No. 346 of 2018 6 their respective charts showing the amount payable and matured and the amount, if any, they have generated from Provident Fund or Pension Fund or any other Fund, e.g. Gratuity Fund or Superannuation Fund etc. by the same date, i.e., 16.04.2019 along with relevant provisions of the contract, which should not be more than two pages.
With regard to the rest of the companies, if any other company has been declared as 'Green Entity' or 'Amber Entity' or 'Red Entity', the Appellant- Union of India will also file an affidavit in regard to such company.
Post these Appeals 'for orders' on 16.04.2019 at 04:00 PM.
In the meantime, the National Highway Authority of India will not take any step to cancel any agreement with any of the companies in question."
10. The learned Counsel for the Applicant has not been able to point out
any order passed in this Appeal continuing the order dated 8th April, 2019,
subsequent to 16th April, 2019, nor there is any reference to the order dated
8th April, 2019 in the detailed final order passed in this Appeal on 12th
March, 2020. The order dated 8th April, 2019 was not an order which
contemplated the continuance of prohibition on the NHAI from cancelling
any Agreement in perpetuity.
11. Much emphasis has been placed by learned Counsel for the
Applicant on order dated 23rd October, 2019, which was passed in IA
No.3320 of 2019. It is useful to extract the order dated 23rd October, 2019,
which is to the following effect:
Interlocutory Application No.2908 of 2021 in Company Appeal (AT) No. 346 of 2018 7 "IA No.3320 of 2019 This appeal has been preferred by 'SREI Infrastructure Finance Ltd.' for direction to 'Infrastructure Leasing and Financial Services Ltd.' as well as 'NHAI' not to terminate the 'Concession Agreement' between 'NHAI' and 'Fagne Songadh Expressway Limited' which was reached for execution of 'Fagne Songadh Expressway Limited'.
Further prayer has been made to direct the Appellant (ILFS) to place the 'Resolution Plan' before the appropriate Committee.
In the present case as the matter is being looked into by the Board of Directors and Committee constituted for individual group companies including two Expressway Ltd. including 'Fagne Songadh Expressway Limited', we are not inclined to deliberate on the issue, however, we are giving liberty to the Appellant to bring the facts to the notice of Board of Directors of 'ILFS' and Committee if constituted that it has already filed the 'Resolution Plan' which is viable and feasible and for the said purpose, it is desirable to continue with the 'Concession Agreement'. If the matter is brought to the notice of the Board of Directors, it will consider the same in accordance with law and the order dated 8th April, 2019 passed by this Appellate Tribunal.
IA stands disposed of."
12. Perusal of the above order indicates that in the Application, direction
was sought to IL&FS as well as NHAI not to terminate the 'Concession
Agreement' between NHAI and Fagne Songadh Expressway Limited, which
Interlocutory Application No.2908 of 2021 in Company Appeal (AT) No. 346 of 2018 8 have been noticed in the first paragraph of the order. However, in the
interim passed on 23rd October, 2019, no such direction was issued as
prayed for, that is, not to terminate the Concession Agreement between
NHAI and Fagne Songadh Expressway Limited. What was observed by this
Tribunal was that liberty was given to the Appellant to bring the facts to
the notice of the Board of Directors of the IL&FS and Committee if
constituted that it has already filed its Resolution Plan, which is viable and
feasible and for the said purpose, it was desirable to continue with the
Concession Agreement. Interim direction was "If the matter is brought to
the notice of the Board of Directors, it will consider the same in accordance
with law and the order dated 8th April, 2019 passed by this Appellate
Tribunal. IA stands disposed of". The reference of order dated 8th April,
2019 was not for purpose of referring to restrain in cancelling of any
Agreement by the NHAI, rather reference to 8th April, 2019 order was with
regard to the earlier part of the order where Union of India was directed to
file an affidavit with regard to declare 'Green Entity' or 'Amber Entity' or
'Red Entity'. Thus, in order dated 23rd October, 2019, the interim direction
passed on 8th April, 2019 restraining the NHAI not to take any step to
cancel the Agreement was not continued. We thus are not persuaded to
submission of Shri Ramji Srinivasan that order dated 23rd October, 2019
continued the restraint order, which was passed against the NHAI from
taking any action to cancel the Agreement.
13. Learned Counsel for the parties have raised the submission and
counter submissions with regard to allegations made in the Termination
Interlocutory Application No.2908 of 2021 in Company Appeal (AT) No. 346 of 2018 9 Notice dated 21st December, 2021. We are of the view that in this
Application, we are not required to adjudicate the factual dispute between
the parties or return any finding as to whether Termination Notice was
issued on sufficient ground or not. The remedy of the Applicant lies
elsewhere. The Applicant is entitled to seek remedy against actions of the
NHAI as per the Concession Agreement dated 22nd March, 2005. We thus
are not inclined to entertain the challenge to Notice dated 21st December,
2021 on merits in the present proceedings. It is, however, relevant to notice
that as per the affidavit filed on behalf of Union of India and directions
issued in this Appeal by this Tribunal from time to time, it is clear that
Resolution Process of IL&FS Group Company is at the final stage and as
submitted by learned Counsel for the Applicant, it is likely to be completed
before 31st March, 2021. In so far as submission raised by learned Counsel
for the lenders is concerned that by termination of Concession Agreement,
they shall be unable to recover their debt, when we are not entertaining the
application at the instance of the Applicant, who is directly aggrieved by
Termination Notice dated 21st December, 2021, the claim of lenders needs
no consideration. On the submission made by learned Counsel for the
lenders, we are not inclined to entertain this Application.
14. In view of the foregoing, we are of the view that I.A. No.2908 of 2021
does not deserve to be entertained and decided in these proceedings. I.A.
No.2908 of 2021 is dismissed. The interim order dated 23rd December,
2021 passed in this Application is discharged. However, looking to the fact
that the Resolution of IL&FS Group Companies including the Applicant is
Interlocutory Application No.2908 of 2021 in Company Appeal (AT) No. 346 of 2018 10 in critical stage and may be completed by 31st March, 2021, we further
direct that Termination Notice dated 21st December, 2021 issued by NHAI
be implemented with effect from 1st April, 2021. Subject to direction as
above, the I.A. No.2908 of 2021 is dismissed.
[Justice Ashok Bhushan] Chairperson
[Dr. Alok Srivastava] Member (Technical)
NEW DELHI
16th March, 2022
Ash/NN
Interlocutory Application No.2908 of 2021 in Company Appeal (AT) No. 346 of 2018 11
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free