Union Bank Of India Erstwhile ... vs Mr. Dinkar T. Venkatasubramanian
- CitationCompany Appeal (AT) (Insolvency) No.729 of 2020
Ratio decidendi
The rule this decision rests on
The Resolution Professional's direction to the financial creditor to continue a non-fund based (LC/BG) facility during the CIRP, to keep the corporate debtor a going concern, makes the payments made to the suppliers under those instruments part of the insolvency resolution process costs; such amounts therefore cannot be deducted from the financial creditor's distribution under the approved resolution plan. A Resolution Professional's duty under Sections 20 and 25 to manage the corporate debtor as a going concern does not permit him to leave the characterisation of such CIRP-period expenditure to the Committee of Creditors as interim finance or as a deductible item; it is his duty to determine and pay insolvency resolution process costs in accordance with Section 53(1)(a), and the Committee of Creditors' power under Section 30(4) to fix the distribution does not extend to deducting CIRP costs from an allotment under the approved plan. Section 17(1)(d) of the Code requires a financial institution maintaining the corporate debtor's accounts to act on the instructions of the interim resolution professional only in relation to the management of those accounts; it does not authorise the resolution professional to compel the institution to continue a non-fund based facility, so non-compliance with such a direction is not, by itself, a contravention of Section 17(1)(d).
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
S. CONTENTS PARA PAGES NO.
1. Factual Background 3 3
2 Appellants Submission 7 4
3 Respondent no.1 Submission (RP) 8 8
4 Rejoinder of Appellant against the reply of RP 9 21
5 Analysis 10 29
6 Findings 10.20 41
7 Order 45
Company Appeal (AT) (Insolvency) No. 729 of 2020 NATIONAL COMPANY LAW APPELLATE TRIBUNAL PRINCIPAL BENCH, NEW DELHI
Company Appeal (AT) (Insolvency) No. 729 of 2020
[Arising out of Impugned Order dated 09 July, 2020, passed by the Adjudicating Authority/National Company Law Tribunal, Chandigarh Bench, Chandigarh in IA No. 222/2020 in Company Petition (IB) No.42/Chd./Hry./2017 (admitted)]
IN THE MATTER OF: Union Bank of India (Erstwhile Corporation Bank) Stressed Assets Management Vertical Overseas Branch M - 93, Connaught Place New Delhi - 110001 Appellant
Versus
1. Mr Dinkar T. Venkatasubramanian Resolution Professional of Amtek Auto Limited EY Restructuring LLP Golf View Corporate Tower B Sector - 42, Gurugram, Haryana Respondent No.1
2. DVI PE (Mauritius) Ltd A company under the laws of the Republic of Mauritius Having its Registered Office at: IQ EQ Fund Services (Mauritius) Limited 33 Edith Cavell Street Port Louis 11324 Through his Counsel Mr Himanshu Gupta Advocate 215 C, Sector 4, MDC, Panchkula Respondent No.2
3. Deccan Value Investors L P A Limited Liability Partnership Incorporated in Delaware USA Having its registered office at: 850, New Burton Road Suite 201, Dover Delaware 19904, USA Through his Counsel Mr Himanshu Gupta Advocate 215 C, Sector 4, MDC, Panchkula Respondent No.3
Company Appeal (AT) (Insolvency) No. 729 of 2020 1 of 46 Present: For Appellant : Mr Gopal Jain, Sr Advocate with Mr Alok Kumar, Mr Manan Gambhir, Mr Nikhil Malhotra and Ms Garima Soni, Advocates.
For Respondent : Mr Sanjay Bhatt, Mr Karan Kohli and Ms Niharika Sharma, Advocates for R1. Mr Chanakya Keswani and Mr Dinesh Pednekar, Advocates for R2 & 3.
Glossary
IRP Interim Resolution Professional NCLT National Company Law Tribunal NCLAT National Company Law Appellate Tribunal I&B Code/ Code Insolvency and Bankruptcy Code CIRP Corporate Insolvency Resolution Process ICD Insolvency Commencement Date CoC Committee of Creditors LC Letter of Credit LHG Liberty Housing Group CD Corporate Debtor
CORAM: Hon'ble Mr Justice M. Venugopal, Member (J) Hon'ble Mr V. P. Singh, Member (T) Hon'ble Dr Alok Srivastava, Member (T)
J U D G M E N T
(Virtual Mode)
[Per; V. P. Singh, Member (T)]
1. The present Appeal emanates from the Order of the Adjudicating
Authority/National Company Law Tribunal, Chandigarh Bench, Chandigarh
dated 09 July 2020, passed in IA No. 222/2020 filed U/S 60(5) of the
Insolvency and Bankruptcy Code, 2016 (in short 'I&B Code') in Company
Petition (IB) No.42/Chd./Hry./2017.
Company Appeal (AT) (Insolvency) No. 729 of 2020 2 of 46
2. The Parties are represented by their original status in the Company
Petition for the sake of convenience.
Factual Background
3. The Appellant (Union Bank of India) Financial Creditor applied for
initiation of Corporate Insolvency Resolution Process under Section 7 of the
Insolvency and Bankruptcy Code, 2016 against Corporate Debtor (Amtek
Auto Limited). The Adjudicating Authority admitted the petition and
appointed Shri Dinkar T. Venkatasubramanian as the Interim Resolution
Professional (IRP).
4. Corporation bank, a Financial Creditor of the Corporate Debtor, now
known as Union Bank of India, filed an Application, IA No 222/2020, seeking
direction for modification of the Approved Resolution Plan of Respondent No.
2 and 3, in compliance with Regulations 42 and 44 of the liquidation Process
Regulation 2016 for not deducting ₹ 34 crores from the final payment to be
made to the Applicant/Appellant as per the scheme of distribution from out
of the amount under the Resolution Plan was rejected. Therefore, feeling
aggrieved by the said Order, the present Appeal is filed.
5. Respondent No. 1 is the Resolution Professional of the CD1, and
Respondents 2 & 3 are jointly the Successful Resolution Applicants.
6. Corporation Bank, a Financial Creditor of the Corporate Debtor, now
known as Union Bank of India, filed the instant IA 222 of 2020 on 12 March
2020 against the Resolution Professional of the Corporate Debtor (Respondent
1 corporate debtor Company Appeal (AT) (Insolvency) No. 729 of 2020 3 of 46 No. 1) and Successful Resolution Applicant 2, (Respondent No. 2 & 3), under
Section 60 (5) (c) of the I&B Code read with Rule 11 of the NCLT Rules seeking
the following directions/reliefs:
a. Allow the instant Application filed by the Applicant and direct the IRP to get the Resolution Plan modified so as to comply with Regulation 42 and 44 of the Liquidation Process Regulation 2016;
b. direct the Respondent Resolution Professional to not to deduct the amount of ₹ 34 crores from the final payment to be made to Applicant as per the scheme of distribution of amount under Resolution Plan; and
c. direct the Respondent Resolution Professional to further include amount of ₹ 6,22,58,072.64 towards LC payments and ₹ 61,39,000 towards Bank Guarantee (BG) payments and the total admitted claim of the Applicant.
7. Appellants Submission
7.1 The Appellant contends that Respondent No.1 erroneously denied the
Appellant's a claim of ₹ 39,61,54,488 towards Non-Fund Based Facility3
despite actively operating the bank accounts of the Corporate Debtor and
being well aware of all the financial transactions, including the fact that the
NFB Facility falls well within the definition of financial debt under Section
5(8)(h) of the IBC. The fact that Respondent No.1 was operating the bank
account of Corporate Debtor can be seen from the documents, Annexure 4-5
at Pg. 111 of the Appeal Paper book.
2 SRA 3 NFB
Company Appeal (AT) (Insolvency) No. 729 of 2020 4 of 46 7.2 The Appellant is one of the dissenting Secured Financial Creditors
allotted the 'Liquidation value as per the allocation sheet and, therefore,
approved by the CoC. The claim of Rs. 39.61 crores were erroneously rejected
by the IRP only because the same was not crystallised.
7.3 Respondent No.1 /RP had been regularly giving instructions regarding
debiting a cash credit account as and when any LC/BG4 is presented before
the Appellant for payment and in case of issuance of any fresh LC/BG (NFB
Facility). This admitted arrangement between the Appellant and Respondent
No.1 is reflected in the letter dated 08.08.2017, annexed as Annexure A-5 at
Pg. 111 of the Appeal Paper book.
7.4 In any event, all the payments were made directly to the
supplier/vendor /beneficiary of the NFB Facility by debiting the cash credit
account of the Corporate Debtor. No amount has been credited towards the
loan account of the Corporate Debtor. It is reiterated that the payments were
made directly to the vendors, and no amount was appropriated or adjusted
by the Appellant towards any outstanding claim under CIRP. Therefore, the
Appellant has not done unjust enrichment by alleged recovery of ₹ 33.34
crores from the Corporate Debtor during the CIRP.
7.5 It is also clearly admitted by Respondent No.1 that the NFB Facility has
been issued in favour of the beneficiary/vendors for the purchase of various
types of steels and other alloys. However, despite this admitted fact,
Respondent No.1 failed to appreciate that the Corporate Debtor is liable to
4 Letter of Credit Bank Guarantee
Company Appeal (AT) (Insolvency) No. 729 of 2020 5 of 46 pay the suppliers/beneficiaries during the CIRP period. The Appellant did the
same by debiting the cash credit account of the Corporate Debtor as
instructed by Respondent No. 1. Therefore, the payments consequently made
to such beneficiaries by debiting the Corporate Debtor's account are
misconceived as recovery towards the dues.
7.6 It is further submitted that since 'LHG'5 failed to fulfil the condition in
the Resolution Plan to provide a cover for equivalent amount from a scheduled
bank in the event, it intends to avail the NFB Facility, the Appellant
specifically mentioned in its letter dated 24.10.2018 that any provision
concerning the NFB Facility will be subject to the fulfilment of the condition
mentioned in the Resolution Plan. The letter dated 24.10.2018 is annexed as
Annexure 4-6 at Pg. 149 of the Appeal Paper book.
7.7 On perusal of the letter dated 30.10.2018 sent by Respondent No. 1 to
the Appellant, it is clear that Respondent No.1 was aware that the NFB Facility
limits were subject to covering the limit by another scheduled commercial
bank. This is in line with the discussions with LHG6 and is also mentioned in
the Resolution Plan. The letter dated 30.10.2018 is marked in the Reply filed
by Respondent No.1 at pg. 45.
7.8 The Appellant references the letter dated 30.10.2018, i.e. Email dated
21.11.2018 sent by Corporate Debtor regarding the Continuance of NFB
Facility of Rs. 43 Crores (NFB Limits) in the capacity of the person-in-charge
5 Liberty House Group 6 Liberty House Group
Company Appeal (AT) (Insolvency) No. 729 of 2020 6 of 46 for the management of the Corporate Debtor, and Respondent No. 1 addressed
himself as the Insolvency Professional in the said Email. The said Email is
annexed in the Reply filed by Respondent No.1, Resolution Professional,
Annexure R, at Pg.49.
7.9 Further, Respondent No.1, in its Reply, has mentioned that there was
no reservation shown or recorded in the CoC minutes on behalf of the
Appellant. Therefore, the CoC meeting dated 07.02.2020 records the
objections raised by the Appellant at para (n) of the CoC meeting. On the
contrary, Respondent No. 1 misrepresented the CoC by giving it a colour of
recovery of LCs made by Appellant from the Corporate Debtor during CIRP.
Based on the incorrect information about the interim finance, the claim of ₹
34 Crores towards LC7 got rejected, despite that the amount was directly paid
to the vendors of the Corporate Debtor from the current account under the
specific instructions of Respondent No. 1 to keep the Corporate Debtor a going
concern.
7.10 Further, the Appellant had also objected vide its letter dated 20.02.2020
to the acts of Respondent No. 1 and made it clear that the LCs availed by the
Corporate Debtor is like a contingent liability. Therefore, the amounts were
being paid directly to the vendors/suppliers of the Corporate Debtor by the
Appellant.
7.11 But Respondent No. 1 misled the CoC by not placing all the facts and
records. In particular, his various requests for debiting the current account
7 Letter of Credit
Company Appeal (AT) (Insolvency) No. 729 of 2020 7 of 46 of Corporate Debtor or issuance of fresh NFB Facility. Furthermore,
Respondent No.1 had also misled the CoC by stating that the Appellant had
made a recovery of ₹ 34 Crores when the vendors of the Corporate Debtor
were the ultimate beneficiaries under the NFB Facility. Therefore, the decision
taken by the CoC is based on the incorrect information provided by
Respondent No.1.
7.12 The Adjudicating Authority failed to consider that the Appellant, a
dissenting Financial Creditor, is entitled to liquidation value according to
Section 53 of the IBC. Therefore, it did not comply with Regulations 42 & 44
of the IBC (Liquidation Process) Regulations, 2016.
7.13 The Adjudicating Authority vide its Impugned Order observed that the
Appellant has not objected to the said actions of Respondent No.1 in the CoC
meetings, contrary to the materials placed before the Adjudicating Authority.
Furthermore, the Appellant had refuted the actions of Respondent No. 1 vide
its Email dated 20.02.2020, which the Adjudicating Authority has overlooked.
Therefore, the Adjudicating Authority has misconstrued the payments made
to the beneficiaries/vendors as recovery by the Appellant and dismissed the
IA. No. 222 of 2020 in CP (IB) in CP (IB) No. 42/Chd./Hry./2017 without any
application of mind.
RESPONDENT NO.1. RESOLUTION PROFESSIONAL's SUBMISSION
8. Respondent No.1 submits that the captioned Appeal is not
maintainable, entirely misconceived and devoid of any substance in facts or
law.
Company Appeal (AT) (Insolvency) No. 729 of 2020 8 of 46
a) The Appellant itself filed the Application under Section 7 of the
Insolvency & Bankruptcy Code, 2016 (hereinafter, "IB Code") seeking
initiation of the Corporate Insolvency Resolution Process (hereinafter,
"CIRP") under the IB Code in respect of Amtek Auto Limited (hereinafter,
"Corporate Debtor" and/or "AAL") and Respondent was appointed as
IRP/RP.
b) During CIRP, Respondent made the Public Announcement on
29.07.2017. Pursuant to the Public Announcement, the Appellant filed
its proof of claim under Form C dated 04.08.2017 as on the insolvency
commencement date (hereinafter, "ICD"), for an aggregate amount of ₹
876,42,09,926/-. In the said claim, the Appellant claimed an amount
of ₹ 39,61,54,488/- under the Non-Fund based Letter of Credit Bank
Guarantee facility (from now on, "NFB Facility"). Respondent RP on
verification and collation of the claim filed by the Appellant in terms of
the provisions of the IB Code and the Insolvency and Bankruptcy Board
of India (Insolvency Resolution Process for Corporate Persons)
Regulations 2016 (from now on, the "CIRP Regulations") verified an
amount of ₹ 836,80,55,438/- as 'financial debt' of the Appellant. The
Appellant was included as a member of the Committee of Creditors
(from now on, "CoC") and was assigned voting right of 6.64% in the CoC
based on its financial debt.
c) The Appellant did not challenge the non-verification of the said
uncrystallised amount and thus accepted the same. The Corporate
Debtor did not receive any material during the CIRP on account of these
Company Appeal (AT) (Insolvency) No. 729 of 2020 9 of 46 uncrystallised LCs, and thus the said un-crystallised amount never
became a "financial debt". A copy of the proof of claim dated 04.08.2017
filed by the Appellant is already produced on record by the Appellant
(Annexure A-3 at 91-99 of the captioned Appeal).
d) Respondent RP in terms of the duty cast under Section 20 & 25
of the IB Code to continue and maintain the business of the Corporate
Debtor as a going concern, requested the Appellant to continue and
maintain the NFB Facility limits at the current level as being drawn by
the Corporate Debtor prior to the insolvency commencement date. The
said request was made on account of the business requirement of the
Corporate Debtor. The Corporate Debtor is engaged in manufacturing,
fabrication, and engineering automotive parts. As part of its said
business, it is required to purchase various types of steel and other
alloys. As per the existing market practice, the purchase and
procurement of steel and alloys is always backed by Letters of Credit
Bank Guarantee issued by the purchaser's Bank in favour of the
beneficiary vendor, and thus the continuation of the NFB Facility by the
Appellant was very much needed as a lifeline for the continuation of the
business of the Corporate Debtor as a going concern.
e) That upon the request made by the Answering Respondent/ RP,
the Appellant agreed to continue the NFB Facility at an existing level as
granted to the Corporate Debtor. On the basis of such understanding,
during the CIRP period, the Appellant from time to time issued various
Letters of Credit Bank Guarantee on behalf of the Corporate Debtor
Company Appeal (AT) (Insolvency) No. 729 of 2020 10 of 46 under the said NFB Facility and on devolvement of them used to deduct
the amount from the collection account of the Corporate Debtor
maintained with them acting as the Financial Institution under Section
17(d) of the IB Code and issue fresh Letters of Credit Bank Guarantee
against the available limit of NFB Facility during the CIRP.
f) By the provisions of the IB Code, a resolution plan submitted by
Liberty House Group Pvt. Limited (from now on, "LHG") was put to
electronic voting by the CoC of the Corporate Debtor in the meeting held
on 02.04.2018 and was approved via e-voting concluded on
05.04.2018. In pursuance of it, the Answering Respondent /RP filed an'
Application, being CA No.114 of 2018 under Section 30(6) & 31(1) of the
IB Code for approval of the resolution plan of 'LHG' before the Ld. NCLT
on 16.04.2018. The Ld NCLT approved the LHG Resolution Plan vide
Order dated 25.07.2018. Later on, LHG defaulted in the implementation
of the Resolution Plan.
g) During the implementation of the LHG resolution plan, the
Appellant, in a high handed and unreasonable manner vide letter dated
24.10.2018, asked the Answering Respondent to get the NFB Facility
covered/backed by a comfort letter/ guarantee by a scheduled
commercial bank despite the fact that during that time the Answering
Respondent was only acting as the Insolvency Professional and the
management of the Corporate Debtor was vested with the Monitoring
Committee constituted under the LHG Resolution Plan.
Company Appeal (AT) (Insolvency) No. 729 of 2020 11 of 46
h) The Respondent/RP responded to the said letter sent by the
Appellant vide letter dated 30.10.2018 and requested the Appellant to
continue the NFB Facility without insisting on the condition as
stipulated till the resolution plan of LHG is implemented. It was also
pointed out that withdrawal of the NFB Facility at that stage would hurt
the operations of the Corporate Debtor as a going concern. A copy of
the letter dated 30.10.2018 issued by the Answering Respondent is
already attached in Annexure R-1.
i) The Appellant, without responding to the said request by
misusing its power and position, imposed auto-debit instructions and
started debiting the collection account of the Corporate Debtor
maintained by it as 'Financial Institution for any devolvement of Letter
of Credit/ Bank Guarantee and made recovery of an aggregate amount
of ₹ 33.34 Crores. Monthly details of Letters of Credits (from now on,
"LCs") opened by the Appellant against deductions for LCs made from
the Corporate Debtor during CIRP are already annexed with the reply
of RP.
j) This unexpected act on the Appellant led to extreme hardship for
the Corporate Debtor to keep up its performance due to this unexpected
reduced working capital at hand. More pertinently, the time during
which the Appellant took this action was when the Corporate Debtor
needed the working capital most due to higher than average sales in the
auto sector on account of the festive season. However, the Corporate
Debtor could not take advantage of the same due to the unexpected
Company Appeal (AT) (Insolvency) No. 729 of 2020 12 of 46 action of the Appellant and lack or non-availability of working capital
to procure the raw material on a timely basis. It is also evident from the
dip in revenues of the quarter ending 31.12.2018, amounting to
approximately INR 261 crores instead of the revenue generated in the
quarter ended 31.09.2018.
k) That alarmed by such arbitrary act on the part of the Appellant
and the continuous fall in the performance of the Corporate Debtor, the
Respondent/RP immediately rushed and convened a meeting with the
Managing Director and the General Manager of the Appellant at the
head office of the Appellant at Mangalore on 21.11.2018 and discussed
the situation caused by such arbitrary action on the part of the
Appellant.
l) That after the meeting, it was agreed that (a) out of the total sanctioned
limit of ₹ 43.00 Cr, ₹ 29.08 Cr, which had been utilised as on date, will
be protected and revolved; (b) No auto-debit for payments of the
outstanding LCs as of 21.11.2018 for ₹ 29.08 Cr. until fresh LCs are
opened; and (c) Concerning the un-utilised limit of ₹ 14 Cr, further
discussion will take place.
m) It is pertinent to note that while it was agreed that further
discussion on the unutilised limit of INR 14 crores would be held,
however, the same never materialised, which led to a reduction of -33%
in the LC limit available with the Corporate Debtor for procurement of
raw material thereby further imposing unnecessary pressure on
Company Appeal (AT) (Insolvency) No. 729 of 2020 13 of 46 working capital and thus disrupting operations. The Answering
Respondent conveyed the aforesaid decision to the concerned branch of
the Appellant with a request not to enforce auto-debit instructions from
the collection account maintained with them under Section 17(d) of the
IB Code. The Answering Respondent further followed it up again vide
Email dated 26.11.2018. Vide letters dated 21.11.2018 and
26.11.2018, the Respondent in his capacity of the Resolution
Professional directed the Appellant to not deduct any amount from the
collection account of the Corporate Debtor maintained with it during
the CIRP suo-moto. The extracts of the letter are reproduced below:
"Post the meeting between Resolution Professional and the MD and GM of the Corporation Bank on 21 November 2018, the RP's office had issued the below mail and signed letter regarding the agreements in the afore- mentioned meeting, to the Circle office in Delhi. As discussed, request you to kindly not initiate any debit (Auto/Manual) of the outstanding amount for the utilised limits of LC as on 22 November 2018 and also support us with issuance of fresh LC's, which is of paramount importance for treasury operations at Amtek Auto Limited.
Also, please let us know in case there is any disconnect in understanding regarding the aforesaid subject matter.
Your continued support in this regard is well appreciated." (verbatim copy)
Company Appeal (AT) (Insolvency) No. 729 of 2020 14 of 46
A copy of the Email dated 21.11.2018 and dated 26.11.2018 sent
by the Answering Respondent to the Appellant is already attached
in Annexure R-1, respectively.
n) However, despite having arrived at the understanding with the
highest level with the Appellant, the Appellant, without any further
communication to the Answering Respondent, arbitrarily and in a high
handed manner, withdrew the NFB Facility granted to the Corporate
Debtor while making recovery of a further amount of ₹ 33.34 Crores
from the collection account of the Corporate Debtor maintained with it
during the CIRP by misusing its power as Financial Institution under
Section 17(d) of the IB Code contrary to the instructions of the
Respondent/RP.
o) The Respondent/RP vehemently protested and objected to the
withdrawal of the NFB facility by the Appellant vide letter/ email dated
14.12.2018. On account of the illegal and unauthorised recoveries
being made by the Appellant and to prevent further loss of working
capital, the Answering Respondent was forced to stop the usage of the
collection account with the Appellant and use another account with
Axis Bank Limited for collections starting from December 2018. This
caused an undue burden on the Corporate Debtor during the already
uncertain times to change the collection account with 43 domestic and
international customers. Furthermore, this entire exercise made the
Corporate Debtor susceptible to certain cyber fraud, which was
eventually identified at an early stage, and its after-effects
Company Appeal (AT) (Insolvency) No. 729 of 2020 15 of 46 were nullified because of the Responding Appellant's proactive
intervention and coordination with multiple institutions. A copy of the
letter/email dated 14.12.2018 sent by the Answering Respondent to the
Appellant is already attached in Annexure R-1.
p) The aforesaid arbitrary, illegal and highhanded actions of
recovery of ₹ 33.34 Crores by the Appellant during the continuation of
the moratorium under the IB Code left the Corporate Debtor high and
dry with an almost negligible amount of working capital or cash in hand
to operate as a going concern.
q) Respondent RP further submitted that the tall claims of support
to the Corporate Debtor during the CIRP averred by the Appellant are
very hollow as the result of the illegal action taken by the Appellant is
recovery/unjust enrichment ₹ 33.34 Crores from the Corporate Debtor
during the CIRP contrary to mandate under Section 17(d) of the IB Code
and prohibited under Section 14 of the IB Code.
r) Respondent RP duly brought the action above of illegal recovery
of ₹ 33.34 Crores made by the Appellant from the Corporate Debtor to
the knowledge of the CoC from time to time. To cover up and avoid
any consequences under the IB Code for such an illegal act of
recovery, the Appellant urged the rest of the members of the CoC
to treat the unlawful recoveries made by it as interim finance. On
being asked, the Answering Respondent, in all fairness and
independence as is expected from an Insolvency Professional under
the IB Code, suggested two options to the CoC to either treat the
Company Appeal (AT) (Insolvency) No. 729 of 2020 16 of 46 illegal recovery made by the Appellant as an 'interim finance' under
the IB Code or accent to deduction of the amount of illegal recovery
made by the Appellant out of distribution amount payable to the
Appellant under the resolution plan submitted by the Respondent No.
2 & 3 in the instant Appeal. Accordingly, the CoC (which includes the
Appellant with its voting share of 6.64%) on deliberation consented to
deduction of the said amount from the distribution amount payable to
the Appellant under the resolution plan submitted by Respondent No.
2 & 3 in the 30th and 31st meeting of the CoC held on 05.02.2020 and
07.02.2020, respectively. This treatment led to an increase in the
Appellant's admitted debt and voting share to 7.72%. A perusal of the
minutes above filed by the Appellant (Refer Annexure A-7 at Page 151-
161 of the instant Appeal) itself shows that no reservation of any kind
was shown or recorded in the said minutes on behalf of the Appellant.
s) Respondent further submits that it had no intention to make any
harsh statements against the Appellant but was forced to do so. Despite
having admittedly made a recovery during the moratorium from the
Corporate Debtor, the Appellant still had the audacity to approach the
Ld. NCLT by filing the Application being IA. No. 222 of 2020 seeking
reliefs against the Respondent/RP for not deducting the illegally
recovered amount by the Appellant from the amount to be distributed
to it in terms of the resolution plan submitted by the Respondent No. 2
& 3 for approval by the Ld. NCLT.
Company Appeal (AT) (Insolvency) No. 729 of 2020 17 of 46
t) The Ld. NCLT, after elaborately hearing the Appellant and the
Answering Respondent and while passing the Order dated 09.07.2020,
took note of the fact that the Appellant accented to deduction of the
amounts of ₹ 33.34 Crores and, in fact, nowhere disputed the
distribution of amounts payable to the Appellant being a 'dissenting
creditor' under the terms of the resolution plan of Respondent No. 2 &
3. The relevant part of the Order dated 09.07.2020 reproduced
hereunder:
"7. The decisions of the Committee of Creditors passed with the required majority percentage as per the Code, are Binding On all the stakeholders, including the dissenting members of Committee of Creditors, if any. No member of the Committee of Creditors, after a resolution plan was approved by the Committee of Creditors with the required majority percentage, on one ground or other, cannot challenge the said decisions of the Committee of Creditors. It is for the Adjudicating Authority to apply its judicious mind whether a particular plan submitted for its approval is in compliance of the provisions of the Code and the Regulations made thereunder. The Applicant even in its rejoinder; to the Reply filed by the Resolution Professional, has not denied the fact of deliberations and acceptance of the action of the Resolution Professional for deducting the amount of Rs.34 Crores and for distribution of amount payable to the Applicant under the Resolution Plan of DVI, by the Committee of Creditors, wherein the Applicant is a member.
Company Appeal (AT) (Insolvency) No. 729 of 2020 18 of 46
8. In the circumstances and for the aforesaid reasons, we do not find any merit in the IA and accordingly, the same is dismissed."
u) Respondent RP states that Appellant did not challenge the
decision taken by the CoC in the 30th and 31st meeting of the CoC held
on 05.02.2020 and 07.02.2020 before the Ld. NCLT and confined its
challenge against the Respondent/RP only despite knowing very well
that the decision to make a deduction of ₹ 33.34 Crores from the
proceeds payable to the Appellant under the Resolution Plan of the
Respondent No. 2 & 3 was taken by the CoC and not the
RP/Respondent; the current challenge deserves to be rejected. It is
further surprising that the Appellant has chosen to not even array the
CoC as a party in the instant Appeal. Section 30(4) of the IB Code casts
supervising distribution amongst all creditors, and the resolution
professional has no say in that. Section 30(4) of the IB Code is
reproduced hereunder for the sake of easy reference of this Hon'ble
Appellate Tribunal:
"(4) The Committee of creditors may approve a resolution plan by a vote of not less than sixty-six per cent. of voting share of the financial creditors, after considering its feasibility and viability, the manner of distribution proposed, which may take into account the Order of priority amongst creditors as laid down in sub- section (1) of section 53, including the priority and value of the security interest of a secured creditor and such other requirements as may be specified by the Board..."
Emphasis Supplied
Company Appeal (AT) (Insolvency) No. 729 of 2020 19 of 46
v) The Hon'ble Supreme Court in the case of Committee of
Creditors of Essar Steel India Limited Through Authorized
Signatory Vs. Satish K. Gupta & Ors. [(2019) SCC Online SC 1478]
in Para 64 of Judgment and Order has reinforced the said position and
has held as under:
"Thus, what is left to the majority decision of the Committee of Creditors is the "feasibility and viability" of a resolution plan, which obviously takes into account all aspects of the plan, including the manner of distribution of funds among the various classes of creditors. As an example, take the case of a resolution plan which does not provide for payment of electricity dues. It is certainly open to the Committee of Creditors to suggest a modification to the prospective resolution applicant to the effect that such dues ought to be paid in full, so that the carrying on of the business of the corporate debtor does not become impossible for want of a most basic and essential element for the carrying on of such business, namely, electricity. This may, in turn, be accepted by the resolution applicant with a consequent modification as to distribution of funds, payment being provided to a certain type of operational creditor, namely, the electricity distribution company, out of upfront payment offered by the proposed resolution applicant which may also result in a consequent reduction of amounts payable to other financial and operational creditors. What is important is that it is the commercial wisdom of this majority of creditors which is to determine, through negotiation with the prospective resolution applicant, as to how and in what manner the corporate resolution process is to take place."
Company Appeal (AT) (Insolvency) No. 729 of 2020 20 of 46 w) In the present case, the Resolution Plan submitted by the
Respondent Nos. 2 & 3 is silent on the manner of distribution to
dissenting creditors. Even otherwise, it is the CoC and not the
Resolution Professional of the Corporate Debtor who is cast with the
duty to decide and supervise the manner of distribution inter-se
creditors. Therefore, the alleged grievance of the Appellant being a
member of the CoC itself against the Answering Respondent is not only
wholly misconceived but contrary to law. The Hon'ble Supreme Court
in Swiss Ribbons Private Limited Vs. UOI (2019) SCC Online SC 73]
has categorically held that the resolution professional is a facilitator of
the resolution process, whose administrative functions are overseen by
the CoC and the Ld. NCLT.
9. Rejoinder of Appellant against the Reply of the Resolution
Professional
a) In its rejoinder to the Reply of the Resolution Professional, the
Appellant vehemently denied that the Appellant accepted the non-
verification of the un-crystallised amount. On the contrary, the
Appellant was denied the claim towards ₹ 39,61,54,488 towards Non-
Fund Based LC/BG Facilities, which by operation of law is a Financial
Debt. Therefore, it is clear that Respondent No.1 is taking a
contradictory stand. On the one hand, the submission of Respondent
No.1 is that the Non-Fund Based LC/BG doesn't become a Financial
Debt due to non-crystallisation.
Company Appeal (AT) (Insolvency) No. 729 of 2020 21 of 46
b) On the other hand, Respondent No. 1 submits that when the said
LC/BG devolves, the same becomes the obligation of the Appellant. It
is further denied that the said un-crystallised amount never became a
'financial debt. It is also explicitly denied that the Corporate Debtor did
not receive any material during the CIRP because of the un-crystallised
Non-Fund Based Facility. In the case of alleged non-receipt of goods,
the same was to be taken up with the supplier of the goods and not the
Bank who has issued the LC at the request of Respondent No.1. It is
submitted that Respondent No. 1 was actively operating the bank
accounts of the Corporate Debtor and was well aware of all financial
transactions, including the fact that the NFB Facility falls well within
the definition of financial debt under Section 5 (8) (h) of the IBC.
c) The Section 5 (8) (h) of the IBC provides the following:
"Section 5 (8): "financial debt" means a debt along with interest, if any, which is disbursed against the consideration for the time value of money and includes -
(h) any counter-indemnity obligation in respect of a guarantee, indemnity, bond, documentary letter of credit or any other instrument issued by a bank or financial institution;".
(c) The Appellant denied that there was an understanding between
the Appellant and the Respondent No. 1 that as and when the LC/BG
would devolve, the same will be paid directly to the beneficiary from the
current account of the Corporate Debtor and fresh LC/BG will be issued
as and when the request for the same was made by Respondent No. 1
Company Appeal (AT) (Insolvency) No. 729 of 2020 22 of 46 for which the amount would be debited from the current account of the
Corporate Debtor. Further, as and when any fresh LC/BG was to be
issued, the same was done on the specific request of Respondent No. 1.
This admitted arrangement is reflected in the documents annexed as
Annexure A-5 on page 111 of the Appeal.
d) The Respondent has clearly admitted that the LCs/ BGs have
been issued in favour of the beneficiary/vendors to purchase various
types of steels and other alloys. However, the respondent has failed to
appreciate that the Corporate Debtor is liable to pay the
suppliers/beneficiaries under the LCs/BG during the ÇIRP period. The
payments consequently made to such beneficiaries by debiting to the
Corporate Debtors accounts have been misconceived as recovery
towards our dues and thereby caused huge loss to the Applicant in
denying the claim.
e) It is submitted that Liberty House Group was selected as a
successful Resolution Applicant and the approved Resolution Plan had
a condition that the Resolution Applicant will provide a cover of an
equivalent amount from a scheduled bank in the event it intends to
avail NFB LC/BG Credit facilities and the same was intimated to the
IRP on 24.10.2018 which the Resolution Plan failed to fulfil. Copy of the
letter dated 24.10.2018 has been annexed and marked in the Appeal as
Annexure A-6 (Pg. 149 to Pg. 150).
Company Appeal (AT) (Insolvency) No. 729 of 2020 23 of 46
f) It is vehemently denied that the Appellant acted in a high-handed
manner. Further, upon perusal of the letter dated 30.10.2018 (page 45
of the Reply of the Respondent No. 1) written by Respondent No. 1 to
the Appellant, it is amply clear that Respondent No. 1 had accepted that
the NFB limits be subject to covering the limit by another scheduled
commercial bank which is in line with the discussions with the
Resolution Applicant and has also been mentioned as a part of
Resolution Plan. Further, it is also denied that Respondent No.1 was
only acting as the Insolvency Professional, and the management of the
Corporate Debtor was vested exclusively with the Monitoring
Committee. Further, the Email dated 21.11.2018 referred to the letter
dated 30.10.2018 sent by Amtek Auto Limited regarding the
Continuance of LC/BG Facilities of ₹ 43 Crores (NFB Limits) in the
capacity of the person-in-charge for the management of the Corporate
Debtor, and Respondent No. 1 addressed himself as the Insolvency
Professional in the said Email dated 21.11.2018. Copy of the Email
dated 21.11.2018 has been annexed and marked in the Reply filed by
Respondent No.1 as Annexure R-1 (Page 49).
g) It is submitted that while honouring the LCs/BGs issued on
behalf of the Corporate Debtor, the Appellant being the Financial
Creditor, had not unduly enriched itself. It is further reiterated that no
amount has been credited towards the loan account of the Corporate
Debtor, and the debits are relating to the payment made to the
supplier/vendor /beneficiary of LC/BG. Therefore, it is incorrect to say
Company Appeal (AT) (Insolvency) No. 729 of 2020 24 of 46 that the appellants have made a recovery of ₹ 33.34 Cr. On the contrary,
the said LCs/BGs have been issued during the CIRP period, and the
same ought to have been considered the CIRP cost because the
Corporate Debtor had received the goods under the said LCs and BGs
during the CIRP period. Therefore, the Corporate Debtor is liable to pay
the suppliers under IBC 2016.
h) The averment made by Respondent No.1 is bald, unsupported
and on the face of it unsustainable. It is submitted that in case of the
festive season which is during October/November in any given year, for
the sales to be successful the raw material required by the Automobile
companies are always supplied well in advance or a few months in
advance to the festive season and not at the time of the season.
Moreover, the admission on the part of the respondent in availing
working capital, not treating the same as preferential debt, non-
arranging the appropriate action in raising the fund and denial of
making payment to suppliers during the CIRP period by the Respondent
No.1 itself shows the cause for the hardship allegedly faced by the
Corporate Debtor.
i) It is specifically averred that the discussion between Appellant
and Respondent No.1 was neither affirmed nor concluded. It is further
submitted that the Reply of Respondent No.1 clearly states that the
issues discussed in the Email dated 21.11.2018 were to be further
deliberated, and various banking norms were to be complied such as
LC/BG charges, the procedure for an amendment to LC, etc., before
Company Appeal (AT) (Insolvency) No. 729 of 2020 25 of 46 agreeing to extend any NFB facility that could be provided afresh. The
fundamental principle of the issuance of LC is to make payment to the
supplier as and when the goods are received. The objections raised by
the respondent for making the payment to the supplier from whom the
goods have been acquired during the CIRP period and further
requesting for issuance of fresh LCs without addressing the crystalised
LCs itself establishes the ignorance of fundamental principles of
selecting the LCs.
j) That the contents of para 3 (1) of the Preliminary Objections are
wrong, incorrect and denied. It is denied that the Appellant, without
any communication to Respondent No.1, arbitrarily withdrew the NFB
Facility granted to the Corporate Debtor. In fact, the Appellant vide its
letter dated 24.10.2018 mentioned that the competent authority had
permitted for providing NFB limit of ₹ 43 crores subject to compliance
with the following condition:
"the resolution of NFB limits as proposed will be accepted subject
to a cover of an equivalent amount from a scheduled Commercial
Bank". Copy of the Letter dated 24.10.2018 is marked and
annexed in the Appeal as Annexure A-6 (Page149 to Pg. 150).
k) Respondent No. 1 is put to the strict proof on the averment that
there has been an unjust enrichment by the Appellant or undue burden
on the Corporate Debtor during the already uncertain times, to change
the collection account with 43 domestic and international customers.
Company Appeal (AT) (Insolvency) No. 729 of 2020 26 of 46 The availing of the LC8 facility during the CIRP period, not considering
the same as preferential debt, not- making/objecting for making
payment to the supplier under the LC during the CIRP period, and the
admission on the part of Respondent No. 1 in shifting the collection
account to another Bank, i.e. Axis Bank to avoid payment to the
supplier under the LCs from whom the goods have been received during
CIRP period, processed and sold to its customer is establishing an act
of diversion of the fund and unlawful enrichment of corporate debtor is
not paying the goods supplied during the CIRP for the reasons best
known to Respondent No. 1 despite acting against the provisions of the
Code and causing loss to the Appellant.
l) The Appellant further denied that the actions of recovery of ₹
33.34 crores by the Appellant is unjust enrichment of ₹ 33.34 crores
from the Corporate Debtor during the CIRP and is contrary to the
mandate under Section 17 and 14 of the IBC and reiterated and
reaffirmed that the payments were made directly to the vendors. No
amount was appropriated or adjusted by the Appellant towards any
outstanding claim under CIRP.
m) Respondent No. 1 further contends it had never objected to
alleged illegal recovery for more than one year before any of the CoC
until the 31st CoC dated 7.2.2020. Respondent No. 1, without placing
all the facts and records before the CoC, particularly his various
8 Letter of credit facility
Company Appeal (AT) (Insolvency) No. 729 of 2020 27 of 46 requests for debiting the current account of Corporate Debtor or issuing
fresh LC/BG9, misinformed the CoC about the correct fact. Thus,
having misled the CoC, Respondent No.1 is foisting their illegal action
on the CoC members. The Appellant further denied that no reservation
was shown or recorded in the CoC minutes on behalf of the Appellant.
The CoC meeting dated 07.02.2020 records the objections raised by the
Appellant at para (n) of the CoC meeting. On the contrary, Respondent
No. 1, in a malafide and violation of the principles of IBC,
misrepresented to the CoC by giving it a colour of recovery of LCs made
by Appellant from the corporate debtor during CIRP and to accord
interim finance status to ₹ 34 Crores towards the rejected LC directly
paid from the current account of the Corporate Debtor, and fresh
LC/BG were issued for the freed limit under the instructions of
Respondent No. 1. The Appellant further submitted that vide its letter
dated 20.02.2020, it had objected to the acts of Respondent No. 1. made
it clear that the LCs availed by the Corporate Debtor were like a
contingent liability. The amounts were being paid directly to the
vendors/suppliers of the Corporate Debtor by the Appellant. They
reiterated that no payment was appropriated or adjusted by the
Appellant towards any outstanding claim under CIRP.
n) The IA. No. 222/2020, filed by the Appellant, was to seek
direction to the IRP not to form or illegally suggest to the COC to deduct
the amount of Rs. Thirty-four crores from the total amount allocated in
9 Bank Guarantee
Company Appeal (AT) (Insolvency) No. 729 of 2020 28 of 46 the Resolution Plan towards payment to the Appellant as per the
allocation sheet. It is submitted that the Appellant is one of the
dissenting Secured Creditors who has been allotted the 'Liquidation
value' as per the allocation sheet and, therefore, approved by the CoC.
The IRP rejected the claim amount of ₹ 39.61 crores only because the
same was not crystallised.
o) The observations of the Hon'ble NCLT in the Order dated
09.07.2020 are contrary to records and erroneous to the extent that the
Appellant consented to deduction of the amount of ₹ 33.34 crores, and
the Appellant nowhere disputed the distribution of amounts payable to
the Appellant being a dissenting creditor under the terms of the
Resolution Plan of Respondent No. 2 and 3. The Appellant raised
objections against the rejection of ₹ 34 Crores by the IRP in the 31st CoC
meeting and the Email dated 20.02.2020 as mentioned in the preceding
paragraphs.
10. ANALYSIS
10.1 Admittedly IA 222/2020 was filed u/s 60 (5) of the IB Code before the
Adjudicating Authority to modify the Resolution Plan, which the Committee
of Creditors approved with more than the required percentage, i.e. 70.07% of
vote share, wherein the Appellant was also a member. However, it dissented
with the said approval.
Company Appeal (AT) (Insolvency) No. 729 of 2020 29 of 46 10.2 The Appellant contends that the Resolution Plan of 'DVI' does not
comply with Regulations 42 and 44 of the Insolvency and Bankruptcy Board
(Liquidation Process) Regulations 2016.
10.3 Appellant contends that the payment by honouring LCs was to the
vendors of the CD10, who happened to be the ultimate beneficiaries. As such,
when the bills became due after debiting the current account of the Corporate
Debtor amounting to ₹ 34 crores, the said action cannot be treated as recovery
by the Applicant and cannot be deducted from the final payment to be made
to the Applicant as per the scheme of distribution of amount under the
Resolution Plan. It is further stated that the amounts of ₹ 6,22,58,072.64
towards LCs payment and ₹ 61,39,000 towards Bank Guarantee payment are
to be included in the total admitted claim of the Applicant.
10.4 The learned Adjudicating Authority has rejected the Application with
the following observation;
"the decision of the COC passed with the required majority percent is as per the Code, are binding on all the stakeholders, including the dissenting members of the Committee of creditors, if any. No member of the Committee of creditors, after a resolution plan was approved by the Committee of creditors with the required majority percentage, on one ground or other, cannot challenge the said decision of the Committee of creditors. It is for the Adjudicating Authority to apply its judicious mind whether a particular plan submitted for its approval is in compliance of the provisions of the Code and the Regulations made thereunder. The Applicant even in its
10 Corporate debtor
Company Appeal (AT) (Insolvency) No. 729 of 2020 30 of 46 rejoinder, to the Reply filed by the resolution professional, has not denied the fact of deliberations and acceptance of the action of the resolution professional for deducting the amount of ₹ 34 crores and further distribution of amount payable to the Applicant under the resolution plan of DVI, by the Committee of creditors, wherein the Applicant is a member."
10.5 ₹ ₹ Before proceeding further, it is necessary to go through the
provisions Regulations 42 and 44 of the Insolvency and Bankruptcy Board of
India (Liquidation Process) Regulations 2016 along with Section 53 of the I &
B Code, which is given below for ready reference;
The Insolvency and Bankruptcy Board of India (Liquidation Process)
Regulations 2016
42. Distribution.--(1) Subject to the provisions of Section 53, the liquidator shall not commence distribution before the list of stakeholders and the asset memorandum has been filed with the Adjudicating Authority.
(2) The liquidator shall distribute the proceeds from realisation within [ninety days] from the receipt of the amount to the stakeholders.
(3) The insolvency resolution process costs, if any, and the liquidation costs shall be deducted before such distribution is made.
44. Completion of liquidation.--
[(1) The liquidator shall liquidate the corporate debtor within a period of one year from the liquidation commencement date, notwithstanding pendency of any application for avoidance of transactions under [* * *] Part II of the Code, before the Adjudicating Authority or any action thereof:
Company Appeal (AT) (Insolvency) No. 729 of 2020 31 of 46 Provided that where the sale is attempted under sub-regulation (1) of Regulation 32-A, the liquidation process may take an additional period up to ninety days.]
(2) If the liquidator fails to liquidate the corporate debtor within [one year], he shall make an application to the Adjudicating Authority to continue such liquidation, along with a report explaining why the liquidation has not been completed and specifying the additional time that shall be required for liquidation.
Section 53 of I & B Code 2016;
53. Distribution of Assets (1) Notwithstanding anything to the contrary contained in any law enacted by the Parliament or any State Legislature for the time being in force, the proceeds from the sale of the liquidation assets shall be distributed in the following Order of priority and within such period and in such manner as may be specified, namely--
(a) the insolvency resolution process costs and the liquidation costs paid in full;
(b) the following debts which shall rank equally between and among the following--
(i) workmen's dues for the period of twenty-
four months preceding the liquidation commencement date; and
(ii) debts owed to a secured creditor in the event such secured creditor has relinquished security in the manner set out in Section 52;
(c) wages and any unpaid dues owed to employees other than workmen for the period of twelve months preceding the liquidation commencement date;
Company Appeal (AT) (Insolvency) No. 729 of 2020 32 of 46
(d) financial debts owed to unsecured creditors;
(e) the following dues shall rank equally between and among the following:--
(i) any amount due to the Central Government and the State Government including the amount to be received on account of the Consolidated Fund of India and the Consolidated Fund of a State, if any, in respect of the whole or any part of the period of two years preceding the liquidation commencement date;
(ii) debts owed to a secured creditor for any amount unpaid following the enforcement of security interest;
(f) any remaining debts and dues; (g) preference shareholders, if any; and (h) equity shareholders or partners, as the case may be. (2) Any contractual arrangements between recipients under
sub-section (1) with equal ranking, if disrupting the Order of priority under that sub-section shall be disregarded by the liquidator.
(3) The fees payable to the liquidator shall be deducted proportionately from the proceeds payable to each class of recipients under sub-section (1), and the proceeds to the relevant recipient shall be distributed after such deduction. Explanation.--For the purpose of this section--
(i) it is hereby clarified that at each stage of the distribution of proceeds in respect of a class of recipients that rank equally, each of the debts will either be paid in full, or will be paid in equal proportion within the same
Company Appeal (AT) (Insolvency) No. 729 of 2020 33 of 46 class of recipients, if the proceeds are insufficient to meet the debts in full; and
(ii) the term "workmen's dues" shall have the same meaning as assigned to it in Section 326 of the Companies Act, 2013 (18 of 2013).
10.6 In the case of Ghanashyam Mishra & Sons (P) Ltd. v. Edelweiss Asset
Reconstruction Co. Ltd., (2021) 9 SCC 657: (2021) 4 SCC (Civ) 638: 2021 SCC
OnLine SC 313 at page 698 Hon'ble Supreme Court has held;
65. Bare reading of Section 31 of the I&B Code would also make it abundantly clear that once the resolution plan is approved by the Adjudicating Authority, after it is satisfied, that the resolution plan as approved by CoC meets the requirements as referred to in sub-section (2) of Section 30, it shall be binding on the corporate debtor and its employees, members, creditors, guarantors and other stakeholders. Such a provision is necessitated since one of the dominant purposes of the I&B Code is revival of the corporate debtor and to make it a running concern.
66. The resolution plan submitted by the successful resolution applicant is required to contain various provisions viz. provision for payment of insolvency resolution process costs, provision for payment of debts of operational creditors, which shall not be less than the amount to be paid to such creditors in the event of liquidation of the corporate debtor under Section 53; or the amount that would have been paid to such creditors, if the amount to be distributed under the resolution plan had been distributed in accordance with the Order of priority in sub-section (1) of Section 53, whichever is higher. The resolution plan is also required to provide for the payment of debts of financial creditors, who do not vote in
Company Appeal (AT) (Insolvency) No. 729 of 2020 34 of 46 favour of the resolution plan, which also shall not be less than the amount to be paid to such creditors in accordance with sub- section (1) of Section 53 in the event of a liquidation of the corporate debtor. Explanation 1 to clause (b) of sub-section (2) of Section 30 of the I&B Code clarifies for the removal of doubts that a distribution in accordance with the provisions of the said clause shall be fair and equitable to such creditors. The resolution plan is also required to provide for the management of the affairs of the corporate debtor after approval of the resolution plan and also the implementation and supervision of the resolution plan. Clause
(e) of sub-section (2) of Section 30 of the I&B Code also casts a duty on RP to examine that the resolution plan does not contravene any of the provisions of the law for the time being in force.
****
93. As discussed hereinabove, one of the principal objects of the I&B Code is providing for revival of the corporate debtor and to make it a going concern. The I&B Code is a complete Code in itself. Upon admission of petition under Section 7 there are various important duties and functions entrusted to RP and CoC. RP is required to issue a publication inviting claims from all the stakeholders. He is required to collate the said information and submit necessary details in the information memorandum. The resolution applicants submit their plans on the basis of the details provided in the information memorandum. The resolution plans undergo deep scrutiny by RP as well as CoC. In the negotiations that may be held between CoC and the resolution applicant, various modifications may be made so as to ensure that while paying part of the dues of financial creditors as well as operational creditors and other stakeholders, the corporate debtor is revived and is made an
Company Appeal (AT) (Insolvency) No. 729 of 2020 35 of 46 on-going concern. After CoC approves the plan, the adjudicating authority is required to arrive at a subjective satisfaction that the plan conforms to the requirements as are provided in sub- section (2) of Section 30 of the I&B Code. Only thereafter, the adjudicating authority can grant its approval to the plan. It is at this stage that the plan becomes binding on the corporate debtor, its employees, members, creditors, guarantors and other stakeholders involved in the resolution plan. The legislative intent behind this is to freeze all the claims so that the resolution applicant starts on a clean slate and is not flung with any surprise claims. If that is permitted, the very calculations on the basis of which the resolution applicant submits its plans would go haywire and the plan would be unworkable.
102.1. That once a resolution plan is duly approved by the adjudicating authority under sub-section (1) of Section 31, the claims as provided in the resolution plan shall stand frozen and will be binding on the corporate debtor and its employees, members, creditors, including the Central Government, any State Government or any local authority, guarantors and other stakeholders. On the date of approval of resolution plan by the adjudicating authority, all such claims, which are not a part of resolution plan, shall stand extinguished and no person will be entitled to initiate or continue any proceedings in respect to a claim, which is not part of the resolution plan.
10.7 It is important to mention that the resolution professional admits in its
Reply that it had suggested the COC two options to either treat the illegal
recovery is made by the Appellant as interim finance under the IB Code or
sent to deduction of the amount of illegally recovered amount by the
Appellant, out of distribution amount payable to the Appellant under the
Company Appeal (AT) (Insolvency) No. 729 of 2020 36 of 46 Resolution Plan. Accordingly, the COC, upon deliberation, consented to
deduction of the said amount from the distribution amount owed to the
Appellant under the Resolution Plan submitted by Respondents No. 2 & 3 in
the 30th and 31st Meeting of the COC held on 5 February 2020 on 7 February
2020 respectively.
10.8 The question as to what may be the interim finance was to be first
decided by the Resolution Professional in terms of Section 5 (15) of the IB
Code provides that "interim finance means any financial debt raised by
the Resolution Professional during the Insolvency Resolution Process
and such other debt as may be notified".
It is further necessary to see whether the alleged amount could have
been treated as 'Insolvency Resolution Process cost' was to be decided in
Section 5 (13) of the Insolvency and Bankruptcy Code 2016, which defines
the term "Insolvency Resolution Process cost".
Sec 5 (13) provides that "Insolvency Resolution Process costs"
means--
(a) the amount of any interim finance and the costs incurred in raising such finance; (b) the fees payable to any person acting as a Resolution Professional; (c) any costs incurred by the resolution professional in running the business of the corporate debtor as a going concern; (d) any costs incurred at the expense of the
Government to facilitate the insolvency resolution process; and
(e) any other costs as may be specified by the Board;
Company Appeal (AT) (Insolvency) No. 729 of 2020 37 of 46 10.9 It is further necessary to mention that the Resolution Professional has
in its Reply admitted that in terms of duty cost upon him under Sections 20
and 25 of the Code to continue and maintain the business of the Corporate
Debtor as a going concern, it had requested the Appellant to continue and
sustain the Non-Fund-Based Facility11 limits at the existing level at being
drawn by the Corporate Debtor prior to the insolvency commencement date.
The said request was made on account of the business requirement of the
Corporate Debtor. The RP further stated that the Corporate Debtor is engaged
in the manufacturing, fabrication, and engineering automotive parts. As part
of its business, it must purchase various steel and other alloys. As per the
existing market practice, the purchase and procurement of steel and alloys
are always backed by a Letter of Credit Bank Guarantee issued by the
purchaser's Bank in favour of the beneficiary vendor, and thus the
continuation of the NBF Facility by the Appellant was very much needed as a
lifeline for the continuation of the business of the Corporate Debtor as a going
concern.
10.10 After the above statement of the RP in its Reply, it is clear that based
on the instructions of the RP given maintaining the business of corporate
debtor as a going concern, the continuation of the non-fund-based facility by
the Appellant in terms of the letter of credit bank guarantee issued by the
appellant bank in favour of the beneficiary vendor was undisputedly
Insolvency Resolution Process cost and was extended as interim finance
during CIRP.
11
NBF Facility
Company Appeal (AT) (Insolvency) No. 729 of 2020 38 of 46 10.11 However, the Resolution Professional left it to the discretion of CoC to
either treat the alleged amount as an 'interim finance' under the IB Code or
deduct that amount out of the distribution amount payable to the Appellant
under the Resolution Plan of Respondent No. 2 and 3.
10.12 It is pertinent to mention that Section 25 of the Code provides the
duties of the Resolution Professional. Under Section 25(2)(c), the RP must
raise interim finance subject to the approval of the Committee of Creditors
under Section 28 of the Code. Further, under Section 20 (2) (1) &(2)(c) of the
Code, the IRP/RP is duty-bound to make every endeavour to protect and
preserve the value of the property of the Corporate Debtor and manage the
operations of the Corporate Debtor as a going concern. For this purpose,
IRP/RP is entitled to raise interim finance.
10.13 In the instant case, RP has admitted that it had requested the
Appellant to continue and maintain the non-fund-based facility limits under
'The Letter of Credit Bank Guarantee' at the current level 'as being drawn
by the Corporate Debtor prior to the insolvency commencement date'.
10.14 Therefore, the payment of the said amount to the vendors of the
Corporate Debtor on the instructions of the RP against the 'Letter of Credit
Bank Guarantee' during CIRP should not have been deducted from out of the
payment of the Appellant, which was allotted to it's share under the approved
Resolution Plan. However, this payment was against the 'Letter of Credit
Bank Guarantee, to the suppliers of the Corporate Debtor, who continued
the supply of goods to the Corporate Debtor to keep the Corporate
Company Appeal (AT) (Insolvency) No. 729 of 2020 39 of 46 Debtor as going concerned. Therefore, it would have been better if the RP
had advised the COC about the correct legal position of the interim finance
so that the COC could have taken the proper decision in this regard.
10.15 However, the RP himself concedes that the continuation of the NFB
Facility by the Appellant was very much needed as a lifeline for the
continuation of the Corporate Debtor's business as a going concern. Still,
despite that, RP asked the COC to decide whether the amount extended
to the Corporate Debtor during CIRP to keep it at a going concern should
be treated as interim finance or not.
10.16 It is further made clear that Payment of CIRP cost in priority to other
debts is mandatory u/s 53(1) of the Code. Therefore, given Section 30 (4) of
the IB Code, COC is empowered to fix the Order of priority amongst creditors
as laid down under Section 53 (1). However, permissibility about the
deduction of CIRP cost from the amount allotted under the approved
Resolution Plan is not covered under Section 30 (4) of the Code.
10.17 In the instant case, Resolution Professional has admitted that it had
suggested the COC two options, to either treat the recovery made by the
Appellant as interim finance under IB code or deduct the amount illegally
recovered by the Appellant, out of distribution amount payable to the
Appellant under the Resolution Plan. Thus, it is clear that RP failed to exercise
its jurisdiction to decide the issue of CIRP cost and left it to the CoC to decide
whether the amount incurred in keeping the Corporate Debtor as a going
concern, by the continuation of letter of credit bank guarantee facility during
Company Appeal (AT) (Insolvency) No. 729 of 2020 40 of 46 the CIRP would be treated as interim finance. However, it was the duty of
IRP/RP itself to decide the CIRP cost. After that, instead of taking advice from
the COC for treating the said expenses as interim finance, he should have
obtained sanction from the CoC for making the payment of the expenses
incurred during the CIRP. Hence, he should have made the payment of CIRP
costs. But, instead of exercising its duty to make payment of the CIRP costs,
RP had advised CoC to deduct that amount from out of the payment payable
to Appellant under the Approved Resolution Plan.
10.18 The RP has further stated that vide its letter dated 30 October 2018,
the Appellant was requested to continue their NFB facility without insisting
on the condition as stipulated until the resolution plan of "LHG"12 is
implemented. It was also pointed out that withdrawal of their NFB facility at
that stage would cause an adverse impact on the operations of the Corporate
Debtor as going concerned. However, without responding to the said request
and considering the same in an arbitrary manner by misusing its power and
position imposed auto-debit instructions, the Appellant started debiting the
collection account of the Corporate Debtor maintained by the Appellant Bank
and made recovery of an aggregate amount of ₹ 33.34 crores. However, the
appellant Bank withdrew their NFB facility granted by it to the Corporate
Debtor while recovering a further amount of ₹ 33.34 crores from the collection
account of the Corporate Debtor. Therefore, the said action of the Appellant
during the CIRP is contrary to the instructions of the RP is against the
mandate of Section 17 (1)(d) of the Code.
12
LBG- 'Liberty House Group' Company Appeal (AT) (Insolvency) No. 729 of 2020 41 of 46 10.19 Section 17(1)(d) of the IBC provides that "the financial institutions
maintaining the accounts of the corporate debtor shall act on the instructions of
the interim resolution professional in relation to such accounts and furnish all
information relating to the corporate debtor available with them to the interim
resolution professional".
10.20 It is pertinent to mention that Section 17 of the Code relates to the
management of the affairs of the Corporate Debtor by an Interim Resolution
Professional. Therefore, the phrase used in Section 17 (1) (d) of the IBC that
financial institution "shall act on the instructions of the IRP" does not mean
that it authorises IRP/RP to compel the financial institution for
maintaining the accounts of the CD to continue the NFB facility
comforted by Bank Guarantee. Therefore, non-compliance with such
instructions of RP can not be considered a violation of Section 17 (1) (d) of the
Code.
10.21 The learned Counsel for the Respondent RP emphasised that Section
30 (4) of the IBC cast a role to supervise distribution amongst all creditors on
the COC, and the IRP had no say in that.
10.22 Section 30(4) of IB Code provides that "the committee of creditors may
approve a resolution plan by a vote of not less than sixty-six per cent of voting
share of the financial creditors, after considering its feasibility and viability the
manner of distribution proposed, which may take into account the order of
priority amongst creditors as laid down in sub-section (1) of Section 53,
Company Appeal (AT) (Insolvency) No. 729 of 2020 42 of 46 including the priority and value of the security interest of a secured creditor,
and such other requirements as may be specified by the Board"
10.23 Given section 30 (4) of the IB Code, it is clear that the Committee of
Creditors may approve a resolution plan with 66% voting share after
considering its feasibility and viability. The manner of distribution
proposed may take into account the Order of priority amongst creditors as
laid down under Section 53 (1) of the Code. But for fixing the Order of priority,
the COC has to consider the priority given under Section 53 (1) of the Code.
Section 53(1) (a) provides 1st priority for paying Insolvency Resolution
Process costs and liquidation costs in full.
10.24 The respondent RP has admitted that a Letter of Credit Bank
Guarantee has been issued favouring the beneficiary/vendor to purchase
various steels and other alloys to keep the CD as a going concern. However,
the Respondent RP has failed to appreciate that the Corporate Debtor is liable
to pay the suppliers/beneficiaries under the LCs/BG during the CIRP period.
The payments consequently may be made to beneficiaries by debiting to the
Corporate Debtor's account have been misconceived as recovery towards
Appellant's dues and thereby caused massive loss to the Appellant /
Applicant in denying its claim.
10.25 It is pertinent to mention that the approved Resolution Plan of 'LHG'
had a condition that the Resolution Applicant will provide the cover of an
equivalent amount from a scheduled bank in the event it intends to avail Non-
Company Appeal (AT) (Insolvency) No. 729 of 2020 43 of 46 Fund Based, LC/BG credit facilities and the same was intimated to the RP on
24 October 2018, which the Resolution Plan failed to fulfil.
10.26 Respondent No. 1, in its Reply, had accepted that NFB limits be
subject to covering the limits by the Scheduled Commercial Bank, which is
in line with the discussions with the Resolution Applicant and has also been
mentioned as a part of the Resolution Plan.
10.27 It is also clear that while honouring the LCs and BGs issued on behalf
of the Corporate Debtor, the Appellant being the Financial Creditor, it had not
unduly enriched itself. No amount has been credited towards the loan
account of the Corporate Debtor, and the debit transactions are related to the
payments made to the supplier/vendor/beneficiary of LC/BG. Therefore, it is
incorrect to say that the appellants have made a recovery of ₹ 33.34 crores.
On the contrary, the said LCs/BCs continued during the CIRP period. The
payment was made to the suppliers of the CD on the instructions of the RP
to keep the CD as a going concern. Therefore, the same ought to have been
considered CIRP cost, and the Corporate Debtor has received the goods under
the said LCs and BG's during the CIRP period. Therefore, the corporate Debtor
is liable to pay the suppliers under IBC 2016.
10.28 It is necessary to point out that Sec 53(1) of the IBC mandates the
priority of payment for the Insolvency Resolution Process Cost and the
Liquidation costs. However, in the instant case, IRP/RP firstly insisted the
Appellant Bank continue Letter of Credit Bank Guarantee Facility during
CIRP at the current level to keep the Corporate Debtor as a going concern.
Company Appeal (AT) (Insolvency) No. 729 of 2020 44 of 46 But after that, RP made an erroneous recommendation to the CoC to either
consider payment against LC/BG as CIRP Cost or deduct that amount from
out of the amount allotted to the Appellant's share under the Approved
Resolution Plan.
10.29 Based on the above, it is clear that the Appellant never recovered any
amount from the payment of ₹ 34 crores, as has been misrepresented by
Respondent No. 1. The Adjudicating Authority vide its impugned Order
observed that the Appellant has not objected to the said actions of
Respondent No. 1 in the COC meetings is contrary to the materials placed
before the Adjudicating Authority. Furthermore, the Appellant had refuted
the actions of respondent No. 1 vide its Email dated 20 February 2020, which
the Adjudicating Authority has overlooked. Therefore, the Adjudicating
Authority has misconstrued the payment made to the Appellant's
beneficiaries/vendors as recovery and dismissed the IA 222 of 2020 in CP (IB)
No.42/Chd/Hry/2017.
10.30 In the circumstances stated above, we have concluded unanimously
that the Appeal deserves to be partly allowed with the following directions.
ORDER Company Appeal (AT) (insolvency) No 729 of 2020 is partly allowed. No
order as to costs.
We further direct Respondent No. 1, Resolution Professional, not to
deduct the amount of ₹ 34 crores, i.e. the amount which has been paid to the
vendors of the Corporate Debtor against the 'Letter of Credit Bank Guarantee'
Company Appeal (AT) (Insolvency) No. 729 of 2020 45 of 46 facility, which continued during the corporate insolvency process period,
under the instructions of the Respondent No. 1 /Resolution Professional to
keep the Corporate Debtor as a going concern, is the CIRP costs. Therefore,
it cannot be deducted from the final payment to the Appellant/Applicant as
per the scheme of distribution of the amount under the approved Resolution
Plan.
No order as to costs.
[Justice M. Venugopal] Member (Judicial)
[V. P. Singh] Member (Technical)
[Dr. Alok Srivastava] Member (Technical) NEW DELHI 27th January, 2022
pks
Company Appeal (AT) (Insolvency) No. 729 of 2020 46 of 46
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free