Umesh Saraf Suspended Director Triumph ... vs Tech India Engineers Pvt Ltd
- CitationCompany Appeal (AT)(Insolvency) No. 548 of 2020
Ratio decidendi
The rule this decision rests on
The Corporate Debtor's failure to reply to a demand notice within the Section 8(2) period does not by itself bar it from showing a pre-existing dispute; the Adjudicating Authority must examine the material placed before it, including correspondence predating the demand notice, to determine whether a dispute existed before the notice was received. An operational creditor's application under Section 9 of the Insolvency and Bankruptcy Code, 2016 cannot be admitted where a dispute regarding the operational debt, pre-existing as on the date of receipt of the demand notice, is shown from the record, and the existence of such a dispute takes the application outside the Code's scheme for initiation.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
[Arising out of order dated 4th June, 2020 passed by the Adjudicating Authority, National Company Law Tribunal, New Delhi, Bench-V, in (IB) No. 1906(ND)/2019]
IN THE MATTER OF:
Mr. Umesh Saraf, Suspended Director, TRIUMPH REALTY PVT. LTD. C/o Hotel The Grand, Plot No. 2, Vasant Kunj, Phase-II, Nelson Mandela Road, New Delhi- 110 070 .. Appellant
Vs.
TECH INDIA ENGINEERS PVT. LTD, D-49, Solaris I, Saki Vihar Road, Powai, Mumbai - 400 072 .. Respondent
Present:
For Appellant: Mr. Arun Kathpalia, Sr. Advocate, with Mr. Yogesh Jagia and Ms. Sumedha Chadha, Advocates
For Respondent: Mr. K K Tiwari, Advocate
JUDGMENT
( 19th October, 2020)
KANTHI NARAHARI, MEMBER (TECHNICAL)
The present appeal arises against the order of the learned
Adjudicating Authority (National Company Law Tribunal, New Delhi
Bench-V) in (IB) No. 1906(ND)/2019 dated 4th June, 2020 whereby,
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 1 of 22 learned Adjudicating Authority admitted the Application filed by the
Respondent herein i.e., TECH INDIA ENGINEERS PVT. LTD, Mumbai
under Section 9 of Insolvency and Bankruptcy Code, 2016 (in short
'IBC')
2. Aggrieved by the above order, the suspended Director of the
Corporate Debtor i.e., Triumph Realty Pvt. Ltd filed the present Appeal
challenging the admission and initiation of Corporate Insolvency
Resolution Process (in short 'CIRP') against the Corporate Debtor for
the reason that there is a pre-existing dispute between the Corporate
Debtor and the Operational Creditor.
3. The learned Adjudicating Authority admitted the Application on
the ground that the Corporate Debtor has not raised any dispute by
giving a suitable reply in pursuance of the Demand Notice dated
11.04.2019 issued under Section 8(1) of IBC by the Operational
Creditor to the Corporate Debtor. The findings of the learned
Adjudicating Authority at paragraphs 13 & 14 are reproduced herein:
...
13. In the light of that decision, when we shall consider the case in hand then we are of the considered view that since it is specifically mentioned in Section 8(2) of the Code that within ten days from the date of the receipt of the demand notice, the corporate-debtor is required to bring to the notice of the operational-creditor, the existence of dispute or the documents regarding the payment of debt, therefore, we have no option, but to hold that since the corporate-
debtor fails to give the reply of the demand notice and
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 2 of 22 raised the disputes, hence after his appearance in response to the notice, he cannot raise it by filing the reply to the application, filed on behalf of the operational-creditor and this has also been held by another NCLT, Delhi Bench in the case of M/s Jai Laxmi Traders v M/s Mayasheel Retail India Ltd.
IB-2184/)ND)/2019.
14. Since, no dispute has been raised in pursuance of the demand notice issued under Section 8(1) of IBC, 2016, therefore, in our considered view, any dispute raised after the appearance of the respondent in pursuance to summons issued after filing the main application is not liable to be accepted." ..
BRIEF FACTS:
4. The Appellant/Corporate Debtor is into business of Hotels,
Tourism and Travel Services and operating and managing luxury
resort at Goa. The Corporate Debtor invited Tender in carrying out
electrical works. The electrical works were assigned to the
Respondent/Operational Creditor under tender process and
Agreement dated 07.06.2016, was executed between the Operational
Creditor and the Corporate Debtor. It is submitted that in terms of the
Agreement and the Letter of Intent (in short 'LOI') dated 20.05.2016,
the payment terms were specifically incorporated therein. In terms of
the LOI in clause -2, a specific mention the time of completion is the
essence of the contract and milestones were accordingly incorporated.
According to LOI, the work was to be completed within 120 days.
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 3 of 22 However, the work was delayed and the same has been communicated
by the Operational Creditor vide e-mail dated 05.12.2017 (Page 244 of
Vol. II). It is further submitted that as per the said e-mail, it clearly
reflects that the project has been delayed and the Operational Creditor
neglected to complete the project and hand over the site to the
Corporate Debtor. From the trail of e-mail correspondences of the
Appellant, it is submitted that the Operational Creditor has not
completed the work and the Corporate Debtor time and again
reminded Operational Creditor to complete the work by pointing out
the defects. Learned Senior Counsel for the Appellant submitted that
vide e-mail dated 29.10.2016 (Page 245, Vol. II) and 24.02.2017 (Page
246, Vol. II), the Appellant pointed out inefficiency and deficiency in
execution of work. It is reiterated that vide e-mail of the Respondent
dated 05.12.2017 (Page 244, Vol.-II), the Respondent/Operational
Creditor admitted delay in execution of work. Further it is submitted
that on 02.04.2018 (Page 247 Vol. II), the Corporate Debtor once again
called upon Respondent/Operational Creditor by way of e-mail
regarding incomplete work at site (Hotel). Learned Senior Counsel
further submitted that the Corporate Debtor assigned pending work to
a third party i.e., Yadav Electrical Work for completion of the Hotel
project since the Operational Creditor could not complete the work. It
is submitted that on 05.11.2018 (Page 255 Vol.-II), the Corporate
Debtor again pointed out Operational Creditor about the discrepancies
of the work executed and requested Respondent/Operational Creditor
to depute technical persons at site where all the discrepancies can be
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 4 of 22 shown. The Appellant/Corporate Debtor on 11.01.2019 appointed IM
Cost Management Private Limited (in short "IMCMPL"), a team of
consulting Engineers to carry out the audit of Civil structures,
electrical, plumbing, finishing work and other miscellaneous
packages. On 4th and 5th February, 2019, one Mr. Shiraj, Project
Engineer of Respondent/ Operational Creditor along with
representative of Appellant carried out joint inspection with IMCMPL
and stated that subsequently no one came forward from Respondent
to explain the measurement or deficiencies pointed out by IMCMPL.
On 11.03.2019 (Page-272 Vol.-II), the Appellant/Corporate Debtor
called upon the Respondent/Operational Creditor for meeting and
resolving all the issues reflected in the Audit Report submitted by
IMCMPL on 05.03.2019 (Page 31 of the Rejoinder, diary No. 21148).
However, the Respondent/Operational Creditor did not attend the
meeting, making bald observation through e-mail dated 20.03.2019
(Page 273 Vol. II). While so, the Respondent/Operational Creditor
issued Demand Notice dated 11.04.2019 (Page 274 vol. II) under
Section 8 of IBC for claiming an amount of Rs. 46,64,878/- against 50
invoices. Learned Senior Counsel further submitted that Corporate
Debtor on 29.04.2019 (Page 283 Vol. II), Appellant reiterated various
defects and deficiencies in the execution of work to the
Respondent/Operational Creditor and called upon the Respondent/
Operational Creditor to rectify the same. He further submitted that
learned Adjudicating Authority was of the view that the
Appellant/Corporate Debtor had not taken into consideration the e-
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 5 of 22 mail dated 29.04.2019. However, the learned Adjudicating Authority
was of the view that the Appellant/Corporate Debtor has failed to reply
to the Demand Notice dated 11.04.2019 which was received by the
Appellant/Corporate Debtor on 16.04.2019. He also submitted that
the learned Adjudicating Authority also observed that in e-mail dated
29.04.2019 nowhere it has been mentioned that the said e-mail is in
the form of Reply to the Demand Notice issued by the
Respondent/Operational Creditor. Further, he submitted that the
learned Adjudicating Authority observed that the Appellant/Corporate
Debtor has not complied with the statutory requirement as
contemplated under Section 8(2) of IBC. He submitted that the
Application under Section 9 filed by the Respondent/Corporate Debtor
was admitted on the sole ground that the Appellant/Corporate Debtor
has not raised any dispute in pursuance to the Demand Notice dated
11.04.2019 and submitted that the learned Adjudicating Authority
failed to consider the existence of dispute prior to the Demand Notice.
Learned Senior Counsel relied upon the following judgments in
support of his case.
i) "Innoventive Industries Ltd. Vs. ICICI Bank and Ors."
- (2018)1 SCC 407 passed by Hon'ble Supreme Court &
ii) "Vinod Mittal Vs. Rays Power Experts & Anr." in
Company Appeal(AT)(Insolvency) No. 851/2019 dated
18.11.2019 passed by this Tribunal.
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 6 of 22
iii) Mr. Gajendra Parihar Vs. M/s Devi Industrial
Engineers & Anr. in Company Appeal(AT)(Insolvency) No.
1370 of 2019 dated 18.03.2020 of this Tribunal.
He prayed this Bench to allow the Appeal by setting aside the
impugned order of the learned Adjudicating Authority.
5. Mr. K.K. Tiwary, learned Counsel appearing for the Respondent
filed his Reply and submitted that there is no infirmity in the impugned
Order passed by the learned Adjudicating Authority and there is no
pre-existence of dispute in the eye of law. Learned Counsel submitted
that by not filing Reply to the Demand Notice dated 11.04.2019 issued
under Section 8(1) of IBC, it is admitted by the Appellant/Corporate
Debtor that they have not raised any dispute. Learned Counsel further
submits that in order to justify its malafide, illegal stand has been
taken by the Appellant/Corporate Debtor which are contradictory
pleas on the face of the record. It is also submitted by the learned
Counsel for the Respondent, that Respondent/Operational Creditor
has completed the work to the satisfaction of the Appellant/Corporate
Debtor. He submitted that some alleged works were done by the third
party contractor is false since the stand has been taken for the first
time in the Reply filed to the Insolvency Petition. He submitted that the
Project Director of the Appellant/Corporate Debtor i.e., Mr. Joshi was
satisfied with the works, documents and Commissioning Reports of
Respondent/Operational Creditor and he did not express any
dissatisfaction on 29.12.2018. He further submitted that the
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 7 of 22 Appellant/Corporate Debtor inspected the work in February, 2019
which was almost 10 months after the work was commissioned and
Appellant/Corporate Debtor was making beneficial uses of the facility
for commercial business. He also submitted that even during the joint
inspection with third party in the month of February, 2019, the system
was found running smoothly and satisfactorily. Hence it is a baseless
submission of the Appellant/Corporate Debtor that the system is
having workmanship issues. He submitted that despite several
reminders from the Respondent/Operational Creditor, the
Appellant/Corporate Debtor did not make the payment for the work
done on account of quality and quantity of work, deficient services and
incomplete work. Learned Counsel further submitted that the correct
position is that, that at no point of time, the Appellant/Corporate
Debtor raised any such plea in response to several e-mails sent by the
Respondent/Operation Creditor. The learned Counsel submitted that
even the Appellant/Corporate Debtor had not replied to the Demand
Notice thereby they failed to raise any issues pertaining to the quality
and quantity of work. He submitted that the Respondent/Operational
Creditor's Project Engineer completed the work and handed over the
project during April, 2018 and there was no payment nor any return
reply against the payment request. Learned Counsel further submitted
that the Appellant/Corporate Debtor having satisfied with the work
done by the Respondent/Operational Creditor issued Completion
Certificate on 15.05.2018. Learned Counsel further submitted that the
Appellant/Corporate Debtor in this Appeal raised issue of delay in
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 8 of 22 construction. He submitted that there was no delay in completion of
the work and the Appellant/Corporate Debtor issued 'Completion
Certificate' without any protest of any nature. Therefore, he submitted
that even this issue is untenable. He submitted that the learned
Adjudicating Authority rightly admitted the Application filed by them
on the ground that the Appellant/Corporate Debtor has not raised any
dispute which is not prior to the Demand Notice by way of Reply to
their Demand Notice dated 11.04.2019, even though the Demand
Notice was served on them on 16.04.2019.
6. The learned Counsel for the Respondent submitted that the
Appellant/Corporate Debtor has not raised any valid ground in this
Appeal and he prayed the Bench to dismiss the Appeal.
FINDINGS:
7. Heard learned Counsel for the respective parties. Perused
pleadings and citations relied upon by them. After analysing the
pleadings, the only issue fell for consideration is whether there is
existence of dispute prior to issuance of Demand Notice dated
11.04.2019 or not?
8. Admittedly, the Respondent/Operational Creditor issued
Demand Notice on 11.04.2019 to the Appellant/Corporate Debtor
demanding Rs. 46,64,878/- and the Appellant/Corporate Debtor
received the said Demand Notice. While so, the Appellant/Corporate
Debtor, vide e-mail dated 29.04.2019 addressed to the
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 9 of 22 Respondent/Operational Creditor whereby it has been stated as
under:
"Dear Mr. Pankaj,
This has reference to the audit team's ie IMCM's representative's visit to site and discussion with your team for verification of qualitative/quantitative work executed by your company. You are very well aware that your representative came on 4th February 2019 and 5th February 2019 date for measurement and verification required by the agency. And your representative were not been able to explain any measurements neither could explain any queries. Hence he committed and confirmed that the billing engineer from your end will be there on 6.2.2019 but the billing engineer did not turn up at site on 3rd day with the supporting." ....
"Kindly note that number of email written by our Project Director specifically pointed out that the bills were submitted by your company without supporting of documents such as drawing, approved measurement sheet, DC, MTC, check list and approval on extra items/rate analysis for the extra items." ....
"Further, you are also fully aware that delay cause in executing the work has resulted in delay in commencement of the operation of the hotel and our company has suffered huge financial loss for the same.
We hereby call upon you to send authorised representative or senior official of the Respondent Company along with all documents/ drawings/reports which were duly certified and signed by the Project
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 10 of 22 Director along with R.A. Bills so that joint meeting can be arranged and carried out at the earliest possible time for the deficiency observed by the Audit Team on qualitative and quantitative and delay in execution of work summary which had already been shared to you."
...
9. Learned Senior Counsel for the Appellant/Corporate Debtor
contended that the apart from e-mails exchanged between the
Appellant and Respondent importantly a specific dispute has been
raised vide emails dated 04.10.2018, 01.11.2018, 04.12.2018.
Admittedly the said e-mails were sent prior to issue of Demand Notice
dated 11.04.2019. We have perused e-mail dated 01.11.2018
(Annexure-12, Vol.-II at page 256) whereby the Appellant/Corporate
Debtor stated as under: -
"Dear Mr. Gupta,
Only submission of bill does not mean the completion and correctness of the works. Your team is more than welcome to see for themselves the incomplete/ rectification works that are being carried out these dates. We are open to show and discuss all the points across the table with your technical person at site."
10. The Appellant/Corporate Debtor sent another e-mail dated
05.11.2018 (Annexure- A13 at page 257) to the Respondent/
Operational Creditor stated as under:
"Dear Sir,
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 11 of 22 We reiterate that we would like to discuss all the items and issues with your technical person at site and show him the discrepancies in the billed and actual executed work in order to settle the account.
It is worth stating that in the contract, any intermediate made against the R.A. bill is only adhoc payment and not necessarily certifies and accepts the work as final completion."
11. Prior to the above e-mail, we have also noticed various
exchange of e-mails between the parties. The Respondent/Operational
Creditor, vide their e-mail dated 05.12.2017 addressed to the
Appellant/Corporate Debtor whereby it has been stated that the
Project is also delayed much beyond the original schedule leading to
enhanced overheads and stated that they need funds to source
materials with respect to work progress. The Respondent/Operational
Creditor, vide e-mail dated 15.05.2018 (Annexure-R6 at page 74 of the
Reply) addressed to the Appellant/Corporate Debtor stating that
testing, commissioning and handing over of partial electrical
works/services at the Triumph Reality Pvt. Ltd. and requested the
Appellant to certify the equipment for the testing and commissioning
and successfully handing over by listing out details of the items.
However, the Appellant/Corporate Debtor has contended that the work
was not completed by the Respondent/Operational Creditor and that
they had given the Work Order to a third party vide Work Order dated
25.08.2018 (Annexure-A7 at page 248). In the e-mail dated 30.08.2018
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 12 of 22 (Annexure-A8 at page 249), the Appellant addressed to the Respondent
whereby it has been stated in paragraph-3 as under:
..
"3. During the verification it was found that some of the items which are not yet commissioned/executed, has been claimed in the R.A. Bill and similarly many items certified for commissioning and handing over, no documentation has been submitted so far. You are advised to make necessary amendments and re- submit the bill with corrected quantities, supported with proper documentation."
..
12. The Appellant (Corporate Debtor), vide e-mail dated 04.10.2018
(Annexure-A11, at page 253) addressed to the Respondent
(Operational Creditor) specifically stated that the team of the Appellant
has closely scrutinized the bills submitted and found that the claims
made therein are exaggerated and not in line with the contractual
terms and at paragraph -3 of this e-mail it has been stated as under:
..
"3. Further, during the actual verification of
works, it was found that in many areas the works
are either incomplete or incorrectly executed,
however, claimed in full. All such works are to being
redone, rectified by other agencies, because you had
abandoned the site"
..
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 13 of 22
13. The Appellant/Corporate Debtor on 11.01.2019 pointed out that
one IM Cost Management Private Limited has been appointed to audit
the civil structures, electrical, plumbing finishing etc and submitted
its report on 05.03.2019. There is no dispute that one Mr. Shiraj,
Project Engineer of the Respondent/ Operational Creditor carried out
joint inspection with IMCMPL. After joint inspection, the representative
of the Respondent/Operational Creditor has not come forward for
further inspection. This is borne out from the records of the Appellant's
e-mail dated 29.04.2019 (Annexure-A18 at page 283) addressed to the
Respondent/Operational Creditor wherein it has been specifically
stated that the representative of the Respondent/Operational Creditor
visited on 4th and 5th February, 2019 for measurement and verification.
However, the Respondent's representative was not able to explain any
measurement neither could explain any query. Further, it has been
stated that the Billing Engineer from the Respondent/Operational
Creditor will be present on 06.02.2019. However, the Billing Engineer
did not turn up at site even on 3rd day. It has been stated in the letter
that in view of the delay in executing the work, resulting in delay in
commencement of the operations of the Hotel and the Company had
to suffer huge financial loss. Learned Adjudicating Authority had taken
note of the e-mail dated 29.04.2019 in the Impugned Order at
paragraph-9 and came to a conclusion that the said e-mail dated
29.04.2019 was not the Reply in response to the Demand Notice dated
11.04.2019 and found that the Appellant/Corporate Debtor has not
complied with the statutory provision of Section 8(2) of IBC.
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 14 of 22
14. We are of the view that the learned Adjudicating Authority
instead of taking technical objection that the above e-mail dated
29.04.2019, may not be a Response/Reply to the Demand Notice
issued by the Respondent/ Operational Creditor, however, the
contents, as raised by the Appellant/Corporate Debtor should have
been taken into consideration for the purpose of deciding the issue to
elucidate any pre-existing dispute keeping in view of trail of exchange
of e-mails regarding deficiency in service.
15. We are inclined to refer the letters/e-mails of the
Respondent/Operational Creditor dated 29.12.2018 addressed to the
Appellant/Corporate Debtor (Annexure-R7 at page 75 of the Reply filed
by the Respondent) wherein it is stated as under:
..
"Dear Sir,
We are handing over Electrical Works, Documents
Details at Triumph Resort 336/1A, village Calwaddo,
Benaulim, Goa- 403716."
..
Along with this letter, the Respondent/Operational Creditor
enclosed Final bill, material communication, testing and
commissioning repots handing over signed letter, Code order etc.
16. The contention of the Appellant/Corporate Debtor that in view
of deficiency of services of Respondent/Operational Creditor forced the
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 15 of 22 Appellant/Corporate Debtor to appoint Professional Engineer from
IMCMPL.
17. From the perusal of e-mail /correspondences between the
Appellant/Corporate Debtor and Respondent/Operational Creditor, it
is the case of the Appellant/Corporate Debtor that the Respondent has
not completed the project in time thereby the Project was got delayed
thereby they suffered losses. On the other side, the stand of
Respondent/Operational Creditor that they have completed the Project
and handed over to the Appellant/Corporate Debtor, however,
Appellant/Corporate Debtor failed to pay bills even after complete of
the project. It is unequivocal that there exists dispute between the
parties prior to the issuance of Demand Notice dated 11.04.2019.
18. We are of the view that the learned Adjudicating Authority
instead of taking a technical objection that the Appellant/Corporate
Debtor has not replied to the Demand Notice issued by the
Respondent/Operational Creditor within statutory period of 10 days
as contemplated under Section 8(2) of IBC, should have analysed the
documents placed before it, before taking such objection.
19. As per Article 141 of the Constitution of India, we are bound by
the decision of the Hon'ble Supreme Court in the matter of "Mobilox
Innovations Private Limited vs. Kirusa Software Private Limited"
reported in (2018) 1 SCC 353 at paragraph 33 held as under:
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 16 of 22 "33. The scheme under Sections 8 and 9 of the Code,
appears to be that an operational creditor, as defined,
may, on the occurrence of a default (i.e. on non-
payment of a debt, any part whereof has become due
and payable and has not been repaid), deliver a
demand notice of such unpaid operational debt or
deliver the copy of an invoice demanding payment of
such amount to the corporate debtor in the form set out
in Rule 5 of the Insolvency and Bankruptcy
(Application to Adjudicating Authority) Rules, 2016
read with Form 3 or 4, as the case may be [Section
8(1)]. Within a period of 10 days of the receipt of
such demand notice or copy of invoice, the
corporate debtor must bring to the notice of the
operational creditor the existence of a dispute
and/or the record of the pendency of a suit or
arbitration proceeding filed before the receipt of
such notice or invoice in relation to such dispute
[Section 8(2)(a)]. What is important is that the
existence of the dispute and/or the suit or
arbitration proceeding must be pre-existing i.e. it
must exist before the receipt of the demand notice
or invoice, as the case may be."
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 17 of 22
20. The Hon'ble Supreme Court clearly held that the dispute must
exist before the receipt of the Demand Notice or Invoices as the case
may be. Further, in the matter of "Innoventive Industries Ltd. Vs.
ICICI Bank and Anr." - (2018)1 SCC 407, in paragraph 29 held
which reads as under:
..
"29. The scheme of Section 7 stands in contrast
with the scheme under Section 8 where an operational
creditor is, on the occurrence of a default, to first deliver
a demand notice of the unpaid debt to the operational
debtor in the manner provided in Section 8(1) of the
Code. Under Section 8(2), the corporate debtor can,
within a period of 10 days of receipt of the demand
notice or copy of the invoice mentioned in subsection
(1), bring to the notice of the operational creditor the
existence of a dispute or the record of the pendency of
a suit or arbitration proceedings, which is pre-existing
- i.e. before such notice or invoice was received by the
corporate debtor. The moment there is existence of such
a dispute, the operational creditor gets out of the
clutches of the Code."
..
21. Further, this Bench in the matter of "Vinod Mittal Vs. Rays
Power Exports & Anr." in Company Appeal(AT) (Insolvency) No. 851
of 2019 dated 18.11.2019 held in paragraph-11 as under: Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 18 of 22
..
11. Having gone through the matter and on considering record, there remains hardly any doubt that the earlier correspondence shows that between the parties there were disputes regarding installation of the project as well as functioning of the same.
Although the project had been commissioned for which Completion Certificate had been issued, still if disputes had arisen between the parties regarding the installation and functioning of the project, the Operational Creditor merely pointed out Certificate of Appreciation dated 19th April, 2015 issued and claims that once Completion Certificate had been issued, Corporate Debtor could not raise issues with regard to the quality of the work done. In fact, the record shows that there had been even a review meeting between Operational Creditor and Corporate Debtor and excerpts of which minutes have been placed on record by the Corporate Debtor at Page - 187 which showed that full installation was yet to be completed (see Page
- 188). There was also discussion regarding Sag Structure Correction Action Plan. In fact, there is Annexure - 24 showing the Experts enquiry on 5th May, 2015 as to when the plant would be declared fully commissioned so that they could start electrical review of the project. Looking to such material on record, it is quite clear that there was pre-existing dispute regarding installation as well as operation of the project. When this is so, the Section 9 Application could not have been admitted. In fact, when e-mail dated 20th October, 2016 (Page - 431) was already before the Adjudicating Authority and it had also noticed the same, the Adjudicating Authority should Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 19 of 22 have found preexisting dispute and the Section 9 Application should have been rejected. Only by observing that the Respondent - Corporate Debtor have not come forward to dispute the Application would not be sufficient to initiate CIRP, if the record already showed existence of dispute."
..
And in the matter of "Mr. Gajendra Parihar Vs. M/s Devi
Industrial Engineers & Anr." in Company Appeal(AT)(Insolvency) No.
1370 of 2019 this Bench dated 18.03.2020 was of the view that
existence of dispute prior to the issuance of Demand Notice, the
Application under Section 9 IBC is not maintainable and once there is
existence of such dispute, the Operational Creditor gets out of the
clutches of the Code.
CONCLUSION:
22. Having gone through the records and the law laid down by the
Hon'ble Supreme Court and the precedents of this Tribunal, we are of
the considered view that the correspondences i.e., e-mail/letters show
that there is existence of disputes prior to issuance of Demand Notice.
23. Exchange of e-mails/correspondences, as referred above, clearly
establishes that there is a pre-existing dispute between the parties
regarding completion of the work and the Appellant/Corporate Debtor
continuously made complaints regarding non-completion of work and
deficiency in services, thereby loss caused to the Appellant/Corporate
Debtor.
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 20 of 22
24. Therefore, it is quite clear that there is pre-existing of dispute
regarding completion of the work and the learned Adjudicating
Authority ought not to have admitted the Application under Section 9
of IBC filed by the Respondent/ Operational Creditor. Even in the
Reply filed by the Appellant/Corporate Debtor before the learned
Adjudicating Authority pursuant to Section 9 Application, it is quite
clear that there was sufficient material produced before the learned
Adjudicating Authority and the learned Adjudicating Authority ought
to have considered the materials placed before it.
25. We are of the considered view that the learned Adjudicating
Authority should have considered the substantial material placed
before it in its correct perspective and law laid down by the Hon'ble
Supreme Court in this regard, before passing the Impugned Order
dated 04.06.2020 thus committed error.
26. It is re-iterated that the Code is a beneficial legislation intended
to put the Corporate Debtor on its feet and it is not a mere money
recovery legislation for the Creditors.
27. For the above reasons, we set aside the Impugned Order dated
04.06.2020 passed in (IB) No. 1906(ND)/2019 by the learned
Adjudicating Authority.
28. Initiation of Corporate Insolvency Resolution Process (in short
'CIRP') against the Appellant/Corporate Debtor is quashed and set
aside. Steps taken in consequence of Impugned Order dated
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 21 of 22 04.06.2020 and the further orders passed during CIRP are all quashed
and set aside.
29. We release the Corporate Debtor from the rigour of Corporate
Insolvency Resolution Process. Interim Resolution Professional/
Resolution Professional will hand over the assets and records to the
Corporate Debtor/Promotor/Board of Director.
30. The matter is remitted back to the Adjudicating Authority to
decide Fee and Cost of CIRP which shall be payable to Interim
Resolution Professional/Resolution Professional by the
Respondent/Operational Creditor.
31. The Appeal is allowed as above. No orders as to cost.
[Justice Bansi Lal Bhat] Acting Chairperson
[Justice Anant Bijay Singh] Member(Judicial)
(Kanthi Narahari) Member(Technical) New Delhi
Akc
Company Appeal (AT)(Insolvency) No. 548 of 2020 Page 22 of 22
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free