The Tribunal's reasoning rests on the following principles, each drawn from the terms of the consent agreement and the facts it records: Where a financial creditor has received the principal sum under a consent settlement and the corporate debtor has paid the agreed instalments of the settled interest, the creditor's claim in the corporate insolvency process is confined to the balance that remains outstanding under the settlement terms; the creditor cannot revive the original claim in its full amount on the ground of a later default unless the consent terms so provide. Where the consent terms provide that, on default, the creditor may revive proceedings "in relation to payment of" the outstanding settlement sum "or part thereof as may be left outstanding", the right of revival is limited to that outstanding sum and does not restore the original debt in its entirety. An adjudicating authority is not required to make a different order from that of the resolution professional where the resolution professional's admission of a claim accords with the consent terms and the amounts actually received, and the approved resolution plan is not otherwise open to challenge in the appeal.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
In the matter of: Techengg Project Services & Equipments (I) Pvt Ltd Appellant Vs Jayesh Sanghrajka & Anr Respondent
For Appellant: Mr. Apratim Animesh Thakur, Advocate. For Respondent. Mr Tishampati Sen, Ms Riddhi Sancheti, Mr. Anurag Anand, Mr. G. Karthikeyan, Advocates for R1.
ORDER
05.09.2022: Heard Mr. Apratim Animesh Thakur, learned counsel for the
Appellant and Mr. Tishampati Sen, learned counsel for the R1/RP.
The present appeal under Section 61 of the Insolvency & Bankruptcy
Code, 2016 has been preferred against an order dated 07.01.2021 passed by
the Adjudicating Authority, (National Company Law Tribunal, Mumbai
Bench, Mumbai) in IA No.500/2020 in CP No.2714/2018. By the said order
the Learned Adjudicating Authority has rejected the interlocutory petition
filed by the Appellant which was filed primarily for the following reliefs:-
i) To set aside the decision of the RP partially rejecting the claim of
the applicant and direct him to admit the claim of applicant in 2
entirety to the tune of Rs.6,52,95,183/- as submitted in Form C
dated 07.12.2018.
ii) To direct the respondents to follow procedures established by law
and principles including principles of fairness, impartiality and
transparency in the conduct of Corporate Insolvency Resolution
Process (CIRP) for Respondent No.2.
iii) To restrain RP from creating any third party interest and dealing
with 15 flats situated at B5/1, Lok Nisarg CHS Ltd, Lok Nisarg,
Vaishali Nagar, B.R. Road, Mulund West, Mumbai 400080 in a
manner that undermines the interest of the applicant with
respect to the claim and security interest of the applicant being
subject matter of the case at hand.
It is not in dispute that earlier the Appellant had filed a petition under
Section 7 of the IBC for initiating Corporate Insolvency Resolution Process
(hereinafter referred to as CIRP) against Respondent No.2, Ariisto Developers
Pvt Ltd, due to non-payment of corporate debt to the tune of Rs.10 crores plus
Rs.4 crores interest amount. However, before admission of the petition filed
under Section 7 of the IBC an agreement was entered into in between the
Appellant and the Corporate Debtor and on the basis of the Consent Terms
which was executed in between the Appellant and the Corporate Debtor on
19th July, 2018, the petition filed by the Appellant before the NCLT was
withdrawn. As per the consent on the date of execution itself Rs. 10 crore
was already received by the Appellant and thereafter for the remaining
amount of Rs.2 crores an agreement was entered into for payment of the said 3
amount in view of the Consent Terms. Payment description has been made
in Consent Term in Clause 1(g), which is at running page 236 to 237. It is
appropriate to reproduce the same i.e. 1(g) as under:
"1(g) The Respondent/Corporate Debtor undertake to the Honourable
Tribunal as under:
i) At the time of signing of these consent terms, the
Respondent/Corporate has handed over the pay order of
Rs.10,00,00,000/- (Rupees Ten Crores) towards the
Principal Outstanding, to the Applicant/Financial Creditor
bearing No.782581 dated June 30, 2018 drawn on HDFC
Bank Ltd, Andheri (East) Branch, Mumbai, receipt whereof
Applicant admits and acknowledges.
ii) The Respondent/Corporate Debtor further undertake to
make payment of additional sum of Rs.2,00,00,000/-
(Rupees Two Crores only) towards full and final one-time
settlement of the interest liability, within 180 days from the
signing of these consent terms as agreed upon to the
Applicant/Financial Creditor herein. The said payment of
Rs.2,00,00,000/- (Rupees Two Crores only) towards full and
final settled interest, the Respondent/Corporate Debtor
undertakes to this Honourable Tribunal to pay to the
Applicant/Financial Creditor as follows:
a) Rs.1,00,00,000/- (Rupees One Crores only), less
applicable TDS, to be paid by the Respondent/Corporate 4
Debtor to the Applicant/Financial on or before October
18, 2018,
b) Rs.50,00,000/- (Rupees Fifty lakhs only) less applicable
TDS, to be paid by the Respondent/Corporate Debtor to
the Applicant/Financial Creditor on or before December
2, 2018.
c) A sum of Rs.50,00,000/- (Rupees Fifty lakhs only) less
applicable TDS, to be paid by the Respondent/Corporate
Debtor to the Applicant/Financial Creditor on or before
January 16, 2019.
It is submitted by the Learned Counsel for the Appellant that since
terms and conditions were breached by the Corporate Debtor regarding non-
payment of Rs.2 crores the Appellant was entitled to get the earlier agreement
restored and in such a situation the Appellant was entitled to claim Rs.
Rs.6,52,95,183/-. Learned counsel for the Appellant has also referred to
Clause 1(h) of the Agreement dated 19th July, 2018 and as such he requests
for directing the Adjudicating Authority to consider the claim to the tune of
Rs.6,52,95,183/-. Since he has referred to Clause 1(h) of the Agreement it
would be apt to reproduce the same as follows:
"h. The parties are at present not ad-idem on the deduction of TDS on sum of Rs.2,00,00,000/- (Rupees Two Crores only) as payable in instalment as aforesaid. Parties with their respective chartered accountants/auditors shall meet and resolve the issues within a period of 15 days from today and arrive at a consensus. Till resolution of applicability of TDS on payment of Rs.2,00,00,000/- (Rupees Two crores only) in three instalments as aforesaid Corporate Debtor on July 20, 2018 shall deposit with Mr. Shyam Devani three post-dated cheques for the entire aggregate amount of Rs.2,00,00,000/- (Rupees Two Crores only) as aforesaid. After expiry of 15 days from the date hereof Corporate 5
Debtor shall replace the Security Cheques with new cheques after deducting applicable TDS on the aforesaid sum of Rs.2,00,00,000/-
(Rupees Two Crores only) ("Security Cheques"). It is further agreed that if the parties alongwith their Chartered Accountants does not arrive at any consensus within the aforesaid period of 15 days, the Escrow Holder Adv. Mr. Shyam Dewani shall not handover the said cheques to the applicant herein."
Mr. Tishampati Sen, learned counsel for the RespondentNo.1 by way of
referring to impugned order submits that the learned Adjudicating Authority
has considered each and every aspect and has given detailed reasons and
reduced the claim of appellant to the tune of Rs.1 crore. He has also referred
to Clause 1(k) of the agreement dated 19.7.2018 which is at running page 238
and is reproduced hereinbelow:-
"k. It is agreed that in case of any default in making the payment of the
amounts as agreed in Clause 1(g) above in any manner whatsoever, the
Applicant/Financial Creditor shall be entitled to revive all the
proceedings in relation to payment of Rs.2,00,00,000/- (Rupees Two
crores only) or part thereof as may be left outstanding, which shall be
withdrawn at present in pursuance to the execution of these consent
terms and also take all such actions/file proceedings for the breach of
the terms of these consent terms and undertaking given to the
Honourable Tribunal, as the case may be."
Learned counsel for the Respondent by way of referring to aforesaid
agreement clause submits that in case of any deviation from the agreement
only dispute was confined to the extent of Rs.2 crores or part thereof and it
was not permissible to restore the earlier agreement. Learned Counsel for the
Respondent No1 further submits that in the present dispute fact remains that 6
CIRP was initiated on an application filed by M/s Dipco Private Ltd. He
submits that the said application was admitted on 20.11.2018. He submits
that despite the fact that as per IBC time has been prescribed for conclusion
of proceedings but by one way or the other it has been delayed and that the
proceeding is still pending before the Adjudicating Authority. The
Adjudicating has approved the resolution plan on 23.03.2021. He submits
that since the resolution plan has already been approved by the Adjudicating
Authority long back nothing is required to be adjudicating in this Appeal. He
submits that filing of the present appeal by the Appellant is an abuse of
process of law.
Besides hearing we have minutely examined the material available on
record. After going through the same, prima facie, we are of the opinion that
there is no reason for interference with impugned order by this Tribunal.
However, before proceeding we propose to reproduce the impugned order
which has been passed by the Adjudicating Authority>
"1.This is an application filed by TechEngg Project Services & Equipments
(India) Private Limited against Mr. Jayesh Sanghrajka, who is the
Resolution Professional of Ariisto Developers Pvt. Ltd. (hereinafter called
as the "Corporate Debtor") seeking the following reliefs:
i. To set aside the decision of the RP partially rejecting the
claim of the applicant and direct him to admit the claim of
applicant in entirety to the tune of Rs.6,52,95,183/- as
submitted in Form C dated 07.12.2018.
7
ii. To direct the respondents to follow procedures established
by law and principles including principles of fairness,
impartiality and transparency in the conduct of Corporate
Insolvency Resolution Process (CIRP) for Respondent No. 02.
iii. To restrain RP from creating any third-party interest and
dealing with 15 flats situated at B5/1, Lok Nisarg CHS Ltd.,
Lok Nisarg, Vaishali Nagar, B.R. Road, Mulund West,
Mumbai - 400 080 in a manner that undermines the interest
of the applicant with respect to the claim and security
interest of the applicant being subject matter of the case at
hand.
2. The counsel for the applicant alleged that the RP has erroneously and
without application of mind, partially rejected the claim of the applicant
on the unsubstantiated and unreasoned ground, as recorded in the
minutes of the 6th CoC meeting, that the claim of the Applicant is
disputed without taking into consideration the following set of facts and
circumstances:
i. That between September, 2014 to November, 2015, the Applicant
provided financial help to the Corporate Debtor of
Rs.10,00,00,000/- at the rate of 24% per annum payable quarterly
against mortgage/sale of 15 flats.
ii. that the Corporate Debtor collaterally signed and issued various
documents in favour of the applicant including but not limited to
Agreement/Memorandum of Understanding, Deed of Mortgage, 8
Deed of Indemnity, Deed of Transfer, Power of Attorney,
Possession Letter etc. towards security but failed to provide the
original title deed, chain agreements/documents, etc. for
necessary due diligence despite repeated requests and hence
never completed the registration process of the said documents.
iii.The Corporate Debtor failed to repay the Principal amount along
with interest and hence, CP No. 425/2018 was filed under Section
7 for initiating CIRP and during the course of proceeding, prior to
the admission of the petition, the applicant and the Corporate
Debtor entered into "Consent Terms" dated 19.07.2018 for
resolution of debt and all the disputes pertaining thereto. In line of
this, the Company Petition bearing number 425 of 2018 was
dismissed as withdrawn vide an order dated 19.07.2018 of this
Tribunal.
iv. However, the Corporate Debtor miserably failed to honour
the terms of the consent and consequently there was a
breach of Consent Terms.
v. According to the Consent Terms, the Corporate Debtor was
to pay a total sum of Rs.12,00,00,000/- towards full and
final settlement of the dispute. However, as captured in
Clause 1(h), the dispute pertaining to deduction of TDS was
to be settled within a period of 15 days from the date of
Consent Terms. The disputed amount in terms of Clause(h)
was only Rs.20,00,000/- towards deduction of TDS if 9
applicable at alland the remainder of Rs.1,80,00,000/- was
admitted by the parties in any case whatsoever. However,
the Chartered Accounts of both the Applicant as well as the
Corporate Debtor discussed the TDS issue and came to the
conclusion that no TDS was required to be deducted by the
Corporate Debtor. But the Corporate Debtor raised an
unnecessary demand for furnishing a certificate as provided
in Form 26A (Rule 31 ACB) of the Income Tax Rules, 1962.
To this, the counsel for the applicant had replied via email
dated 17.08.2018 stating that the entire dispute pertaining
to TDS stands resolved as discussed between the Chartered
Accountants of the parties and no certificate under Form
26A(Rule 31ACB) was required. There was no reply by the
Corporate Debtor to this email and the dispute was deemed
to be resolved.
vi. The counsel for the applicant further mentioned that there
were cheques provided to the applicant by the Corporate
Debtor in respect of Clause 1(I) of the Consent Terms which
were dishonoured with the remarks "Funds Insufficient"
and a legal notice was issued by the applicant on
23.10.2018. The Counsel for the Corporate Debtor replied to
the said Notice on 25.10.2018 wherein it enclosed a Demand
Draft of Rs. 90,00,000/- and once again requested for a
certificate in pursuance of Form 26A (Rule 31ACB). 10
vii. vii. He further submitted that with a bona fide intent to close
the TDS dispute, the Applicant agreed to issue Form 26A
Certificate (Rule 31ACB) and asked the Corporate Debtor to
release the balance amount of Rs.10,00,000/- of the first
instalment immediately after receipt of this communication.
But despite this, the Corporate Debtor failed to comply and
blatantly breached the Consent Terms. The counsel for the
applicant therefore, stated that the Consent Terms stand
breached and the Applicant is reinstated in the original
position thereby being entitled to claim the interest in terms
of the original Agreement @24% per annum payable
quarterly which was duly computed and submitted to the
Respondent no. 01 in Form C dated 07.12.2018.
3. Because of the abovementioned reasons, the counsel for the applicant
mentioned, that the applicant was constrained to file MA No. 1953 of
2019 before this Tribunal on 29.05.2019 praying therein the partial
rejection of claim of applicant by the RP and directing him to accept the
claim in entirety to the tune of Rs.6,52,95,183/- as submitted in Form C
dated 07.12.2018. The applicant furthermore had asked in its interim
prayer to restrain Respondent No. 01 from admitting and acting in
pursuance of any Resolution Plan that undermines the interest of the
applicant with respect to the claim of the Applicant being subject matter
of the present case at hand. This application was dismissed by this 11
Tribunal vide an order dated 13.11.2019 for being premature, without
adjudicating upon the rights of the applicant on merits.
4. The counsel for the applicant mentioned that the Hon'ble Supreme
Court and the High Courts, in a catena of judgments, have held that in a
situation where there is breach of the settlement agreements entered into
between the parties, the cause of action cannot be construed in such an
event and cannot be merely limited to breach of settlement agreement.
Therefore, it is essentially a matter of interpretation by the Court of the
Consent Terms to determine whether the intention of the parties is clear
that by execution of the Consent Terms, the original cause of action is
discharged.
5. He further stated that a conjoint reading Clause 1(b) and 1(c) of the
Consent Terms has to be accorded and upon such a conjoint reading, it
appears that the intention of the parties is that only upon the receipt of
payment of full and final settlement amount of RS. 2,00,00,000/- against
interest due, the settlement agreement comes to full effect and the original
cause of action would stand discharged as until then all the documents
in relation to which the cause of action has arisen is kept in escrow.
Clause 1(c) makes it categorical that handing over of the documents to
the Corporate Debtor is to take place only when the full and final
settlement amount of Rs.2,00,00,000/- against interest due is received
by the applicant.
6. The senior counsel appearing for the RP has denied all the contentions
levied against the RP stating that they are false, baseless and devoid of 12
merits and has submitted that he has acted according to the provisions
of the Code. He submitted that the RP has rejected the claim of the
applicant after due verification of documents submitted by the applicant
along with its proof of claim (Form C) as well as books of accounts of the
Corporate Debtor. He submitted that the RP has conducted the CIRP in a
transparent and fair manner.
7. He further stated that Mr. S Gopalkrishnan was appointed as the IRP
vide an order dated 20.11.2018 of this Tribunal. Later on, he received
around 76 claims from various persons claiming to be financial creditors
of the Corporate Debtor and upon receiving the claims and the documents
filed along therewith, the IRP was pleased to accept or reject claims. He
further mentioned that as per the list of claims of Financial Creditors as
on 07.12.2018, the IRP accepted applicant's claim amount to the tune of
Rs. 1,00,00,000/- as against the applicant's total claim of Rs.
6,52,95,183/-.
8. The present applicant was subsequently appointed as the RP in the
1st CoC meeting held on 14.12.2018 and later this Tribunal sanctioned
this appointment vide an order dated 23.01.2019.
9. He further mentioned that the RP, on persistent request of the applicant
to reconsider its claim in entirety, perused the documents on the basis of
which the claim was made. He stated that the RP also perused a copy of
Corporate Debtor's Balance Sheet dated 31.03.2018 wherein the amount
due and payable to the applicant is shown to be Rs. 10,00,00,000/-. 13
10. The counsel for the applicant stated that it is pertinent to note that
the applicant is facing serious tax demand and is in receipt of the notices
from the Income Tax Department for non-payment of TDS amount
deducted by the Corporate Debtor during the Financial Year 2015-16 &
2016-17 out of the interest amount paid and/or was payable to the
Applicant by the Corporate Debtor. He further stated that it was a ploy
by the Corporate Debtor with clear intention since beginning to confuse
and mislead the applicant and not to pay the already agreed amount to
the applicant as per the Consent Terms entered into by the applicant and
the Corporate Debtor as the Corporate Debtor is a serious defaulter in
paying the statutory dues also.
11. The Senior Counsel for the RP stated that on 19.07.2018, the
Corporate Debtor and the Applicant had settled their claims and all
disputes by entering into Consent Terms during the course of proceedings
in CP 425/2018 wherein the Corporate Debtor had agreed to pay Rs.
10,00,00,000/0- towards the principal liability and Rs. 2,00,00,000/-
towards full and final settlement of interest in the manner provided in the
Consent Terms. On bare reading of the Consent Terms, specially clauses
1, 1(a), 1(b), 4, 5 and 6, it is apparent that the parties had entered into
the aforesaid Consent Terms with an intention of full and final settlement
of all their disputes including but not limited to the one arising out of or
in connection to CP 425/2018.
12. He further stated that nowhere in the Consent Terms it is mentioned
that the applicant would be entitled to claim an alleged amount of Rs. 14
6,52,95,183/-. Rather, Clause 1(k) of the Consent Terms provides that in
case of default in Corporate Debtor's payment, the Applicant shall be
entitled to revive all proceedings in relation to payment of Rs.
2,00,00,000/- (Rupees Two Crores Only) or any part thereof as may be
left outstanding, which shall be withdrawn at present in pursuance to
the execution of the Consent Terms and also take all such actions/file
proceedings for the breach of Consent Terms and undertaking given to
the Hon'ble Tribunal, as the case may be.
13. The Senior Counsel for the RP further alleged that pursuant to the
Consent Terms, the Corporate Debtor had paid principal amount of Rs.
10,00,00,000/- through pay order bearing no. 782581 dated 30.06.2018
drawn on HDFC Bank Ltd. and this fact is not disputed by the applicant.
He alleged that this is a preferential transaction as per Section 43 of the
Code and the same can be avoided.
14. The Senior Counsel for the RP stated that the Corporate Debtor had
agreed to make payment of Rs. 2,00,00,000/- towards full and final
settlement of interest liability within 180 days in three instalments in the
following manner [Clause 1(g) of the Consent terms]:
i. Rs. 1,00,00,000/- less applicable TDS, on or before 18.10.2018:
this payment was made by the Corporate Debtor at the rate of 10%
i.e. net amount of Rs. 90,00,000/- through Demand Draft bearing
No. 148369 dated 24.10.2018 drawn on HDFC Bank which was
encashed by the Applicant and this fact has been admitted by the
applicant at para 14(k) pg.30 of its application as well as at the 15
letter marked as Annexure A-22 to the application. The Senior
counsel for RP alleged that this is a preferential transaction as per
Section 43 of the Code and the same cannot be avoided;
ii. Rs. 50,00,000/- less applicable TDS, on or before 02.12.2018;
iii. Rs. 50,00,000/- less applicable TDS, on or before 16.01.2019.
In respect of the ii. and iii. transaction which were due on
02.12.2018 and 16.01.2019 respectively, it was mentioned that
the Company Petition was admitted vide an order dated
20.11.2018 under Section 7 of the Code against the Corporate
Debtor and hence, the applicant could have claimed his
outstanding of only Rs. 1,00,00,000/- against the Corporate
Debtor to the IRP/RP.
15. The counsel further mentioned that it is pertinent to mention here that
out of total settlement amount of Rs.12,00,00,000/- agreed between the
parties as provided in the Consent Terms, the applicant had received
substantial amount of Rs.10,00,00,000/- towards principal outstanding
at the time of signing the Consent Terms and Rs.1,00,00,000/- less
applicable TDS towards interest as stated in aforementioned paras.
Stating this, he concluded that thus, the balance outstanding was
Rs.1,00,00,000/- only and therefore, the applicant's claim of
Rs.6,52,95,183/- is unreasonable, baseless and hence, inadmissible in
the light of the Consent Terms entered into by the applicant and the
Corporate Debtor.
16
16. Further, regarding the second issue of the applicant i.e. the Security
available with the Applicant against such claim, the Senior Counsel for
the RP stated that Clause 1(b) of the Consent Terms provides that upon
receipt of the principal amount of Rs.10,00,00,000/-, the applicant would
have to forthwith give up all the rights arising out of all Deeds,
Agreements Documents, Negotiable Instruments, Memorandum of
Understanding etc. executed by the Corporate Debtor in the captioned
matter. And as the applicant has admittedly received the aforesaid
principal amount upon signing of the Consent Terms, the applicant is
barred from claiming security interest.
17. The Senior Counsel for the RP further stated that the copies of the
letters submitted to the RP by the applicant vide email dated 26.05.2019
are nothing but not only various correspondences between the applicant
and the Secretary of the Society wherein the aforesaid 15 Flats of the
Corporate Debtor are situated and the same do not prove any right or
interest of the Applicant in the said 15 flats of the Corporate Debtor.
18. Making the above submissions, the Senior Counsel for the RP prayed
for the dismissal of this application on the following grounds:
i. that the applicant's claim is unreasonable, baseless and hence,
inadmissible in the light of the Consent Terms dated 19.07.2018
and the payments made by the Corporate Debtor in pursuance of
the Consent Terms;
ii. That the applicant is attempting to unjustly enrich himself by
claiming higher amount that which is actually outstanding and is 17
trying to go beyond what was agreed between the parties as
mentioned in the consent terms.
iii. That the amounts received by the applicant amount to
preferential transactions as per Section 43 of the Code;
viii. That the allegations levelled against the RP are baseless and
suffer from want of merit as he has acted according to the
provisions of law and in complete fairness.
FINDINGS
19. We have heard all both the parties, perused and taken all the
documents submitted by them into consideration. After going through the
pleadings, we believe that the RP has rightfully partially accepted the
applicant's claim after due consideration of the documents provided to
the IRP/RP. We would further like to observe that the RP has acted in
accordance with the provisions of the Code and the applicable rules and
regulations made thereunder and also followed the principles of law
including the principles of fairness, impartiality and transparency.
20. Also, the Senior Counsel for the RP had stated that even otherwise,
the applicant has submitted various documents along with its claim Form
in respect of purported/alleged claim of security interest, these
documents are without signature of either of the parties or all the parties,
without dates, without details of amount or without applicable stamp
duty or registration, as the case may be. In view of this, such documents 18
were not taken in consideration by the IRP or RP for determining the
purported/alleged claim of security interest of the applicant.
21. The Senior Counsel for the RP has already brought on record that the
Principal amount due and payable was already paid by way of a
Demand Draft bearing No. 148369. He also terms this transaction as a
preferential transaction. But this is not the subject matter of this
Application and we need not deal with it in here.
22. It is clear from the facts of the case that out of total settlement amount
of Rs.12,00,00,000/- agreed between the parties as provided in the
Consent Terms, the applicant had received substantial amount of
Rs.10,00,00,000/- towards principal outstanding at the time of signing
the Consent Terms and Rs.1,00,00,000/- less applicable TDS towards
interest and thus the balance outstanding was Rs.1,00,00,000/- only.
Therefore, we are of the opinion that this application needs to be
dismissed and there is no wrong committed by the RP in deciding upon
the claim of the applicant. With the above directions and observations,
this Interlocutory Application numbered 500 of 2020 is dismissed and is
accordingly disposed of."
It is evident, on examination of the aforesaid impugned order, that there
is no dispute regarding payment of amount which is Rs.10 crores which was
claimed by the appellant. The said amount was already received on the date
of the agreement i.e. 19.07.2018 and on the basis of the said agreement earlier
petition filed by the appellant was withdrawn. So far as amount of Rs.1 crore
is concerned para 14(i) of the impugned order categorically reflects that after 19
deducting Rs.10 lakhs as TDS, Rs.90 lakhs was already paid to the appellant.
Only for remaining amount of Rs.1 crore, two cheques of Rs.50 lakhs each
were issued. Dispute is only to the said amount. On examination of the claim
the RP has also accepted regarding claim of the appellant of Rs. 1 crore. We
have also perused the terms and conditions as has been explained by the
appellant as well as learned counsel for Respondent which we have quoted
hereinabove. On going through the same and in view of the fact that the
amount of Rs.10 crore was received by the appellant on 19.07.2018 and
thereafter Rs.90 lacs after deducting Rs.10 lacs as TDS, we are of the opinion
that the Adjudicating Authority has rightly approved the decision of
Resolution Professional by reducing appellants' claim to Rs.1 crore only.
There was no reason for the Adjudicating Authority to pass a different order.
Moreover there is no dispute on approval of Resolution Plan by the
Adjudicating Authority.
We find no merit in the Appeal. The Appeal stands dismissed without
cost.
(Justice Rakesh Kumar) Member (Judicial)
(Dr. Ashok Kumar Mishra) Member (Technical) Bm/gc
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free