Sudha Electrical vs Leena Power-Tech Engineers ...
- CitationComp. App. (AT) (Ins) No. 2381 of 2024
Ratio decidendi
The rule this decision rests on
Under Section 9 of the Insolvency and Bankruptcy Code, an operational creditor's petition for initiation of the CIRP must establish, at the threshold, an undisputed debt and a default in payment of it, meaning that the debt has fallen due for payment at the time of the alleged default; the petitioner bears the statutory burden of establishing both. Where the existence of the contract or work order on which the time for payment depends is genuinely disputed, and that dispute requires independent proof rather than being a patently feeble defence, the existence of an undisputed debt and of default is not established and the petition cannot be admitted; the Adjudicating Authority cannot resolve such a question by a preponderance-of-probability enquiry of the kind a civil court would undertake. A failure to reply to a demand notice under Section 8 does not, by itself and in every case, amount to an admission of the debt or of the time for its payment; its effect depends on the facts of each case.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
SUDHA ELECTRICAL ...Appellant
Through it Proprietor Yogendra Chaudhary
Vs ...Respondent LEENA POWER-TECH ENGINEERS PVT. LTD.
(Arising out of Impugned Order dated 25.10.2024 passed by the Adjudicating Authority (National Company Law Tribunal, Mumbai Bench-V, Mumbai) in C.P. (I.B) No. 515/MB/2023)
For Appellant: Mr. Chandra Shekhar Yadav & Mr. Astitva Srivastava, Advocates for Appellant.
For Respondent: Mr. Arvind Nayar, Sr. Adv. With Sinha Shrey Nikhilesh, Mr. Parth Davar, Mr. Naman Kapoor, Diskha Dadu, Ms. Swastik Verma, Ms Nayan Dubey & Ms. Faraaz Khan, Advocates for Respondent.
JUDGEMENT
Per Justice N. Seshasayee, Member (Judicial)
This Appeal is preferred by an Operational Creditor whose petition to initiate a
CIRP Proceedings under Section 9 IBC was dismissed on the ground that there 2
subsists, (a) a pre-existing dispute between the parties vis-à-vis a debt which the
appellant claims that the respondent had defaulted to pay despite a demand;
and (b) the CIRP is not maintainable under Secc.10A of IBC.
FACTS
2.1 The material facts which led up to the institution of this appeal are as
below:
(a) The appellant is engaged in the business of supplying and erecting
and testing and commissioning of electrical equipments, transformers,
gensets control penal, laying of cables, etc.
(b) Be that as it may, certain Rahul Cables Pvt. Ltd. had obtained
certain Government contract involving laying of 220 Kv copper cables and
132 Kv cables and work associated therewith in Navi Mumbai, Pune and
Andhra Pradesh. It (Rahul Cable) had awarded sub-contract to the
respondent/corporate debtor herein. According to the corporate debtor, it
engaged the appellant for performing its contracted work.
(c) According to the respondent/corporate debtor, on 18.09.2019,
23.12.2019 and 15.01.2020, it had placed three separate work orders with
the appellant. Except for the nature of work to be done thereunder, the
terms of the three work orders are identical. The appellant contends that
no work order of the kind which the respondent pleads has never been
Company Appeal (AT) (Ins) No.2381 of 2024 3
issued to him. In other words, its contention is that the contract between
the parties was oral.
(d) According to the appellant - Operational Creditor, it had performed
the work required to be performed by it, and raised 5 invoices dated
09.01.2020, 23.01.2020, 13.02.2020, 28.02.2020 and 13.03.2020 for a
combined total value of Rs.4,98,28,613.71.
(e) On 24.06.2020, the respondent had made part payment of
Rs.76,00,975/- and also paid Rs.4,22,277/- towards GST. As on
31.03.2022, according to the appellant, the respondent is liable to pay an
outstanding balance of Rs.4,18,05,361/-. And, the respondent had
confirmed the same on 01.04.2022. As on 09.01.2023, inclusive of
interest at 24% p.a. the respondents are liable to pay sum of
Rs.6,73,42,138/-.
(f) Since the debt due to the Operational Creditor was not paid, it
issued a demand Notice dated 09.01.2023 as required under Sec. 8 of IBC.
The notice, though was duly served, did not evoke any response or reply
from the respondent. Wasting no time the appellant invoked Sec.9 IBC.
(g) In Part IV of Form 1, the appellant has indicated that the debt
became due for repayment on the respective dates of invoices.
2.2 Notice was served on the respondent and it appeared to contest the petition
with its reply. Its defences are twofold:
Company Appeal (AT) (Ins) No.2381 of 2024 4
a) that the initiation of action is barred under Section 10A of the IBC and
hence the very invocation of sec.9 IBC is not maintainable. In terms of
clause 5 of the work order (something which the appellant disputes), the
respondent is required to pay only 20% of the invoice value within 90 days
of the invoice. If so reckoned, the respondent will have 90 days time to
pay the paid 20% from the respective dates of the invoices. Accordingly,
the time for payment of 20% on each of the five invoices would arise only
after 25.03.2020, the date from which Sec.10A embargo in invoking IBC
would intervene.
b) In terms of clause 5(2) of the work Order, 70% of the balance (after the
initial payment of 20% of the invoice value) is required to be paid only after
a completion certificate along with testing and commissioning report, duly
signed by the authorized person of M/s. Rahul Cables (as contemplated in
clause 3 of the work order) is made available along with few documents
indicated in clause 5. The appellant has not produced any completion
certificate as mandated in Clause 5(2) read with Clause 3(vi) of the work
order. Hence, the 70% of the invoice was not paid. So far as the balance
10% is concerned, the appellant is entitled to be paid only after a period of
12 months from the date of testing and commissioning. Therefore, till
such time the appellant establishes its right to be paid as per the terms of
payment, the respondent is entitled to withhold it. And, the appellant has
not produced any material to show that it has done the work as
contemplated in the work order nor produced any of the documents that
Company Appeal (AT) (Ins) No.2381 of 2024 5
it is required to produce as contemplated in clause 5 read with 3 of the
work Order. On the other hand, the respondent has raised a dispute that
the work has not been done even prior to the institution of CIRP under
sec.9 of IBC. In essence neither is there a debt as contemplated in the IBC
nor the claim of the appellant is dispute-free. The appellant has grossly
suppressed the material facts and consequently the very institution of
petition under Sec.9 IBC is not maintainable.
c) Admitting that it has made a part payment of Rs.76,00,975/- the
respondent would explain that it merely represents the 20% of the invoice
value as required to be paid. And the GST of Rs.4,22,277/- is also paid as
it is statutorily required to be paid on the 20% of the amount.
2.3. The Adjudicating Authority upheld the defences taken by the respondent
and refused to admit the CIRP. This Order is now under challenge.
THE ARGUMENTS:
3. Taking this Tribunal extensively through the few documents including the
GST returns etc., the learned counsel for the appellant argued that:
a) in Part IV of Form I, the appellant has indicated in unequivocal terms that
the date of default to pay the debt commenced from the date of the invoice.
In terms of Sec. 10A IBC which the Parliament thought it fit to introduce
during the Covid-days, only in cases where the default has arisen on or
Company Appeal (AT) (Ins) No.2381 of 2024 6
after 25th March, 2020 (the day on which the Government clammed
lockdown) across the country, initiation of a CIRP proceeding is barred.
However, in the instant case, the invoices are issued between 09.01.2020
and 13.03.2020 and they are well before 25.03.2020 from which date alone
the bar under Section 10A would come to play.
b) So far as the alleged pre-existing dispute is concerned, the respondent has
not denied any one of the 5 invoices issued by the appellant between
09.01.2020 and 13.03.2020. Instead it proceeded to confirm it on
01.04.2022. Indeed, acknowledging the debt, the respondent had even a
made part payment on 24.06.2020 and also deposited Rs.4,22,277/-
towards GST. And most significantly, the respondent has not even chosen
to reply the statutory notice issued on it under Sec.8 IBC denying the claim
of the appellant.
c) The CIRP was laid on 21.02.2023. During the pendency of the same, on
18.04.2023, the respondent had paid Rs.25.0 lakhs, which is corroborated
by the e-mail of the bank. Indeed, there has been WhatsApp chats between
the appellant and the representative of the respondent preceding this
payment, and is made available on record as Annexure 4. This factum
was overlooked by the Adjudicating Authority.
d) The respondent contends that the appellant transacted business with the
former based on certain work Orders, but they were never given to the
latter. The transaction was based on an Oral agreement, and work Orders
Company Appeal (AT) (Ins) No.2381 of 2024 7
produced by the respondent are unilateral documents which do not bind
the appellant.
When the debt is not challenged, and when the respondent defaults in paying
it despite a demand, it exposes the respondent to the perils of IBC. The issue
of existence of a pre-existing dispute is a hurriedly invented exit route but it
is unsupportable on facts.
4. The response of the respondent's counsel was candid and along
predictable lines. He argued:
a) The contract which the respondent had entered into with the appellant
involves both supply of goods and services associated with erection,
commissioning and testing of electrical cables. It was entered into as part
of the contract which M/s Rahul Cables was awarded by the Government.
To deny these work orders itself is denied. Indeed, in the copies of the
work Orders produced by the appellant in its paper-book (all photocopies),
the signature of the appellant's representative is seen.
b) The terms of the work Orders are unambiguous. The appellant is required
to supply goods and services, erect and commission and them and they
have to be tested, and certificates of the due commissioning and testing
must be obtained from the agent of the contractor, and produce the same
for claiming the value of the invoices raised for the purpose. It is here the
appellant chose to turn the other way.
Company Appeal (AT) (Ins) No.2381 of 2024 8
c) So far as the right to claim the amount which the appellant claims as debt,
in terms of the work Order, it would arise only after 90 days of the date of
the invoice. And the earliest of invoice is dated 09.01.2020, and if 90 days
is added to it, the right to claim the invoice amount would arise only in
April, 2020. And the last of the invoice is dated 13.03.2020, a few days
prior to lockdown due to Covid commenced which eventually necessitated
the introduction of Sec.10A of the IBC, but the 90 days from there would
expire only about mid-June, 2020, which fell within the period covered by
Sec.10A.
d) It is true, some amounts as stated by the appellant were paid, but they do
not indicate that the respondent has admitted the entire liability. It is still
waiting for the certificate duly signed by the authorized agent of the
respondent vis-à-vis the commissioning and testing etc. While it is not
disputed that no reply was issued to the notice under Sec.8 IBC, yet it
cannot constitute an admission of debt, and the appellant is still under an
obligation to establish that there existed an undisputed debt or the default
in paying it within the meaning of Sec.3(11) and 3(12) of IBC.
5. In his reply to the submission of the counsel for the appellant, the learned
counsel for the appellant submitted that the signatures of the representative of
the appellant in the copies of the work orders as seen in the appellant's paper-
Company Appeal (AT) (Ins) No.2381 of 2024 9
book is intended to authenticate the document as per procedure, and it should
not be construed as an admission of having received the work orders in question.
Discussion & Decision
6. Two factors that may provide a cause for a creditor to set in motion a CIRP
either under Sec.7 or under Sec.9 IBC are existence of a debt within the meaning
of Sec.3(11) and the default of the debtor to pay it as defined in Sec.3(12) of the
Code.
7.1 In the present case, there is no dispute that the appellant has not issued
any of the five invoices. It also goes as an admitted fact that on 24.06.2020
(when Covid Wave I was in full swing), that the respondent had paid Rs.
Rs.76,00,975/- towards part payment of the invoice amount besides
Rs.4,22,277 towards GST at 18%. This is followed by a payment of Rs.25.0 lakhs
on 18.04.2023, some two months after the CIRP was laid. Here, the respondent
would argue that whatever amount it had paid only constitutes 20% of the
invoice value which the respondent is required to pay as per Clause 5 of the work
Order. (This tribunal has verified it and it works out to 20.27%). This implies
that the respondent had paid substantial part of the 20% of the invoice amount
in June, 2020, and the balance after the institution of petition under Sec.9 IBC.
What could be gathered here is that the respondent had admitted that the
appellant had performed its contractual obligation, whether wholly or partly, for
the respondent would not have paid anything if the appellant had failed to
perform its part of the contract at all.
Company Appeal (AT) (Ins) No.2381 of 2024 10
7.2 Secondly, it was argued that the respondent has not challenged the
correctness of the invoice value, for it has confirmed it on 01.04.2020, and that
it is not disputed. It however, requires to be noted that the respondent contends
that payment of the balance amount could be withheld till the appellant
produces the certificate of erection, commissioning and testing as stipulated in
clause 5 of the work Order. In other words, according to the respondent, mere
assertion of the completion of the work by the appellant and raising of invoices
will not automatically entitle the latter to claim the invoice-amount, unless the
work done by the appellant is certified in the manner contemplated. In that
sense, the right to claim the value of the work done is conditioned upon
something more - the production of the certificate and few other documents
enumerated in clause 5 of the work Order. What if the quality of work at the
time of such certification itself is challenged? Will the appellant still be eligible
to claim the invoice-amount? That would then become debatable.
8. There is another issue. Even if the correctness of the invoice-amount is
presumed to be true, is there a default within the meaning of Sec.3(12) of the
Code? Sec 3(12) defines a 'default' as, "non-payment of debt when whole or part
or instalment of the amount of debt has become due and payable and is not
paid by the debtor or the corporate debtor, as the case may be". This amplifies
the fact that not only should there be an undisputed debt, but such debt must
have become due for payment at the time when the default is said to have
occurred. In the instant case, even if the existence of debt is presumed, still it
requires to be established by the appellant that it had fallen due for payment.
Company Appeal (AT) (Ins) No.2381 of 2024 11
9. Here there are two versions: The respondent claims that the appellant had
performed its obligation only based on the work Orders whereas the appellant
claims that no work order of the kind was ever given to it. To stretch it further,
the appellant's contention is that inasmuch as the contract between the parties
was oral, the terms of the work orders vis-à-vis the time for payment as
stipulated in Clause 5 thereof would not bind it. Here it may be stated that the
first installment of part payment of Rs.76,00,975 was paid on 24.06.2020 which
was 90 days after the last invoice dated 13.03.2020. However, it cannot ipso
facto be concluded for the purposes of working the IBC that the appellant had
undertaken the work only pursuant to a written work order. There therefore, is
an obvious dispute, and unless this dispute is resolved the time for payment
could not be ascertained.
10. IBC is not intended as a recovery mechanism for realization of debts. Only
where a company by design or default deny the creditor of their dues, law steps
into take control of the affairs of the erring company and arrange to pay off the
creditors either through the process of resolution or liquidation. Therefore, in
every case where a creditor initiates a CIRP, the burden is on the creditor to
satisfy the conscience of the Adjudicating Authority that there exists a debt
which the respondent has not disputed at any time prior to the institution of the
CIRP, and that the debt is not paid when it fell due for payment despite a demand
to pay. It does not even require a debtor to contest the issue, for the statutory
burden is on the creditor to establish that its case qualifies for initiating the CIRP
against the debtor.
Company Appeal (AT) (Ins) No.2381 of 2024 12
11. If the facts of the present case are spread on this plane, it raises a serious
doubt as to whether the time for payment of the entire invoice amount has
arisen. The nature of enquiry contemplated by the IBC is summary in character,
where the criteria prescribed for invoking it should be kept either beyond debate,
or at least must be capable of being ascertained without great degree of forensic
scrutiny. Contextually, the law as declared by the Hon'ble Supreme Court in the
early days of the IBC in Mobilox Innovations Pvt. Ltd., Vs Kirusa Software
Pvt. Ltd. [(2018) 1 SCC 353] is of considerable value. It says:
"51........ all that the adjudicating authority is to see at this stage is whether there is a plausible contention which requires further investigation and that the "dispute" is not patently feeble legal argument or an assertion of fact unsupported by evidence...."
12. The approach is to keep the allegations of the creditor a constant, and to
test the quality of defence offered by the debtor - its character and quality. Here
neither the existence of the debt or the time for payment should depend on the
proof of another independent fact, and this is the bottom line. In this case
however, there has arisen a need to investigate if there was a work order, and if
its terms determine the time for repayment. Unless a finding is entered on this
issue, it may be difficult to decide whether the respondent has committed a
default in payment. The work order whose existence the respondent asserts and
the appellant denies deserves a probe, and it is more than a plausible defence.
13. There however, is a jurisdictional limitation on the tribunal in ascertaining
the existence of the jurisdictional facts - of debt and default. The extent of
Company Appeal (AT) (Ins) No.2381 of 2024 13
enquiry contemplated under the scheme of the IBC does not require it to be
matched to an enquiry which civil courts may engage in - to probe one issue
linked to another issue, and enter a finding in one to feed a finding in another
based on rule of preponderance of probability.
14. Much was argued that the respondent has not replied to notice under
Sec.8 IBC. A failure to reply to Sec.8 IBC ipso facto cannot be construed as an
admission of debt or the time of payment at all circumstances. It depends on
the facts of each case. In the context of the facts of this case, given the fact that
the time of first part-payment of Rs.76,00,975/- is made on 24.06.2020, after
90 days from the date of the last invoice (dated 13.03.2020), marginally tilts the
scale in favour of the respondent yet not conclusively, for, existence of the work
order and whether the appellant had performed its part of the contract based on
the terms of the work order have to be probed independently, and as stated
earlier, the adjudicating authority cannot decide this basic fact on the thumb
rule of preponderance of probability which civil court employs without
restriction.
15. To restate the known, the IBC may not be understood as a hungry octopus
violently spreading its tentacles to prey on every corporate debtor, though
outside the IBC world it is dubbed as a monster mechanism ready to swallow
their affairs. While the scheme of the Code is creditor centric, IBC is not
unconscious of its impact on the commercial solvency of a going company and
its existential stability, the fundamental right to do business and right to
Company Appeal (AT) (Ins) No.2381 of 2024 14
property of the shareholders, besides the reputation of the corporate managers.
And, since the working of the IBC divests the right of the Board of the Corporate
Debtor to manage its affairs, it is made imperative that the existence of
jurisdictional facts - of debt and default must align perfectly with their statutory
definition and are kept beyond any controversy. In Indus Biotech Pvt. Ltd., Vs
Kotak India Venture (Offshore) Fund [(2021)6 SCC 436], the Hon'ble Supreme
court has held,
"21.... If in every case where there is debt, if default is also assumed and the process becomes automatic, a company which is ably running its administration and discharging its debts in planned manner may also be pushed to corporate insolvency resolution process and get entangled in a proceeding with no point of return...."
It underscores why care should not be spared in initiating a CIRP. The
appellant's case fails right here.
16. Turning to the findings of the Adjudicating Authority, we do not propose
to interfere with its ultimate conclusion of dismissing the CIRP under Sec.9 IBC,
but modifies its line of reasoning: (a) the Adjudicating Authority has presumed
the existence of the work Order which the respondent contends, but we consider
that it requires further proof and that unless it is ascertained, it would be difficult
to hold if the time for payment of the invoice amount has arisen; (b) since the
Adjudicating Authority has presumed the existence of work Orders, it ventured
to calculate whether the date for payment of each of the invoice-amount after
the expiry of 90 days from the date of invoice fell after 25.03.2020 for invoking
Sec.10A IBC. Since we propose not to presume the Work Order as the foundation
Company Appeal (AT) (Ins) No.2381 of 2024 15
of the contract between the parties, we have decided not to speculatively apply
the 90 days waiting period for payment as contemplated in Clause 5 of the Work
Order. We therefore, refrain from entering a finding on the application of
Sec.10A of the Code vis-a-vis the facts of the present case.
17. In conclusion, we find that the Order of the Adjudicating Authority does
not require to be interfered with and consequently it is dismissed, but without
any costs.
[Justice N. Seshasayee] Member (Judicial)
[Arun Baroka] Member (Technical) rs/sk
Company Appeal (AT) (Ins) No.2381 of 2024
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.