State Bank Of India vs Mbl Infrastructures Limited & Anr
- CitationCompany Appeal (AT) (Insolvency) No. 539 of 2022
Ratio decidendi
The rule this decision rests on
Where a Resolution Plan has been approved by the Adjudicating Authority and that approval has been upheld by the Supreme Court, all stakeholders, including the Committee of Creditors and its member lenders, are obliged to take steps to implement the Plan, and a lender cannot refuse implementation by relying on viability or feasibility concerns that should have been addressed before the CoC approved the Plan. The exclusion, by the Adjudicating Authority, of the period during which the approval was under challenge in appellate proceedings initiated by the lenders themselves does not amount to a modification of the approved Resolution Plan, where the Supreme Court has itself approved such exclusion on account of litigation pending against the approval. The Adjudicating Authority may direct the lenders to undertake the steps required of them under an approved Resolution Plan, and such directions are within its power where they are in aid of implementation of the Plan; a creditor's own failure to seek directions for non-implementation under the Regulations does not preclude the Authority from issuing them, and the Resolution Applicant must likewise carry out its own obligations under the Plan.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
NATIONAL COMPANY LAW APPELLATE TRIBUNAL, PRINCIPAL BENCH, NEW DELHI Company Appeal (AT) (Insolvency) No. 539 of 2022 (Arising out of Order dated 11.03.2022 passed by the Adjudicating Authority (National Company Law Tribunal), Kolkata Bench, Kolkata in I.A. No.(IB)626/KB/2021 in C.P.(IB) No.170/KB/2017)
IN THE MATTER OF: State Bank of India Stressed Asset Resolution Group, Corporate Centre, 21st Floor, Make Tower 'E' Cuffe Parade, Mumbai-400005. ... Appellant
Vs
1. MBL Infrastructures Limited, 308, 3rd Floor, Baani Corporate One, Commercial Centre, Jasola, New Delhi-110025.
2. Anjanee Kumar Lakhotia, B-37, 1st Floor, Soami Nagar (South), New Delhi - 110017. ... Respondents
Present:
For Appellant: Mr. Krishnendu Datta, Sr. Advocate, Ms. Moulshree Shukla, Mr. Rahul Gupta, Ms. Varsha, Mr. Krishan Singhal, Advocates
For Respondents: Mr. Ratnako Banerji & Mr. Arun Kathpalia, Sr. Advocate, Ms. Anusuya Salwan, Mr. Bankim Garg, Mr. Rachit Wadhwa, Ms. Nikita Salwan, Mr. Shaunak Mitra, Mr. Aditya Dhupar, Advocates
JUDGMENT
ASHOK BHUSHAN, J.
This Appeal by State Bank of India ("SBI"), one of the Member of the
erstwhile Committee of Creditors ("CoC") of M/s MBL Infrastructures
Limited has been filed challenging the order dated 11.03.2022 passed by
Company Appeal (AT) (Insolvency) No. 539 of 2022 1 National Company Law Tribunal, Kolkata Bench, Kolkata in I.A.
No.(IB)626/KB/2021 filed by Respondent herein, in which IA, the
Adjudicating Authority has issued certain directions to the Appellant for
implementation of the approved Resolution Plan. Aggrieved by the order
and directions issued by the Adjudicating Authority, the Appellant has
come up in this Appeal.
2. Brief facts of the case for deciding the Appeal are:
(i) M/S MBL Infrastructures Ltd. was set-up by one Mr. A. K.
Lakhotia. Certain financial facilities were extended to M/S
MBL Infrastructures Ltd. in which default was committed,
resulting in initiation of proceedings under Section 7 of the
Insolvency and Bankruptcy Code, 2016 (hereinafter referred to
as the "Code"). On 30.03.2017, Section 7 Application was
admitted and Corporate Insolvency Resolution Process
("CIRP") begun.
(ii) Mr. A.K. Lakhotia, submitted a Resolution Plan. After
submission of Plan by Mr. A.K. Lakhotia, Section 29A was
introduced in the Code with effect from 23.11.2017. The
Adjudicating Authority declared the Resolution Applicant
eligible vide order dated 18.12.2017, which was challenged by
Punjab National Bank by way of an Appeal, where an interim
order was passed that without prior approval of the Appellate
Tribunal, no Plan shall be accepted. An Appeal was also filed
by the RBL Bank.
Company Appeal (AT) (Insolvency) No. 539 of 2022 2
(iii) The Appellate Tribunal permitted the Appeals to be withdrawn
on 23.03.2018. Thereafter, Resolution Plan was approved by
75.80% voting share. By an order dated 18.04.2018, the
Adjudicating Authority approved the Resolution Plan and also
excluded the period of 106 days.
(iv) The State Bank of India, IDBI Bank, Bank of Baroda and Bank
of India filed four separate Appeals, challenging order dated
18.04.2018 passed by the Adjudicating Authority, before the
Appellate Tribunal. The main ground of challenge in the
Appeal was that Resolution Applicant was ineligible in view of
Section 29A. From time-to-time meeting of all financial
creditors and lenders were held wherein various issues were
discussed.
(v) By order dated 16.08.2019, Appellate Tribunal confirmed the
Plan approval order. A Contempt Application was also filed by
the Resolution Applicant against the State Bank of India, on
which an order was passed by the Adjudicating Authority on
21.10.2019, disposing of the Contempt Petition with direction
to the Committee of Creditors/ Monitoring Committee to
implement the Resolution Plan in entirety.
(vi) Bank of Baroda filed a Civil Appeal No.8411 of 2019, assailing
the Plan approval order. The Consortium Bank has appointed
Forensic Auditor.
Company Appeal (AT) (Insolvency) No. 539 of 2022 3
(vii) The Hon'ble Supreme Court vide its judgment dated
18.01.2022 dismissed the Appeal filed by Bank of Baroda. The
Hon'ble Supreme Court although held that Resolution
Applicant was not eligible under Section 29A, but noticing the
subsequent facts, including the fact that Resolution Applicant
has already infused Rs.63 crores and Corporate Debtor is a
on-going concern, Hon'ble Supreme Court did not interfere
with the order approving the Resolution Plan and was of the
view that Resolution Plan be implemented.
(viii) Before dismissal of the Appeal on 18.01.2022, the Resolution
Applicant had filed IA No. (IB)626/KB/2021 seeking exclusion
of period between 18.04.2018 until disposal of the application.
The Adjudicating Authority vide order dated 11.03.2022
disposed of the IA No. (IB)626/KB/2021 and in paragraphs 11,
12 and 13, the Adjudicating Authority issued following
directions:
"11. After hearing both the parties at length and after going through the pleadings and documents placed on record including the judgments passed by the Hon'ble Supreme Court and the Hon'ble NCLAT, we direct the SBI, the lead bank of the working capital consortium to take steps for implementation of the approved resolution plan by executing working capital consortium documents;
i. By executing capital consortium documents; ii. By issuing Bank guarantee and letters of credit as per approved resolution plan
Company Appeal (AT) (Insolvency) No. 539 of 2022 4
iii. By issuing certificate regarding availability of line of credit as per approved resolution plan iv. And by issuing net worth certificate/ solvency certificate required for bidding in tenders for public section infrastructure projects.
12. It is further directed that meeting available Non Fund Based limits and execution of documentation in respect thereof, shall form an integral part of the approved plan. It is further ordered that the period from 18th April, 2018 till 18th January, 2022 when the Hon'ble Supreme Court passed the judgment and order shall be formally excluded from calculation of the period for implementation of the plan and all dates mentioned in the resolution plan are consequentially extended for implementation of the resolution plan.
13. We understand the concern of the State Bank of India as submitted by the Ld. Counsel, and we direct that forensic audit on the issues like whether the applicants have infused Rs.66 crore or not can be taken up and continued at their end, and the applicants shall provide all the necessary cooperation to the bank in this regard but for the present the prime importance is the implementation of the resolution plan. In case there is any hindrance or non-cooperation by the applicants in the conduct of the forensic audit, the bank can always seek directions from this Adjudicating Authority."
(ix) The State Bank of India aggrieved by this order has come up in this Appeal."
3. We have heard Shri Krishnendu Datta, learned Senior Counsel
appearing for the Appellant, Shri Ratnako Banerji, learned Senior Counsel
Company Appeal (AT) (Insolvency) No. 539 of 2022 5 and Shri Arun Kathpalia, learned Senior Counsel appearing on behalf of
Respondent.
4. The learned Counsel for the Appellant submits that there was no
interim order passed by the Hon'ble Supreme Court staying the
implementation of the Plan, hence, there was no occasion to exclude the
period from 18.04.2018 to 18.01.2022. It is submitted that Lenders have
approved the Resolution Plan keeping in mind a particular time-line under
which the Plan was to be implemented and Lenders have to receive the
money. By exclusion of period of three years and nine months, the
Resolution Plan stands modified, which is impermissible. Granting of
exclusion of three years and nine months fundamentally alters the
Resolution Plan from one by term of ten years to one by term of fourteen
years. It was not open to the Adjudicating Authority to allow modification
of any nature or to permit the conditional implementation. The impugned
order passed by the Adjudicating Authority has altered the very basis on
which the Resolution Plan was adjudged as feasible and viable. The
impugned order failed to take into account that Respondent No.2
(Resolution Applicant) has repeatedly defaulted in implementing the
Resolution Plan. First default committed by the Resolution Applicant is its
failure to bring promoters contribution. The Resolution Applicant has also
failed to discharge the debt of Operational Creditor. The Resolution
Applicant has also failed to comply with cash flow monitoring. The
Resolution Applicant was obliged to issue NCD to the Financial Creditors.
The Corporate Debtor failed to issue the NCD in accordance with due
Company Appeal (AT) (Insolvency) No. 539 of 2022 6 procedure of law including SEBI guidelines. The Resolution Applicant has
never been serious about implementing the Plan. The SBI is a public
financial institution and it cannot disburse finance to entities without
satisfying itself that financial affairs of the entities are not mismanaged.
The SBI and other Financial Creditors were unable to further finance the
Corporate Debtor as the implementation requirement under the Resolution
Plan, the Resolution Applicant never cooperated for a proper forensic audit.
The forensic audit conducted by the erstwhile Resolution Professional
remined inconclusive and unsatisfactory for the Lenders. The Lenders
appointed new Forensic Auditor on 04.10.2019. The new Forensic Auditor
also could not provide a conclusive report. The Lenders appointed another
Forensic Auditor - M/s BDO LLP, but the Corporate Debtor did not
cooperate with the Forensic Auditor.
5. The learned Counsel for the Respondents, refuting the submissions
of the learned Counsel for the Appellant submits that it is the Appellant
and other Lenders, who were never interested in implementing the Plan
and the order of the approval dated 18.04.2018 was challenged by many
Lenders including the State Bank of India. Challenge by the Lenders,
culminated in dismissal of Civil Appeal by Hon'ble Supreme Court on
18.01.2022. During this period, the Lenders had no intention to implement
the Plan. It is apparent from the fact that SBI did not execute necessary
documents regarding execution of working capital consortium document.
The argument regarding cash flow monitoring, in the meeting held on
03.05.2018, all the Banks unanimously agreed that the pool account with
Company Appeal (AT) (Insolvency) No. 539 of 2022 7 SBI shall be the pool account envisaged in the Plan. All proceeds of
Respondent No.1 were deposited and all expenditure were made from the
said pool account. There was sufficient cash flow monitoring in terms of
the Plan. The pool account was in absolute control of the SBI. The Banks
have appointed independent and reputed statutory Auditors of their choice.
Two rounds of forensic audit were already concluded by the Forensic
Auditors empaneled with SBI and approved unanimously by the CoC
without any adverse findings against Respondent No.1. The Promoters
contribution of Rs.63.30 crores (Rs.40.11 crores fresh + Rs.23.19 crores
existing credit) was brought in the pool account by the Promoters within
one quarter of order dated 18.04.2018. All payments that could made,
which were not dependent on execution of documents by SBI were made.
The payment of liquidation value to Dissenting Financial Creditors were
always been available with Respondent No.1 in form of working capital.
Despite being assured since 30.05.2018, the liquidation value has not been
collected by Dissenting Financial Creditors, first on the ground of pending
Appeals before the Appellate Tribunal, thereafter pending Civil Appeal
before the Hon'ble Supreme Court and now again pending Appeal before
this Tribunal. The issue of NCD and their redemption is dependent on SBI
executing the documents as decided unanimously by all Banks on
03.05.2018. The Respondents have implemented all terms of the Plan
except which is dependent on the SBI. The exclusion of period from
18.04.2018 to 18.01.2022 was reasonable and necessary since during the
aforesaid period Lenders themselves were litigating against the approval of
Company Appeal (AT) (Insolvency) No. 539 of 2022 8 Resolution Plan and they had no intention to implement the Plan. The
Banks were clearly of the view that the Plan being already under challenge,
they cannot risk disbursement of significant public money without final
adjudication of the issue raised. When the Banks themselves had no
mindset to implement the Plan, they cannot complain regarding the
exclusion of the subject period during which period was Lenders
themselves, who were challenging the approval of the Plan. The Corporate
Debtor is an infrastructure company executing civil engineering projects
particularly roads and highways. Before approving the Plan, a TEV Study
Report was got conducted by PNB Investment Services Ltd. There was an
economic viability study much before approval of the Resolution Plan. As
per the Techno Economic Viability Report for effective implementation of
the Resolution Plan availability of Bank Guarantees, Letters of Credit and
working capital facility by the Working Capital Consortium was essential.
By approving the Plan, assenting working capital Banks agreed to continue
to make available Non-Fund Based ("NFB") facilities (Bank Guarantees and
Letters of Credit) of Rs.303.63 crores. After approval of the Plan erstwhile
Resolution Professional handed over the management to the Board of
Directors of the Company in terms of the approved Plan. A new working
capital consortium comprising of six assenting Banks was constituted with
the Appellant-SBI as the lead Bank. The Bank got conducted forensic
audit, in which audit report, nothing adverse was found. The Plan was not
implemented by working capital consortium led by SBI. Despite all, the
Banks unanimously agreed to implement the Plan in meeting held on
Company Appeal (AT) (Insolvency) No. 539 of 2022 9 03.05.2018, the Bank had returned NCD stating non-implementation of
the Plan by SBI. Under the circumstances, Respondent was constrained
to file IA No. (IB)626/KB/2021. The Respondent is continuing as a going
concern and several projects have been completed by the Respondent after
approval of Resolution Plan and it was due to non-cooperation of the
Lenders that further steps could not be taken.
6. We have considered the submissions of learned Counsel for the
parties and have perused the record.
7. While noticing the facts of the case, we have noted that even before
approval of the Resolution Plan by the CoC, the issue of ineligibility of
Resolution Applicant was raised and against the order of the Adjudicating
Authority, declaring the Resolution Applicant eligible, Appeals were filed by
Punjab National Bank and RBL Bank, which Appeals were withdrawn on
23.03.2018 by an order of the Appellate Tribunal. Thereafter, Plan was
approved on 18.04.2018. After approval of the Plan by the Adjudicating
Authority, again a set of litigation was initiated by the Lenders, including
the SBI. Four Appeals were filed challenging the Plan approval order. In
the Appeal, which was filed by the Lenders against the Plan approval order,
there was order passed by this Appellate Tribunal that decision regarding
approval or rejection of the Plan, shall not be taken without leave of the
Appellate Tribunal. Ultimately, the Appeals were dismissed by the
Appellate Tribunal on 16.08.2019. We may notice the Minutes of the
Meeting of Consortium Lenders held on 02.03.2019, where issues
regarding Resolution Plan were noticed. The Minutes clearly notice that
Company Appeal (AT) (Insolvency) No. 539 of 2022 10 SBI has challenged the eligibility of the Resolution Applicant before the
Appellate Tribunal. The Appellate Tribunal has also passed an order
directing that no order shall be passed in the contempt proceedings, if any,
filed against the Financial Creditor. Following part of the Minutes is
relevant to notice where details of challenge in the Appellate Tribunal has
been noticed:
"In the meantime IDBI, BOB and OBC approached NCLAT, challenging Resolution Plan approved by NCLT Kolkata. NCLAT vide order dated 09.05.2018 instructed execution as per its orders.
Against the final order of NCLT Kolkata regarding approval of Resolution Plan, IDBI Bank vide appeal No.194/2018 and BOI vide 235/2018 have approached NCLAT Delhi. The case has been admitted on 21.05.2018 and the next date of hearing is 20.03.2018.
The NCLAT Delhi has issued orders on 09.05.2018 and directed that the execution of plan is subject to decision of NCLAT and till then the company has to ensure to protect the value of its assets.
As this, SBI also filed an appeal in NCLAT, reporting ineligibility of Sh. Lakhotia u/s 29A on 03.07.2018. The Hon'ble NCLAT dismissed the appeal on the basis of limitation & did not hear the merits on request of senior lawyer from Sh. A.K. Lakhotia side.
SBI has impleaded application with BOI and approached NCLAT, challenging eligibility of Sh. Lakhotia to be Resolution Applicant with suppressing the facts before NCLT Kolkata to become eligible Resolution Applicant u/s 29A on 18.12.2017.
Company Appeal (AT) (Insolvency) No. 539 of 2022 11 On 20.03.2019 Hon'ble NCLAT issued orders
"Heard in part. We also discussed the matter with the promoters, who are also the Resolution Applicant, about improving the plan before going into the question of legality of the approved plan and the impugned order. Post the case for further under the heading for "Orders on 8th April, 2019 at 2 PM. Until further order, the Adjudicating Authority will not pass any order on the contempt proceedings petition, if any, filed against the Financial Creditor and the officers of the Financial Creditor and others."
SBI apprised that SAMB-II is being shifted to new location and requested all lenders to note new address as under:-
State Bank of India, SAMB-II, 11st Floor, STC Building, Jawahar Vayapar Bhawan, Janpat, New Delhi-110001.
The meeting ended with a vote of thanks by AGM, SBI."
8. The fact that the Financial Creditors right from the very beginning,
even before approval of the Resolution Plan have been raising ineligibility
issue in respect of the Resolution Applicant and after approval of the Plan
several Appeals were been filed by the Lenders themselves, challenging the
approval order contending that Resolution Applicant is ineligible. When
Lenders themselves were challenging the approval of the Plan, it is
reasonable to comprehend that Lenders were not keen to implement the
Plan. The Resolution Applicant has initiated contempt proceedings in
which also subsequently the Adjudicating Authority while disposing of the
contempt application directed the SBI to implement the Resolution Plan.
Company Appeal (AT) (Insolvency) No. 539 of 2022 12
9. Now, we come to the judgment of the Hon'ble Supreme Court dated
18.01.2022 by which order, the Appeal filed by the Bank of Baroda against
the order of the Appellate Tribunal, confirming the approval order was
dismissed. It is relevant to notice that in paragraph 31 of the judgment,
the Hon'ble Supreme Court had noted that Respondent is an on-going
concern. The Hon'ble Supreme Court has also noticed that Respondent
No.3 has infused over Rs.63 crores. The Hon'ble Supreme Court has also
approved the order of Adjudicating Authority, granting extension of
exclusion on account of pending litigation. The Hon'ble Supreme Court
although after considering the submission of the parties held that the
Resolution Applicant was not eligible to submit the Resolution Plan under
Section 29A(b) of the Code, however, Hon'ble Supreme Court even after
holding that Resolution Applicant is not eligible, did not chose to interfere
with the Plan approval order. We may in this regard refer to paragraphs
61, 62, 63 and 64 of the judgment of the Hon'ble Supreme Court, which is
to the following effect:
"61. Having held so, we would like to come to the last part of our order. Though the very resolution plan submitted by the Respondent No. 3, being ineligible is not maintainable, much water has flown under the bridge. The requisite percentage of voting share has been achieved. We may also note that the percentage has been brought down from 75% to 66% by way of an amendment to Section 30(4) of the Code.
62. Secondly, majority of the creditors have given their approval to the resolution plan. The adjudicating authority has rightly noted that it was accordingly
Company Appeal (AT) (Insolvency) No. 539 of 2022 13 approved after taking into consideration, the techno- economic report pertaining to the viability and feasibility of the plan. The plan is also put into operation since 18.04.2018, and as of now the Respondent No. 1 is an on-going concern. Though, the Respondent No.11 has taken up the plea that its offer was conditional, it has got a very minor share which may not be sufficient to impact by adding it with that of the appellant and Respondent No.7. The Respondent No.7 and the Respondent No.11 did not choose to challenge the order of the appellate tribunal.
63. We need to take note of the interest of over 23,000 shareholders and thousands of employees of the Respondent No.1. Now, about Rs. 300 crores has also been approved by the shareholders to be raised by the Respondent No.1. It is stated that about Rs. 63 crores has been infused into the Respondent No.1 to make it functional. There are many on-going projects of public importance undertaken by the Respondent No.1 in the nature of construction activities which are at different stages.
64. We remind ourselves of the ultimate object of the Code, which is to put the corporate debtor back on the rails. Incidentally, we also note that no prejudice would be caused to the dissenting creditors as their interests would otherwise be secured by the resolution plan itself, which permits them to get back the liquidation value of their respective credit limits. Thus, on the peculiar facts of the present case, we do not wish to disturb the resolution plan leading to the on-going operation of the Respondent No.1."
Company Appeal (AT) (Insolvency) No. 539 of 2022 14
10. The Hon'ble Supreme Court in its order made it clear that Resolution
Plan has to be implemented as the Corporate Debtor being a on-going
concern and Promoters have infused over Rs.63 crores. The Hon'ble
Supreme Court also noticed that interest of over 23,000 shareholders and
thousands of employees have to be taken care of. The observations made
by the Hon'ble Supreme Court is clear and categorical that Plan is required
to be implemented.
11. The submission of learned Counsel for the Appellant that order of
Adjudicating Authority excluding the period from 18.04.2018 to
18.01.2022 amounts to modification of the Plan, cannot be accepted. The
Adjudicating Authority has only excluded the period for implementation of
the Plan. Under the Plan, period was provided for implementation was ten
years, the exclusion was granted because of series of litigations, which were
initiated by the Lenders themselves, culminating into dismissal of Civil
Appeal filed by the Bank of Baroda before the Hon'ble Supreme Court. The
exclusion of the period during which litigations between the parties,
instituted by the Lenders was going on, is both just and fair. The Lenders,
who were throughout contending that the Resolution Applicant is ineligible
and they were challenging the approval order before the Appellant Tribunal
as well as before the Hon'ble Supreme Court, have no mindset to implement
the Resolution Plan. The learned Counsel for the Appellant has cited
judgment of the Hon'ble Supreme Court in Jaypee Kensington Boulevard
Apartments Welfare Association vs. NBCC (India) Ltd. - (2022) 1 SCC
401; Ebix Singapore Pvt. Ltd. vs. CoC of Educomp Solutions Ltd. -
Company Appeal (AT) (Insolvency) No. 539 of 2022 15 (2021) SCC OnLine 707; Committee of Creditors of Essar Steel India
Ltd. vs. Satish Kumar Gupta and Ors. - (2020) 8 SCC 531 and Pratap
Technocrats v. Monitoring Committee Reliance Infratel - (2021) 10
SCC 623 to support its contention that Resolution Plan cannot be modified
by the Adjudicating Authority, not it can be whittled down by the
Adjudicating Authority.
12. As observed above, present is not a case where Resolution Plan has
been modified by the Adjudicating Authority. The Adjudicating Authority
vide order dated 11.03.2022 has already granted extension by the
impugned order for the period from 18.04.2018 to 18.01.2022, which
period was taken in the litigation initiated by the Lenders themselves. It is
also relevant to notice that while approving the Resolution Plan on
18.04.2018, the Adjudicating Authority has granted exclusion of 106 days.
The Hon'ble Supreme Court in its judgment dated 18.01.2022 has
approved the exclusion on account of litigation and proceedings. We may
recapitulate paragraph 32 of the Hon'ble Supreme Court, which is to the
following effect:
"32. Both the forums have rightly construed the issue qua extension and exclusion. Admittedly, there were earlier rounds of litigation and proceedings were pending against the interim orders. This issue has also been concluded finally by this Court inter alia holding that in such a scenario exclusion has to be granted, in light of the time spent in litigation."
Company Appeal (AT) (Insolvency) No. 539 of 2022 16
13. When the Hon'ble Supreme Court in earlier round has approved the
exclusion of the period during which litigation were pending, no exception
can be taken to the exclusion of the period from 18.04.2018 to 18.01.2022
as directed in the impugned order by the Adjudicating Authority. The
learned Counsel for the Appellant submitted that it was the Respondent,
who did not cooperate in the implementation of the Plan and they have not
issued the NCD as per the due procedure, hence, the documents regarding
working capital were not executed by the Bank. Whereas, the Respondent
case is that it was the Appellant, who did not discharge its obligation under
the Plan and on the other hand the Respondent has discharged its
obligation by bringing Promoters' contribution to the extent of Rs.63 crores.
The learned Counsel for the Appellant submitted that Promoters'
contribution which was required to be brought up was about Rs.102 crores
and Rs.63 crores was not sufficient. Be that as it may, when the
substantial money was brought by the Promoters contribution, the Lenders
could have initiated the part of process, requiring the Promoters to bring
the balance money.
14. The object of the Code especially in a case where Resolution Plan has
been approved and which approval also received the confirmation from
Hon'ble Supreme Court, it is obligatory on all stake holders to initiate the
implementation of the Plan, trying to find excuses for refusal to implement
by either of the parties cannot be justified. All stake holders had to act in
a manner so as to implement the Resolution Plan. The Lenders cannot
absolve themselves from carrying out their obligation in the Resolution Plan
Company Appeal (AT) (Insolvency) No. 539 of 2022 17 by raising one or other pretext. The submission of the learned Counsel for
the Appellant that due to granting of extension of three years and nine
months in the implementation of the Plan, the Plan is no more viable,
cannot be accepted. Viability and feasibility of the Plan is required to be
considered at the stage when Plan is to be approved by the CoC. After the
Plan has been approved, the issue of viability and feasibility cannot be
allowed to be raised by the Appellant. The Adjudicating Authority did not
modify the Plan in any manner and exclusion of the period from 18.04.2018
to 18.01.2022, cannot be said to be any kind of modification in the Plan.
15. In the Insolvency and Bankruptcy Board of India (Insolvency
Resolution Process for Corporate Persons) Regulations, 2016, under
Regulation 39, sub-regulation (9), a creditor is allowed to apply to
Adjudicating Authority for direction in case there is any non-
implementation of the Resolution Plan. At no point of time, the Appellant
made an application praying for any direction to the Resolution Applicant
towards implementation of the Plan alleging any non-implementation. It
was the Resolution Applicant, who had filed application for contempt
against the Bank and thereafter I.A. No.(IB)626/KB/2021 praying for
direction to the Appellant. The directions, which have been issued by the
Adjudicating Authority in paragraph 11 as noted above, are directions,
which were required to be undertaken by the Lenders and directions issued
by the Adjudicating Authority are in accordance with the Resolution Plan.
No exception can be taken to the directions issued in paragraph 11. The
Lenders and Banks are obliged to discharge their obligations as per the
Company Appeal (AT) (Insolvency) No. 539 of 2022 18 Resolution Plan. The fact that directions have been issued to the Appellant,
cannot mean that Resolution Applicant is not to perform its obligation as
per the Resolution Plan.
16. The learned Counsel for the Appellant has submitted that
Respondent has not cooperated with forensic audit. The learned Counsel
for the Respondent submits that although carrying out forensic audit was
not part of the Resolution Plan, but Bank itself has got conducted the
forensic audit in which audit Report no adverse findings were given against
the Resolution Applicant. Hence, conducting the forensic audit again and
again cannot be a ground for the Appellant to refuse the implementation of
the Resolution Plan. The learned Counsel for the Respondent further
submits that Hon'ble Supreme Court in its order dated 26.10.2021
recorded that the issue of forensic audit stood addressed.
17. The learned Counsel for the Resolution Applicant has undertaken to
perform all its obligations under the Plan as and when it arises according
to the Resolution Plan. Recording the aforesaid statement of the Resolution
Applicant, we are of the view that there is no ground to interfere with the
impugned order passed by the Adjudicating Authority, which order is
clearly in aid of implementation of the Resolution Plan. The
implementation of the Resolution Plan being obligation and duty of all stake
holders as per the scheme of the IBC, as observed above, the Resolution
Applicant shall also carry out its obligation under Resolution Plan
promptly, while the Lenders will discharge their obligations in the Plan and
as per directions issued in the impugned order by the Adjudicating
Company Appeal (AT) (Insolvency) No. 539 of 2022 19 Authority. We, while upholding the impugned order also direct the
Resolution Applicant to carry out its obligations in the Resolution Plan
along with carrying out all the obligations by the Lenders. Subject to above,
the Appeal is dismissed. No order as to costs.
[Justice Ashok Bhushan] Chairperson
[Barun Mitra] Member (Technical)
NEW DELHI
23rd May, 2023
Ashwani
Company Appeal (AT) (Insolvency) No. 539 of 2022 20
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.