State Bank Of India & Ors. & Ors vs Jyoti Structures Limited & Ors. & Ors
- CitationComp. App. (AT) (Ins) No. 388
Ratio decidendi
The rule this decision rests on
In contempt proceedings, a finding of civil contempt requires that the adjudicating authority first record a prima facie satisfaction that a clear, unambiguous and unequivocal case of wilful and deliberate disobedience of its orders is made out, before issuing a show cause notice. Contempt proceedings, being quasi-criminal in nature, require that the alleged contemnor be served with a notice setting out the gist of the specific charges against him, and be afforded a meaningful opportunity to explain and defend his conduct before any punishment is imposed. A sentence of imprisonment for contempt cannot be imposed upon a corporate or institutional entity without identifying, by name, the specific individual(s) who are found to have wilfully and deliberately disobeyed the court's directions; an order that is silent on the identity of the offender cannot be sustained.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
[Arising out of the Impugned Order dated 16.02.2026 passed by the Adjudicating Authority, National Company Law Tribunal, Mumbai, Bench-I in Contempt Application No. 39 of 2025 and Contempt Application No. 41 of 2025 in C.P. (IB) 1137/MB/2017]
IN THE MATTER OF:
1. State Bank of India Having its registered office at State Bank of India, Commercial Branch, N.G.N. Vaidya Marg, Bank Street, Horniman Circle, Fort, Mumbai - 400 001 Email: amtl.cbmumbai@sbi.con, rmamtl.cbmum@sbi.co.in
2. Bank of India Having its registered office at Bank of India, Andheri Large Corporate Branch, MDJ Building, Andheri (W), Mumbai - 400 058 Email: andherilcb.mumbainorth@bankofindia.co.in, asset.mnz@bankofindia.co.in
3. Canara Bank Having its registered office at Mid Corporate Branch, Fort Market, Ground Floor, Canara Bank Bldg., Adi Marzban Street, Ballard Estate, Mumbai - 400 001 Email: cb5505@canarabank.com
4. ICICI Bank Having its corporate office at ICICI Bank Towers, Bandra Kurla Complex, Bandra (East), Mumbai, Maharashtra 400 051 Email: Atit.Dedhia@icicibank.com
5. Indian Bank Having its registered office at: Stressed Asset Management Branch, Mumbai Office No. 73, 7th Floor, Mittal Chambers, Nariman Point, Mumbai-400 021 Email: mumbaifort@indianbank.co.in, s816@indianbank.co.in, armmumbai@indianbank.co.in, A112@indianbanl.co.in, horecovery@indianbank.co.in
6. Union Bank of India Having its registered office at Union Bank of India, Mumbai main office, Union Bank Bhavan, Nariman Point, Mumbai - 400 021 Email: ubin0549576@unionbankofindia.com, samvmumbai@unionbankofindia.com; chandradeep@unionbankofindia.bank, tnlavand@unionbankofindia.bank ...Appellant(s)
Versus
1. Jyoti Structures Limited Having its registered office at: Valecha Chambers, 6th Floor, New Link Road, Andheri (West), Mumbai, Maharashtra - 400 053
2. Abhinav Angirish Residing at: B/1602, Oberoi Sky Heights, Lokhandwala Back Road, Lokhandwala Cx., Andheri West, Mumbai, Maharashtra - 400 053
3. Sharad Sanghi Residing at: No. 23, Sea Gul, Carmicahel Road, Gamdevi, ...Respondent(s) Mumbai, Maharashtra - 400 026
Present: For Appellant : Mr. Tushar Mehta (Solicitor General), Mr. Sunil Fernandes, Sr. Advocate with Mr. Abhishek
Page 2 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 Mukherjee, Mr. Animesh Bisht, Ms. Surabhi Khattar, Mr. Aniruddh Gambhir, Mr. Shivansh Vishwakarma and Mr. Harsh Rathi, Mr. Sriharsh Rai, Anuh A., M. Naik, Vailarh Ram, Advocates. For : Mr. Darius Khambata, Sr. Adv. & Mr. Arun Respondents Kathpalia, Sr. Advocate with Mr. Anuj Tiwari, Ms. Diksha Gupta, Ms. Shalini Basu, Mr. Shivendranath Mishra and Mr. Sameer Mishra, Vaibhav Vats, Advocates for R1. Mr. Abhijeet Sinha, Sr. Advocate with Mr. Malak Bhatt and Ms. Samridhi, Advocates for R2 and R3.
JUDGMENT
(Hybrid Mode) Per: Barun Mitra, Member (Technical)
The present appeal, preferred under Section 61 of the Insolvency and
Bankruptcy Code, 2016 ('IBC' in short), arises from the order dated
16.02.2026 (hereinafter referred to as the 'Impugned Order') passed by the
Adjudicating Authority (National Company Law Tribunal, Mumbai Bench-1)
in Contempt Application No. 39 of 2025 and Contempt Application No. 41 of
2025 filed in C.P. (IB) N0.1137 (MB) 2017. By the said Impugned Order, the
Adjudicating Authority has disposed of both Contempt Application Nos. 39 &
41 of 2025 filed by Respondent No. 1-Jyoti Structures Ltd. and Respondent
Nos. 2 and 3-Shareholders of Corporate Debtor by directing the Appellants to
release the rolled over BG limits failing which they would be subject to one
day simple imprisonment in civil prison. Aggrieved by the impugned order,
the Appellants - Lender Banks have preferred the present appeal.
Page 3 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026
2. Coming to the brief factual matrix of the present case at hand, the
relevant points which require to be noticed are as follows:-
• The Adjudicating Authority had admitted the Corporate Debtor-Jyoti
Structures Ltd. ('JSL' in short) into Corporate Insolvency Resolution
Process ('CIRP' in short) on 04.07.2017.
• The resolution plan submitted by Sharad Sanghi - Respondent No. 3
was approved by the Adjudicating Authority on 27.03.2019. The
Committee of Creditors ('CoC' in short) which had approved the
resolution plan interalia comprised of the Appellant Banks viz. State
Bank of India, Bank of India, Canara Bank, ICICI Bank, Indian Bank
and Union Bank of India and were assenting Financial Creditors of the
Corporate Debtor.
• The approved resolution plan provided for roll-over/issuance of Bank
Guarantees ('BGs' in short)/Letter of Credits ('LCs' in short) by the
Appellants to the Corporate Debtor. The resolution plan provided for
entering into definitive agreements pursuant to which Non-Fund Based
Facility Agreement ('NFB Agreement' in short) was entered into
between the Appellants who are Non-Fund Based Lenders of the
Borrower-Corporate Debtor. The NFB Agreement outlined the detailed
terms and conditions for issuance of NFB limits.
• In terms of the NFB Agreement, the Appellants were to issue BGs/LCs
to the Corporate Debtor immediately upon the "Closing Date" which
"Closing Date" was achieved on 09.11.2021.
• On achievement of the Closing Date, the proposed
shareholders/investors in the Corporate Debtor Company had infused
Page 4 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 Rs. 170 Cr. based on terms and conditions of the approved resolution
plan and in terms of the NFB Agreement, the obligation of the
Appellants as NFB Lenders to release the NFB limits became
purportedly operational.
• As the Appellants allegedly failed to release the NFB limits as provided
for in the approved resolution plan and envisaged in the NFB
Agreement, the Respondents preferred I.A No. 4959 of 2023 and I.A No.
5023 of 2023 before the Adjudicating Authority under Section 60(5) of
the IBC. The Adjudicating Authority in its order dated 20.08.2024
(hereinafter referred to as 'August 20 NCLT order') held that NFB limits
ought to have been released at the first instance by the Appellant
Lenders as contemplated in the Plan and directed the Appellants to
release the NFB limits to the Corporate Debtor and the Respondents
shall furnish information/documents to the Appellant lenders required
by them for review of financial performance of the Corporate Debtor
after its first release.
• The 20 August NCLT order passed by the Adjudicating Authority was
challenged by the Appellants before this Tribunal. This Tribunal
however dismissed the appeal filed by the Appellants on 09.12.2024
(hereinafter referred to as 'December 9 NCLAT order') and confirmed
the August 20 NCLT order. While upholding the order of the NCLT, this
Tribunal also observed that the clauses of the NFB Agreement have to
be read in a manner to give effect to the plan and not make any clause
of the plan otiose and unworkable, the plan having been approved by
Page 5 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 the lenders themselves wherein a conscious decision was taken to roll-
over NFB facilities by the existing lenders.
• On 18.02.2025, the Shareholders of the Corporate Debtor had
submitted an OTS proposal which was followed by OTS proposal from
the Corporate Debtor for Rs. 507 Cr. to the Appellants as an alternative
to the release of NFB Limits which proposal also mentioned that if the
same is not accepted by the Joint Lenders Meeting ('JLM' in short) of
the Lenders on or before 31.03.2025, the OTS proposal shall stand
withdrawn. While there was some discussion on the quantum of the
OTS proposal during the JLM meeting held on 03.06.2025, majority of
the Appellant Banks were in favour of release of NFB Limits. Another
JLM was conducted on 10.09.2025 wherein the Appellants discussed
the status of approval of sanction/roll over of the NFB limits in which
meeting the representatives of the Borrower was also present.
• While some of the Appellant Lenders had either issued fresh sanction
letter or were in the process of issuing such sanction letters sanctioning
their portion of NFB limits, the fresh sanction letters were objected to
by the Respondents-Corporate Debtor and Shareholders for the NFB
facilities had already stood rolled-over in terms of the plan and also
because the fresh sanction orders imposed terms which were
inconsistent with the approved resolution plan and NFB Agreement.
• Since NFB Limits were not released by the Appellants, two separate
Contempt Applications were filed by Respondents No. 1 and by
Respondent No. 2 and 3 against the Appellants seeking release of NFB
Limits on 12.10.2025.
Page 6 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 • Before the Contempt Applications could be adjudicated by the
Adjudicating Authority, Bank of Baroda released its BGs/LCs to the
Borrower on 17.10.2025 which was followed suit by IDBI Bank.
• On 25.11.2025, the Adjudicating Authority in its interim orders
directed all Appellants to adhere to the conditions in the approved
resolution plan and to ensure that sanction letters were issued in
accordance with the terms of the approved resolution plan.
• On 17.12.2025, the Appellants filed an additional affidavit placing on
record the sanction letters issued by each Bank.
• The Adjudicating Authority passed the impugned order on 16.02.2026
disposing both the Contempt Applications by issuing directions to the
Appellant Lenders to release the rolled over BG limits in the manner
provided under the resolution plan and in terms as were applicable to
those limits prior to CIRP within one month from the date of the order
failing which one day simple imprisonment in civil prison was ordered
against the Appellants.
• Aggrieved by the impugned order, the present appeal has been filed by
the Appellants challenging the impugned order on 24.02.2026.
3. Shri Tushar Mehta, Ld. Solicitor General and Shri Sunil Fernandes, Ld.
Sr. Counsel appeared on behalf of the Appellants; Shri Darius Khambata and
Shri Arun Kathpalia, Ld. Sr. Counsels appeared on behalf of the Respondent
No. 1 and Shri Abhijeet Sinha, Ld. Sr. Counsel appeared on behalf of the
Respondents No. 2 and 3. All the parties were heard at length extensively. At
the very outset we would like to observe that the arguments canvassed and
documents relied upon by Respondent No. 1 to 3 being common and
Page 7 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 overlapping, we propose to conjointly record their submissions for reasons of
convenience.
4. Making submissions on behalf of the Appellants, Ld. Solicitor General
submitted that the Contempt Application Nos. 39 & 41 of 2025 filed in CP (IB)
No. 1137 of 2017 before the Adjudicating Authority under Section 425 of the
Companies Act, 2013 and Section 12 of the Contempt of Courts Act, 1971,
suffered from inherent infirmity since the contempt applications were filed by
the Respondents without identifying or implicating any individual as the
alleged contemnor. It was vehemently contended that in the absence of
individuals being specifically named for having wilfully disobeyed the
directions of the court, the present contempt order imposing one day simple
imprisonment is not sustainable in the eyes of law. It was contended that the
impugned order was vitiated in law because the Adjudicating Authority had
directly imposed punishment without recording prima-facie satisfaction that
a case of contempt was made out and without having issued a show cause
notice to the Appellants communicating the gist of charges and giving an
opportunity to defend themselves.
5. Submission was pressed by the Appellants that the Respondents had
clearly failed to unequivocally satisfy that the essential ingredient of contempt
proceedings of wilful and deliberate disobedience of court directions had been
met in the present case. It was asserted that the primary ground on which
the Respondents had filed the contempt application was that the 20 August
NCLT order and 09 December NCLAT Order had laid down that the Appellants
were required to release the NFB limits to the Respondents without issue of
sanction letter which was a fallacious and misconceived argument. It was
Page 8 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 asserted that when the Adjudicating Authority in its own interim order while
hearing the contempt application on 25.11.2025 had itself directed the
Appellants to issue sanction letters in accordance with the resolution plan,
the question of having committed a contempt for having issued sanction
letters could not have arisen. The interim order dated 25.11.2025 is
reproduced below:
"5) Having considered the submissions and in the circumstances, we consider it appropriate to direct all the Eight Banks, viz. (i) State Bank of India; (ii) Bank of India; (iii) Indian Bank; (iv) ICICI Bank Ltd;
(v) Canara Bank; (vi) IDBI Bank Ltd; (vii) Union Bank of India; and
(viii) Bank of Baroda to adhere to the conditions as per the approved Resolution Plan and shall ensure that the Sanction Letter in accordance with terms of the approved Resolution Plan is issued to the Corporate Debtor."
(Emphasis supplied)
6. It was submitted that the issuance of fresh sanction letters for rolling
over the existing NFB exposure alongwith conditions did not constitute
disobedience of August 20 NCLT order or the 09 December NCLAT Order as
has been misconstrued by the Respondents. Elaborating further, it was added
that even the impugned order had not only taken cognizance of the sanction
letters with conditions issued by the Appellants but that the Adjudicating
Authority neither questioned the authority or competence to issue such
sanction orders nor held that the conditions contained therein tantamount to
committing any wilful disobedience of the directions of the Court. Following
paragraphs from the impugned order were adverted to:
"37.However, the issuance of fresh sanction letter for rolling over the existing exposure cannot be considered to the disobedience of the order of this Tribunal so long as the limits are made available in accordance
Page 9 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 with the approved Resolution Plan as observed by us in the order dated 20.08.2024.
38.It is not clear to us whether the Corporate Debtor was availing NFB limits under consortium financing arrangement. However, if the Corporate Debtor was availing the earlier NFB limits under consortium financing arrangement, the stipulation of consortium before release of rolled over limits cannot said to be contrary to the approved Resolution Plan even in view of clause 2.2 of NFB agreement providing for individual obligation on part of each Respondent dehors performance of such obligation by one or more Respondents. On the contrary, in case the Corporate Debtor was not availing the earlier NFB limits under consortium financing arrangement, the stipulation of consortium before release of rolled over limits certainly results into disobedience of the order of this Tribunal and cannot be said an issue of interpretation.
39.Further, the condition in relation to due diligence prior to release of NFB facility can only be extended to project specific due diligence and not to the company label due diligence. Nonetheless, we do not find any disobedience of order in stipulating valuation of securities.
40.Since the personal guarantors have already executed deed of personal guarantee in favour of Security Trustee acting for the benefit of relevant Respondent Lenders, we of considered view the specific stipulation in this relation in the sanction letter does not result into any disobedience.
42.As regards pre condition of credit rating, we find that rating conditions are post released and are ordinarily imposed by the lenders in case last financing for fiscal discipline, we do not consider these conditions to be contravening the stipulations of roll-over if the credit rating does not result into review of company profile beyond the approved Resolution Plan and the order dated 24.08.2024.
43.Further, as regards the conditions alleged to be "Inconsistent terms and provisions" by the Applicant, it is noted that these conditions mandates are in nature of general conditions which are incorporated by the lenders and ought to have been they're in the earlier sanctions as well. However, the Respondents ought to be specific in relation to covenants or general conditions to ensure that none of these conditions contravene the approved Resolution Plan. In relation to stipulation of 100% margin for issuance of guarantees covering disputed liabilities, we do not find any disobedience in this relation.
Page 10 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026
51. Some of the conditions and issuance of sanction letter found bona- fide by this Tribunal cannot be considered as wilful disobedience. The Hon'ble Supreme Court in case of Dinesh Kumar Gupta v. United India Insurance Co. Ltd., (2010) 12 SCC 770 held at para 23 that " ......... Bearing this important factor in mind, it is relevant to note that a proceeding for civil contempt would not lie if the order alleged to have been disobeyed itself provides scope for reasonable or rational interpretation of an order or circumstance which is the factual position in the instant matter. It would equally not be correct to infer that a party although acting due to misapprehension of the correct legal position and in good faith without any motive to defeat or defy the order of the Court, should be viewed as a serious ground so as to give rise to a contempt proceeding".
(Emphasis supplied)
7. It was also asserted that even the resolution plan and the NFB
Agreement expressly provided that the request of Respondents for issue of
BGs/LCs was to be based on due consideration of the project by the issuing
Lender and after taking into consideration of applicable laws and regulations
to the satisfaction of the Lender. Attention was adverted to the relevant clause
in the Plan as reproduced below:
Resolution Plan(Schedule VI, Clause F(1)
"The Proposed Investors have not sought any fresh BG/LC limits, but have only sought a roll-over, utilisation/issuance of the BG/LC limits to the extent of the current exposure of financial creditors as on the date on which the CoC votes on this Final Resolution Plan. Provided however that any such utilisation/issuance of the BG/LC will be done based on due consideration of the project by such creditor issuing the LC/BG and subject to applicable laws and regulations for such issuance / utilisation. However, the approval for the same will not be unreasonably withheld by the relevant Secured Financial Creditor issuing the BG/LC. Also, prior to issuance/ utilisation of the LC/BG, the BG/LC issuing bank will be provided with all details of the project including but not limited to the client, location, and project funding while requesting for issue of rolled over BG/LC, for its evaluation."
(Emphasis supplied)
Page 11 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026
8. That the Appellant-Lenders were also entitled to appraise the projects
of the Respondent while issuing sanction letters also formed part of the
definitive documents which was expressly provided for in the NFB Agreement.
Canvassing this argument, attentions was drawn to read with Recital D Article
1.1; Clause 2.4(a)(i) and (iii) of NFB Agreement which are as reproduced below:
NFB Agreement
"(D) The execution of this Agreement and other Financing Documents by the Borrower has been authorised to give effect to the terms of the Approved Resolution Plan.
ARTICLE 1.1 "Financing Documents" means this (a) this Agreement; (b) any Security Document; (c) the lntercreditor Agreement; (d) sanction letters/renewal letters issued by Lenders from time to time and (e) any other agreement or document so designated by Lenders and the Borrower;"
2.4(a)(i) Subject to the terms and conditions set forth in this Agreement, the Borrower may request a Lender to issue, in a form, manner and tenor acceptable to such Lender based on due consideration of the Borrower and the project by such Lender, a Letter of Credit or Bank Guarantee for its own account, up to the Lender's available Limit in respect of the relevant Letter of Credit Facilities or Bank Guarantee Facilities, as the case may be. The Letter of Credit Facilities and the Bank Guarantee Facilities may be interchanged upto the extent as set out in Schedule I.
(ii)Any request by the Borrower for issuance of a Letter of Credit or Bank Guarantee (or the amendment, renewal or extension of a Letter of Credit or Bank Guarantee) may be made by the Borrower by sending a notice to the relevant Lender (reasonably in advance of the requested date of issuance, amendment, renewal or extension), requesting such Lender to issue the Letter of Credit or Bank Guarantee or identifying the Letter of Credit or Bank Guarantee to be amended, renewed or extended, and setting out the information as required by the relevant Lender to prepare, amend, renew or extend such Letter of Credit or Bank Guarantee, including details pertaining to the project including but not limited to the client, location, and project funding while requesting for issue of rolled over BG/LC, for its evaluation.
...
Page 12 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 2.4(a)(iii)Any such utilisation/issuance of a Bank Guarantee or Letter of Credit will be done based on (a) due consideration of the Borrower and the project by such Lender issuing the Bank Guarantee or Letter of Credit and subject to applicable laws and regulations for such issuance / utilization, to the satisfaction of the Lender. However, the issuance of the same will not be unreasonably withheld by the relevant Lender issuing the Bank Guarantee or Letter of Credit. Also, prior to issuance / utilisation of the Bank Guarantee or Letter of Credit, the issuing Lender will be provided with all details of the project including but not limited to the client, location, and project funding while requesting for issue of rolled over Bank Guarantee or Letter of Credit, for its evaluation and (b) the funding/ financial arrangements required for undertaking and completing the project (including any fund based or non-fund based financing, or milestone based payment in terms of the relevant EPC contract for the project, as applicable), for which the Bank Guarantees/ Letters of Credit is being requested from the relevant Lender(s), has been arranged by the Borrower and requisite documents to this effect having been submitted to the relevant lender prior to the issuance of the Bank Guarantees/ Letters of Credit. The Lender(s) shall also, prior to the issuance of any LC/ BG, as required, have the right to appoint a lenders' independent engineer for appraisal and evaluation of the project. The reasonable costs and expenses of such LIE shall be borne by the Borrower. Such appointment shall not be unreasonably withheld or delayed by the Lenders."
(Emphasis supplied)
9. Even the August 20 NCLT order at paras 7.1 and 7.2 had recognised
that the Lenders were entitled to appraise the projects of the Company before
releasing the NFB facilities which is as extracted:
"7.1. There is no dispute between the parties that the Respondents have right to evaluate each project awarded by the customer of Company. The dispute before us pertains to the Respondent's right to also evaluate the Company as such before releasing Non-Fund Facilities, which shall result into issuance of Guarantee(s)/Letter of Credit by the Respondents in relation to projects awarded to the Company, as is contemplated in NFB Agreement having been entered subsequent to approval of Resolution Plan in terms of stipulation contained in such approved Resolution Plan that the parties shall enter into definitive agreements.
Page 13 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 7.2. It is not in dispute that Resolution Plan contemplate for appraisal of Project only, however, NFB Agreement contemplate for consideration of company as well as project. The consideration of company as stipulated in NFB agreement is the bone of contention and has caused holding back the NFB facilities by the Respondents, though the Guarantees/Letter of Credit in force as on date of approval of Resolution Plan were allowed to be continued...
(Emphasis supplied)
10. Further the above finding has also been affirmed by this Tribunal in its
9 December order at para 24 wherein it held "that the lenders shall examine
the project for which bank guarantees have been asked for and the Respondent
shall have right to constantly monitor the business performance of the company
and shall be competent to raise flag at appropriate time in case of deviation and
take corrective action at that time and company shall furnish
information/documents required by the lenders for review of financial
performance of the company after its first release". The NCLAT order had only
prohibited the reassessment and reappraisal of the Borrower as a condition
precedent for release of BGs/LCs and Appellants having adhered to this
observation committed no breach of 09 December NCLAT order. However,
incorporation of other conditions as provided for in the resolution plan and
the NFB Agreement and incorporation of conditions arising out standard
banking requirements had not been prohibited either by the 20 August NCLT
or the 09 December NCLAT orders.
11. It was vehemently contended that it was misconceived on the part of
the Respondents to contend that no fresh sanction letters could have been
issued and that BGs/LCs limits were to be released to the Corporate Debtor
Company by the Appellant Lenders unconditionally. It was also asserted that
the conditions in the sanction letters issued by the Appellants were neither
Page 14 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 unreasonable not did it involve any evaluation or appraisal of the Borrower
Company. In fact when the rationale for each and every condition in the
sanction letter was explained in details by the Appellants before the
Adjudicating Authority, these conditions could not be seen to be a defiance of
the court directions. When neither the resolution plan nor the NFB Agreement
nor the August 20 NCLT order or the December 9 NCLAT order put any
embargo on the issue of sanction letters or imposing of conditionalities
therein, there was no basis to substantiate wilful disobedience of court
directions by the Appellants or any cogent ground for the Adjudicating
Authority to hold that the Appellants by their conduct had committed
contempt of the orders of the NCLT or this Tribunal. When the impugned order
itself records that it has found the issuance of the sanction letter with
conditions to be bonafide, clearly this could not thereafter be a good ground
for holding the Appellants to be contemnors. Further, the impugned order at
para 59 having noted that the conduct of the Appellants on release of NFB
limits has been guided by their concern for safety of public money and
adherence to RBI norms, this clearly demonstrates that Appellants had raised
their defence to justify their conduct, hence, the finding of wilful disobedience
of the courts' order cannot be sustained.
12. It was also asserted that the Appellants had acted in good faith and
issued sanction letters as a positive step towards release of NFB limits while
the delay in the release of NFB limits was entirely attributable to the conduct
of the Respondents who without fleshing out reasons for their purported
objections to the conditions contained in the sanction order have
unreasonably desired unconditional release of NFB limits. The August 20
Page 15 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 NCLT Order was confined to directing the Appellants to release the NFB limits
at the first instance but did not prohibit the Appellants from issuing sanction
letters with specific terms and conditions therein for such release. The
Appellants having issued the sanction letters had fully discharged their
obligations. Onus had shifted to the Respondents to accept and comply with
the terms of the sanction letters. Having refused to accept the sanction letters,
NFB limits could not have been released by the Appellant Banks. Moreover,
the Respondents had insisted on unconditional release which was an
arbitrary demand on their part and towards perpetration of this unreasonable
demand, they chose to file a contempt application while circumventing their
own obligations to accept and act upon the sanction letters. Hence, while the
Appellants having demonstrated their bonafide, the Borrowers by not
accepting the sanction letters are disentitled from contending that the
Appellants had wilfully disobeyed the orders of NCLT and NCLAT.
13. A lot of emphasis was laid by Ld. Solicitor General that the Appellants
being bound by standard banking compliance requirements, issuance of
sanction letters constituted an integral part of the standard banking norm for
availing of BGs/LCs, the fundamentals behind issuance of sanction letters
did not suffer from any impropriety. The issuance of sanction also cannot be
objected to particularly so since sanction letters were issued to the Corporate
Debtor even prior to its getting admitted into CIRP. It was further added that
the Appellants are governed by RBI Regulations and these Regulations
required periodical review of credit limits and adherence to internal policies
Page 16 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 relating to NFB facilities, which has also been recorded in the impugned order
at para 33 (ix) which is as extracted below:
"ix. Banks are required to make internal policies relating to guarantees on aspects such as tenor, renewal. [The RBI (Commercial Banks Credit Facilities) Directions, 2025 issued on 28.11.25 consolidate the extant regulations. They contemplate compliance by banks of their internal policies put in place even for the purpose of renewal."
14. Furthermore, it was added that the stance of the Respondents that the
obligations of the Appellants to release the BG/LC limits was several and not
joint was entirely misplaced. Clause 2.2(a) of the NFB Agreement itself
stipulated the liability of the Lenders to be separate and the relevant clause
is as extracted hereunder:
2.2. Obligations of the Lenders
a) Except as specifically set out in this Agreement, the obligations of the Lenders under this Agreement are several. No Lender shall be responsible for the obligations of any other Lender. The failure of any Lender to carry out its obligations under this Agreement shall not relieve the Borrower or any other Lender from any of its obligations under this Agreement.
(Emphasis supplied)
15. Moreover, the impugned order has itself recorded that if the Corporate
Debtor was availing earlier NFB limits under consortium financing
arrangement, the stipulation of consortium was not contrary to the terms of
plan. In support of their contention, the Appellants adverted attention to
paragraph 38 of the impugned order which is to the effect:
"38. It is not clear to us whether the Corporate Debtor was availing NFB limits under consortium financing arrangement. However, if the Corporate Debtor was availing the earlier NFB limits under consortium financing arrangement, the stipulation of consortium before release of rolled over limits cannot said to be contrary to the approved Resolution Plan even in view of clause 2.2 of NFB agreement providing for individual
Page 17 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 obligation on part of each Respondent dehors performance of such obligation by one or more Respondents. On the contrary, in case the Corporate Debtor was not availing the earlier NFB limits under consortium financing arrangement, the stipulation of consortium before release of rolled over limits certainly results into disobedience of the order of this Tribunal and cannot be said an issue of interpretation."
Therefore, it was contended that when the previous sanction letters provided
for consortium financing arrangement, such an arrangement now in the
sanction orders cannot be said to be contrary to the resolution plan. Even if
it is accepted for argument's sake that there was a condition of several liability
on the Lenders, the very fact that Lenders have issued their respective
sanction letters and have also confirmed their willingness to release their
individual share of the NFB limits, there was no evidence of any violence being
caused to the court directions. It was pressed hard that it not incumbent upon
the Appellants to follow the course of action adopted by Bank of Baroda (BoB)
and IDBI Bank of separate release of NFB limits by them whose exposure was
distinguishably smaller in comparison to the limits of the other Appellants
which ranged from Rs. 51 Cr. to Rs. 101 Cr. as against Rs. 3 Cr. to 3.75 Cr.
in case of BoB and IDBI Bank.
16. It was also contended that when any order is susceptible to more than
one interpretation, this amounts to ambiguity in the direction of the Court
and it is a well settled legal precept that disobedience to an ambiguous order
is a clear defence to contempt action as has been held in the judgement of
Hon'ble Supreme Court in Ram Kishan v. Tarun Bajaj & Ors., (2014) 16
SCC 204 which is as reproduced here under:
"15. It is well-settled principle of law that if two interpretations are possible, and if the action is not contumacious, a contempt proceeding would not be maintainable. The effect and purport of
Page 18 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 the order is to be taken into consideration and the same must be read in its entirety. Therefore, the element of willingness is an indispensable requirement to bring home the charge within the meaning of the Act."
17. Reliance was also placed on the judgement of Hon'ble Supreme Court
in Sushila Raje Holkar Vs. Anil Kak (2008) 14 SCC 392 to contend that
the effect and purport of the impugned order cannot be seen in a fragmented
manner but read in its totality and if multiple interpretations are possible,
there is a good defence against being held guilty of contempt. The relevant
portion of the said judgement is as under:
"28. ...... It is a well-settled principle of law that if two interpretations are possible of the order which is ambiguous, a contempt proceeding would not be maintainable. In State of Bihar v. Sonabati Kumari it was stated: (AIR p. 225, para 18)
"18. (2) The second contention urged was that even if on a proper construction of the order, read in the light of the relevant pleadings, the State Government was directed to abstain from publishing a notification under Section 3(1) of the Act, still, if the order was ambiguous and equivocal and reasonably capable of two interpretations, a party who acted on the basis of one of such interpretations could not be held to have wilfully disobeyed the order. Stated in these terms, the contention appears unexceptionable. For its being accepted in any particular case, however, two conditions have to be satisfied: (1) that the order was ambiguous and was reasonably capable of more than one interpretation, (2) that the party being proceeded against in fact did not intend to disobey the order, but conducted himself in accordance with his interpretation of the order."
Harping on the fact that contempt jurisdiction has a narrow compass, it was
contended that not only the finding of the Adjudicating Authority about wilful
disobedience of the court directions cannot be sustained but also that the
contempt proceedings are liable to be set aside as punishment for contempt
Page 19 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 has been imposed without identifying specific individuals and without
notifying them the positive finding recording contempt having been committed
by them and giving them an opportunity to be heard in their personal
capacity.
18. Rebutting the arguments canvassed by the Appellants, the Ld.
Counsels representing the interests on behalf of Respondents No. 1, 2 and 3
in unison defended the decision of the Adjudicating Authority holding the
Appellants to be in contempt of their directions of 20.08.2024 which had been
affirmed by this Tribunal on 09.12.2024. It is the contention of the
Respondents that the Appellants as the assenting financial creditors of the
Corporate Debtor Company in the CoC had themselves approved and
consented to the resolution plan. Hence they were required to fulfil their
reciprocal obligations under the resolution plan, particularly so, when the
Investors/Shareholders of the Corporate Debtor had already complied with
their part of obligations under the resolution plan of infusing funds. The
Respondents as on the Closing Date had already infused Rs. 170 Cr. by way
of equity in terms of the resolution plan and because the Appellants had not
yet fulfilled their reciprocal obligations of releasing NFB limits, the
Shareholders of the Corporate Debtor were compelled to infuse additional Rs.
732 Cr. The continued failure of the Appellants to release/disburse the
BGs/LCs has put to jeopardy the investment made by the shareholders of the
Company and amounts to clear defiance of court directions.
19. It was also submitted that Corporate Debtor being an Engineering
Procurement and Construction (EPC) Company was heavily reliant on
banking support and hence sought roll-over of existing BGs/LCs limits as
Page 20 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 envisaged under the resolution plan which was not only necessary for the
growth of revenue and margin of the Corporate Debtor but was essential for
its survival. The resolution plan in its Executive Summary at Clause 2(b) had
clearly stipulated that the Shareholders/Investors of the Corporate debtor
would require a roll-over of the BGs/LCs to the extent of the current exposure
of the Financial Creditors as on the date of approval of the resolution plan
approved by the CoC. The said clause is as reproduced below:
"2. Restructuring of Debt
(b) Engineering Procurement & Construction ("EPC") business is dependent on banking support. In this regard, the Proposed Investors have not sought any fresh limits. The Proposed Investors would only require roll-over of bank guarantees ("BG")/letter of credit ("LC") limits to the extent of the current exposure of financial creditors as on the date on which the CoC votes on this Final Resolution Plan.
This will ensure growth of revenue and margins for the Company, which are crucial for meeting debt repayment commitments. The roll-over of the BG /LC limits is only applicable to the extent of released/ discharged/ cancelled/ returned (by the beneficiaries) BGs/LCs (and not invoked/ encashed BGs/LCs). This is further explained in paragraph F of Section VI.
In case any new BG/LC, that is issued after the BG/LC limit being rolled over, is invoked or encashed, the amount of such invocation/ encashment will be payable by the Company on demand, as per the terms of the BG/LC."
It was emphasised that the Respondents had only sought issuance of existing
BGs/LCs limits and no fresh limits were sought.
20. Besides the resolution plan, even the NFB Agreement which gave effect
to the terms of the approval resolution plan also recorded the obligations of
the Appellants to issue BGs/LCs. Recital C and D of the NFB Agreement read
as under:
Page 21 of 41
Comp. App. (AT) (Ins) No. 388 & 389 of 2026 "(C) In furtherance of the terms of the Approved Resolution Plan, the Borrower and the Lenders have agreed that the Lenders shall make available to the Borrower the Facilities up to an amount not exceeding an aggregate of their respective Limit in the manner stipulated in Schedule I hereto and upon the terms and conditions set out in this Agreement for existing or future projects to be undertaken by the Borrower. This Agreement sets out the terms and conditions of the Facilities sanctioned to the Borrower, as extended and modified by the Lenders."
(Emphasis supplied)
Also, Article 5 of the NFB Agreement provided that the Appellant were obliged
to disburse the NFB limits effective as on Closing Date which is as reproduced
below:
"5.1 PRE-DISBURSEMENT CONDITIONS
The obligation of the Lenders to disburse/permit it the utilization and/or Drawal of the Facilities under this Agreement shall be effective as on the Closing Date. Provided that this is without prejudice to the continuation of the any bank guarantee or letter of credit or indemnity issued by a Lender under the sanction letters and subsisting as on the Effective Date which shall continue and be in full force and effect and shall be governed by the terms of this Agreement and the Approved Resolution Plan."
(Emphasis supplied)
21. The NFB had thus clearly set out the terms and conditions of the
facilities sanctioned to the Corporate Debtor Company which contractually
obligated the Appellants to disburse BGs/LCs to the Corporate Debtor
immediately upon the Closing Date. No fresh sanction letter was contemplated
under the NFB Agreement. It is an undisputed fact that the Closing Date was
achieved on 09.11.2021 and yet until now even after nearly five years, the
Appellants have been dragging their feet by not disbursing/releasing the
BGs/LCs. Once, the resolution plan was approved by the Adjudicating
Authority it had become statutorily binding on all concerned including the
Page 22 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 Appellants. The resolution plan had also provided for the execution of
definitive documents which were to supersede and replace the terms of all
agreements with all existing financial creditors of the Corporate Debtor
Company including the Appellants. When the resolution plan provided for
roll-over of existing NFB limits, it clearly implied that the Appellants had
already sanctioned the NFB limits and issue of fresh sanction letters by the
Appellants cannot be viewed as compliance with their reciprocal obligations
as has been wrongly asserted by the Appellants.
22. When the resolution plan was approved by the Appellant Banks in their
capacity as CoC members, the plan had become final and binding on all
stakeholders including the Appellants. The Appellants were obliged and
bound by the plan to release/disburse NFB limits to the Corporate Debtor in
accordance with the resolution plan and the NFB Agreement. Embattled as
they were in making debt repayments and in improving their business
performance, it was added that the Respondents had made multiple requests
to the Appellants to issue the BGs/LCs as they were heavily reliant on the
NFB limits. This was a case where the Appellants despite having already
secured their share of profits by sale of equity shares received by them from
the Corporate Debtor on the Closing Date, and reaped the gains from the
resolution plan they were wilfully jeopardising the revival of the Corporate
Debtor by non-release of NFB limits.
23. Since, the Appellants had not been acceding to the request of the
Respondents for issue of BGs/LCs, the Shareholders had approached the
Adjudicating Authority following which it issued clear directions on
Page 23 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 20.08.2024 for immediate and several release of NFB limits by the Appellants
at the first instance. The relevant orders are as extracted below:
"7.7. ... Accordingly, we have no hesitation to hold that CoC was conscious of proposals in the Resolution Plan in relation to NFB limits and they voted on the Plan realising fully well that the said NFB limits are to be released, subject to project appraisal...... 7.9. ...However, we are of the considered view that the NFB limits ought to have been released at the first instance by the lenders as contemplated in the plan."
24. It was emphatically asserted that non-release of BGs/LCs had also been
frowned upon by this Tribunal on 09.12.2024 by observing that the CoC while
approving the plan had consciously decided to roll-over NFB facilities by the
existing Lenders such conduct was akin to stopping the Corporate Debtor
from carrying out its normal functions which was never the object of
resolution plan. The relevant paragraph of the said order is as reproduced
below:
24. ...... We have noticed the relevant clauses of the plan which indicate that various repayments have to be made by company out of cash flow and revenue generated. The company being EPC contractor has to carry out and to work the contract to earn revenue, without the company carrying any contract it cannot generate revenue. Stopping the company to not able to work any contract due to non-release of bank guarantee is akin to stopping the company from carrying out normal function which shall lead non-compliance of the repayment obligation of the company which can never be object of approval of the Resolution Plan. Counsel for the Respondent has also relied on Joint Lenders' Meeting held on 26.09.2024 i.e. after passing of the order passed by the Adjudicating Authority where IDBI Bank has also flagged the issue the non-release of NFB limits may jeopardise the operations of the company which will impact the repayment of NCDs to assenting Financial Creditors......"
(Emphasis supplied)
Page 24 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026
25. However, the Appellants had consciously and deliberately failed to
comply with their reciprocal obligations to release the sanction/rolled-over
NFB limits at the first instance as directed by the 20 August NCLT order which
was subsequently duly affirmed by this Tribunal vide order dated 09.12.2024.
This non-release of NFB limits was in gross violation of the judicial orders
passed. Failure to discharge their reciprocal obligations under the resolution
plan inspite of clear directions by the Adjudicating Authority and this Tribunal
clearly constituted contempt of the court's authority.
26. Once the primary step of issuance of sanction orders had taken place
after the approval of the resolution plan and the Appellants had signed the
NFB Agreement setting out the detailed terms and conditions and procedure
for issue of BGs/LCs, the procedural requirement of sanction order already
stood met and the Appellants thereafter cannot insist on issuance of a fresh
sanction. By issuing fresh sanction letters, four years after Closing Date, the
Appellants had effectively restarted the process. Moreover, the Appellants
have issued afresh sanction letters without demonstrating any shortcoming
or deficiencies on the part of the Corporate Debtor Company which had led to
non-release of BGs/LCs to the Company Corporate Debtor. Issuance of fresh
sanction was nothing but a disguised attempt to create a new parent
document to govern the relationship between the Appellants and the
Corporate Debtor in a manner which was at variance from the original
relationship envisaged under the resolution plan and the NFB Agreement and
a contrived afterthought to resile from their obligations under the plan.
Therefore, the intent was clearly to delay and/or avoid releasing of the NFB
limits. The fresh sanction letters cannot be taken as an innocent, innocuous
Page 25 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 and harmless document but a strategised and calculated design to repudiate
their committed obligations and obstruct the release of the NFB limits. This
was clearly a wilful breach of the direction given by the Adjudicating Authority
and this Tribunal in their respective orders of 20.08.2024 and 09.12.2024.
27. It is the case of the Respondents that it has been the consistent
approach of the Appellants not to release the BGs/LCs which had been rolled
over under the resolution plan in spite of multiple opportunities given to them.
The same intransigence can be seen when the Appellants again failed to abide
by the interim order dated 25.11.2025 passed by the Adjudicating Authority
wherein the Appellants were directed to ensure that their sanction letter was
to be in accord with the terms of the approved plan. Despite clear directions
to the Appellants to adhere to the terms and conditions of the resolution plan,
they proceeded to issue fresh sanction letters and insisted on compliance with
new terms and conditions set out therein in variance with the approved
resolution plan and NFB Agreement. As no forward action was taken by the
Appellant Banks, the Respondents were left with no choice but to file the
contempt application. Even the impugned order at Para 59 had provided yet
another opportunity to the Appellants to release the BGs/LCs in the manner
provided in the approved resolution plan. Instead of complying thereto, the
Appellants chose to file an appeal before this Tribunal. In such circumstances,
the impugned order has rightly found the conduct of the Appellants to be
intentionally evasive in discharging their obligations of disbursing the NFB
limits by issue of BGs/LCs which amounted to wilful disobedience of the
orders of 20.08.2024 and 09.12.2024 issued by the Adjudicating Authority
and this Tribunal respectively.
Page 26 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026
28. It was further contended by the Respondents that the Appellants have
made the release/disbursal of NFB limits subject to availability of limit by
other lenders. This conditionality was never contemplated in the plan or the
NFB Agreement. In terms of the "General Terms of the Facilities" under the
NFB, the Banks had already sanctioned facilities to the Corporate Debtor
Company and that upon the Closing Date being achieved 'each of the Lenders
had already agreed to extend/lend to the Borrower the facilities to the
maximum extent of the limits as was clearly spelt out in Clause 2.1(a) of the
NFB Agreement. Further, the NFB Agreement at Clause 2.2(b) clearly provided
that the obligation of each NFB Lender was to release its respective limit and
that the obligation of each of the Lenders was 'several'.
"2.2. Obligations of the Lenders
a) Except as specifically set out in this Agreement, the rights of the Lenders under this Agreement are separate and independent rights and any debt to any Lender arising under the Financing Documents from the Borrower shall be a separate and independent debt from debt owed to any other Lender. Except as specifically set out in this Agreement, a Lender may separately enforce any of its rights arising out of this Agreement."
The approved resolution plan had also stipulated that the BG limits will be
allowed to be used as LCs as per business needs. Clause 2.4 of the NFB
Agreement under the caption 'Terms of the Facilities' also provided that the
LC and BG facilities may be interchanged up to the extent as set out in
Schedule I.
29. Once the Closing Date was achieved by which time the investors had
already infused their share, the obligation of the NFB lenders to
release/disburse the NFB limits severally and separately had become
Page 27 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 operational and having failed to release the same, they acted in contravention
of the resolution plan and NFB Agreement. Further, the contention of the
Appellants that release of NFB limits was joint was misplaced as it fails to
explain how BoB and IDBI Bank had released the NFB limits on their own
steam. It was also pointed out that merely because the comparative quantum
of exposure of BoB and IDBI were not as large as much as of the Appellants,
the margin of exposure cannot be a cogent ground not to comply with binding
release orders issued by the Adjudicating Authority and this Tribunal. It was
also pointed that on the one hand the Appellants have claimed that they were
not bound by the decision taken by BoB and IDBI but at the same time have
also claimed that the release of NFB limits have to be done by the consortium.
This mutually contradictory stance was also in contravention of the NFB
Agreement which expressly sets out that the obligation of the Appellants was
several and not joint.
30. Submission was also pressed that the Appellants had taken shield of
compliance with RBI Regulations as a condition for non-release of the NFB
limits without specifically spelling out as to which applicable laws or
regulations of the standard banking practices prevented them from releasing
the BGs/LCs limits. It was asserted that the 09 December NCLAT order had
already dealt with this aspect at para 24 of its order which is as reproduced
below:
"24. The above clause which has been relied by Counsel for the Appellant as its heading showing is towards 'precautions for averting frauds'. The above clause is for the purposes of averting frauds. Present is not a case that the borrower is asking for issuance of NFB facilities which will lead to perpetuating any fraud on the lenders. Present is a case where Resolution Plan has already been
Page 28 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 approved by the CoC where decision was consciously taken to roll- over NFB facilities by the existing lenders. It is also not the case that the borrower has defaulted in any of the bank guarantees or letter of credit so as to give any apprehension in the mind of the lenders that borrower will not be able to honour the service the NFB facilities."
Taking the plea of RBI Regulations was a farcical ploy adopted by the
Appellants to justify their wilful and deliberate action of not issuing the
BGs/LCs. It was also pointed out that when BoB and IDBI Bank which were
also public sector banks could have issued BGs/LCs upon demand by
Corporate Debtor under the NFB Agreement, it remains unexplained as to
how the RBI circulars prevented the Appellants from issuing the BGs/LCs.
The ground of adherence to RBI norms and Internal Banking Procedures been
resorted to frustrate the release of the NFB limits which was clearly an
attempt to defy the judicial directions contained in the August 20 NCLT Order
and December 9 NCLAT Order.
31. Asserting that the directions of the Adjudicating Authority were clear,
unambiguous and therefore binding, submission was pressed that conduct of
the Appellants satisfy all ingredients of wilful and deliberate disobedience of
court direction. Reliance was placed on the judgment of the Hon'ble Supreme
Court in Maninderjit Singh Bitta Vs. Union of India, (2012) 1 SCC 273
wherein it was held that every person is expected to obey the orders of the
Court in its true spirit and where the party does not obey the orders of the
Court nor approaches the Court seeking extension of time for compliance or
variation of the order, the only possible inference is that the party intends to
disobey the orders of the Court. The persistence on the part of the Appellants
insisting on issue of fresh sanction letters with new terms and conditions
Page 29 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 clearly amounted to wilful disobedience and defiance of Courts orders which
tantamount to committing contempt.
32. We have extensively heard the Ld. Counsel for all the parties and have
noted the rival contentions in great details and perused the records carefully.
33. It is an undisputed fact that the impugned order has stemmed out from
the prayers made in two contempt applications which had been filed by the
Respondents herein.
34. At this stage, it may be useful to glance at the prayers contained in the
two Contempt Applications which have been filed by the Respondents which
is reproduced below:
Cont. App. 39 of 2025
"In view of the above-mentioned facts and circumstances the Applicant most respectfully prays that this Hon 'ble Tribunal may be pleased to order and direct:
a) That this Hon'ble Tribunal order that the Respondents are guilty under Section 74(3) of the Code for willfully and knowingly contravening the provisions of the Approved Resolution Plan;
b) That this Hon'ble Tribunal order that the Respondents are guilty of contempt of this Hon'ble Tribunal and the Hon'ble Appellate Authority for willful, deliberate disobedience/breach of the order dated 20 August 2024 passed in Interlocutory Application No. 5023 of 2023 by this Hon'ble Tribunal and order dated 9 December 2024 of the Hon'ble Appellate Authority by way of which it affirmed order dated 20 August 2024, in terms of Section 12 of the Contempt of Courts Act, 1971;
c) Order the chairmen/officers in-charge of the Respondent banks, to undergo imprisonment and pay fine in terms of Section 74(3) of the Code and Section 12 of the Contempt of Courts Act, 1971;
d) Order and direct Respondents to purge contempt by forthwith complying with the order dated 20 August 2024 passed in Interlocuto1y Application No. 4959 of 2023 by this Hon'ble Tribunal and order dated 9 December 2024 of the Hon'ble Appellate Authority by way of which it affirmed order dated 20 August 2024;
Page 30 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026
e) Pass any such other order or orders as this Hon'ble Tribunal may deem fit, proper, and appropriate in the interest of justice;
f) Costs of this Application."
Cont. App. 41 of 2025
"In view of the above-mentioned facts and circumstances the Applicant most respectfully prays that this Hon'ble Tribunal may be pleased to order and direct:
a) That Respondent banks (No. 1 to 7) are guilty under Section 74(3) of the Code for willfully and knowingly contravening the provisions of the Approved Resolution Plan;
b) That this Hon'ble Tribunal order that the Respondent banks (No.1 to
7) are guilty of contempt of this Hon'ble Tribunal and the Hon'ble Appellate Authority for willful, deliberate disobedience/breach of the order dated 20 August 2024 passed in Interlocutory Application No. 5023 of 2023 by this Hon'ble Tribunal and order dated 9 December 2024 of the Hon'ble Appellate Authority by way of which it affirmed order dated 20 August 2024, in terms of Section 12 of the Contempt of Courts Act, 1971;
c) Order the officers in-charge of Respondent banks (No.1 to 7) to undergo imprisonment and pay fine in terms of Section 12 of the Contempt of Courts Act, 1971 and/or Section 74(3) of the Code;
d) Order and direct the Respondent banks (No.1 to 7) to purge the contempt by forthwith complying with the order dated 20 August 2024 passed in Interlocutory Application No. 5023 of 2023 by this Hon'ble Tribunal and order dated 9 December 2024 of the Hon'ble Appellate Authority by way of which it affirmed order dated 20 August 2024;
e) Pass any such other order or orders as this Hon'ble Tribunal may deem fit, proper, and appropriate in the interest of justice;
f) Pass an order granting the costs of this Application in favour of the Applicants."
35. It would be constructive to see how the Adjudicating Authority had
disposed of both the Contempt Applications. The relevant para 59 of the
impugned order is as reproduced below:
"59. It is noted that the Respondent's Officers are in contempt of this Tribunals order however their defiance arises from their concern for safety of public money and adherence to the RBI norms. Accordingly, we Page 31 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 are of considered view that end of justice would be met if the Respondents release rolled over BG limits in the manner provided in the approved Resolution Plan and in terms as were applicable to those limits prior to commencement of CIRP within one month from the date of communication of this Order, considering that the Applicant as well as the Respondents have a long way to go together and any disharmony between them may be prejudicial to their business interest as well. In case, the Respondents failed to do so within the period allowed, this Tribunal orders one day of simple imprisonment in civil prison and the application herein, shall inform the Prison authorities for taking appropriate action for compliance of this order."
36. It was contended by Ld. Solicitor General that the Adjudicating
Authority in the present case has neither formed any prima-facie satisfaction
of unambiguous and unequivocal case of wilful disobedience nor issued any
show cause notice for contempt at any stage. The Adjudicating Authority on
15.10.2025 had merely directed issuance of routine notice calling upon the
Appellants to file replies without framing precise charges against the
Appellants. Pursuant to these directions, notices which came to be issued
were not "Show Cause Notices" as contemplated under NCLT Rules or Section
12 of Contempt of Courts Act. Neither did the routine notice identify any
specific conduct constituting contempt nor was it addressed to specific
individuals. Contempt proceedings being quasi criminal in nature,
compliance with procedural requirement is not an empty formality but
requires to be essentially complied with. But in the present case the
Adjudicating Authority failed to record that its prima-facie satisfaction that a
case of contempt had been made out but went ahead to impose punishment
which suffers from grave procedural infirmities and that too without
identifying the specific officers of the Appellants before imposing of
punishment. The direction of imprisonment of the Respondents who are
Page 32 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 corporate entities without identifying the individual contemnors, the
contempt order could not have been passed.
37. Per contra, it is the case of the Respondents that the Appellants despite
being aware of the fact that in terms of the NFB Agreement, they were required
to disburse the NFB limits from the Closing Date, they have dragged their feet
for nearly five years in disbursing the NFB limits and have now issued fresh
sanction orders which are objectionable since the sanction orders contain a
string of conditionalities which were alien to the resolution plan and the NFB
Agreement executed in pursuance of the plan. It was also emphatically
asserted that the intent of Respondents behind filing the contempt application
was only to make the Appellants see sense and release the NFB limits which
was vital for their survival as crucial for their revival. The idea behind filing
the contempt application was to simply make the Appellants comply with the
court orders for release of NFB limits for the successful resolution of the
Corporate Debtor. The intent of the Respondents was not to send the
Appellants to civil prison but to tackle the undue hostility on their part in the
release of NFB limits.
38. We are conscious that the power to punish a person for contempt is
undoubtedly a powerful and potent weapon in the hands of court but it is also
well-recognised that this power has to be exercised with utmost caution and
circumspection and cannot be used unless the Court is fully satisfied beyond
doubt that the alleged contemnor has deliberately and intentionally violated
the order of the Court. Therefore, mere disobedience is not enough to hold a
person guilty of civil contempt unless it is accompanied with an element of
Page 33 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 deliberate and wilful intent to defy the orders of the court. Any party which
complains breach of courts' order by the other party must allege deliberate or
contumacious disobedience of the court's order and only if such allegation is
proven and substantiated before the court that contempt can be said to have
been made out. It follows therefore that in matters of contempt, following the
due procedure and the principles of natural justice is of great significance.
The court must serve a formal, personal notice of show-cause on the person
charged with contempt which notice must be accompanied by the precise and
explicit charges framed against him so that he knows exactly what he is
required to defend. A simple or generic notice is not sufficient. The person so
charged must also be given a fair chance to file an affidavit in reply to the
show-cause notice as why he should not be punished. The court must give
the person a fair opportunity to present his defence before making a final
determination on whether the purported conduct is contemptuous or
otherwise. As in the present case, the contempt proceedings have resulted in
penal consequences of imprisonment, it is all the more incumbent upon us to
satisfy ourselves whether procedural compliances have been met with or not.
39. Emphasising that contempt proceedings require a two-stage process
viz., (i) recording of prima facie satisfaction before issuing show case notice;
and (ii) framing of a precise charge so that the alleged contemnor is conscious
of the case he has to meet, it was asserted by the Ld. Solicitor General that
the Adjudicating Authority having brushed aside these procedural niceties
has exercised the contempt jurisdiction in a casual manner which is not
sustainable in the eyes of law. Reliance was placed on the judgement of the
Page 34 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 Hon'ble Supreme Court in Om Prakash Jaiswal Vs. D.K. Mittal & Anr.
(2000) 3 SCC 171 wherein adverting attention to the well-established practice
of following the two-stage process, it has been laid down that:
"15. ...... Filing of an application or petition for initiating proceedings for contempt or a mere receipt of such reference by the court does not amount to initiation of the proceedings by court. On receiving any such document it is usual with the courts to commence some proceedings by employing an expression such as "admit", "rule", "issue notice" or "issue notice to show cause why proceedings for contempt be not initiated". In all such cases the notice is issued either in routine or because the court has not yet felt satisfied that a case for initiating any proceedings for contempt has been made out and therefore the court calls upon the opposite party to admit or deny the allegations made or to collect more facts so as to satisfy itself if a case for initiating proceedings for contempt was made out. Such a notice is certainly anterior to initiation. The tenor of the notice is itself suggestive of the fact that in spite of having applied its mind to the allegations and the material placed before it the court was not satisfied of the need for initiating proceedings for contempt; it was still desirous of ascertaining facts or collecting further material whereon to formulate such opinion. It is only when the court has formed an opinion that a prima facie case for initiating proceedings for contempt is made out and that the respondents or the alleged contemners should be called upon to show cause why they should not be punished; then the court can be said to have initiated proceedings for contempt. It is the result of a conscious application of the mind of the court to the facts and the material before it. Such initiation of proceedings for contempt based on application of mind by the court to the facts of the case and the material before it must take place within a period of one year from the date on which the contempt is alleged to have been committed failing which the jurisdiction to initiate any proceedings for contempt is lost. The heading of Section 20 is "limitation for actions for contempt". Strictly speaking, this section does not provide limitation in the sense in which the term is understood in the Limitation Act. Section 5 of the Limitation Act also does not, therefore, apply. Section 20 strikes at the jurisdiction of the court to initiate any proceedings for contempt."
40. Another judgment relied upon by the Appellant in support of the two-
stage process is that of this Tribunal in G. Ravi Shankar Vs. S
Page 35 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 Radhakrishnan in CA(AT)(CH) No. 93 of 2023 wherein it was held as
follows:
"7. It is only when the Tribunal comes to a conclusion of an apparent, intentional and deliberate contempt having been committed, then only after framing of a charge under Rule 13 of the Contempt of Courts Rules, the appellant may be called upon to appear in-person before the Tribunal, if required as per law."
41. Reliance has also been placed on the judgment of Hon'ble Supreme
Court in L.P Misra Vs. State of UP (1998) 7 SCC 379 wherein it was held
that the court could not have passed the contempt order without issuing a
show-cause notice or giving an opportunity to the Appellants to explain the
alleged contemptuous conduct.
42. Yet another judgement which had been adverted to is that of the Hon'ble
Delhi High Court in McDonald's India Private Limited v. Union of India &
Ors. 2018 SCC OnLine Del 6617, as extracted below:
"35. There can be no quarrel with the proposition that the proceedings under the Contempt of Courts Act, 1971 are quasi criminal in nature. Initiation of action under the criminal law is one of great import and therefore, a serious matter. The burden and standard of proof in contempt proceedings is the same standard of proof as required in criminal proceedings. Great circumspection is required to be exercised by the court or the forum conferred with power to punish for contempt. Such action cannot be undertaken merely based on conjectures or surmises. The proceedings of contempt of court are generally treated as sui generis. Though the procedure adopted both under the common law and the statute in this context has invariably been summary in nature and the provisions of the Code of Criminal Procedure or the Evidence Act do not strictly control the same, it is essential that the court or the forum follows the procedure that is fair and objective. Before issuing notice calling upon the alleged contemnor to answer the charge of contempt, the court or the forum must record satisfaction that there is a clear, unambiguous and unequivocal case made out showing willful and contumacious conduct by the respondent. The procedure to be followed, after formal cognizance is taken, must
Page 36 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 include framing of a precise and specific charge or notice so as to inform the party in question as to the charge he is to meet. It may be added that it is not always necessary to frame a formal charge as in a criminal trial. It is sufficient if the gist of the specific allegations is made clear to the alleged contemnor affording him the opportunity of being heard in his defence. Further, the charge must be substantiated by clear and reliable evidence to be adduced at the trial. ......
49. The NCLT, rather than acting in hurry or undue haste, as is alleged, has taken the neutral course of treating the application seeking initiation of contempt proceedings or for the parties in question to be asked to purge, merely as an application filed in the wake of its order dated 13.07.2017. The decision as to whether or not a prima facie case of willful disobedience, defiance or commission of any act constituting contempt is made out, would undoubtedly be taken by the NCLT after it has secured the replies and considered the contentions having heard the parties in question. The argument that NCLT has acted arbitrarily, or with bias, is without basis. By giving opportunity to show cause, it has instead acted in most fair manner, following the spirit of the rules. [Rule 59]."
(Emphasis supplied)
43. In their defence, however, the Respondents have argued that that in
McDonalds India judgement supra it has been held that it is not always
necessary to frame a formal charge and that it is sufficient if the gist of specific
allegation is made clear to the alleged contemnor affording him an opportunity
of being heard in his defence. In the present case, notice had been issued to
the Appellants on 29.10.2025 directing them to appear before the NCLT and
the Respondent had been directed to serve a copy of their contempt
application upon all Appellants which had also been complied with.
Furthermore, in the interim order dated 25.11.2025 the NCLT had given the
Appellant Banks another opportunity to comply with the directions to issue
sanction letters in accordance with the terms of the approved resolution plan
which not having been complied with, the Adjudicating Authority committed
no infirmity in holding the conduct of the Appellant Banks to be neither in
Page 37 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 compliance with the approved resolution plan nor in terms of the August 20
NCLT Order and December 9 NCLAT Order and therefore their conduct to be
in contempt of the court.
44. Having perused the judgements cited by both the Appellants and the
Respondents, we are not inclined to agree with the submission made by the
Respondents dispensing with the need for the Adjudicating Authority to
record prima-facie satisfaction of wilful disobedience and communication of
the charges on the alleged contemnors. The Adjudicating Authority in this
case has directly imposed punishment without first passing an order
recording its prima-facie satisfaction that there is a contempt. Further the
imposition of punishment without issue of a show cause notice to the
Appellants setting out the issues/charges which allegedly constituted
contempt of the August 20 NCLT Order and December 9 NCLAT order is a
procedural breach. Further, penalty can be visited only after receipt of
explanation and oral hearing of the specific individuals to be penalised which
has not happened.
45. We find that the judgements relied upon by the Appellants adequately
support the submissions made by them that contempt proceedings
necessarily require recording of prima-facie satisfaction by the concerned
court of law of wilful disobedience of its orders followed by framing of precise
charges against the alleged contemnor to be met by the alleged contemnor
before being visited with any punishment arising out of the contempt
proceedings. The minimal requirement of following the procedure prescribed
Page 38 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 by law has been clearly overlooked by the Adjudicating Authority in the
present case.
46. Court must first ascertain facts and satisfy itself that a prima facie case
of contempt is made out, and only thereafter should it call upon the alleged
contemnors to show cause why they should not be punished. It is also to be
kept in mind that contempt can be initiated against specific individuals and
the principle of natural justice necessitates that a meaningful opportunity is
to be allowed to the identified contemnors so as to give them an opportunity
to defend themselves. The Adjudicating Authority in the present case has
neither formed any prima facie satisfaction for issue of show- cause notice for
contempt but merely directed issuance of routine notice without framing
precise charges against specific individual representing the respective
Appellant lenders. Furthermore, when the sanction letters have been
independently issued by each of the Appellant Banks, which sanction terms
are at variance from each other, the Adjudicating Authority without going into
the specific sanctions order and identifying how each of them breached the
directions of the court could not have passed a composite order for contempt
against the Appellant Banks and that too without naming the specific officers
who are charged with contumacious disobedience. We also find that the
Appellants have rightly drawn strength from the judgment of Hon'ble Supreme
Court in Union of India Vs. Satish Chandra Sharma (1980) 2 SCC 144
which has held as follows:
"10. We are a little startled that a court in the contempt jurisdiction should deprive the personal liberty of a person without naming in the order whom the court's bailiff should take into custody or the jail authorities should receive........ The constitutional sanctity of liberty
Page 39 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026 and the (then) protection of property will become chimerical and the processual law will hang limp if the substantive order is silent and identifying the offender is left over as a ministerial measure. ........ Nameless humans cannot be whisked off to prison even in the name of contempt by insertion of the name after the judgment is delivered. Natural justice is a pervasive doctrine integral to processual fair play in Indian jurisprudence. For this reason alone, the extant order under challenge is vulnerable-against both the attachment of unspecified property and detention of unnamed contemners."
(Emphasis supplied)
47. To our minds, for the reasons stated above, the Adjudicating Authority
has given a go-by to the procedural requirements which are required to be
mandatorily followed in contempt proceedings particularly so when a one-day
imprisonment has been ordered as penal consequence rendering the
proceedings quasi-criminal in character. We find that the impugned order
subjecting the Appellants to contempt and consequential civil imprisonment
suffers from impropriety since punishment arising from contempt is required
to be directed against an individual(s) who are found to have wilfully and
deliberately disobeyed the court directions. In the present case, the
Respondents in their contempt application have not identified specific
individual(s) by name as alleged contemnors nor made express and specific
charges of violation of court directions by them. Since contempt jurisdiction
has not been exercised by the Adjudicating Authority in accordance with the
procedure prescribed by law, in such circumstances, the impugned order
cannot be sustained.
48. In view of the forgoing discussion, the Appeal is allowed. The impugned
order is set aside with the following directions:
Page 40 of 41
Comp. App. (AT) (Ins) No. 388 & 389 of 2026
(i) It shall be open to the Respondents to send a written communication to
each of the Appellant Banks separately for release/disbursal of NFB limits in
terms of August 20 NCLT order and December 09 NCLAT order.
(ii) The Appellant Banks so approached may send their categorical response
on the request for release/disbursal of NFB limits to the Respondents within
a period of one month from the date on which the request is received from the
Respondents. The Appellant Banks are also directed to cooperate in providing
the name of the specific Officer(s) dealing with the disbursal/release of NFB
limits to the Respondents while sending their respective responses.
(iii) In the event, the Respondents are aggrieved with the response received
from the Appellant Banks in respect of Serial No. (ii) above, the Respondents
shall have the liberty to revive their Contempt Applications before the
Adjudicating Authority by indicating the name of specific Officer(s) of each
Appellant Banks by filing fresh averments and pleadings which the
Adjudicating Authority may consider in accordance with law, without being
influenced in any manner with any observations made by this Tribunal in this
order.
(iv) The parties shall bear their own costs.
[Justice Ashok Bhushan] Chairperson
[Mr. Barun Mitra] Member (Technical) Place: New Delhi Date : 26.05.2026 Sheetal
Page 41 of 41 Comp. App. (AT) (Ins) No. 388 & 389 of 2026
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free