Srinivasa Reddy Velagala vs Sravanthi Infratech Pvt. Ltd
- CitationCompany Appeal (AT)(Insolvency) No. 188 of 2020
Ratio decidendi
The rule this decision rests on
Where a contract under which the default arose has not been terminated by either party and continues to subsist, a Section 9 application founded on a default under that contract is not barred by limitation, the default being treated as a continuing one. A claim in respect of the provision of goods or services under such a subsisting contract, which is due and payable, is an operational debt within the meaning of Section 5(21) of the Insolvency and Bankruptcy Code, 2016. A contract that contains no clause providing for its frustration or termination by efflux of time, and that has not been terminated by either party, is not frustrated merely by the passage of time.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
Srinivasa Reddy Velagala, Director, K.P.R. Chemicals Limited, R/o Biccavolu (Village & Mandal), East Godavari District- 533 342 Andhra Pradesh Corporate Debtor/ ... Appellant Vs.
Sravanthi Infratech Pvt. Ltd. Thro. Its Vice President/Authorized Representative, Reg. Office at LG Floor, Rider House, 136, Sector-44 Gurgaon- 122 002 Haryana Operational Creditor/ .. Respondent Present:
For Appellant: Mr. Bommineni Vivekananda and Mr. Kameshvedual, Advocates
For Respondent: Mr. Sanchit Kumar Sahijpal, Advocate
JUDGMENT
(1st February, 2021)
KANTHI NARAHARI, MEMBER (TECHNICAL)
The present appeal preferred challenging the order of the
Adjudicating Authority (National Company Law Tribunal, Amaravati
Company Appeal (AT)(Insolvency) No. 188 of 2020 Page 1 of 14 Bench, Hyderabad, in TCP No. 82/9/AMR/2019 [CP (IB) No.
123/9/HDB/2018) whereby the Adjudicating Authority admitted the
Application filed by the Respondent herein and initiated Corporate
Insolvency Resolution Process (in short 'CIRP') by appointing Interim
Resolution Professional.
BRIEF FACTS:
2. Learned Counsel for the Appellant mainly raises two grounds
stating that the Application filed under Section 9 of Insolvency and
Bankruptcy Code, 2016 (in short 'IBC') by the Respondent herein
(Operational Creditor) was barred by limitation as prescribed under
Article 137 of Limitation Act 1963. Second ground raised by the
Appellant is that the contract was frustrated by efflux of time. Since
the Respondent failed to establish the above grounds he prays the
Bench to allow the Appeal by dismissing Section 9 Application. The
learned Counsel corroborated his arguments on legal and factual
issues.
3. Learned Counsel for the Respondent submitted that the
Application filed under Section 9 of IBC by them before the
Adjudicating Authority does not barred by limitation on the ground
that the contract, which they entered with the Appellant is still
subsisting. He further submitted that there is no such provision that
the contract would frustrate by efflux of time. He submitted that there
is continuous correspondence between the Respondent and the
Company Appeal (AT)(Insolvency) No. 188 of 2020 Page 2 of 14 Appellant and the Appellant even did not reply to the correspondences
and even to the Demand Notice. He further submitted that the claim
of the Respondent admittedly an operational debt the same is due and
payable. He further submitted that the Appeal does not have any merit
and prayed the Bench to dismiss the same.
Factual Matrix of the case: -
4. Heard learned Counsel for the respective parties, perused the
pleadings, documents submitted in their support. The learned
Adjudicating Authority framed issues - viz, (a) whether the Company
Petition is maintainable, (b) whether they owed an operational debt to
the Respondent and, (c) whether the Company Petition is barred by
limitation. Learned Adjudicating Authority dealt with the issues and
found that the Application filed by the Respondent herein is not barred
by limitation as contemplated under Article 137 of the Limitation Act
and held that the debt owed by the Appellant herein is an operational
debt. With the aforesaid findings, the Application filed by the
Respondent herein under Section 9 of IBC was admitted.
5. The Appellant herein invited International Competitive Bids by
publishing advertisement in newspaper on 13.12.2010 for setting up
a 225 MW gas based combined cycle Power Station at Bikkavolu, East
Godvari District, Andhra Pradesh. The Respondent being the lowest
bidder, was awarded the contract for execution of the aforementioned
Company Appeal (AT)(Insolvency) No. 188 of 2020 Page 3 of 14 project and a Letter of Award (LOA) was accordingly granted on
24.12.2010 for an amount of Rs. 827 Crores.
6. The said contract comprises of four EPC (Engineering
Procurement and Construction) for offshore and onshore equipment
supply for a value of Rs. 687 Crores, Civil & Construction works
amounting to Rs. 80 Crores, Engineering Custom clearance, erection
testing and commissioning service at a cost of Rs. 57 crores and
transportation services for offshore equipment contract for Rs. 3
crores. It is an admitted fact that the contract was signed by the
Appellant and the Respondent on 09.02.2011. It is also an admitted
fact that the Appellant paid an amount of Rs. 50.15 Crores in
instalments.
7. The grievance of the Respondent is that the Appellant did not
pay 10% of total contract amounting Rs. 82.7 Crores. Respondent
submitted that out of Rs. 82.7 Crores, they received only Rs. 50.15
Crores and the balance amount was not paid by the Appellant. He
further submitted that the Appellant did not honour the terms and
conditions of the contract. It is further submitted that the Appellant
engaged various vendors/suppliers and given them various
subcontracts to meet the time line of the EPC contract. Due to non-
payment of the amount by the Appellant herein, various sub-
contractors have raised litigations against the Respondent herein
which led the Respondent to suffer huge loss and damage.
Company Appeal (AT)(Insolvency) No. 188 of 2020 Page 4 of 14
8. From the aforesaid facts we have seen that except the grievance
raised by the Appellant herein with regard to limitation contending
that the claim of the Respondent herein does not fall under the
category of Operational debt and the contract was frustrated by efflux
of time. The other factual aspects are admitted. Therefore, we deal with
the same.
9. The EPC contract was supposed to be completed in 14 months.
It is seen from the pleadings that the work was suspended by the
Respondent vide communication dated 30.07.2011 for the reason that
the Appellant did not fulfil the contract obligation. It is also on record
that the Letter of Award signed on 24.12.2010 and the payments were
released to the extent of Rs. 50.15 Crores and the second instalment
of 10% of the contract had to be released on finalisation and
submission of un-price of such order goods. It is submitted that the
Respondent issued notice on 15.02.2011. The Respondent submitted
that they had suspended work by communicating letter dated
30.07.2011 to the Appellant herein. A copy of the letter dated
30.07.2011 is enclosed in Volume-III of the Appeal Paper Book at page
574 as Annexure-A/9. Respondent addressed the said letter to the
Appellant whereby it is stated as under;
"To
KPR Chemicals Private Limited S. No. 24/2, Nallamilli Road, Biccavolu- 533343
Company Appeal (AT)(Insolvency) No. 188 of 2020 Page 5 of 14 Kind Attn: Mr. Rajshekhar Reddy (ED)
Subject: Notice for suspension of the contract.
Dear Sir,
This is in reference to the our letter dated 15.02.2011
regarding initial advance payment, even after five
months of continuous follow up with you, the balance
payment of Rs. 32.55 crores have not been received
against initial advance.
Thus the 100% advance has not been received by SIPL
and the contractual obligation as per clause 5.1 of the
contract has not fulfilled by M/s KPR chemicals
Limited.
Therefore Sravnathi Infratech Private Limited hereby
notifies to you that all the EPC activities for the KPR
chemicals Ltd. (225 MW combined cycle power project)
will be under suspension till the all the contractual
obligation are fulfilled by you.
Kindly acknowledge the receipt of this notice.
Thanking you,
Yours sincerely
For Sravanthi Infratech Private Limited"
Wherefrom it is evident that the balance payment of Rs. 32.55 Crores
was not paid by the Appellant. For the aforesaid reason the work on
Company Appeal (AT)(Insolvency) No. 188 of 2020 Page 6 of 14 the project site was suspended till the contractual obligations are
fulfilled. Respondent further submitted that there is no reply from the
Appellant to this letter.
10. Learned Counsel for the Appellant vehemently contended that
by addressing a letter dated 30.07.2011 to the Appellant, the
Respondent themselves frustrated the contract. On the other hand,
the learned Counsel for the Respondent contended that there is no
such clause in EPC Contract with regard to frustration of contract.
However, there are clauses enumerated under the agreement dated
09.02.2011. Article 14 of the Contract dated 09.02.2011 provides for
termination of the contract. A copy of the EPC Contract is enclosed at
Annexure-A/4(page-116, Vol. I). Clause 14.1 deals with the
termination for Owner's convenience. According to the said clause,
"14.1 Termination for Owner's Convenience.
Owner may for its convenience terminate any part of the Supplies or any or all remaining Supplies hereunder at any time upon at least 30(Thirty) days' prior written notice to Supplier specifying the part of the Supplies to be terminated and the effective date of termination. Upon receipt of such notice, Supplier shall promptly initiate steps to stop provision of such terminated Supplies. In the event of a partial termination, Supplier shall continue to produce the part of the Supplies not terminated. In case of a termination of part of the Supplier's Work, Owner shall authorize a Scope Change Order making reasonable adjustments to one or more of the Company Appeal (AT)(Insolvency) No. 188 of 2020 Page 7 of 14 Schedule Unit(s). Completion date, Scheduled Facility Completion Date, the Contract Price, the Contract Schedule, the Performance Guarantees and any other affected provisions of this Agreement, as applicable. In the event of termination by Owner under this Article 14.1, Owner shall pay to Supplier (or Supplier may retain) such amounts as are required pursuant to Article 4.4 hereof. In case of a termination of all or remaining part of the Supplier's Work, the Owner shall provide at least 30 days' prior written notice to Supplier providing details of the reasons for such termination and the effective date of termination. Owner will authorize a Scope Change Order making reasonable adjustments to the Contract Price as applicable."
11. Further, Clause 14.2 deals with termination upon non-payment
by Owner.
"14.2 Termination Upon Non-Payment by Owner. If Owner fails to pay to Supplier any payment as required hereunder and such failure continues for 25 days after written notice thereof has been given to Owner by Supplier, then Supplier shall give ten days' prior written notice thereof to Owner and the Financing Parties, and thereafter may stop all performance of Supplier's obligations hereunder until Supplier receives payment of all amounts then due plus reasonable suspension and resumption expenses. Owner shall be responsible for reimbursement of all costs incurred by Supplier as a result of the stoppage of Supplier's work. If Supplier's performance hereunder is suspended by Supplier
Company Appeal (AT)(Insolvency) No. 188 of 2020 Page 8 of 14 pursuant to this Article 14.2, Owner will authorise a Scope Change Order making an equitable adjustment to the Scheduled Unit(s) Completion Date, Scheduled Facility Completion Date and the Contract Schedule and required reasonable adjustments to one or more of the Contract Price, the Terms of Payment and any relevant terms and conditions of this Agreement, as appropriate. If such suspension continues uninterrupted for at least four months, or if two or more suspensions exist for an aggregate of at least four months, Supplier may terminate this Agreement; provided that Supplier shall give the Financing Parties a further 60 days prior written notice, and opportunity to cure, before terminating this Agreement. In the event of such a termination by Supplier, Owner shall pay to Supplier (or Suppler may retain) such amounts as are required pursuant to Article 4.4. hereof.
12. Learned Counsel for the Respondent submitted that the
Appellant could have invoked Article 14.1 for termination of contract
since the said clause provides for termination for Owners Convenience.
Before invoking the said clause, the Owner can issue a prior 30 days'
Notice to the Supplier specifying the part of the supplies to be
terminated and effective date of termination. According to this Clause,
the Owner either terminate the whole contract or terminate the part of
the supplies. While doing so, the Owner shall pay to the Supplier such
amount as are required pursuant to Article 4.4 thereof. The learned
Counsel also submitted that the Respondent can also terminate the
Company Appeal (AT)(Insolvency) No. 188 of 2020 Page 9 of 14 contract invoking clause 14.2 of Article 14 if Owner fails to pay
Supplier any payment as required thereunder and such failure
continues for 25 days' after written notice thereof has been given to
Owner by Suppler, then the Supplier shall give 10 days' prior written
notice thereof to Owner and the Financing Parties and thereafter may
stop all performances of Supplier's obligation therein until Supplier
receives payment of all amounts then due plus reasonable suspension
and resumption expenses. However, the Respondent did not invoke
this clause for terminating the contract despite several challenges and
financial constrains faced by them from their Suppliers/Vendors.
13. As stated supra, the Respondent by letter dated 30.07.2011
suspended the work for non-receipt of payment. In view of non-receipt
of payment from the Appellant, the Respondent could not pay to the
Venders/Suppliers, those who have supplied goods and rendered
services to the project of the Appellant due to non-availability of fund.
14. Apart from the above, we have also perused a letter dated
05.01.2012 addressed by the Appellant-Company to the Chief
Engineer, IRP Division, Central Electricity Authority, Sewa Bhawan, R
K Bhawan, New Delhi [page-54, Annexure-D(Colly)] to the Reply of the
Respondent. The Appellant has admitted:
..
Company Appeal (AT)(Insolvency) No. 188 of 2020 Page 10 of 14
"The project is in advance stage of development, all the
major clearances for the project has been received by
the project company and construction is in full swing."
..
Further the status of the project was given in the said letter and
requested the Central Electricity Authority to allocate 1.2 mmscmd of
gas for 225 MW CCPP so that the project can be commissioned on
schedule.
15. Further, the Respondent issued a Demand Notice dated
02.07.2018 to the Appellant under Section 8(1) of IBC (in Form-3
under Rule - 5 of the IBC Application to Adjudicating Authority) Rules,
2016. The Appellant did not reply to this Notice nor raised any
existence of dispute prior to the issuance of this Notice.
16. In answer to the plea of barred by limitation i.e., as per the
amendment to the IBC incorporating Section 238A to the IBC
applicability of the limitation to the Applications filed under IBC. It is
seen from the correspondences between the parties and from the
perusal of the clauses/articles as enumerated under the EPC contract
that the contract has not been terminated by either parties and the
contract still subsists. Therefore, the Adjudicating Authority rightly
held that there is no termination of contract and the issue raised with
regard to barred by limitation cannot be accepted. Therefore, we hold
Company Appeal (AT)(Insolvency) No. 188 of 2020 Page 11 of 14 that the Application filed by the Respondent under Section 9 of IBC
before the Adjudicating Authority is not barred by limitation.
17. Further the issue is whether the claim of the Respondent is an
Operational Debt. The Operational Debt is defined under sub-section
21 of Section 5 of IBC which reads as under:
..
"5(21) "operational debt" means a claim in respect of
the provision of goods or services including
employment or a debt in respect of dues arising under
any law for the time being in force and payable to the
Central Government, any State Government or any
local authority."
..
18. Admittedly, the claim of the Respondent is an operational debt.
Therefore, the arguments of the Appellant that the claims of the
Respondent is not an operational debt does not hold any field.
19. Efflux of time:
The other issue with regard to frustration of contract by efflux of
time is concerned, we hold that the EPC contract between the
Appellant and Respondent still subsists and there is no such clause in
the contract regarding frustration or termination by efflux of time, we
hold that there is no merit in this point and accordingly, we negate this
point issue also.
Company Appeal (AT)(Insolvency) No. 188 of 2020 Page 12 of 14
20. Learned Counsel for the Appellant relied upon a judgment in the
matter of KLA Construction Technologies Pvt. Ltd. V. CKG Realty
Pvt. Ltd., rendered in CA(AT)(Ins.) No. 67/2018. In this judgment this
Tribunal was of the view that if the machinery or equipment was not
moved to the construction site would be a debatable issue which can
be agitated before the Civil Court. However, in the facts of the present
case, the Appellant did not raise any existence of dispute prior to the
issuance of Demand Notice and there is no termination of contract as
held by us. Therefore, this judgment is not applicable to the facts of
the present case.
21. Learned Counsel for the Appellant also relied upon the decision
of Hon'ble Apex Court in B.K. Educational Services Pvt. Ltd. Vs.
Paras Gupta & Associate, AIR 2018 SC 5601 and Vashdeo R.
Bhojwani Vs. Abhudaya Co-operative Bank Ltd. (2019) 9 SCC 158
citing that the period of limitation for Applications seeking initiation of
CIRP under Sections 7 & 9 of IBC is covered under Article 137 of the
Limitation Act and therefore three years period to be taken into
consideration from the date when default occurs for the purpose of
limitation. It is reiterated that when we already held that there is no
termination of contract from either of the parties, therefore, the
contract still subsists and the claim is within limitation.
CONCLUSION:
Company Appeal (AT)(Insolvency) No. 188 of 2020 Page 13 of 14
22. From the perusal of the facts it is evident that the default has
arisen out of EPC Contract, which itself is a continuing contract. Even
from the Demand Notice dated 02.07.2018 in particulars of operational
debt at column-1, the Respondent had clearly stated that the debt fell
due on 24.12.2010 and the last payment made to the Respondent was
on 25.02.2011 through RTGS. It is also mentioned that the debt
continues to fall even today as the EPC contract between the Appellant
and Respondent never terminated by either parties.
23. We hold that the Adjudicating Authority had rightly admitted the
Application of the Respondent which in our considered opinion does
not require any interference in the instant Appeal.
24. From the facts and legal position, as explained above, the Appeal
is devoid of any merit and liable to dismissed. Accordingly, the Appeal
is dismissed. No order as to costs.
[Justice Venugopal M.] Member (Judicial)
(Kanthi Narahari) Member(Technical)
Pronounced by one Member of the Bench in terms of Rule 92(1) of the NCLAT Rules, 2016.
(Kanthi Narahari) Member(Technical)
New Delhi
Akc
Company Appeal (AT)(Insolvency) No. 188 of 2020 Page 14 of 14
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free