Smt. Suman Dhir & Ors vs M/S. Gyan Ganga Educational Institute ...
- CitationCompany Appeal (AT) No. 44 of 2018
Ratio decidendi
The rule this decision rests on
Where a prior order is reasonably capable of more than one interpretation, a proceeding for contempt for its breach is not maintainable, since wilful disobedience cannot be established against a party acting on a plausible reading of it. A court exercising contempt jurisdiction cannot re-examine the correctness of an earlier decision which has become final between the parties; it must take that decision as it stands and determine what it directs. Where the earlier order's direction on interest rate is not expressly stated and the general body resolution fixing a lower rate from a specified date has not been challenged, the expression "agreed rate" in that order is capable of the interpretation given by the respondents, so non-payment at the higher rate does not amount to wilful disobedience.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
2. Shri Sarvesh Dhir, S/o Shri B.K. Dhir, R/o MIG 19, Indravati Colony, Raipur, Chhattisgarh ....Applicants Vs.
1. M/s. Gyan Ganga Educational Institute Pvt. Ltd. School Campus, Administrative Block, 10th KM, Vidhan Sabha Road Vill. Naraha PO GSI (Mandhar) Raipur- 493111 Chhattisgarh
2. Shri Sachin Shandiliya, Director, M/s. Gyan Ganga Educational Institute Pvt. Ltd. School Campus Administrative Block 10th KM, Vidhan Sabha Road Vill. Naraha PO GSI (Mandhar) Raipur- 493111, Chhattisgarh
3. Smt. Manju Shandilya, Director, M/s. Gyan Ganga Educational Institute Pvt. Ltd. School Campus Administrative Block 10th KM, Vidhan Sabha Road Vill. Naraha PO GSI (Mandhar) ...Contemnors / Raipur- 493111, Chhattisgarh Respondents For Applicants: Ms. Shweta Bharti, Mr. Anil Tiwari, Mr. Aayusha Aankul, Advocates. 2
For Contemnors/ Mr. Amit Shankar, Mr. Jeevesh Nagrath, Ms. Respondents: Mithila Jain, Advocates for Contemnors 1-3
JUDGMENT
(26th November, 2021)
Ashok Bhushan, J.
1. This Contempt proceeding has been instituted to punish the
Contemnors for breach and wilful disobedience of the final judgment dated
20.08.2019 passed by this Tribunal in Company Appeal (AT) No. 44 of 2018.
The Applicants had filed Company Appeal (AT) No. 44 of 2018 against the
judgment dated 06.11.2017 passed by the National Company Law Tribunal
("Tribunal" for short), Mumbai Bench, Mumbai by which the Tribunal has
dismissed the Company Petition No. 109/2013 filed by the Applicants with
cost. The Applicants had filed a petition under Sections 397, 398, 399, 402,
403, 406, 235, 237 and 247 read with Section 111 of the Companies Act,
1956 against the alleged acts of oppression, mismanagement, fraud,
manipulation etc. before the Company Law Board, Mumbai Bench, Mumbai.
The Company Appeal (AT) No. 44 of 2018 was disposed off by this Tribunal
vide judgment dated 20.08.2019, the following order was passed:-
"33. For above reasons and observations, the impugned order dated 6.11.2017 is upheld with the following directions:-
i) 1st Respondent will pay the appellants their balance of unsecured loan with interest at agreed rate which
Contempt Case (AT) No. 27 of 2020 in Company Appeal (AT) No. 44 of 2018 3
Respondents have discontinued providing since 1.4.1999 within one month of this order.
ii) The Respondent No.1 company will get the price of each share determined by registered valuer who will act as per Section 247 of the Companies Act, 2013.
Respondent No.1 Company will ensure compliance within one month of the date of this Judgment.
iii) After getting report of Registered Valuer, Board of Directors of 1st Respondent will offer shares of 1st and 2nd appellant to the existing shareholders adopting procedure akin to Section 62 of the Companies Act, 2013 within one month of the offer given by the company. In case none of the existing shareholders purchase the shares of 1st and 2nd appellant, in that event 1st respondent will purchase the shares of 1st and 2nd appellant within one month thereafter.
iv) There shall be no order as to costs."
2. The Applicants' case is that after the order dated 20.08.2019, the
Applicants filed a Review Petition No. 23 of 2019 before this Tribunal which
was rejected. Applicants also filed Appeal being Civil Appeal No. 1220-1221
of 2020 before the Hon'ble Supreme Court which too was dismissed vide order
dated 14.02.2020. The Applicants gave a legal notice dated 25.02.2020 to the
Contemnors, demanding payment of a total amount of Rs. 20,349,111/-
towards the balance of unsecured loan with compound rate of interest at 15%
per annum from 01.04.1999 to 29.02.2020. The Contemnors had filed an
Application for execution of the judgment and order dated 20.08.2019 before
the NCLT, Bench at Cuttak seeking for following directions:-
Contempt Case (AT) No. 27 of 2020 in Company Appeal (AT) No. 44 of 2018 4
"a) Direct the Respondent No.1 & 2 to accept the balance of unsecured loan with interest at agreed rate since 01.04.199 amounting to Rs. 9,21,598/- (Rupees Nine Lakhs Twenty One Thousand Five Hundred and Ninety Eight Only) and Rs. 28,88,503/- (Rupees Twenty Eight Lakhs Eighty Eight Thousand and Five Hundred and Three Only); and
b) Direct Respondent No.1 and 2 to transfer their shares in favour of Petitioner No.1 in lieu of the consideration amount as per the valuation report annexed; or
c) Direct Respondent No.4 (ROC) to transfer the shares of Respondent No.1 and 2 in the name of Petitioner No.1; and
d) Direct Respondent No.1 and 2 to pay the cost amount of Rs. 1,00,000/- (Rupees One Lac Only) each to the Petitioners."
3. Legal notice was replied. In the execution petition, the Contemnors
stated that two cheques, Cheque No. 017386 in the name of Applicant No.1
drawn on Allahabad Bank amount to Rs. 9,21,598/- and Cheque No. 017369
drawn on Allahabad Bank in the name of Applicant No.2 amounting to Rs.
28,88,503/- was sent by speed post which was not received by the Applicants.
Hence, the execution application has been filed. The Applicants filed the
present Contempt Application on 19.08.2020.
4. This Tribunal heard the Contempt Case on several occasions. On
19.10.2020, following order was passed by this Tribunal:-
"19.10.2020: At request of Ms. Sweta Bharti, the Learned Counsel for the Petitioners/ Appellant for filing
Contempt Case (AT) No. 27 of 2020 in Company Appeal (AT) No. 44 of 2018 5
a proposal in respect of the balance unsecured loan with interest @ 10% compounded annually which the Respondents have to pay from 1.4.1999 the matter is adjourned to 6th November, 2020. The Learned Counsel for the Appellant is directed to serve a copy of the said proposal to the Learned Counsel for the Respondent one week well in advance before the next date of hearing.
The Registry is directed to List the matter on 6th November, 2020 as Part Heard."
5. The above order indicates that the time was granted for filing proposal
in respect of the balance unsecured loan with interest @ 10% compounded
annually from 01.04.1999.
6. Again matter was adjourned by order dated 08.01.2021 for filing a
proposal in respect of the balance unsecured loan with interest @ 10%
compounded annually which the Respondents have to pay from 01.04.1999.
The order sheet of this Court dated 01.03.2021 indicates that the Learned
Counsel for the Appellant has filed proposal on 22.02.2021 for payment of
balance of unsecured loan along with compound interest @ 15% per annum
from 01.04.1999 to 28.02.2021. On 02.06.2021, following order was passed
by this Tribunal:-
"02.06.2021: It is stated that the Applicants/ Original Appellants have not complied with the directions given by this Tribunal in order dated 19th October, 2020 read with order dated 8th January, 2021. The Applicants to comply with the same before the next date.
Contempt Case (AT) No. 27 of 2020 in Company Appeal (AT) No. 44 of 2018 6
2. Learned Counsel for the Respondents submits that he may be permitted to file Interlocutory Application making an offer to deposit the amount as per the calculation of the Respondents and permission may be given for the same. Respondents may file the Interlocutory Application as stated.
List the Contempt Case on 14th July, 2021."
7. The Contempt Application was heard thereafter. We have heard Learned
Counsel for the Applicants as well as Learned Counsel for the Respondents.
8. Ms. Sweta Bharti, Counsel appearing for the Applicants contends that
the Applicants have not submitted the proposal as directed by this Tribunal
in respect of balance unsecured loan with interest @ 10% compounded
annually which Respondents had to pay from 01.04.1999 rather they insist
that they should be paid the amount @ 15%. It is submitted that the judgment
of this Tribunal dated 20.08.2019 has become final between the parties
according to which judgment the Respondents were obliged to make payment
of unsecured loan with interest @ 15% compounded. Hence, the Applicants
are entitled for payment of unsecured loan with interest @ 15% compounded
annually. The Respondents having failed to pay such amount have committed
contempt of this Tribunal's order dated 20.08.2019 and are liable to be
punished.
9. Learned Counsel appearing for the Respondents submits that the
Respondents have not committed any contempt of this Tribunal's order rather
in pursuance of the order dated 20.08.2019, they have calculated the amount
Contempt Case (AT) No. 27 of 2020 in Company Appeal (AT) No. 44 of 2018 7
and sent two cheques of Rs. 9,21,598/- and Rs. 28,88,503/- as on
30.09.2019 which cheque were not received by the Applicants. Hence, the
Respondents left with no remedy, has filed an Application for execution of the
judgment and order dated 20.08.2019 before the Adjudicating Authority
where the matter is pending. It is submitted that the cheques were sent to the
Respondents in the month of September, 2019 which they refused to accept.
Learned Counsel for the Respondents submits that for unsecured loan
interest @ 15% was to be payable till 30.09.1998 and thereafter it was to be
paid @ 10% per annum upto 31.03.1999. However, under the orders of this
Tribunal dated 20.08.2019, the rate of interest have been calculated @ 10%
and was not limited to 31.03.1999. It is submitted that the resolution dated
25.09.1998 was passed in the Seventh Annual General Meeting of the
shareholders of Gyan Ganga Educational Institute Pvt. Ltd., Raipur, which
Resolution is binding on all. The Respondents have calculated the amount of
unsecured loan to be paid to the Applicants @ 15% till 30.09.1998 and from
01.09.1998 @ 10% which is substantial compliance of the judgment of this
Tribunal dated 20.08.2019. It is further submitted that due to the above, this
Tribunal in its orders, as noted above, directed the Applicants to submit a
proposal for payment @ 10% w.e.f. 01.04.1999. The Applicants have not
submitted the above proposal which itself indicates that the Applicants are
not ready to comply with the orders passed by this Tribunal.
10. We have considered the submissions of the Learned Counsel for the
parties and have perused the record.
Contempt Case (AT) No. 27 of 2020 in Company Appeal (AT) No. 44 of 2018 8
11. The judgment dated 20.08.2019 passed in Company Appeal (AT) No. 44
of 2018 has become final between the parties whereunder direction (i) the 1st
Respondent was to pay the Appellants their balance of unsecured loan with
interest at agreed rate which Respondents have discontinued providing since
01.04.1999 within one month of this order. There is no dispute between the
parties that as per the Agreement dated 07.09.1991 on the unsecured loan of
the Applicants, the Respondent No.1 was to make payment @ 15% annually
compounded. The Applicants themselves have brought on record the
proceedings of general body meeting dated 25.09.1998 as Annexure-B which
has been referred to and relied in Paragraph 6 of the Application. Paragraph
6 of the Application states as follows:-
"6. Thereafter, the Contemnors started to pay the interest on the unsecured loans of the Petitioner at the compound rate of 15% in per annum up to 30.09.1998, as the same is evident from the minutes of Seventh Annual General Meeting of the Shareholders of Contemnor No.1 held on 25.09.1998 which was also part of the records of the Appeal filed before this Hon'ble Tribunal. The copy of the minutes of the Annual General Meeting dated 25.09.1998 of Contemnor No.1 annexed herewith and marked as Annexure- B"
12. Now we revert to the proceedings of the Annual General Meeting dated
25.09.1998 which indicates that it was resolved that from 01.10.1998 the
interest will be paid to the shareholders on their unsecured loans only at 10%
per annum compound rate of interest upto 31.03.1999. The Resolution
passed on 25.09.1998 is to the following effect:-
Contempt Case (AT) No. 27 of 2020 in Company Appeal (AT) No. 44 of 2018 9
"(7) Shri R.P. Singh moved a resolution that as the company had run into loss during 1997-98 and the inflationary trend during the current year and souring high, the company would be operating on a very tight budget and it would not be able to contain the financial burden of paying interest on unsecured loans at the compound rate of 15% per annum. Shri Sachin Shandilya and some other members also supported this resolution and by a majority at votes by show hands the following resolution was adopted.
"Resolved and as it resolved that from 1-10-98 the interest will be paid to the shareholders on their unsecured loans, only at 10% per annum compound rate of interest upto 31-3-99, and thereafter no interest will be payable on unsecured loan and those members who wish to withdraw their unsecured loans in part or in full may apply after 1-4-99 with three months notice so that the loan could."
13. Learned Counsel for the Applicants submits that this Tribunal's
judgment dated 20.08.2019 did not direct payment of interest @ 15% rather
the expression used by this Tribunal was 'with interest at agreed rate'. It is
submitted that the Resolution dated 25.09.1998 having never been
challenged by the Applicants, the Resolution of the general body with regard
to the rate of interest have to be given effect and the agreed rate which is to
be paid to the Applicants is @10% from 01.04.1999. The order passed by this
Tribunal dated 19.10.2020, as extracted above, indicates that this Tribunal
in its order noted the filing of the proposal of the balance unsecured loan with
10% interest compounded annually w.e.f. 01.04.1999. Although the proposal
Contempt Case (AT) No. 27 of 2020 in Company Appeal (AT) No. 44 of 2018 10
with interest @ 10% as was prayed to be submitted by the Appellants was
never submitted rather Applicants have submitted the proposal with interest
@ 15% per annum from 01.04.1999 but in the facts of the present case, we
are satisfied that there is no wilful disobedience on the part of the
Respondents so as to punish the Respondents for contempt. The Respondents
even before filing of the Contempt Application has issued two cheques in
favour of the Applicant Nos. 1 & 2 as noted above calculating the interest @
10% compounded annually from 01.04.1999.
14. The fact that Respondents themselves have filed application for
execution of the judgment dated 20.08.2019 is sufficient to indicate that the
Respondents intended to comply the Judgment. We however cannot lose sight
of the fact that the judgment dated 20.08.2019 having become final between
the parties, the Respondents are liable to pay the amount. We further noticed
that in the order passed by this Tribunal dated 20.08.2019, there is no
direction to make payment of interest @ 15% since 01.04.1999. Learned
Counsel for the Appellant submits that direction to pay 15% interest is
decipherable from the observations made in paragraph 32. It is submitted by
the Respondents that the amount included by the Applicants is unsecured
loan on which the Respondents were paying interest @ 15% and TDS was also
being deducted.
15. The above observation notices the case of the Respondents that they
were paying interest @ 15%. There is no dispute that the earlier interest @15%
was being paid till 30.09.1998 and the above observations only indicate that
the payments were earlier made @ 15% but that the above observations
Contempt Case (AT) No. 27 of 2020 in Company Appeal (AT) No. 44 of 2018 11
cannot read to mean that even from 01.04.1999 the Respondents agreed to
make the payment @ 15%. The expression 'at agreed rate' as contained in
paragraph 33 of the judgment of this Tribunal dated 20.08.2019 is capable of
interpretation as put by the Respondents. When general body Resolution
dated 25.09.1998 have expressly decided to pay interest @ 10% from
01.04.1999 and the general body Resolution is not denied or challenged by
the Applicants, their insistence that the unsecured loan was to be paid @ 15%
annually even after 01.04.1999 cannot be accepted. It is well settled that it is
not permissible to the Court to examine the correctness of the earlier decision
which has become final between the parties. However, when an order was
reasonably capable of more than one interpretation a proceeding for contempt
would not be maintainable. The Hon'ble Supreme Court in "Tamilnad
Mercantile Bank Shareholders Welfare Association (1) vs. Tamilnad
Mercantile Bank Limited- (2008) 15 SCC 529" paragraphs 8 and 9 laid
down the following:-
"8. Having heard learned counsel for the parties, we are of the opinion that the expression "duly registered"
cannot be said to be free from any ambiguity. It is apparent that the parties to the suit construed the said expression differently. The learned Single Judge while passing the consent order did not specifically spell out that the said expression would mean that the power of attorneys must be registered with the Registrar of Assurances.
9. It is now well settled that when an order is ambiguous and was reasonably capable of more that
Contempt Case (AT) No. 27 of 2020 in Company Appeal (AT) No. 44 of 2018 12
one interpretation, a proceeding for contempt would not be maintainable."
16. We are thus satisfied that no case has been made out to punish the
Respondents for contempt. The Respondents having themselves initiated
proceedings for execution of the judgment dated 20.08.2019 and have
expressed their willingness to deposit the entire amount with interest @ 15%
till 30.09.1998 and thereafter @ 10% per annum annually compounded till
the date payment is made, we permit the Respondents to deposit the amount
as above before the Executing Court within one month from today. The said
amount shall be remitted by the Executing Court to the Applicants. The
Executing Court shall also verify whether the amount so deposited is as per
above and in the event any shortfall is found in the amount, the Respondents
shall be directed to deposit the said amount also which may be remitted to
the Applicants. The execution proceedings may be concluded by the Executing
Court at an early date preferably within three months of the date when copy
of this order is produced. The Contempt Application is disposed off,
accordingly.
[Justice Ashok Bhushan] Chairperson
[Justice Jarat Kumar Jain] Member (Judicial)
[Dr. Ashok Kumar Mishra] Member (Technical)
New Delhi Anjali
Contempt Case (AT) No. 27 of 2020 in Company Appeal (AT) No. 44 of 2018
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free