Shyam Kumar Garg vs Sunrise 14 A/S Denmark & Anr
- CitationCompany Appeal (AT) (Insolvency) No. 587 of 2019
Ratio decidendi
The rule this decision rests on
The Tribunal may, in exercise of its inherent powers under Rule 11 of the National Company Law Appellate Tribunal Rules, 2016, accept a settlement between the parties and set aside an admission order under Section 7 of the Insolvency and Bankruptcy Code, 2016, where the settlement disposes of the financial creditor's claim and the parties are bound by its terms. Where a settlement is accepted in this manner, the application under Section 7 stands disposed of as withdrawn, and the consequential orders (appointment of the Interim Resolution Professional, declaration of moratorium, and actions taken pursuant to the impugned order) fall with the setting aside of the admission order. The parties to a settlement so accepted are bound by its terms, and the Tribunal retains the power, upon default in payment, to recall its order and revive the Corporate Insolvency Resolution Process.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
Shyam Kumar Garg .... Appellant
Vs
Sunrise 14-A/S Demnark & Anr. .... Respondents
Present: For Appellant: Ms. Ranjana Roy Gawai, Advocate with Mr. Shyam Kumar Garg, Appellant.
For Respondents: Mr. Manish Kumar Jha, Advocate for Respondent No.1.
Mr. Anil Bhatia, Interim Resolution Professional.
ORDER
10.06.2019 Sunrise 14 A/S Denmark ('Financial Creditor') filed application under Section 7 of the Insolvency and Bankruptcy Code, 2016 (I&B Code) against Metalore Overseas Pvt. Ltd. ('Corporate Debtor'). The Adjudicating Authority (National Company Law Tribunal), Principal Bench, New Delhi by impugned order dated 13th May, 2019 having admitted the application, the present Appeal has been preferred by Shyam Kumar Garg, Shareholder of Metalore Overseas Pvt. Ltd. ('Corporate Debtor').
2. When the matter was taken up on 29th May, 2019, learned Counsel for the Appellant submitted that the parties have reached settlement in principle and a formal agreement in regard to terms of settlement will be placed by the next date. The parties were allowed to reach settlement. Matter was posted to 4th June, 2019 and in the meanwhile 'Interim Resolution Professional' was directed not to constitute 'Committee of Creditors', if not yet constituted.
Company Appeal (AT) (Insolvency) No. 587 of 2019 Page 1 of 10 3. An affidavit has been filed on behalf of the Appellant, enclosing the terms of settlement dated 4th June, 2019, which are as follows: -
"Execution Version June 4, 2019
SETTLEMENT AGREEMENT
THIS Settlement Agreement ("Agreement") executed on this 4th day of June 2019
By and Between
Maersk Trade Finance A/S, a public limited liability company incorporated under the laws of Denmark, having its registered address at Esplanaden 50, DK-1263 Copenhagen K, with company registration no. (CVR) 32345808 hereinafter referred to as "MTF" (which expression shall unless repugnant to the context or meaning thereof mean and include its successors and assigns).
And
Mr. Shyam Kumar Garg and Mr. Rahul Garg, erstwhile Promoters/Directors and Shareholders of Metalore Overseas Private Limited ("Metalore") (having majority control in the management of Metalore Oversea Private Limited), having their office address at 536, DLF Tower, Shivaji Marg, Moti Nagar, New Delhi- 110015 hereinafter referred to as "Metalore Promotors" (which expression shall unless repugnant to the context or meaning thereof be deemed to include their heirs, executors, administrators and assigns).
MTF And Metalore Promotors are hereinafter collectively referred to as "Parties".
WHEREAS:
A. A Trade Finance Facility Agreement ("Facility Agreement") dated February 14, 2017 was executed by and between MTF and Metalore. MTF had sanctioned a trade finance facility to Metalore for an amount of up to USD 250,000 (United States Dollars Two Hundred and Fifty Thousand only) for the purposes and in accordance with the terms and conditions set forth in the Facility Agreement.
B. The shareholding structure of Metalore as on the date of execution of these presents is more particularly itemized in Annexure - A hereto.
C. On March 30, 2017, a sum of USD 247,392, was accordingly disbursed by MTF to Metalore in accordance with the terms of
Company Appeal (AT) (Insolvency) No. 587 of 2019 Page 2 of 10 the Facility Agreement. However, upon the contractual date of repayment i.e. Due Date May 9, 2017, Metalore failed to make payment to Metalore.
D. Consequent thereto, MTF issued several reminders to Metalore qua payments due under the Agreement. As no payments were forthcoming from Metalore, MTF was constrained to file an Insolvency Application before the NCLT, Principal Bench i.e. C.P. No. 832(P.B.)/2018 under the Insolvency and Bankruptcy Code, 2016 ("Code").
E. The outstanding payable by Metalore to MTF under the Facility Agreement as on May 1, 2018 is USD 222,722 (including LIBOR interest and default interest) (United States Dollars Two Hundred and Twenty Two Thousand seven hundred and Twenty Two only).
F. The Insolvency Application was finally disposed vide Order dated May 13, 2019 wherein the NCLT, Principal Bench directed initiation of the Corporate Insolvency Resolution Process. In accordance with the Code, Mr. Anil Bhatia, Interim Resolution Professional ("IRP"), has taken charge over the control and management of Metalore.
G. Being aggrieved, Mr. Shyam Kumar Garg (in his capacity as aggrieved party) filed an Appeal before the NCLAT i.e. Company Appeal (Ins.) No.587/2019 ("Appeal").
H. During the pendency of the Appeal, the Metalore Promotors have approached MTF with an offer to pay a sum of USD 150,000 (United States Dollars One Hundred and Fifty Thousand only) ("Settlement Amount") in full and final settlement of all the dues and liabilities of Metalore towards MTF and MTF has agreed to accept the Settlement Amount in full and final satisfaction of all outstanding dues.
I. For the above-mentioned purpose, the Parties are desirous of recording the terms and conditions of their settlement in writing to regulate their rights and obligations in accordance with terms and conditions mutually agreed to as follows.
NOW THEREFORE, the Parties agree as follows:
1) The above Preamble shall be considered as an integral part of the present Agreement.
2) As per records maintained by MTF, the total amount due and payable as on May 1, 2018 by Metalore to MTF is USD 222,722 (including LIBOR interest and default interest) (United States Dollars Two Hundred and Twenty Two Thousand seven hundred and Twenty Two only). However, in accordance with
Company Appeal (AT) (Insolvency) No. 587 of 2019 Page 3 of 10 the settlement arrived at between MTF and the Metalore Promotors, the Metalore Promotors agree and undertake that they shall pay to MTF the Settlement Amount of USD 150,000 (United States Dollars One Hundred and Fifty Thousand only) in full and final settlement of outstanding dues under the Facility Agreement, on the following terms and conditions:
a) The Metalore Promotors shall make available the Settlement Amount in the account of Metalore i.e. Indusind Bank Sector 18 NOIDA. Account Number C/A 259810009430 upon execution of the present Agreement;
b) Upon directions from the NCLAT on the next date of hearing of the Appeal i.e. June 4, 2019, the IRP will forthwith transfer the Settlement Amount to the account designated by MTF i.e. USD Account Beneficiary Name:
Maersk Trade Finance A/S Beneficiary Address:
Esplanaden 50, DK-1263 Copenhagen K Beneficiary Bank Name: Citi Bank London Beneficiary Bank Address: Canary Wharf Group, 25 Canada Square, Canary Wharf, London E14 5LB, UK Beneficiary Account No: 17777647 Beneficiary Swift Code:
CITIGB2LXXX Beneficiary IBAN No:
GB35CITI18500817777647 Bank Key / ABA no: 185008; and
c) The settlement arrived at between the Parties will be taken on record by the NCLAT and accordingly the pending proceedings shall stand disposed by Order of the NCLAT.
3) Undertaking by Metalore Promotors:
Metalore Promotors hereby irrevocably and unconditionally agree, confirm and undertake that:
a) They shall strictly comply with all the terms and conditions of the present Agreement;
b) They shall execute such further documents, deeds and writings and do such further acts, deeds or things as may be necessary or required to effectuate the settlement arrived at between the parties;
c) They are entering into the present Agreement in their own volition without any representation or warranty made by MTF.
Company Appeal (AT) (Insolvency) No. 587 of 2019 Page 4 of 10 4) Undertaking by MTF
MTF shall upon receipt of the Settlement Amount, hereby irrevocably and unconditionally agrees, confirms and undertakes that:
a) It shall issue an email to the IRP and the Metalore Promotors acknowledging receipt of the Settlement Amount;
b) The receipt of the Settlement Amount will be towards full and final settlement of the financial dues payable by Metalore to MTF under the Facility Agreement; and It will strictly comply with all the terms and conditions of the present Agreement;
5) Indemnity
(i) Metalore Promotors shall defend, indemnify and hold
harmless MTF and its officers, directors, employees, agents and affiliates, from and against all the losses incurred or suffered by MTF or any such person arising out of, resulting from any breach of Metalore Promotor's warranties, representations, covenants or undertaking contained herein.
(ii) Notwithstanding anything contained in any other provision of this Agreement, MTF shall not be liable for any indirect, incidental or consequential loss or damage (including lost profits or loss of business) suffered or incurred by the other party in connection with the present Agreement.
6) Miscellaneous
(i) Governing Law
This Contract shall be governed by and construed in accordance with Indian Law with non-exclusive jurisdiction of the courts of New Delhi.
(ii) Entire Agreement
On and from the date of execution of this Agreement, this Agreement shall constitute an integral part of each of the Facility Agreement and shall always be read along with the Facility Agreement. No amendment to this Agreement shall be valid unless agreed to in writing by both the Parties.
Company Appeal (AT) (Insolvency) No. 587 of 2019 Page 5 of 10 (iii) Captions
The captions herein are included for convenience of reference only and shall be ignored in the construction or interpretation hereof.
(iv) Assignment
Neither Party shall transfer or assign this Agreement to any third party in whole or in part without the prior written consent of the other Party.
(v) Counterparts
This Agreement may be executed in any number of counterparts and all such counterparts taken together shall be deemed to constitute one and the same instrument.
IN WITNESS WHEREOF the Parties hereto have here in set and subscribed their respective hands on the day and year first herein above mentioned.
Signed and delivered by the within named
1. Shyam Kumar Garg (Sd/-)
2. Rahul Garg (Sd/-)
Signed and delivered by the within named
Maersk Trade Finance A/S
Sd/-
Signed and delivered by the within named
In the presence of witnesses:
1) Manish K. Jha (Sd/-) B-303, Ansal Plaza, Delhi-49.
2) (Sd/-) Ram Mohan Singh 114, Canare Apartment, Sec 13, Rohini N Delhi 110085
Company Appeal (AT) (Insolvency) No. 587 of 2019 Page 6 of 10 Annexure-A METALORE OVERSEAS PVT. LTD. LIST OF SHARE HOLDERS
S.No Name Address No. of Face Amount % of . shares value share 1 SHYAM S/O LATE SH. T.R. 921900 10 9,219,000 50.022 KUMR GARG, C-2, PLOT C- GARG 5, BHAMASHAH MARG, DELHI- 110009
2 SARITA W/O SH SHYAM 15000 10 150,000 0.814 DEVI GARG GARG, C-2, PLOT C- 5, BHAMASHAH MARG, DELHI- 110009
3 ASHOK 10000 10 100,000 0.543 KUMAR JAYSAL
4 ASHOK S/O SH. M.R. 1100 10 11,000 0.060 GOYAL GOYAL, KD-124 PITAM PURA, DELHI-110034
5 RAHUL S/O SH SHYAM 125000 10 1,250,000 6.782 GARG GARG, C-2, PLOT C- 5, BHAMASHAH MARG, DELHI- 110009
6 KRAC 20000 10 200,000 1.085 Securities Pvt. Ltd.
7 Gomati 333A, 2nd Floor, 50000 10 500,000 2.713 Consultants Santnagagar, East of Private Kailash, New Delhi- Limited 110065
8. Karda B-163, 1st Floor, 50000 10 500,000 2.713 Traders Amar Colony, Private Lajapat Nagar-IV, Limited New Delhi-110024.
9 Marco IT 326, L.G.F., Sant 50000 10 500,000 2.713 Systems Nagar, East of Private Kailash, New Delhi- Limited 110065.
10 Commo Info 333A, 2nd Floor, 50000 10 500,000 2.713 Solutions Santnagagar, East of Private Kailash, New Delhi- Limited 110065
Company Appeal (AT) (Insolvency) No. 587 of 2019 Page 7 of 10 11. Techno Soft 36, 3rd Floor, Deepak 50000 10 500,000 2.713 Infosystem Building, 13 Nehru Private Place, New Delhi- Limited 110019.
12 Yunan Sales B-87, Block-B, 50000 10 500,000 2.713 Private Defence Colony, New Limited Delhi-110024
13 Sai Infoweb 326, L.G.F., Sant 50000 10 500,000 2.713 Private Nagar, East of Limited Kailash, New Delhi- 110065.
14 Purus B-87, Block-B, 50000 10 500,000 2.713 Marketing Defence Colony, New Private Delhi-110024 Limited
15 Kushaagra R-17, Private Colony, 50000 10 500,000 2.713 Exports Sri Niwaspuri, New Private Delhi-110065 Limited
16 M3M Traders 7B/11, Sri Niwaspuri, 50000 10 500,000 2.713 Private New Delhi-110065 Limited
17 Next R-17, Private Colony, 50000 10 500,000 2.713 Generation Sri Niwaspuri, New Exim Private Delhi-110065 Limited
18 Groupone 7B/11, Sri Niwaspuri, 50000 10 500,000 2.713 Informative New Delhi-110065 Services Private Limited
19 Round Square B-163, 1st Floor, 50000 10 500,000 2.713 Exim Private Amar Colony, Limited Lajapat Nagar-IV, New Delhi-110024.
20 Third R-17, Private Colony, 50000 10 500,000 2.713 Generation Sri Niwaspuri, New Traders Delhi-110065 Private Limited
21 Pragaya B-163, 1st Floor, 50000 10 500,000 2.713" Multi Traders Amar Colony, Private Lajapat Nagar-IV, Limited New Delhi-110024.
4. Mr. Manish Jha, learned Counsel appearing on behalf of Sunrise 14 A/S/ Denmark ('Financial Creditor') accepted that the parties have reached
Company Appeal (AT) (Insolvency) No. 587 of 2019 Page 8 of 10 settlement, as quoted above. However, it is informed that the Respondent is yet to receive the amount in terms of the settlement.
5. Mr. Anil Bhatia, Interim Resolution Professional appears in person and submits that he has already incurred expenses of Rs.1,65,000/- towards advertisement and some litigation. He further submitted that he is entitled for a fee for working about 30 days. He also accepted that 'Committee of Creditors' have not yet been constituted.
6. Taking into consideration the aforesaid fact that the parties have settled the matter, in exercise of inherent powers under Rule 11 of the National Company Law Appellate Tribunal Rules, 2016, we allow the settlement and set-aside the impugned order dated 13th May, 2019. In the result, Company Petition No. IB-832(PB)/2018 filed by Sunrise 14 A/S, Denmark is disposed of as withdrawn. The Appellant, other Shareholders/ Directors of the 'Corporate Debtor' and Sunrise 14 A/S, Denmark will be bound by the terms of settlement. In case, the Appellant or Shareholders/ Directors or the 'Corporate Debtor' fails to pay the amount in terms of the settlement, it will be open to the Respondent Sunrise 14 A/S Denmark ('Financial Creditor') to move before this Appellate Tribunal for recall of this order and to revive the 'Corporate Insolvency Resolution Process' against M/s Metalore Overseas Private Limited. They may also file an application for initiation of contempt proceedings against the concerned Managing Director/ Directors and Shareholders including the Appellant.
7. Taking into consideration the fact and that 'Interim Resolution Professional' has worked for 30 days, we assess his fee at Rs.1,00,000/-. This apart, he will also be entitled for an amount of Rs.1,65,000/- towards cost incurred by him, i.e. total Rs.2,65,000/-. The Respondent Sunrise 14 A/S Denmark has advanced a sum of Rs.2,00,000/-, after deducting TDS. Therefore, 'Interim Resolution Professional' will be entitled for another sum of Rs.65,000/- only. The 'Corporate Debtor' will pay Rs.2,00,000/-, which includes TDS amount to the Sunrise 14 A/S Denmark, apart from the amount payable in terms of settlement. The amount of Rs.2,00,000/- be paid within 15 days. The rest amount of Rs.65,000/- be paid by the 'Corporate Debtor' to the 'Interim Resolution Professional' (Mr. Anil Bhatia)
Company Appeal (AT) (Insolvency) No. 587 of 2019 Page 9 of 10 within 15 days. We also make it clear that if the amount is being received by the 'Corporate Debtor' in US Dollar, parties will intimate the matter to the concerned Authority of the Government of India and may enclose a copy of this order.
8. In effect, order (s) passed by Ld. Adjudicating Authority appointing 'Interim Resolution Professional', declaring moratorium and all other order
(s) passed by Adjudicating Authority pursuant to impugned order and action taken by the 'Resolution Professional' are set aside. The application preferred by the Respondent under Section 7 of the I&B Code is disposed of as withdrawn. The Adjudicating Authority will now close the proceeding. The Respondent Company is released from all the rigour of law and is allowed to function independently through its Board of Directors from immediate effect.
9. The appeal is allowed with aforesaid observations and directions. No costs.
[Justice S. J. Mukhopadhaya] Chairperson
[Justice A.I.S. Cheema] Member (Judicial)
[Kanthi Narahari] Member (Technical)
Ash/SK
Company Appeal (AT) (Insolvency) No. 587 of 2019 Page 10 of 10
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free