Shreenathji Infrastructure vs Namasthetu Infratech Private Limited
- CitationCompany Appeal (AT) (Insolvency) No. 2153 of 2024
Ratio decidendi
The rule this decision rests on
Where an operational creditor's Section 9 petition is met by a genuine, pre-existing dispute between the parties — evidenced by correspondence raising non-completion, quality and quantity defects, and a termination of the work order before the demand notice — the existence of such a dispute on the record is sufficient for the Adjudicating Authority to dismiss the petition; disputed questions of fact of that kind cannot be resolved in summary insolvency proceedings and must be decided in a trial. A claim for damages arising from frustration of a contract under Section 56 of the Indian Contract Act, 1872, lies in unliquidated damages under Section 73 of that Act and is to be determined by a Civil Court after trial; it does not constitute an operational debt amenable to a Section 9 petition. A writ petition dismissed on the ground that contractual disputes must be pursued through the contract remedy, and which contains only observations rather than a determination of the disputed debt, does not displace the finding of a pre-existing dispute in insolvency proceedings.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
IN THE MATTER OF: Shreenathji Infrastructure Through its Authorized Representative, Amit Kumar Malpani, Civil and Mining Contractor Office at: A-3/6os, Aakriti Green Bhopal - M.P.- 462042 ...Appellant
Versus
M/s Namasthetu Infratech Pvt. Ltd, Through its Director Registered Office: The Great Eastern Galeria Complex, 5o2, 5th Floor, Plot No. 20, Sector No.4, Nerul, Navi Mumbai - 400706 ...Respondent
Present: For Appellant : Mr. Vishal Bhatnagar and Mr. Veer Pratap Singh, Advocates
For Respondent : Mr. Rohit Gupta and Mr. Rhythm Buaria, Advocates
JUDGMENT
(Hybrid Mode)
[Per: Arun Baroka, Member (Technical)]
That the instant Appeal is being filed under Section 61 of the Insolvency
and Bankruptcy Code, 2016 ("IBC") against the order dated 17th May 2024
("Impugned Order") passed by the Ld. National Company Law Tribunal,
Mumbai Bench ("Adjudicating Authority'') in CP (IB) No. 393/MB/2022 titled
"Shreenathji Infrastructure Vs. M/s Namasthetu Infratech Pvt Ltd." by way of which the Ld. Adjudicating Authority had dismissed the Petition filed by the
Appellant under Section 9 of the IBC.
Submissions of the Appellant:
2. The Appellant - Shreenathji Infratech - Operational Creditor (OC) is a
partnership firm registered in MP and is engaged in the business of
construction of civil and engineering works, mining, drilling, earthwork. The
Appellant brings to our notice that various work orders dated 14 September
2018, 10 September 2018, and 5 January 2019 were awarded to it by the
Corporate Debtor Company-M/s Namasthetu Infratech, for the installation of
mobile stone crushing plants, earthwork in excavation and supplying and
filling muroom in depressions. The Appellant also brings to our notice that
the Airport Authority of India (AAI) on 3rd September 2019 issued a letter to
one M/s Vishal Infratech Limited for the removal of the stone crusher
installed in the airport site. AAI stopped the Operational Creditor from
carrying out the work in the said site on the ground of lack of approval to
carry out the crushing work. The Appellant also claims that the District
Collector granted requisite approvals and permission to the Operational
Creditor to carry out upgradation work in the said site on 12 September 2019.
Appellant claims that the CD Company from 1st September 2019 onwards
stopped making payments to the Operational Creditor for the work already
carried out and being carried out on the said site. The Appellant issued a
demand notice/invoice demanding payment under the code as per Form 3
and 4, on 7 December 2019 and 16 December 2019. The Appellant claims
that on 23rd August 2020, FIR bearing number 0244/2020 was also filed
Company Appeal (AT) (Insolvency) No. 2153 of 2024 2 of 26 against the CD company, and the charge sheet has also been filed on the said
FIR. On 20th January 2022, the Appellant filed the Company Petition bearing
number (IB/393/2022), namely Shreenathji Infrastructure versus M/s
Namasthetu Infratech Pvt. Ltd. under Section 9 of the Code before NCLT
Mumbai. The matter was heard by NCLT Mumbai on various dates, and on
17th May 2024, the Adjudicating Authority dismissed the said petition under
Section 9 of the Code.
3. Respondent Company were not unaware of the said impediment and a
problem with the installation of crushing plant in the area of AAI. The
Respondent Company had failed to expeditiously inform the Appellant about
the same. It was obligatory upon Respondent Company to make sure, that
the Respondent Company have the requisite permission/sanction or not. If
not, then Respondent Company should not have executed the letter of work
orders presented to Appellant. In lieu of that work order(s), Appellant invested
huge amount for installing the crusher on the work site to execute and
complete the work order(s). On 07.12.2019/16.12.2019, the Appellant sent
the notice of demand in terms of Section 8 of the Insolvency and Bankruptcy
Code, 2016 read with Rule 5 (1) (a) of Insolvency and Bankruptcy (Application
to Adjudicating Authority) Rules, 2016 in Form 3 and Form 4 prescribed
thereunder along with the copies of invoices and other documents relied upon
by the Appellant. In terms of the notice a request was made to Respondent
Company to clear the outstanding payments due to the Appellant. The Ld.
Adjudicating Authority has failed to see that the notice was dispatched by
speed post at the registered office address of the Respondent. After the service
Company Appeal (AT) (Insolvency) No. 2153 of 2024 3 of 26 of notice by email, the Appellant neither received any reply nor payment, nor
any notice of dispute.
4. Respondent Company has received the amount from the AAI through
Vishal Infrastructure but have not cleared the outstanding payments to the
Appellant and as such they are liable to pay the outstanding amount together
with interest thereon to the Appellant because there is a substantial cost of
financing involved for every business.
5. The Respondent Company, in its reply to the company petition filed by
the Appellant before the Ld. Adjudicating Authority, has not objected to or
disputed the non-performance of the contract. Silence or non-denial of
specific allegations by the Respondent Company implies acceptance of those
allegations. In the present case, the Respondent company has neither refuted
the claims regarding the completion of work as assigned under the contract
nor provided any evidence to counter the assertions of the Appellant regarding
the performance of its obligations. The failure of the Respondent Company to
specifically deny or challenge the completion of work under the contract
constitutes an implied admission of the facts asserted by the Appellant.
According to legal principles, particularly under Order VIII Rule 5 of the Civil
Procedure Code, 1908, which states that every allegation of fact in the plaint,
if not denied specifically or by necessary implication, shall be taken to be
admitted. The order passed by the Ld. Adjudicating Authority fails to take into
consideration the lack of contestation by the Respondent Company regarding
the performance of the contract. Adjudicating Authority did not adequately
Company Appeal (AT) (Insolvency) No. 2153 of 2024 4 of 26 address the unchallenged assertions made by the Appellant that in
September 2019, the officials of AAI stopped the Appellant from working the
crushers and informed that the installation of crusher was not allowed in the
said site from the very beginning and no approval has been acquired from the
same.
6. The Appellant asked the Respondent Company to provide the copy of
agreement between AAI and Vishal Infrastructure, but the same was not
provided to the Appellant and keeping the matter delayed on the one pretext
or the other. Eventually, it came to Appellant's knowledge that in consonance
with the agreement dated 19.02.2018 between AAI and Vishal Infrastructure
Ltd. the installation of crushing plant within AAI area was never allowed. The
Respondent Company without acquiring the requisite permission, ordered the
Appellant to start installing stone crushers in the said site. The Respondent
Company have for the First work order cleared the amount of
₹4,61,01,411.50/- (₹ Four Crore Sixty-One Lakhs Four Hundred Eleven and
Five Paisa Only) and asked the Appellant to continue the process of making
infrastructure in the said site of AAI. The Respondent company has not
cleared payments of the Appellant since September 2019. The total
outstanding amount as per the books of accounts is ₹1,54,56,473/- (Rupees
One Crore Fifty-Four Lacs Fifty-Six Thousand Four Hundred and Seventy-
Three only).
7. There has been no existing dispute with respect to the outstanding
payment. As per the terms and conditions of installing crushers the
Company Appeal (AT) (Insolvency) No. 2153 of 2024 5 of 26 Respondent Company is liable to pay interest at the rate of 24% to the
Appellant in addition to the outstanding amount, calculated on the
outstanding amount against various invoices from the date of invoice.,
thereby disregarding crucial evidence and the principles of natural justice.
Adjudicating Authority's order does not provide clear reasoning or findings on
the key issue of whether the work assigned under the contract was not
completed and by whose fault. Instead, it appears to have overlooked the
absence of a dispute on this fundamental aspect. Such an omission renders
the order vague and legally unsustainable, as it lacks a thorough examination
of the uncontested facts presented by the Appellant. The Hon'ble Supreme
Court in Union of India Vs. Ibrahim Uddin & Anr. (2012) 8 SCC 148
emphasized the necessity for judicial orders to reflect consideration of all
material evidence and arguments. An order that fails to address uncontested
claims is flawed and warrants appellate intervention. So much so, in Vishnu
Dutt Sharma Vs. Daya. Sapra (2009) 13 SCC 729, the Supreme Court held
that non-denial of specific allegations leads to an inference of admission of
such facts. Adjudicating Authority has failed to recognize, the undisputed
completion of the work and directing the Respondent company to make the
due payments to the Appellant.
8. The whole contract for up-gradation of Jabalpur Airport took place at
the initiation of the AAI, they were aware of the work carried out in the given
site and being in the knowledge that the requisite permission not being taken
by the Respondent Company or by the Vishal Infrastructure Ltd. with whom
the AAI had executed the contract, it was their responsibility to stop the
Company Appeal (AT) (Insolvency) No. 2153 of 2024 6 of 26 crushers from being installed, instead, they chose to maintain the status quo
and interfered after one year, after the Appellant has invested huge amount
of money in said project and carried on half of the work. It is necessary to
hold them responsible for the one-year inactivity and interference later on.
9. The Respondent Company issued a letter dated 09.08.2019 to the
Appellant outlining specific terms for invoicing, which stated that some
invoices should be issued through Tax Invoices and for the balance quantity,
the new rate as per the letter could be considered. This letter was sent as a
part of the agreement renegotiation and was crucial for the Appellant and
financial understanding between the parties. In the reply, the Respondent
Company neither accepted nor denied the receipt and the terms outlined in
the letter dated 09.08.2019. The absence of any rebuttal or acknowledgment
from the Respondent company signifies a lack of contestation regarding the
terms which were proposed by the Respondent Company to the Appellant.
According to the principle of implied acceptance, the non-response from the
Respondent company can be construed as an acceptance of the terms
mentioned in the letter. The Respondent Company's silence or failure to
address the contents of the letter dated 09.08.2019 implies that they had no
objections to the terms specified therein.
10. Adjudicating Authority has failed to see the Non-Performance
Attributable to AAI's Intervention, not the Appellant. The Appellant entered
into a contract with the Respondent company to perform certain crushing
and excavating work at a specified site. The Appellant commenced the work
Company Appeal (AT) (Insolvency) No. 2153 of 2024 7 of 26 as per the contractual terms and in good faith. There was Intervention by AAI
during the execution of the contract, the AAI intervened and halted the work.
AAI declared that the site area was not permitted for crushing and excavating,
citing regulatory and safety concerns. AAI's intervention was beyond the
control of the Appellant and directly impacted the ability to perform the
contractual obligations. Adjudicating Authority failed to see that the non-
performance was not due to Appellant's Actions. The cessation of work was
mandated by a Regulatory Authority (AAI), which had jurisdiction over the
site area. Therefore, the non-performance of the contract cannot be attributed
to any fault, negligence, or failure on the part of the Appellant. The Appellant
was ready, willing, and able to perform the contractual duties but was legally
restrained from doing so by the AAI. That the intervention by AAI constitutes
a force majeure event or an instance of frustration of contract under Section
56 of the Indian Contract Act, 1872, as the performance of the contract
became impossible due to an unforeseen and uncontrollable external event.
Adjudicating Authority ought to have seen that performance of a contract is
excused when prevented by an act of government or a regulatory authority.
In Satyabrata Ghose Vs. Mugneeram Bangor & Co. (1954 AIR 44, 1954
SCR 310), the Hon'ble Supreme Court held that a contract becomes void
when its performance is rendered impossible due to circumstances beyond
the control of the parties. Adjudicating Authority erroneously attributed non-
performance to the Appellant without considering the legal and factual
context of AAI's intervention. Adjudicating Authority failed to recognize that
the stoppage of work by AAI, a governmental authority and absolves the
Company Appeal (AT) (Insolvency) No. 2153 of 2024 8 of 26 Appellant from any liability of non-performance under the contract. The
principle that parties are discharged from contractual obligations when
performance is made impossible by an unforeseen event is well-established.
The Hon'ble ·Supreme Court in Energy Watchdog Vs. CERC (2017) 14 SCC
80 reiterated that performance is excused when prevented by an unforeseen
event beyond the parties' control. So much so, additionally, Naihati Jute
Mills Ltd. V s. Hyaram Jagannath (AIR 1968 SC 522) established that if a
contract becomes impossible to perform due to an external event, the affected
party is not liable for non-performance. The Appellant has been performing
its contractual obligations diligently and in accordance with the agreed terms,
but the Respondent Company failed make the payments to the Appellant
outstanding payments since September 2019. Despite the completion and
performance of the work as per the contract, the Respondent Company has
failed to clear the payments due to the Appellant since September 2019. As
per the books of accounts maintained by the Appellant, the total outstanding
amount due from the Respondent Company is ₹1,54,56,473/- (Rupees One
Crore Fifty-Four Lacs Fifty-Six Thousand Four Hundred and Seventy-Three
only). The significant delay in payment has severely impacted the financial
stability and operational capacity of the Appellant. The Appellant relies on
timely payments to manage its cash flow, procure materials, pay salaries, and
cover other operational expenses necessary to continue the work. The non-
clearance of dues by the Respondent company has created a financial strain,
making it extremely difficult, if not impossible, for the Appellant to continue
performing the work under the contract. The failure to make timely payments
Company Appeal (AT) (Insolvency) No. 2153 of 2024 9 of 26 constitutes a breach of the contractual obligations on the part of the
Respondent Company. As per the terms of the contract, the Respondent
Company is required to make payments within the stipulated time frame to
ensure the smooth progress of work. The long-standing non-payment is a
clear violation of these terms. Adjudicating Authority failed to considered that
the party failing to fulfil its financial obligations under a contract cannot
expect the other party to continue performing without receiving due
compensation. The Hon'ble Supreme Court, drawing upon the principles set
out in Chitty on Contracts, has consistently affirmed that non-payment of
contractual dues by one party entitles the counterparty to withhold or
suspend its performance until payment is made. In S.P. Singh Vs. State of
Punjab, (1967) 1 SCR 754, the Court held that a party to a contract who
suffers from a breach by the other party is entitled to stop performance until
the breach is rectified.
11. Adjudicating Authority, in its judgment and order vide dated
17.05.2024, failed to consider the severe financial impact and operational
constraints faced by the Appellant due to the non-payment of dues by the
Respondent Company. Adjudicating Authority's judgment and order vide
dated 17.05.2024 is erroneous and unjust as it overlooks the fundamental
breach of contract by the Respondent Company and the resulting inability of
the Appellant to continue work without receiving the outstanding payments.
Adjudicating Authority failed to see that the AAI issued the notice on
03.09.2019 to the Vishal Infrastructure Ltd. to stop the crushing work and
remove the crushers. The work at the said site was stopped because of the
Company Appeal (AT) (Insolvency) No. 2153 of 2024 10 of 26 notice dated 03.09.2019. The AAI. continued to release the running bill
payments in the. favour of Vishal Infrastructure Ltd. knowing fully well that
the Respondent company is not making the said payments to the Appellant
through Respondent company for the work being done at the AAI site.
Adjudicating Authority failed to see that the work order and consent letter
signed between the Appellant and the Respondent Company did not mention
that it would be the Appellant's responsibility to acquire the required work
permissions. However, Clause 24 (a) of the agreement signed between the
Respondent Company and Vishal Infrastructure Ltd. clearly and specifically
states that all necessary registrations for complying local/state/central
labour/other regulations as. required shall be obtained by the Vishal
Infrastructure Ltd. and any penalty, damages, claims arising out of the failure
to comply with the above shall be borne by the Vishal Infrastructure Ltd.
Despite the abovementioned specific clause, the Vishal Infrastructure Ltd.
has not been made to take the responsibility for the same; however, the
Appellant has been facing consequences of their misdeed even at the hands
of AAI.
12. Adjudicating Authority has failed to see that the FIR was lodged and
registered and the Chargesheet has been filed. The said documents both
substantially a part of evidence which points to the fact that there has been
a commission of offences by the Respondent company upon the Appellant, as
a charge sheet would not take effect unless the investigating police do not find
vital evidence which link the said Corporate Debtor with the offences
committed.
Company Appeal (AT) (Insolvency) No. 2153 of 2024 11 of 26
13. Adjudicating Authority failed to see that the Appellant has also filed the
Writ Petition before the Hon'ble Madhya Pradesh High Court, Principal
Seat at Jabalpur, WP bearing no. 22703/2022 and the same was averred
in the rejoinder to the affidavit of reply filed by the Respondent, however, the
said rejoinder was not taken on record. Nonetheless, the Hon'ble High Court
dismissed the Writ Petition vide dated 24.11.2022 but gave some findings in
the impugned order, the relevant paras of the impugned order are reproduced
herein:-
"5. On hearing learned counsel, we do not find any merit in this petition. Undoubtedly, there is a contract entered into by respondent No.1 in favour of respondent No.3 and the sub-contract thereafter in favour of respondent No.2 and the consequential allotment of work in favour of the writ petitioner. Therefore, if it all any action has been taken by respondent No. 1, the same may affect the contractual obligations of the petitioner and other respondents. Therefore, the petitioner would have to seek remedy under contract. The matter of contract cannot be questioned in a writ petition under Article 226 of the Constitution of India. Be that as it may, the prayer made herein is for initiation of an enquiry. In case the plea of the petitioner is to be accepted then an enquiry has to be ordered on the finding that certain illegalities have been committed by the respondents under contract. Therefore, once again the terms of the agreement would have to be scrutinized to find out if there is any violation and only after coming to a conclusion that there are violations that subsequent orders could be passed. Even assuming this exercise is to be done, the same would not, under any circumstances, result in the initiation of an enquiry against any of the respondents, since what is contended is based on the violation of the terms and conditions of the contract. If that were to be so, the petitioner has a remedy elsewhere. Therefore the prayer sought for by the petitioner herein for the initiation of an enquiry,
Company Appeal (AT) (Insolvency) No. 2153 of 2024 12 of 26 in our considered view, would not arise in the facts and circumstances of this case.
6. Even otherwise, the relief sought for is to direct respondent No.1 to constitute an enquiry for the officers of respondent No.1 as stated herein. It is respondent No.1 who had entered into contract with respondent No.3 and thereafter respondent No.3 entered into contract with respondent No.2. The work order as such has been issued by respondent No.2 to the petitioner. Therefore, prima facie even if there is any grievance of the petitioner, it can only be against respondent No.2 and none else. Even otherwise, we do not wish to comment on the same since in matters of contract, the remedy of the petitioner lies elsewhere. The question of directing initiation of an enquiry against officials of respondent No. 1, in our considered view, is wholly misconceived and is alien to the facts and circumstances of the case. Hence we do not find any ground to interfere."
14. Adjudicating Authority failed to take the aforesaid order into
consideration, the same had clearly stipulated that the genesis of the dispute
has never been the contract executed between the parties herein, the dispute
was that the Appellant was made to enter into the contract which was defied
illegal, as, the project was of AAI, the agreement executed between the AAI
and the Vishal infrastructure had an impediment that crushing plant cannot
be installed, however, the Respondent made Appellant to enter into the
agreement for installation of crushing plant having had the knowledge that
the same is illegal in consonance with the ·contract executed between the AAI
and Vishal Infrastructure ltd. and the Adjudicating Authority passed the
order while dismissing the petition of the Appellant stating and observing that·
there was a non- performance of the contract on the part of the Appellant.
Company Appeal (AT) (Insolvency) No. 2153 of 2024 13 of 26
15. Ld. Adjudicating Authority has erred to see that the illegal contract
predominantly and undisputedly performed by the Appellant cannot be ruled
out and negatived on the ground of non- performance. Adjudicating Authority
erred in completely ignoring the balance sheet which proves that payments
were made by the Respondent Company to the Appellant in lieu of the
performance of the tasks assigned on regular basis and the Respondent has
accepted that there is a debt due. The Adjudicating Authority erred to even
cite and did not follow the statutory rule and the guidelines issued by the
judgements of Hon'ble Supreme Court and have failed to see as to whether
the Respondent has raised a dispute which can be described as "a pre-existing
dispute" as understood by the Hon'ble Supreme Court in the decision in
Mobilox Innovations (P) Ltd. versus Kirusa Software (P) Ltd. The answer
is in negative. Adjudicating Authority has erred to see that the plea of non-
performance of the contract may have had with the Respondent with the
precondition that the said contract executed between the Respondent and
Appellant did not have invalidation from the AAI, as, the project was of AAI
and the Respondent was to perform the work, as, assigned by Vishal
infrastructure ltd, however, the said work i.e. installation of crushing plant
was never allowed by the AAI. Adjudicating Authority has erred to see that
mere by averring non-performance does not suffice the purpose, as, against
the non-performance as alleged, the Respondent has not taken any legal
recourse against the Appellant, therefore, there is no question of non-
performance of contract subsisted. The Respondent was never aggrieved by
the act of the Appellant and therefore, did not initiate any legal recourse
Company Appeal (AT) (Insolvency) No. 2153 of 2024 14 of 26 against the Appellant. The same depicts the Respondent had no grievance to
redress qua Appellant.
Submissions of the Respondent
16. The Respondent, the Corporate Debtor, claims that the Appellant is
guilty of suppressing the true nature and the extent of the pre-existing
disputes between the parties. A mala fide attempt has been made by the
Appellant to mislead this appellate tribunal into believing that an operational
debt is due. The said appeal is nothing but an attempt to usurp monies which
are neither due nor payable to the Appellant by the Respondent.
17. Respondent brings to our notice that there was a pre-existing dispute
between the Appellant and the Respondent. The Respondent, with a letter
dated 15 November 2019, had terminated the work order dated 14 September
2018. The Appellant issued the notice invoking the provisions of the Code on
16 December 2019, which is after the issuance of the letter terminating the
work order issued by the Respondent in favour of the Appellant. The said
work order was terminated due to the failure of the Appellant to complete the
contract within the stipulated time. The Respondent had warned the
Appellant time and again regarding the lackadaisical approach of the
Appellant. Hence, there was a pre-existing dispute between the parties before
the issuance of the notice dated 16 December 2019.
18. The alleged claim of the Appellant inter alia relates to the alleged
recovery of ₹1,54,56,473 with interest at the rate of 24%, which comes to
₹80,37,366 calculated up to November 2021, which is outstanding as per the
books of accounts of the Appellant. There is no acknowledgement of debt by Company Appeal (AT) (Insolvency) No. 2153 of 2024 15 of 26 the Respondent. However, it is the Appellant who owed money to the
Respondent for work not done by the Appellant.
19. The Appellant has wrongfully issued notice dated 16 December 2019
and invoked the provisions of the Code in view of the fact that there was a
pre-existing dispute. The Appellant had failed to perform its obligations under
the terms and conditions agreed between the Respondent and the Appellant
as per the work orders dated 14 September 2018, 16 December 2018, and 5
January 2019.
20. The Respondent claims that the Appellant was required to commence
the business with the required facilities. The Appellant failed to commence
the business of the installation of the mobile stone crushing plant at Jabalpur
site and supply the crushed aggregate as per the grading requirement form
WMM, and GSB mix, and also failed to provide the contractual amount of
crushed aggregate with all required facilities in compliance with the work
order dated 14 September 2018. Furthermore, the validity of the said work
was twelve months; however, despite the repeated assurances, the Appellant
failed to supply the crushed aggregate as per the grading requirement form
WMM, and GSB mix as per the terms and conditions of the work order.
21. As per the work order dated 14 September 2018, the Appellant was
supposed to supply GSB quantity of 5,040,000 CFT; however, the quantity
supplied by the Appellant was 131,444 CFT only up to March 2019, leaving
a balance of 4,908,556 CFT, which the Respondent had to acquire from other
agencies for which the Respondent had to incur additional costs for acquiring
Company Appeal (AT) (Insolvency) No. 2153 of 2024 16 of 26 the same. The Respondent incurred about ₹88,867,952 for acquiring the
balance 4,908,556 CFT.
22. If the Appellant had done their work on time, then the Respondent
would have spent ₹6,01,298,11 (₹49,08,556 X ₹12.25 per CFT). However, the
extra cost that they had to spend was ₹ 88,86,952/- less ₹ 6,01,298,11/-
which comes to ₹ 2,87,38,141/- excluding GST and ₹ 3,39,11,066 including
GST at the rate of 18%. The Respondent claims that it has therefore incurred
a loss of ₹2,87,38,141/- excluding GST, and the Respondent reserves its right
to recover the same from the Appellant.
23. The Respondent claims that they had to incur extra cost with respect
to the work order dated 5 January 2019 due to non-completion of Moorum
embankment of the runway. The period of the contract/work had to be
extended by 31st March 2020 for the completion of the embankment. The
total quantity of Moorum to be supplied was 200,000 cubic meters; however,
the quantity supplied by the Appellant was 140,645 cubic meters. Due to
non-supply of the quantity of Moorum as per the agreement and extension of
work, various machineries were deployed, which was an extra burden to the
Respondents. The total cost of these machineries was ₹5,355,000 without
diesel. The cost of diesel itself was ₹3,929,800. Respondent also claims that
the extra cost due to the extended period is ₹1,02,48,750 including GST.
Therefore, the Respondent incurred a loss of ₹1,02,48,750 including GST.
Respondent reserves its right to recover the same from the Appellant.
Company Appeal (AT) (Insolvency) No. 2153 of 2024 17 of 26
24. The Respondent also brings to our notice that the excavated stuff
stacked in the runway portion was not used for crushing till the expiry of the
period of crushing, that is, 14th March 2019. Hence, the question of granting
permission on 12th September 2019 did not arise in any event. Assuming,
without admitting, there was no permission for excavation from 12th
September 2019, the contract should have been completed before that day.
However, the reality was that the contract was not even 3% completed after
the completion of one year from the date of issuance of the work order.
25. The Respondent also brings to our notice that the erection of the
crusher was not objected to by the Airport Authority of India till September
2019. The Airport Authority of India asked to remove the crusher because the
place where excavated stuff was stacked by the Appellant for crushing was
the same place that was supposed to be used by the Airport Authority of India
for work to be started by them. The period of completion for the work was up
to 14th March 2019, and since the same was not completed in time, the
Appellant was liable for delays.
26. The Respondent also wrote many letters to the Appellant on:
11 June 2019 14 June 2019 20 June 2019 25 June 2019 26 June 2019 5 July 2019 8 August 2019 21 October 2019 15 November 2019
Company Appeal (AT) (Insolvency) No. 2153 of 2024 18 of 26 not only disputing the quality of work done but also the minuscule quantity
being supplied by the Appellant under the said contracts/work orders. In
these letters, the Respondent time and again called upon the Appellant to
rectify their mistakes in executing the contract, to provide GST returns, as
after claiming GST from the Respondent, the Appellant did not deposit the
same with the Department. By letters dated 5th July 2019 and 15 November
2019, the Respondent terminated the contract and cancelled the orders given
to the Appellant, as the Appellant had only provided about 2% of the quantity
under the orders dated 14 September 2018, 10 December 2018, and 5
January 2019. The Appellant has deliberately not filed the above-mentioned
letters before the NCLT and also before the Appellate Tribunal.
27. The Appellant's purported claim is not a debt at all under the provisions
of Section 3(11) and/or operational debt under Section 5(21) of the IBC. Since
the Appellant's purported claim is not a debt and/or operational debt, the
question of any default under Section 3(11) of the Code does not arise, since
there is no amount that has become due and payable and is not paid by the
Respondent.
28. The appeal is gross abuse of process of law, as the same is being used
as an arm-twisting tactic to coerce the Respondent into making payment of
amounts which are not due at all.
29. The Appellant filed the Company Petition under Section 9 of the Code,
being CP (IB) No. 393/MB/2022, for an operational debt of ₹15,456,473/-
plus 24% interest per annum, i.e. ₹ 80,37,366/-.
Company Appeal (AT) (Insolvency) No. 2153 of 2024 19 of 26
30. It is also brought to our notice by the Respondent that the date of
default was stated to be the 31st day from the date of each invoice, as 30 days'
credit was admissible to the Respondent. The demand notice dated 16th
December 2019 was sent by the Appellant, but the same was not replied to
by the Respondent, and neither was the balance amount paid. However, the
Respondent had, prior in time, sent a termination notice dated 15th November
2019, and the Appellant, as an afterthought and as a counter blast, sent a
demand notice and also lodged an FIR No. 0244 dated 23rd August 2020 in
the police station against the Respondent under Section 420, 294, and 506
IPC. A charge sheet has also been filed on the said FIR. The Respondent also
brings to our notice that quashing proceedings are pending in respect of the
aforesaid FIR.
31. The Respondent claims that the appeal and the petition raises disputes
relating to the questions of fact. Hence, the same can only be decided by way
of trial and not before the NCLT or before the Appellate Tribunal.
32. Furthermore, Respondent objects to Appellant bringing additional
documents on record at the appellate stage, as there is no provision in law
applicable to the present proceedings that allows a party to bring documents
on record before this Appellate Tribunal, as they were not before the NCLT.
Appraisal
33. We have heard counsels of both sides and perused the material placed
on record.
Company Appeal (AT) (Insolvency) No. 2153 of 2024 20 of 26
34. We observe that the Adjudicating Authority has clearly noted that the
work which was awarded to the Appellant-Operational Creditor was as per
the work order dated 14th September 2018 and was to be completed on or
before March 2019. The Adjudicating Authority has also noted that the
reliance of the petitioner on the letter of the Airport Authority of India dated
3rd September 2019, is baseless and cannot be referred to appreciate the
case of the petitioner. The petitioner was given the task which had to be
completed by March 2019. The incomplete task on the part of the petitioner
clearly shows that it is the petitioner who has failed to perform his assigned
task within the stipulated time period. We find no infirmity on the part of the
Adjudicating Authority in coming to this conclusion that it is the petitioner
who has failed to perform his assigned task within the stipulated time period.
Even if there was no permission for excavation from 12th September 2019 as
claimed by the Appellant, we observe that the contract should have been
completed before that day. However, we find that the contract was not even
3% completed after the completion of one year from the date of issuance of
the work order.
35. We also observe from the reply of the Respondent that it wrote many
letters to the Appellant on 11 June 201, 14 June 2019, 20 June 2019, 25
June 2019, 26 June 2019, 5 July 2019, 8 August 2019, 21 October 2019, 15
November 2019 not only disputing the quality of work done but also the
minuscule quantity being supplied by the Appellant under the said
contracts/work orders. In these letters, the Respondent time and again called
upon the Appellant to rectify their mistakes in executing the contract, to
Company Appeal (AT) (Insolvency) No. 2153 of 2024 21 of 26 provide GST returns, as after claiming GST from the Respondent, the
Appellant did not deposit the same with the Department. As a sample, we
note the extracts of one such letter dated 25 June 2019, which is as follows:
36. Furthermore, by letters dated 5th July 2019 and 15 November 2019,
the Respondent terminated the contract and cancelled the orders given to the
Appellant, as the Appellant had only provided about 2% of the quantity under
the orders dated 14 September 2018, 10 December 2018, and 5 January
2019. It is brought to our notice that the Appellant has deliberately not filed
Company Appeal (AT) (Insolvency) No. 2153 of 2024 22 of 26 the above-mentioned letters before the NCLT and also before the Appellate
Tribunal.
37. It is also brought to our notice that since the Appellant had not
supplied the required quantity of material within time, therefore the
Respondent had to acquire the same after incurring additional cost, which
we have noted in the submissions of the Respondent.
38. The Respondent brings to our notice that the case of the Appellant is
that the Respondent, despite having knowledge about the fact that they did
not have the permission from the AAI to work at the Jabalpur airport or to
set up the crusher near the runway, led the Appellant to believe that they in
fact did have permission. On this belief alone, the Appellant spent a lot of
money to set up the crusher plant. We have gone through one of the work
orders dated the 14th September 2018, wherein it is clearly noted to supply
the required crushed aggregate as per grading requirement for WMM and
GSB mix. The same work order in special conditions notes that all machinery,
crusher unit shifting charges to and fro, shall be to the account of the
Appellant. The Respondent is interested in the supply of the crushed
aggregate and not in the installation of the stone crushing plant, which is
just incidental and for the convenience of both parties.
39. The Respondent also brings to our notice that the Appellant's best case
is that since AAI stopped the work and since the Respondent did not have
any prior permission, there was frustration and breach of contract, and hence
the Appellant could not perform the work order. Appellant's case is that AAI
Company Appeal (AT) (Insolvency) No. 2153 of 2024 23 of 26 stopped it from performing the work because there was no permission, and
this was known to the Respondent from day one. We observe that such an
argument is not tenable as the letter of removal of stone crusher installed in
the airport site was issued on 3rd September 2019, and AAI had stopped the
operational contractor from carrying out the work in the said site on the
ground of lack of approval to carry out crushing work. It is important to note
that the work order was issued by the Appellant on 14th September 2018,
and the validity of the said work order was for 12 months. Therefore, the
whole work was to be completed by 14th September 2019. During this period,
there was a lot of correspondence with respect to the delay and further
subcontracting by the Appellant and finally, the Respondent had already
issued the notice for termination on 5th July 2019 and finally the work order
on 15 November 2019. We further note that the Appellant issued the notice
invoking the provisions of the code on 16th December 2019 demanding
payment and filed the appeal under Section 9 of the Code on 20th January
2022, which is almost after more than a year. In the meantime, the Appellant
had also filed an FIR on 23rd August 2020, which has been noted by us herein
earlier in the submissions of both sides.
40. Even if the argument of the Appellant is accepted that there is a
frustration or breach of contract, we observe that the only relief that the
Appellant is entitled to is only unliquidated damages under Section 73 of the
Indian Contract Act for frustration of the contract under Section 56 of the
Contract Act, and can only be ordered by a Civil Court after a trial.
Company Appeal (AT) (Insolvency) No. 2153 of 2024 24 of 26
41. We also observe that the Operational Creditor never carried out any
task; rather, it subcontracted the work to be completed by one Mr. Rudra
Yadav and failed to pay the amount due of ₹56,56,129/-, who in turn
approached the Corporate Debtor to get the same amount released. The
Operational Creditor had abandoned the work, and there were many other
disputes between the Operational Creditor and the Corporate Debtor. The
Adjudicating Authority has noted it from para 29 to 32 in the impugned order
and has come to a conclusion that, in their view, there is a clear pre-existing
dispute between the parties.
42. We observe that the Respondent had, with a letter dated 15th November
2019, already terminated the work order dated 14th September 2018. The
Appellant invoked the provisions of the code on 16th December 2019 by
issuing a notice demanding the payment. However, the Section 9 proceedings
were initiated by the Appellant only some time on 20th January 2022, which
is almost after more than a year. We observe that there were many issues
regarding non-completion and quality of the work for which lot of
correspondence was going on between the two parties prior to the issuance
of the demand notice. These issues are not superfluous or issues which have
been made up by the Respondent.
43. The Appellant has also relied on a police complaint and an FIR
registered against the Corporate Debtor Company and also the charge sheet
which has been filed in the said FIR. It has been brought to our notice that
the Respondent is defending these proceedings. In any case, the Adjudicating
Authority has clearly brought out our pre-existing dispute in this case.
Company Appeal (AT) (Insolvency) No. 2153 of 2024 25 of 26 Therefore, we cannot rely upon such proceedings in coming to a conclusion
with respect to Section 9 proceedings.
44. Appellant has also heavily relied upon the observations in the writ
petition which it had filed before Hon'ble High Court of Madhya Pradesh,
Principal Seat at Jabalpur. We find that the writ petition was dismissed, and
separately the Adjudicating Authority has clearly brought out the preexisting
disputes. Therefore, the order in the writ petition before the Hon'ble High
Court of Madhya Pradesh has no relevance.
45. We thus observe that the disputes raised by the Appellant in the appeal
and the petition are disputed questions of facts, and hence the same can only
be decided by way of a trial and not before this forum and they are pre-
existing disputes and the Adjudicating Authority cannot be faulted upon in
dismissing the Appeal under Section 9 of the Code.
Order
46. Accordingly, the appeal is hereby dismissed and all related IAs are also
disposed of accordingly. No orders as to costs.
[Justice N. Seshasayee] Member (Judicial)
[Arun Baroka] Member (Technical)
[Indevar Pandey] Member (Technical) New Delhi.
May 19, 2026.
pawan
Company Appeal (AT) (Insolvency) No. 2153 of 2024 26 of 26
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free