Miss Lucy
← All judgments

Sanjeev Bhatjiwale S/O Shri Balchandra ... vs Ms Chhaya Gupta Resolution ...

National Company Law Appellate Tribunal23 July 2026

Ratio decidendi

The rule this decision rests on

The Tribunal's reasons rest on two propositions. First, a claimant who seeks recognition of a financial debt or allottee claim after the claim period and after approval of a resolution plan must establish, by evidence, that the disbursement was actually made to the corporate debtor; allotment letters and self-serving affidavits stating the manner of payment do not discharge that burden in the absence of proof of disbursement. Second, once a resolution plan has been approved by the Adjudicating Authority and implemented, a belated claimant has no right to upset it, and an application to have such a claim entertained at that stage is not to be entertained where the claim is unsupported by evidence available with the corporate debtor.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

NATIONAL COMPANY LAW APPELLATE TRIBUNALPRINCIPAL BENCH, NEW DELHICompany Appeal (AT) (Insolvency) No. 596 of 2026& I.A. No. 2299 of 2026

IN THE MATTER OF: Sanjeev Bhatjiwale ...Appellant

Versus

Chhaya Gupta & Anr. ...Respondents

Present: For Appellant : Present but appearance not marked. For Respondents : Mr. Tarak Damani, Advocate for R-1. Mr. Ayush J. Rajani, Ms. Khushboo Shah, Advocates for R-2.

ORDER

(Hybrid Mode)

23.07.2026: This appeal is against an impugned order dated 30.01.2026

passed by the learned National Company Law Tribunal, Indore Bench in I.A

No.501 (MP) of 2024 in CP (IB) No.56(MP) of 2021 whereby the learned

Adjudicating Authority has dismissed the application filed by the Appellant

under Section 60(5) of the Insolvency and Bankruptcy Code, 2016.

2. It is submission of the learned counsel for the Appellant that the

Appellant is a homebuyer in the real estate project "Pinnacle 'D' Dreams"

developed by the Corporate Debtor and was issued allotment letter on

14.04.2015 in respect of Flat No.801 in Premium Tower-2. Appellant had paid

amount of total consideration of Rs.36,87,900/- towards said allotment.

3. It is alleged the Appellant upon becoming aware of the resolution

proceedings and approval of resolution plan, had approached the learned

Cont'd.../ Adjudicating Authority by filing I.A No.501 (MP) of 2024 seeking recognition of

his claim as an allottee of the Corporate Debtor, however, the said application

was dismissed vide the impugned order.

4. It is the submission of the learned counsel for the Appellant the entire

consideration of Rs.36,87,900/- was paid in cash for the subject flat and

admittedly, the said amount was not paid to the Corporate Debtor but was

allegedly paid to one Anis Mohammed, an Operational Creditor of the

Corporate Debtor on assurance of the Corporate Debtor's management that it

shall be considered as a payment towards the flat. Accordingly, the Appellant

paid entire amount on 14.04.2015 to Mr. Anis mohammed.

5. Admittedly, the CIRP in the present case was admitted vide order dated

17.03.2022 by the learned NCLT and Mr. Sanjay Kumar Singh was appointed

as Interim Resolution Professional, who made public announcement on

31.03.2022 in the prescribed Form A. Admittedly, the last date of submission

of claim was 14.04.2022 but the Appellant did not file any claim during this

period. Further Admittedly, the resolution plan was submitted by Respondent

No.2, which was approved by the CoC and later on an application by the

Resolution Professional viz IA No 254 of 2023, the learned Adjudicating

Authority had approved the resolution plan vide order dated 05.04.2024. It

was only thereafter, on 27.11.2024, the application was filed by the Appellant.

6. We have also perused the impugned order most specifically Paras 10 to

12, which are as under:

Company Appeal (AT) (Ins.) No. 596 of 2026 2 of 4 "10. With respect to proof of disbursement and status as a Financial Creditor, we find that the Appellant's claim hinges on alleged payments of Rs. 36,87,900/- by cash. To prove the disbursement, allotment letter & affidavit stating the manner of payment, has been placed on record. However, on scrutiny of the said documents, they unable to demonstrate that the disbursement of Rs. 36,87,900/- was effected from the Applicant to the account of the CD. The Respondent has not specifically refuted this averment, contending merely that no claim was filed prior to approval of the Resolution Plan, rendering relief unavailable. Nevertheless, the burden lies upon the claimant to establish financial disbursement [Swiss Ribbons Pvt. Ltd. v. Union of India, (2019) 4 SCC 17].

11. The Applicant's submission supported by the fundamental statutory duty of the RP. Under Section 18(1)(b) of the IBC, 2016, the IRP (and subsequently the RP) is mandated to "receive and collate all the claims submitted by creditors". While the term "receive" implies a passive role dependent on filings, the term "collate" suggests an active duty to verify and arrange claims. Further, Regulation 36(2) of the IBBI (Insolvency Resolution Process for Corporate Persons) Regulations, 2016, prescribes the contents of the Information Memorandum. The IM must contain "details of all material litigation and crucially, a list of creditors and liabilities".

12. It is observed that the Applicant rely on the judgment of the NCLAT in Puneet Kaur v. K V Developers Pvt. Ltd. [Company Appeal (AT) (Insolvency) No. 390 of 2022] to argue that this duty extends to liabilities reflected in the books of accounts, even if no formal claim is filed. Further rely on the Greater Noida Industrial Development Authority v. Prabhjit Singh Soni & Anr. [(2024) 2 S.C.R. 258], wherein the Supreme Court allowed the recall even though the claimant (GNIDA) had not filed the

Company Appeal (AT) (Ins.) No. 596 of 2026 3 of 4 claim in the correct form, because their status as a financial creditor was evident from the nature of the lease and the records. However, the status of the Applicant as homebuyers is not evident from the allotment letter & affidavit stating the manner of payment, in absence of proof of disbursement of funds. The Resolution Professional's duty is confined to collating claims, without power to adjudicate beyond the documentary evidence available."

7. We have gone through the impugned order and we are not inclined to

interfere in such reasoned order passed by the Adjudicating Authority.

Admittedly, the resolution plan has since been approved by the Adjudicating

Authority on 05.04.2024 and has also been implemented, hence, there is no

right of the Appellant now to upset such plan, approved and implemented,

more so when such claim was filed in absence of any evidence with the

Corporate Debtor, hence, his application was not rightly entertained at this

stage. Appeal is thus dismissed. All pending application are also disposed

of.

[Justice Yogesh Khanna] The Officiating Chairperson

[Barun Mitra] Member (Technical)

[Ajai Das Mehrotra] Member (Technical) Archana/MD

Company Appeal (AT) (Ins.) No. 596 of 2026 4 of 4

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free