Sanjay Pandurang Kalate vs Jayesh Natvarlal Sanghrajka & Ors
- CitationCompany Appeal (AT) (Insolvency) No. 148 of 2026
Ratio decidendi
The rule this decision rests on
Condonation of a refiling delay in an appeal is governed by the test of sufficient cause, which must be construed liberally in the interest of justice, but the liberal construction does not dispense with the requirement that the appellant give a specific and adequate explanation for the delay, and the appellant must be vigilant in curing defects notified by the Registry; general or non-specific reasons, such as unspecified holidays, do not constitute sufficient cause for an inordinate delay. Where an appeal challenges approval of a resolution plan and the plan has already been implemented before the appeal was filed, the appellant bears a heightened obligation to act promptly in removing defects so the appeal may be heard, and failure to do so, together with a failure to pay the prescribed fee on repeated notifications, weighs against condonation of the refiling delay.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
NATIONAL COMPANY LAW APPELLATE TRIBUNAL, PRINCIPAL BENCH, NEW DELHI Company Appeal (AT) (Insolvency) No. 148 of 2026 & I.A. Nos. 284, 553 of 2026 (Arising out of Order dated 25.06.2025 passed by the Adjudicating Authority (National Company Law Tribunal), Mumbai Bench, Court-V in I.A. No.6/2024 in C.P.No.283(IB)/MB/2023)
IN THE MATTER OF:
Sanjay Pandurang Kalate, Suspended Director of Envirant Developers Pvt. Ltd ...Appellant
Versus
Jayesh Natvarlal Sanghrajka, Resolution Professional of Envirant Developers Pvt. Ltd. & Ors. ...Respondents
Present:
For Appellant : Mr. Abhishek Anand, Mr. Kaushal Bansal, Ms. Palak Kalra, Advocates. For Respondents : Mr. Amir Arsiwala, Ms. Neha Arya, Advocate for R-1. Mr. Abhijeet Sinha, Sr. Advocate with Mr. Vishesh Kalra, Ms. Simran Shadija, Ms. Heena Kochar, Advocates for R-2. Mr. Varun Klara, Mr. Samir Mlaik, Mr. Shahan Ulla, Advocates for R-3.
JUDGMENT
ASHOK BHUSHAN, J.
IA No.284 of 2026 : This is an application filed by the Appellant
praying for condonation of refiling delay of 136 days in refiling of the
Appeal.
2. Brief background facts of the Appeal need to be noticed:
Company Appeal (AT) (Ins.) No.148 of 2026 & IA No.284 of 2026 1
(i) The Appellant is a Suspended Director of the Corporate
Debtor ("CD") - Envirant Developers Pvt. Ltd. The Corporate
Insolvency Resolution Process ("CIRP") against the CD
commenced vide order dated 19.05.2023 of the Adjudicating
Authority. The Appellant filed Company Appeal (AT) (Ins.)
No.742 of 2023 before this Tribunal challenging the
admission order of Company Petition and initiation of CIRP,
which Appeal was dismissed on 05.10.2023.
(ii) The Appellant also filed an IA No.2002 of 2023 before the
Adjudicating Authority, alleging that insolvency petition by
Respondent was initiated in alleged collusion with certain
individuals, which application although initially dismissed by
the Adjudicating Authority, against which an Appeal filed
before this Tribunal was also dismissed. But under orders of
the Hon'ble Supreme Court, the Company Appeal (AT) (Ins.)
No.1209 of 2023 was heard and this Tribunal set aside the
orders of the Adjudicating Authority and granted the liberty
to the Appellant to approach the Adjudicating Authority
afresh for appropriate relief. In exercise of liberty granted on
19.04.2024, the Appellant filed IA No.3960 of 2024 before the
Adjudicating Authority in the main Company Petition. The
said application remained pending and was heard on several
occasions.
Company Appeal (AT) (Ins.) No.148 of 2026 & IA No.284 of 2026 2
(iii) The Resolution Plan submitted by Respondent was approved
by Committee of Creditors ("CoC") with 100% vote share and
IA No.06 of 2024 was filed by the Resolution Professional
("RP") for approval of the Plan.
(iv) By the impugned order in the present Appeal dated
25.06.2025, the Resolution Plan has been approved by the
Adjudicating Authority. Aggrieved by which order, this
Appeal was filed by the Appellant.
3. This Appeal has been filed by the Appellant on 06.08.2025. There
being delay in refiling of the Appeal, the Appellant has filed IA No.284 of
2026 seeking condonation of refiling delay of 136 days (which as per the
Registry the delay is of 140 days). Notices were issued in the application,
in response to which reply has been filed by Respondent Nos.1 and 2.
4. In the reply filed by Respondent No.1, Respondent No.1 has given
details of the proceedings and has brought on the record various orders
passed by Adjudicating Authority in IA No.3960 of 2024, where Appellant
did not complete the hearing in the application and sought several
adjournments.
5. Respondent No.2 in its reply has submitted that the Resolution
Plan, which was approved by the Adjudicating Authority on 25.06.2025
has already been implemented as far back as on 12.07.2025 and the
Appeal itself has become infructuous. There is no proper explanation in
the application for condonation of huge delay. The Appellant has filed a
Company Appeal (AT) (Ins.) No.148 of 2026 & IA No.284 of 2026 3 defective Appeal and inspite of repeated notifications, the Appellant was
not diligent or interested in removing the defects within the time bound
manner.
6. We have heard learned Counsel for the Appellant as well as learned
Counsel appearing for Respondents.
7. Learned Counsel for the Appellant in support of the application
submits that the Appeal was initially filed on 06.08.2025 and defects were
informed on 11.08.2025 and due to complexity of matter and bulky set of
documents, the Appellant refiled the matter on four occasions. The
Appellant is based in Pune and faced logistical difficulties in procuring
legible copies of documents. In Paragraphs (ii) and (iii), the Appellant has
given following reasons for delay:
"ii. That challenging the impugned order, the instant Appeal was initially filed on 06.08.2025 and defects were notified on
08.08.2025, with a period of seven days granted for removal of defects, expiring on 15.08.2025. Due to the complexity of matter and bulky set of documents the Applicant, however, re-filed the matter on four occasions being 22.08.2025, 26.09.2025, 22.10.2025 and 15.11.2025. The delay occurred as the Appellant, who resides in the Pune, faced logistical difficulties in procuring legible copies of documents and transmitting the same to the Applicant at Delhi. Owing to the said bona fide circumstances, the delay in re-filing is neither deliberate nor intentional.
iii. Further, the delay of 136 days in the present matter has occurred on account of intervening holidays due to Diwali, coupled with Chath Pooja and Sundays, which rendered the offices closed which thereby further contributed to the delay."
Company Appeal (AT) (Ins.) No.148 of 2026 & IA No.284 of 2026 4
8. Respondent No.2 in its reply has pleaded that the Appellant has
repeatedly attempted to delay the matter. In Paragraph 8 to 11 and 18 of
the reply, Respondent No.2 pleaded following:
"8. Since, there is no valid and cogent reason for condoning delay, there is no sufficient cause for condoning such delay. Further, in the strict timeline of IBC there cannot be any sufficient cause in these facts. The order impugned in the Appeal is a plan approval order dated 25.06.2025. This order already stands implemented as far back as on 12.07.2025 and therefore the Appeal itself is infructuous. It is respectfully submitted that once the plan is implemented, a time barred and an egregiously delayed appeal ought not to be considered and no delay be condoned for such an Appellant.
9. On several occasions, the Ld. NCLT recorded observations regarding the alleged dilatory conduct of the Appellant, as reflected in its orders dated 24.04.2025, 02.05.2025, and 27.05.2025, wherein it was noted that the Appellant had sought time and adjournments during the proceedings. Even after taking time, the Appellant has not even been present for hearings. In view of the said conduct as recorded by the Ld. NCLT, the Appellant is rot entitled to any discretionary or equitable relief from this Hon'ble Tribunal.
10. In fact, even before the Ld. NCLT, the only attempt by the Appellant is to delay the proceedings. The Appellant has repeatedly taken attempts to delay the matter and essentially waste the courts time. The conduct is evident from the order dated 16.12.2024, where the Appellant was engaging in dilatory tactics to delay the hearing, knowing fully well that the record as sought to be presented was not available. This needs to be seen in the present context where the Appellant has refiled the appeal after a delay of 136 days, in an appeal which was otherwise filed with a delay of 12 days.
Company Appeal (AT) (Ins.) No.148 of 2026 & IA No.284 of 2026 5
11. The plan process was fully to the knowledge of the Appellant, who claims to be the erstwhile promoter of the Corporate Debtor, now post resolution, a revived company under the management and control of the Respondent No.2.
18. With respect to paragraph 2(ii), the Respondent denies all averments made therein. The Applicants have failed to provide any particulars or basis as to why such defects were raised by the Registry or why it took the Appellant such an inordinate period to cure the same. There is no explanation whatsoever specifying the number of days of delay, nor is there any explanation for each day's delay, which is mandatory in law. The Appellant cannot take advantage of the fact that it initially filed a defective appeal. The Registry notified five sets of defects on 08.08.2025, 22.08.2025, 26.08.2025, 22.09.2025, 25.10.2025 and 15.11.2025. Despite such repeated notifications, it appears that the Appellant was not diligent or interested in removing the defects within a time-bound manner."
9. The Appeal filed by the Appellant was an Appeal challenging order
of approval of Resolution Plan. The Appeal although was filed on
06.08.2025 and defects were notified on 11.08.2025, but the Appellant
took several months in removing the defects. Rejoinder affidavit has been
filed by the Appellant, where the Appellant has sought to explain the date
of defect, nature of defects raised and the steps taken by the Appellant in
Paragraph-6.
10. Shri Abhijeet Sinha, learned Senior Counsel appearing for
Respondent No.2 has placed reliance on judgment of the Hon'ble Supreme
Court in Civil Appeal No.11827 of 2025 in Abhijit Realtors and
Infraventures Pvt. Ltd. & Anr. vs. Rohit Mehra & Anr., in which case,
the Hon'ble Supreme Court observed that the Resolution Plan having
Company Appeal (AT) (Ins.) No.148 of 2026 & IA No.284 of 2026 6 been acted upon and implemented, the Appeal is to be dismissed. It is
useful to quote entire order dated 19.03.2026 of the Hon'ble Supreme
Court, which is as follows:
"We find from the record that the resolution plan in the case on hand was approved by the adjudicating authority on 06.05.2024 and the appeal filed against such approval was dismissed by the National Company Law Appellate Tribunal, Principal Bench, New Delhi, on 23.12.2024.
Though the present appeal was filed before this Court on 24.12.2023, that is, just one day later, the same was defective and it came to be re-filed with a delay of 100 days. The matter was put up before the Court only on 23.05.2025, on which day the delay was condoned and notice was issued.
However, we find that even before the issuance of notice in this matter, the resolution plan was acted upon and implemented, whereby the monies due payable thereunder were paid to the financial creditors and other stakeholders on 07.04.2025 itself.
Given this fact, we see no purpose in going into the merits of the matter at this late point of time. On this short ground, the appeal is dismissed.
Pending application(s), if any, shall stand disposed of."
11. We are conscious that in the present application, the Appellant has
prayed for condonation of delay in refiling. Learned Counsel for the
Appellant has also placed reliance on the judgment of this Tribunal and
various orders of this Tribunal, where this Tribunal has condoned the
refiling delay in the facts of the said cases. Reliance has also been placed
on the judgment of the Hon'ble Supreme Court in Civil Appeal No.5106
of 2025 - CA Ramachandra Dallaram Choudhary vs. Adani
Company Appeal (AT) (Ins.) No.148 of 2026 & IA No.284 of 2026 7 Infrastructure & Developers Pvt. Ltd., where the Hon'ble Supreme
Court condoned the refiling delay. The Hon'ble Supreme Court has held
that sufficient cause has to be construed liberally in the interest of
justice. In Paragraph-10, following was observed:
"10. Having regard to the fact that the appellant despite limitations had done all that was necessary for filing of the appeal within 30 days, and then 15 days, i.e., within the prescribed and extended period of limitation, respectively, as well as dependency of the appellant on its lawyers who, in turn, were dependent on their clerk to re-file the appeal, and there were some missteps contributing to the present situation, coupled with the fact that the issue sought to be raised by the appellant in the appeal filed before the NCLAT, if answered in its favour, would ensure to the benefit of the debtors, and also that better justice is always achieved when a lis is decided on a contested hearing rather than on default, we need to take an overall view of the matter. We are of the considered opinion that the words "sufficient cause" in this case ought to have been construed liberally and that interest of justice would be best served if, upon condonation of delay in refiling of the appeal, the NCLAT proceeds with the hearing of the appeal on merits. Ordered accordingly."
12. There can be no dispute to the proposition of law that refiling delay
in an Appeal has to be liberally construed. But when we look into the
facts of the present case and explanation offered by the Appellant,
specially the various litigations, which were undertaken by the Appellant
- the Suspended Director of the CD as detailed in the Appeal itself and
the fact that Resolution Plan was approved on 25.06.2025, which
according to Respondent No.2 has been implemented on 02.07.2025,
filing of the Appeal on 06.08.2025 was subsequent to the implementation
Company Appeal (AT) (Ins.) No.148 of 2026 & IA No.284 of 2026 8 of the Plan and apart from refiling delay, the Appeal was filed beyond 30
days with delay of 12 days. When the Appellant has filed the Appeal
challenging the approval of the Resolution Plan, the Appellant has to be
more vigilant in removing the defects, so that Appeal could be heard.
Inspite of defects being communicated to the Appellant on several
occasions, the Appellant failed to take prompt action in clearing the
defects. The reasons which have been given in Paragraph (iii) that delay
of 136 days has occurred on account of intervening Diwali holidays,
coupled with Chat Pooja and Sundays, which rendered the offices closed,
thereby further contributing to delay, are general in nature, without any
specific dates regarding Diwali holidays and other holidays. Defects were
informed to the Appellant on four occasions. In the rejoinder affidavit, the
Appellant has brought on record various defects communicated to the
Appellant. The defects indicate that defects were intimated several times,
which were not cured and defects also included that fee should be
deposited as per the Appeal and Rs.1000/- for each IAs and the proof
thereof. In the facts of the present case and nature of defects, which
indicate that the Appellant was not vigilant in curing the defects, not
depositing of the fee was a defect, which itself indicate that the Appellant
was not serious in curing the defect.
13. Learned Counsel for the Appellant has relied on various orders of
this Tribunal. Refiling delay in each case depends on the facts and
sequence of events. In the facts of the present case, we are not satisfied
Company Appeal (AT) (Ins.) No.148 of 2026 & IA No.284 of 2026 9 that there is sufficient explanation given by the Appellant for condonation
of inordinate delay of 136 days in refiling of the Appeal.
14. In view of the above discussion, application for condonation of
refiling delay is rejected. Consequently, the Memo of Appeal is also
rejected. There shall be no order as to costs.
[Justice Ashok Bhushan] Chairperson
[Indevar Pandey] Member (Technical)
NEW DELHI
21st April, 2026
Ashwani
Company Appeal (AT) (Ins.) No.148 of 2026 & IA No.284 of 2026 10
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free