Miss Lucy
← All judgments

Sandvik Asia Pvt. Ltd vs The Indure Pvt. Ltd

National Company Law Appellate Tribunal13 December 2019

Ratio decidendi

The rule this decision rests on

Where an operational creditor's Section 9 application is accompanied by a notice of dispute received before the demand notice under Section 8, the Adjudicating Authority is required under Section 9(5)(ii)(d) to reject the application, since the existence of a pre-existing dispute on the debt is a ground for rejection. Under Section 9(5), the Adjudicating Authority may admit an operational creditor's application only if, among other conditions, no notice of dispute has been received by the operational creditor and there is no record of dispute in the information utility; a disputed debt raised before the demand notice bars admission. Following Mobilox Innovations Pvt. Ltd. v. Kirusa Software Pvt. Ltd., the Adjudicating Authority at the threshold need only determine whether a dispute exists in fact that is plausible and not spurious, hypothetical or illusory; it need not be satisfied that the defence is likely to succeed or examine the merits of the dispute beyond that inquiry.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

1NATIONAL COMPANY LAW APPELLATE TRIBUNAL, NEW DELHI

(Arising out of Order dated (14.06.2019) passed by the Adjudicating Authority (National Company Law Tribunal) Principal Bench New Delhi in CP (IB) - 1643 (PB)/2018)

Company Appeal (AT) (Insolvency) No.737 of 2019

IN THE MATTER OF:

M/s.Sandvik Asia Private Limited Mumbai-Pune Road, Dapodi Pune - 411 012 ...Appellant

Vs.

M/s.The IndurePrivate Limited The Indure House, Greater Kailash - II, New Delhi - 110 048 ...Respondent

Present:

For the Appellant: Mr. Sabyasachi Chaudhury with Mr.Debarshi Dutta and Mr.Rajat Pradhan, Advocates. For the Respondent : Mr.Prashant Mehta with Ms.Neha Tanwar, Mr. Anish Kumar, Mr.Varun Gupta, Ms.Simron, Advocates.

JUDGMENT

( 13th December, 2019)

Dr. Ashok Kumar Mishra, Technical Member

The Appellant M/s.Sandvik Asia Private Limited has filed an appeal under

Section 61(1) of the 'Insolvency and Bankruptcy Code, 2016 (for short, 'the I&B

Company Appeal (AT) (Insolvency) No.737 of 2019 2

Code') R/w Rule 11 of NCLAT Rules, 2016 against the impugned order dated

14th June, 2019 passed by National Company Law Tribunal, ('for short

Adjudicating Authority'), Principal Bench, New Delhi in CP No.(IB) - 1643

(PB)/2018 rejecting the Appellant's Application. The Appellant has filed the

Appeal under Section 9 of the Code seeking initiation of Corporate Insolvency

Resolution Process (for short 'CIRP') against the Respondent i.e. The Indure

Private Limited. The Appellant has declared that he has filed the said Appeal

within the period of limitation specified under Section 61(2) of the I&B Code.

2. The Appellant ('Operational Creditor' before the Adjudicating Authority)

is a part of Sandvik Group which is a Global Engineering Group and is involved

in the business of tools systems for industrial metal cutting, providing technical

and service solutions for mining and construction industries etc.

3. The Respondent (Corporate Debtor before the Adjudicating Authority) is

an EPC Contractor and involved in the manufacturing of ash handing systems on

turnkey basis.

4. The Appellant has also raised 73 invoices on the Respondent for a total

sum of Rs.34,72,35,271/-. Out of these 73 invoices, 16 invoices remain unpaid.

The 16 unpaid invoices were raised between 4th September, 2014 and 22nd

November, 2017. The Appellant is continuously chasing payment and also NTPC

"the Employer" was involved, for whom both the parties were working for a

particular contract in terms of Deed of Joint Undertaking dated 12 th November, Company Appeal (AT) (Insolvency) No.737 of 2019 3

2010 executed between M/s.Sandvik Asia Private Limited, registered office at

Mumbai-Pune Road, Dapodi, Pune 411012 and M/s. the Indure Private Limited

registered office at Indure House, Greater Kailash -II New Delhi 110 048.

5. Thereafter, the parties have entered into a contract for successful

performance of the relevant system (i.e. Stacker cum Reclaimer along with

associated auxiliary equipment). As per the said Deed of Joint Undertaking that

in case of any breach of the Contract committed by the Contractor, the parties

undertake, declared and confirm that they shall be fully responsible for the

successful performance of the Stacker-cum-Reclaimer and associated auxiliary

equipment and undertake to carry out all the obligations and responsibilities under

the contract in order to discharge the Contractor's obligations and responsibilities

stipulated in the Contract. Further if the NTPC sustains any loss or damage on

account of any breach of the Contract, they are 'jointly and severally undertake

to promptly indemnify, and pay such losses/damages caused to the NTPC' on its

written demand without any demur, reservation, contest or protest in any manner

whatsoever. The Deed of Joint Undertaking also states that in case of Award, in

addition to the Contract Performance Security furnished by the Bidder, the parties

shall furnish "as Security" and on demand Performance Bank Guarantee in favour

of the NTPC in a form acceptable to NTPC as per provisions of the Bidding

Documents. The value of such Bank Guarantee shall be equal to quarter percent

(0.25%) of the total contract price of the Contract awarded by the NTPC to the

Company Appeal (AT) (Insolvency) No.737 of 2019 4

Contractor and it shall be guarantee towards the faithful performance/compliance

of this Deed of Joint Undertaking in accordance with the terms and conditions

specified herein. The Bank Guarantee shall be unconditional, irrevocable and

valid for entire period of Contract, i.e. till ninety (90) days beyond the end of the

Defect Liability period of the Coal Handling Plant; Package under the Contract.

In case of delay in completion of the defect liability period, the validity of this

bank Guarantee shall be extended by the period of such delay. The Bank

Guarantee amount shall be promptly paid to the NTPC on demand without any

demur, reservation, protest or contest; any dispute that may arise in connection

with this Deed of Joint Undertaking shall be settled as per arbitrator

procedure/rules mentioned in the Contract Document. This Deed of Undertaking

shall be construed and interpreted in accordance with the laws of India and the

Courts of Delhi shall have exclusive jurisdiction.

6. The Appellant has filed the Appeal with the basic purpose of getting the

money as he has been chasing the payment since 18th December, 2015 at the time,

the outstanding amount was of Rs.4.6 Crore. There was internal correspondence

between the parties on 01.02.2016 wherein they have discussed about the genuine

details of the supplier and deduction from bills. The Adjudicating Authority has

observed that the Appellant has chased the payment vide email dated 15.04.2016

and also vide e-mail dated 03rd June 2017. The Appellant has also issued a notice

for non-payment of dues vide letter dated 09.01.2018 and also issued a Demand

Company Appeal (AT) (Insolvency) No.737 of 2019 5

Notice dated 20.03.2018, wherein the outstanding amount was raised of Rs.

2,25,82,259/- along with interest of Rs. 97,86,723/-.

7. The Respondent has replied the said Demand Notice vide letter dated 31st

March, 2018 raising the question on account of liquidated damages, pre mature

demand which is not yet payable, issues regarding non-revalidation of the

Advance Payment Bank Guarantee as provided in terms of the contract in spite

of repeated requests and follow-ups etc.

8. The Respondent has also elaborately submitted that there is a net recovery

amount of Rs.5,01,67,062.05/-. They have also submitted that the Terms and

Procedures of Payment, Functional Guarantees and Performance Bank Guarantee

are elaborately defined in the Deed of Joint Undertaking executed on 12th

November, 2010.

9. The Respondent has reiterated the various averments made in the Appeal

as mentioned supra and submitted that the Adjudicating Authority has rejected

the said Application on the ground of existence of dispute prior to issuance of

demand notice under Section 8.

10. The various submissions reflects that Appellant is chasing their payment

since December, 2015 directly & also through NTPC. While Respondent is

raising the issue of dispute with reference to the programme including the

additional cost incurred by them when Appellant has abandoned their programme

Company Appeal (AT) (Insolvency) No.737 of 2019 6

midway. Deed of Joint Undertaking also stipulates the Dispute Resolution

Mechanism.

11. Hence, considering the various facts and circumstances including

submission made by the both the parties it is a clear case of chasing of payments

& existence of disputes in terms of Insolvency and Bankruptcy Code, 2016. The

Adjudicating Authority can admit the Application only if the following

conditions are fulfilled as per Section 9(5) of the I&B Code, 2016:

Section 9(5) - The Adjudicating Authority shall, within fourteen days of the receipt of the application under sub-section (2), by an order

(i) admit the application and communicate such decision to the operational creditor and the corporate debtor if,-

(a) the application made under sub-section (2) is complete;

(b) there is no [payment] of the unpaid operational debt;

(c) the invoice or notice for payment to the corporate debtor has been delivered by the operational creditor;

(d) no notice of dispute has been received by the operational creditor or there is no record of dispute in the information utility; and

(e) there is no disciplinary proceeding pending against any resolution professional proposed under sub-section (4), if any;

(ii) reject the application and communicate such decision to the operational creditor and the corporate debtor, if -

(a) The application made under sub-section (2) is incomplete;

Company Appeal (AT) (Insolvency) No.737 of 2019 7

(b) There has been [payment] of the unpaid operational debt;

(c) The creditor has not delivered the invoice or notice for payment to the corporate debtor;

(d) Notice of dispute has been received by the operational creditor or there is a recorded of dispute in the information utility; or

(e) Any disciplinary proceeding is pending against any proposed resolution professional:

Provided that Adjudicating Authority, shall before rejecting an application under sub-clause (a) of clause (ii) give a notice to the applicant to rectify the defect in his application within seven days of the date of receipt of such notice from the adjudicating authority.

12. The Hon'ble Supreme Court in Mobilox Innovations Private Limited

Vs.Kirusa Software (P) Ltdin 2017 (11) SCALE 754 wherein at Para 40 has held

that:

"Once the Operational Creditor has filed an application, which is

otherwise complete, the Adjudicating Authority must reject the

application under Section 9(5)(2)(d) if notice of dispute has been

received by the Operational Creditor or there is record of dispute in

the information utility. It is clear that such notice must bring to the

notice of the Operational Creditor the "existence" of a dispute or the

fact that a suit or arbitration proceeding relating to a dispute is

pending between the parties. Therefore, all that the Adjudicating

Authority is to see at this stage is whether there is a plausible Company Appeal (AT) (Insolvency) No.737 of 2019 8

contention which requires further investigation and that the

"dispute" is not a patently feeble legal argument or an assertion of

fact unsupported by evidence. It is important to separate the grain

from the chaff and to reject a spurious defence which is mere bluster.

However, in doing so, the Court does not need to be satisfied that the

defence is likely to succeed. The Court does not at this stage examine

the merits of the dispute except to the extent indicated above. So long

as a dispute truly exists in fact and is not spurious, hypothetical or

illusory, the adjudicating Authority has to reject the Application".

13. Heard learned counsel for both the parties. We have carefully perused the

pleadings of both the parties and extant provisions of the Code and the law on the

issue.

14. We have the following observation on the present issue:

a) The Appellant is no doubt chasing payment continuously from 2015.

They have also involved NTPC to pressurize to the Corporate Debtor

to release the said payment.

b) The Operational Creditor has not completed the work within the

stipulated contract schedule and failed to fulfill their contractual

obligations leading to disputes between the parties.

Company Appeal (AT) (Insolvency) No.737 of 2019 9

c) There is exchange of legal notice and its reply in the month of

March, 2018 where the disputed issues are raised in respect of

recovery of debts and claims.

15. All these suggests that the debt in question is disputed and the dispute was

raised prior to issuance of demand notice under Section 8 of the Code.

Accordingly, the Adjudicating Authority has rightly rejected the Application.

Hence, we find no merits in the Appeal and the same is accordingly

dismissed. No order as to costs.

(Justice Jarat Kumar Jain) Member (Judicial)

(Mr. Balvinder Singh) Member (Technical)

(Dr.Ashok Kumar Mishra) Member (Technical)

RK/SS

New Delhi

Company Appeal (AT) (Insolvency) No.737 of 2019

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free