S. S. Infraconstructions Private ... vs Parvati Sweetners And Power Limited
- CitationCompany Appeal (AT) (Insolvency) No.1394 of 2022
Ratio decidendi
The rule this decision rests on
Where a financial or operational creditor's claim under Section 9 of the Insolvency and Bankruptcy Code, 2016 arises from invoices, the limitation period runs from the date on which payment falls due under the invoices and the default occurs, not from the date on which the creditor's later demand notice is replied to and payment is refused, and an application for appointment of an arbitrator filed after that limitation period has expired does not extend it. An email from the corporate debtor requesting the operational creditor to submit its bills and a statement of account does not amount to an acknowledgement of liability under Section 18 of the Limitation Act, 1963, and so does not extend or restart the limitation period.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
IN THE MATTER OF: S. S. Infraconstructions Pvt. Ltd. ...Appellant
Versus
Parvati Sweetners and Power Ltd. ...Respondent
Present:
For Appellant: Mr. Ramnesh Jerath, Advocate.
For Respondent: Mr. Rishi Sood and Ms. Akshita, Advocates.
ORDER
01.12.2022: I.A. No. 4346 of 2022: This is an application praying for
condonation of delay of 79 days in refiling the Appeal. Sufficient grounds have
been shown in Paras 5 and 6 of the application by the Appellant. Refiling delay
is condoned. I.A. No. 4346 of 2022 stands disposed of.
2. I.A. No. 4362 of 2022: This is an application praying for condonation
of 13 days delay in filing the Appeal. Learned counsel for the Appellant submits
that the Appellant came to know of the impugned order on 30.06.2022 and
delay was caused. Cause shown sufficient, delay is condoned. I.A. No. 4362
of 2020 stands disposed of.
Cont'd.../ -2-
3. Heard learned counsel for the Appellant. This Appeal has been filed
against the order dated 23.06.2022 of the Adjudicating Authority by which
order application filed by the Appellant under Section 9 has been dismissed
as barred by time. The Corporate Debtor had appointed the Appellant as
contractor for carrying out civil work. Invoices were issued by the Operational
Creditor from 30.09.2012 to 26.03.2013 and last payment was received by the
Appellant on 28.02.2013. The application under Section 9 has been filed by
the Appellant on 30.07.2019. The Adjudicating Authority dismissed the
application as barred by time. In para 7 of the order following has been
observed:
"7. Admittedly, in the present case, the invoices under reference were raised between 30.09.2012 to 26.03.2013 and the last payment by the Corporate Debtor was made on 28.02.2013. The date of default is stated to be the dates on which invoices were raised on & from 26.09.2012 to 25.12.2012. Therefore, considering the date of last payment as acknowledgement of the existing debt, the period of limitation has expired (after three years) on 27.02.2016. The application for appointment of an arbitrator was filed on 17.01.2017, i.e. much beyond the period of limitation, therefore, the said application for appointment of an arbitrator cannot be said to have extended the period of limitation. As such, the application filed on 30.07.2019 under Section 9 of the IBC, 2016 is beyond the period of limitation and
Company Appeal (AT) (Insolvency) No. 1394 of 2022 -3-
accordingly, we hold that the said application is not maintainable under the IBC, 2016 and accordingly, the same stands rejected and disposed of."
4. Learned counsel for the Appellant challenging the order contends that
right to sue accrued to the Appellant when demand notice was replied on
15.03.2019 denying entitlement of the Appellant for payment. It is submitted
that there was no dispute earlier to that. He further submits that an email
dated 12.12.2014 was sent by the Corporate Debtor where all bills submitted
by the Operational Creditor were called for. Hence, the application was not
barred by time.
5. We have considered the submissions of learned counsel for the
Appellant and perused the record.
6. Admittedly, the invoices were issued from 30.09.2012 to 26.03.2013.
The email dated 12.12.2014 on which reliance has been placed by the
Appellant only states that "....please mail me all the bills submitted by yourself
and statement of account since beginning". The said email even do not come
within the meaning of acknowledgement under Section 18 of the Limitation
Act. The submission of the Appellant that right to sue accrued when demand
notice was replied on 15.03.2019 refusing to make payment, cannot be
accepted. In the present case, after issuance of the invoices when payment
was not made, cause of action arose to take appropriate proceeding. Even the
Arbitration Application was filed on 17.01.2017. We, thus, are satisfied that
Company Appeal (AT) (Insolvency) No. 1394 of 2022 -4-
no error has been committed by the Adjudicating Authority in rejecting the
application as barred by time. There is no merit in the Appeal. Appeal is
dismissed.
[Justice Ashok Bhushan] Chairperson
[Dr. Alok Srivastava] Member (Technical)
[Barun Mitra] Member (Technical) Archana/nn
Company Appeal (AT) (Insolvency) No. 1394 of 2022
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free