Ratio decidendi
The rule this decision rests on
Where the Committee of Creditors approves a resolution plan within the extended insolvency timeline but the resolution professional has too little time left to make the statutory filing under Section 31 before the Adjudicating Authority, and that shortfall arises from the legal formalities required to be completed before filing rather than from the resolution professional's lapse, the Appellate Tribunal may, under its power in Rule 11 of the NCLAT Rules, extend the corporate insolvency resolution process beyond the 330-day outer limit for the period necessary to permit the filing. Such extension is an exception to the general rule that 330 days is the outer limit, and it is to be exercised only where refusal would imperil the interests of stakeholders and drive the corporate debtor into liquidation. A refusal by the Adjudicating Authority to entertain a Section 31 application in these circumstances, where the process was completed within the extended period, is a miscarriage of justice that frustrates the object of the Code, and the Appellate Tribunal may set aside such an order and direct the Adjudicating Authority to consider the application on its merits.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
Ritu Rastogi, Resolution Professional, Benlon India Ltd. ...Appellant
Versus
Riyal Packers ...Respondent
Present: For Appellant : Mr. Krishnendu Datta, Ms. Meera Murali and Mr. Ankur Mittal, Advocates Advocates For Respondent: Mr. Naveen Kumar, Advocate
ORDER
(Through Virtual Mode)
16.06.2020 After hearing Mr. Krishnendu Datta, learned counsel
representing the Appellant and Mr. Naveen Kumar, learned counsel representing
the Respondent, we find that the 'Committee of Creditors' has approved the
'resolution plan' of Mr. Surender Kumar Chawla on 5th February, 2020 while the
application for approval of the 'resolution plan' before the Adjudicating Authority
was filed by the 'Resolution Professional' on 17th February, 2020. It is manifestly
clear that there has been a delay of 10 days in filing the application under Section
31 of the 'Insolvency and Bankruptcy Code, 2016 ('I&B Code', for short) on the
part of the 'Resolution Professional' for seeking approval of the 'resolution plan'
of Mr. Surender Kumar Chawla.
Mr. Krishnendu Datta, learned counsel appearing on behalf of the
Appellant submits that the approval of the 'resolution plan' on the part of the 2
'Committee of Creditors' is well within the extended timeline but since the
'Resolution Professional' was merely left with one day for filing the application
under Section 31 of the 'I&B Code' before the Adjudicating Authority, he could
not lay the approved resolution plan under Section 31 of the 'I&B Code' before
the Adjudicating Authority as he had to first comply with the legal formalities
like seeking performance guarantee and other statutory compliances. It is
submitted that the hardship encountered by the 'Resolution Professional' is not
on account of any lapse on his part but due to certain statutory compliances to
be made, which are mandatory or without adhering to which the 'resolution plan'
could not be placed before the Adjudicating Authority. He further submits that
the instant case is a fit one for exercise of power under Rule 11 of the 'NCLAT
Rules' in terms of the law enunciated by the Hon'ble Apex Court in 'Committee
of Creditors of Essar Steel India Limited vs. Satish Kumar Gupta & Ors.
(Civil Appeal No. 8766-67/2019). Paragraph 79 thereof relied upon in support
of the submission, reads as follows:
"However, on the facts of a given case, if it can be shown to the Adjudicating Authority and/or Appellate Tribunal under the Code that only a short period is left for completion of the insolvency resolution process beyond 330 days, and that it would be in the interest of all stakeholders that the corporate debtor be put back on its feet instead of being sent into liquidation and that the time taken in legal proceedings is largely due to factors owing to which the fault cannot be ascribed to the litigants before the Adjudicating Authority and/or Appellate Tribunal, the delay or a large part thereof being attributable to the tardy process of the Adjudicating Authority and/or the
Company Appeal (AT) (Insolvency) No. 482 of 2020 3
Appellate Tribunal itself, it may be open in such cases for the Adjudicating Authority and/or Appellate Tribunal to extend time beyond 330 days. Likewise, even under the newly added proviso to Section 12, if by reason of all the aforesaid factors the grace period of 90 days from the date of commencement of the Amending Act of 2019 is exceeded, there again a discretion can be exercised by the Adjudicating Authority and/or Appellate Tribunal to further extend time keeping the aforesaid parameters in mind. It is only in such exceptional cases that time can be extended, the general rule being that 330 days is the outer limit within which resolution of the stressed assets of the corporate debtor must take place beyond which the corporate debtor is to be driven into liquidation."
It is further submitted that this Appellate Tribunal has in identical
circumstances invoked Rule 11 of the NCLAT Rules to mitigate the hardship
encountered by the 'Resolution Professional'. Reliance is placed upon the
judgment of this Appellate Tribunal in 'Company Appeal (AT) (Insolvency) No.
1425 of 2019' decided on 17th January, 2020.
Having heard learned counsel for the parties and given our anxious
consideration to the matter in hand, we are of the considered opinion that the
instant case is fit one for exercising power under Rule 11 of the NCLAT Rules.
Admittedly, the 'resolution plan' of Mr. Surender Kumar Chawla has been
approved by the 'Committee of Creditors' within the extended timelines duly
allowed by this Appellate Tribunal and the process of the approval of the
'resolution plan' of Mr. Surender Kumar Chawla by the 'Committee of Creditors'
Company Appeal (AT) (Insolvency) No. 482 of 2020 4
was completed within the extended period as allowed by this Appellate Tribunal.
However, since only one day was left for the 'Resolution Professional' to file an
application under Section 31 of the 'I&B Code' for placing the approved
'resolution plan' before the Adjudicating Authority for approval which despite
diligence and best efforts on his part was improbable as he was left only with
one day to complete all legal formalities including seeking performance
guarantee in terms of the approved 'resolution plan', further extension of time
by 10 days enabling the 'Resolution Professional' to seek approval of the
'resolution plan' from the Adjudicating Authority is warranted. This is a fit case
for exercising the jurisdiction by this Appellate Tribunal being an exceptional
case to depart from the general rule of 330 days being outer limit prescribed
under the law for completion of the 'corporate insolvency resolution process'
inclusive of period of judicial intervention. We are also of the considered opinion
that failure to exercise discretion in a matter of this nature would have serious
implications imperilling the legitimate interests of all stakeholders and inevitable
conclusion would be to push the 'Corporate Debtor' into liquidation which has
to be avoided at all costs.
For the foregoing reasons, we find that the impugned order cannot be
supported. Refusal to exercise discretion by the Adjudicating Authority, in our
considered opinion, has resulted in miscarriage of justice and frustrating the
object of the 'I&B Code'. We accordingly allow the appeal, set aside the
impugned order and extend the period of 'corporate insolvency resolution
process' by 10 days till 17th February, 2020 i.e. the date of filing the application
under Section 31 of the 'I&B Code' by the 'Resolution Professional'. The
Adjudicating Authority is accordingly directed to consider the application of the
Company Appeal (AT) (Insolvency) No. 482 of 2020 5
'Resolution Professional' under Section 31 of the 'I&B Code' for approval of the
'resolution plan' of Mr. Surender Kumar Chawla already approved by the
'Committee of Creditors' by according consideration to the same in accordance
with law.
The appeal is accordingly disposed of.
[ Justice Bansi Lal Bhat ] Acting Chairperson
[ Justice Jarat Kumar Jain ] Member (Judicial)
[ Shreesha Merla ] Member (Technical) /ns/RR/
Company Appeal (AT) (Insolvency) No. 482 of 2020
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free