Ratio decidendi

The rule this decision rests on

Where a financial creditor's application under Section 7 of the Insolvency and Bankruptcy Code has been settled and no Committee of Creditors has yet been constituted, the Tribunal may permit withdrawal of the application and dispose of it as withdrawn. The costs of the Interim Resolution Professional and the resolution process are to be borne equally by the corporate debtor and the financial creditor, the Interim Resolution Professional to furnish details of costs and fees payable by each party. Where the Adjudicating Authority's order appointing an Interim Resolution Professional and declaring moratorium is set aside on appeal, the orders consequential upon it, including the freezing of accounts and the actions taken by the Interim Resolution Professional, fall with it and are declared illegal and set aside, so that the corporate debtor is released from the moratorium and may function through its Board of Directors.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

NATIONAL COMPANY LAW APPELLATE TRIBUNAL, NEW DELHICompany Appeal (AT) (Ins) No. 318 of 2019

IN THE MATTER OF: Raju Verma ....Appellant Vs. Kaushalya Ahluwalia & Anr. ....Respondents Present: For Appellant: Present but appearance not marked. For Respondents:

ORDER

24.04.2019: Learned counsel for the parties informed that draft would be

handed over by Appellant to the Respondent- Financial Creditor in course of

the day.

2. In view of the aforesaid fact, as the matter has been settled and since

Committee of Creditors has not been constituted, we allow the Respondent to

withdraw application under Section 7 of the I&B code and dispose of

application under Section 7 as withdrawn.

3. So far as fee and expenditure incurred by the Interim Resolution

Professional is concerned, Corporate debtor and Financial Creditor, both

parties will bear 50% each of the entire resolution cost. The Interim Resolution

Professional will give details of cost incurred and fee entitled to the parties.

4. The impugned order dated 19.03.2019 passed by the Adjudicating

Authority, (National Company Law Tribunal) Principal Bench, New Delhi is

set aside. The Adjudicating Authority will close the proceeding.

-2-

5. In the result, order(s) passed by the Adjudicating Authority appointing

'Interim Resolution Professional', declaring moratorium, freezing of account,

and all other order(s) passed pursuant to impugned order and action taken by

the 'Interim Resolution Professional', including the advertisement published

in the newspaper calling for applications and actions are declared illegal

and are set aside. The 'Corporate Debtor' is released from the rigour of

law and is allowed to function independently through its Board of Directors

from immediate effect.

6. The appeal stands disposed of with aforesaid observations. However,

there shall be no order as to cost.

[Justice S. J. Mukhopadhaya] Chairperson

[Justice Bansi Lal Bhat] Member (Judicial) sa/gc

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free