Power Trust Promoter Of Hiranmaye ... vs Mr. Bhuvan Madan Interim Resolution ...
- CitationComp. App. (AT) (Ins) No. 81 of 2024
Ratio decidendi
The rule this decision rests on
Where pre-implementation conditions precedent in a restructuring approval are not met, the restructuring approval does not fructify and ceases to remain alive, and the original loan agreement revives and continues to survive. A later restructuring approval that expressly refers to an earlier one does not, without more, keep the earlier approval alive; where the later approval is a revision that novates the earlier terms, the earlier approval's obligations are superseded and default is to be assessed under the later approval and the original agreement. Payments made in response to a creditor's demand letters, accompanied by a unilateral caveat by the debtor that receipt will be deemed acceptance of a proposal, do not result in automatic renewal or revival of a restructuring approval that has already failed for non-fulfilment of conditions precedent. For the purposes of Section 10A of the Insolvency and Bankruptcy Code, 2016, the date of default is determined by reference to the agreement under which the first unpaid obligation fell due; where the operative default dates fall outside 25.03.2020 to 24.03.2021, the bar under Section 10A does not apply. The Adjudicating Authority is entitled to examine all documents having a direct or indirect bearing on an application under Section 7 in determining whether a default has occurred, and a debtor's claimed financial viability does not, in the absence of legal or factual basis, defeat an application where debt and default are established.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
(Arising out of the Order dated 02.01.2024 passed by the National Company Law Tribunal, Kolkata Bench in I.A. (IB) No. 1020/KB/2022 and IA (IB) No. 828/KB/2023 and CP (IB) No. 138/KB/2021)
IN THE MATTER OF:
Power Trust, Promoter of Hiranmaye Energy Ltd. Having its registered office at: Plot X1, 2 & 3, 2nd Floor, Block- EP, Sector-V, Salt Lake, Kolkata- 700091 ...Appellant
Versus
1. Mr. Bhuvan Madan (Interim Resolution Professional of Hiranmaye Energy Ltd.) Having his address at: A-103 Ashok Vihar Phase-3, New Delhi-110052 Email id: madan.bhuvan@gmail.com ...Respondent No. 1
2. REC Ltd. (formerly, Rural Electrification Corporation Ltd.) Having its registered office at: Core-4, CGO Complex, 7, Lodhi Road, Pragati Vihar, New Delhi 110003 Email id: siddharthasingh@recl.nic.in ...Respondent No. 2
Present
For Appellant: Mr. Joy Saha, Sr. Advocate, Mr. Krishnendu Datta, Sr. Advocate along with Mr. Pranjit Bhattacharya, Ms. Muskan Bangani, Ms. Raj Sarit Khare & Mr. Ashish Choudhary.
For Respondents: Mr. Abhinav Vasisht, Mr. Saurav Panda, -2- Comp. App. (AT) (Ins.) No. 81 of 2024
Ms. Mohan Nighawan and Ms. Priya, Advocates for REC Ltd. Mr. Shashank Agarwal, Advocate for IRP.
JUDGEMENT
(25 .01.2024 )
NARESH SALECHA, MEMBER (TECHNICAL)
1. The present Appeal i.e., Company Appeal (AT) (Insolvency) No. 81 of
2024 has been filed by Power Trust, Promoter of Hiranmaye Energy Ltd (in
short 'the Corporate Debtor') under Section 61 of the Insolvency & Bankruptcy
Code, 2016 (in short 'Code') being aggrieved by the Impugned Order dated
02.01.2024 passed by the National Company Law Tribunal, Kolkata Bench (in
short 'Adjudicating Authority') in C.P. (IB) No. 138/(KB)/ 2021 where the
Adjudicating Authority has admitted application filed under Section 7 of the
Code, by REC Ltd., Respondent No. 2 herein and who is the Financial Creditor
of the Corporate Debtor.
2. Mr. Bhuvan Madan is the Respondent No. 1 herein is the Resolution
Professional of the Corporate Debtor.
3. Heard the Counsel for the Parties and perused the records made available
including the cited judgements.
-3-
Comp. App. (AT) (Ins.) No. 81 of 2024
4. It is the case of the Appellant that he is one of the main promoters of the
Corporate Debtor holding about 74% of the issued and paid-up capital of the
Corporate Debtor.
5. It has been brought out that the Corporate Debtor had taken the term loan
of Rs. 1,859 Crores from the Respondent No. 2 and a common loan agreement
was entered between the Corporate Debtor and Respondent No. 2 on 19.06.2013
for setting of a project to provide thermal power plant at Haldia consisting of
three units of 150 MW each (total 450 MW). The Appellant further submitted
that due to cost over runs, on 30.10.2015, the Corporate Debtor and the
Respondent No. 2 entered into amendment No. 1 for an additional term loan
facility of Rs. 446.97 Crores.
6. The Appellant submitted that the Corporate Debtor entered into power
purchase agreement on 28.12.2010, 06.04.2018 and 03.07.2020 with West
Bengal State Electricity Distribution Company Ltd. (in short 'WBSEDCL').
7. The Appellant brought out that on 30.06.2018, the Respondent No. 2
classified the Account of the Corporate Debtor as Non-Performing Assets
('NPA') due to alleged default committed by the Corporate Debtor in making
due payments. The Appellant stated that the Corporate Debtor conducted several
meetings with Respondent No. 2 for restructuring of loans in terms of RBI
circular dated 07.06.2019 and accordingly on 21.02.2020, the Respondent No. 2
issued its approval for Resolution Plan ( restructuring without change in -4- Comp. App. (AT) (Ins.) No. 81 of 2024
ownership) and the repayment obligation of the Corporate Debtor was to
commence from 31.12.2020 and interest was to be paid on monthly basis
commencing from 30.06.2020, which falls within the period stipulated under
Section 10A of the Code.
8. The Appellant assailed the conduct of the Respondent No. 2, who despite
restructuring of the credit facilities, filed an application under Section 7 of the
Code for alleged default in payment of Rs. 2,183.19 Crores which was finally
admitted wrongly by the Adjudicating Authority and the Corporate Debtor was
put under Corporate Insolvency Resolution Process (in short 'CIRP').
9. The Appellant brought out that he moved a Writ Petition before Hon'ble
Calcutta High Court vide W.P.A no. 10679 of 2021 which was dismissed by an
order dated 02.07.2021 and which was further challenged by the Corporate
Debtor before the Division Bench vide W.P.A no. 10679 of 2021 which was
also disposed vide order dated 06.07.2021.
10. The Appellant emphasised that the Corporate Debtor is in public service
of supplying electricity to common consumers hence action taken by the
Adjudicating Authority was incorrect. It is the case of the Appellants that
alleged default period was squarely covered under Section 10 A of the Code,
hence the impugned order is illegal and perverse.
11. It is the case of the Appellant that during pendency of Section 7
application, the Respondent No. 2 issued a letter dated 16.12.2021 to the -5- Comp. App. (AT) (Ins.) No. 81 of 2024
Corporate Debtor demanding Rs. 29.47 Crores as part of repayment obligation,
which was paid by the Corporate Debtor on 26.12.2021.
12. The Appellant submitted that date of default mentioned in Part IV of
Section 7 application is 31.03.2018 and also stated is the date of classification of
the account of Corporate Debtor as NPA being 31.06.2018 and even after this
date the Respondent no. 2 as well as Power Finance Corporation Ltd. (in short
'PFC'), another Financial Creditor of the Corporate Debtor, restructured the
credit facilities of the corporate debtor vide letter dated 29.09.2020, therefore,
the date of default could not continue to be 30.06.2018.
13. It is further the case of the Appellant that Respondent No. 2 along with
PFC were fully involved in the management and control of the Corporate
Debtor by way of their nominee Directors appointed on the Board of Corporate
Debtor.
14. The Appellant submitted that entire proceed of the sale of electricity of
the Corporate Debtor was routed through a Trust and Retention Account (in
short 'TRA'), which has been operational since September, 2013 under control
of Respondent No. 2 and PFC and therefore, the initiation of Section 7
application by the Respondent No. 2 was mischievous and was done only with
intentions to harm the Corporate Debtor.
-6-
Comp. App. (AT) (Ins.) No. 81 of 2024
15. The Appellant pleaded that the Corporate Debtor is financially viable
since it has PPA agreement with WBSEDCL and there were continuous inflow
of money which was under control of TRA.
16. The Appellant also stated that the Corporate Debtor has made a payment
of Rs. 50 Crore to the Respondent No. 2 and PFC on 24.12.2021 with clear
caveat written by the Corporate Debtor stating that 'your receipt of the payment
of the said sum of Rs. 50 Crore will be deemed and constructed by us to be an
acceptance by you of the proposal contained herein'. In this context, the
Appellant stated that since the payment was received and accepted by
Respondent No. 2 and PFC, the restructuring agreement was automatically
extended and therefore, there was no debt and default.
17. The Appellant reiterated that Respondent No. 2 has been playing hide and
seek by way of accepting payments from the Corporate Debtor from time-to-
time and simultaneously pursuing application under Section 7 of the Code
before the Adjudicating Authority. The Appellant submitted that under such
circumstances, the Corporate Debtor filed an IA (IB) no. 1020 of 2022 before
the Adjudicating Authority on 13.09.2020 with request for injunction and stay in
CP (IB) No. 138/2021 and to declare restructuring agreements dated 24.09.2020
and 14.01.2021 to be valid. The Appellant also pleaded that even during the
pendency of IA No. 1020 of 2022, the Respondent No. 2 kept on writing and
demanding payments in terms of the demand letters. It is the case of the -7- Comp. App. (AT) (Ins.) No. 81 of 2024
Appellant that although IA No. 1020 of 2022 was being heard, the Adjudicating
Authority reserved the order and passed the order dated 21.03.2023 in both on
CP (IB) No. 138 of 2021 and also on IA No. 1020 of 2022. The Appellant
submitted that the Corporate Debtor also filed IA (IB) No. 828 of 2023 with
request to dismiss CP (IB) no. 138/KB/2021 and after hearing the matter was
reserved for orders on 17.07.2023. The Appellant brought out that ultimately
vide impugned order dated 02.01.2024, the said CP (IB) no. 138/2021, IA (IB)
no. 1020 of 2022 and IA (IB) no. 828 of 2023 were dismissed by the
Adjudicating Authority and passed the order for CIRP of the Corporate Debtor.
18. The Appellant once again emphasised that the Corporate Debtor is
financially viable as between 01.11.2021 to 01.11.2022, the Corporate Debtor
has raised the bills of Rs. 916.95 Crores upon the WBSEDCL and during the
Financial Year 2021-22 the Corporate Debtor earned EBITDA of Rs. 259.94
Crores and the EBITDA of the Corporate Debtor for the FY 2022-23 was
Rs. 308 Crores and therefore, the Corporate Debtor with such outstanding
earnings cannot be deemed to be insolvent.
19. The Appellant submitted that the impugned order is illegal and arbitrary
since the Resolution Plan (restructuring without change in ownership) has been
approved by Respondent No. 2 dated 21.02.2020 and the first payment was to
be made on 31.12.2020 and therefore the first default could have been
committed by the Corporate Debtor only on 31.12.2020 which was within the -8- Comp. App. (AT) (Ins.) No. 81 of 2024
period covered under Section 10A of the Code. The Appellant assailed the
impugned order which completely ignored this vital fact and did not dealt and
discussed restructuring approval dated 21.02.2020 in the impugned order and
the Adjudicating Authority therefore committed fatal error. It is the case of the
Appellant that an I.A. No.828 of 2023 was filed specifically contending that the
default occurred on 30.06.2020 and 31.12.2020 within a Section 10A period,
however, the Impugned Order records the existence of the First Restructuring
proposal but there was no discussion or adjudication in respect of the First
Restructuring proposal. The Appellant pleaded that the Impugned Order is non-
speaking and unreasoned and suffers from the vice of non-consideration of
argued issues making the same unsustainable. The Appellant cited judgment
rendered in the case of Gandhar Oil Refinery (India) Ltd. Vs. City Oil Pvt.
Ltd., 2022 SCC OnLine NCLAT 4145]
20. The Appellant submitted that in fact there were two restructuring plans
approved by the Respondent No. 2 i.e. first restructuring approval dated
21.02.2020 and second restructuring approval dated 29.09.2020. In this
connection he further submitted that second restructuring approval dated
29.09.2020 specifically provided that the same was revision of first restructuring
approval dated 21.02.2020 therefore the first restructuring approval dated
21.02.2020 was valid and remained in existence and the default could have been
committed only on or from 31.03.2020 falling within the period specified under -9- Comp. App. (AT) (Ins.) No. 81 of 2024
Section 10A of the Code. The Appellant submitted that the continued Second
Restructuring approval cannot be construed to be an independent document,
inasmuch as, the First Restructuring approval was never terminated and
therefore, the date of default under the Second Restructuring approval being
31.03.2021, cannot be deemed to be the date of default, which must be held to
be 30.06.2020 followed by 31.12.2020.
21. The Appellant countered the arguments of the Respondent No. 2 with
reference to 'pre implementation conditions' since, the restructuring approval
were never terminated by the Respondent No. 2 and as such this remained valid.
The Appellant further contended that the Impugned Order is vitiated by an error
apparent on the face of the record, as it failed to consider or deal with the
approved resolution plan dated 21.02.2020. Additionally, despite the Corporate
Debtor's argument that the novation of the second restructuring approval dated
29.09.2020 constituted a new and independent agreement superseding the
original cause of action, this argument was not addressed in the Impugned
Order.
22. The Appellant asserted that the Corporate Debtor honoured each demand
for payment made by the Financial Creditor, and therefore, it should not be
deemed to have defaulted in payment of its debts and therefore the Section 7
application should not have been admitted by the Adjudicating Authority. The
Appellant stated that there has been no termination or recall of the Common -10- Comp. App. (AT) (Ins.) No. 81 of 2024
Loan Agreement, the First Restructuring approval continued on 29.09.2020 and
in the absence of specific termination and/or recalling of the loan, the right to
demand repayment has not arisen. The Appellant pleaded that the claim arises
only when the loan has been recalled and the restructuring approval have been
terminated and as such the Company Petition itself was not maintainable.
23. The Appellant elaborated that between 16.12.2021 to 01.12.2023 (i.e.,
after the institution of the Company Petition), the Respondent No. 2 on various
dates demanded payment of a sum of Rs. 198.84 Crores and received and
accepted payment of Rs. 187.28 Crores and an additional sum of Rs. 129.74
Crores having been paid to PFC Ltd. The Appellant argued that payment of a
sum of Rs. 317.02 Crores during the pendency of the Company Petition clearly
demonstrate that the Corporate Debtor is not insolvent.
24. It is the submission of the Appellant that by demanding and receiving
payments after filing of the Company Petition, Respondent No. 2 has waived
and abjured and/or given a go-bye to its prayer for resolution within the
mechanism of the Code and therefore, the Company Petition was liable to be
dismissed by the Adjudicating Authority.
25. It is the case of the Appellant that any adjudication as to whether or not
the First Restructuring approval as continued on 29.09.2020 was given effect to
and/or acted upon and/or was being performed as on the date of the Impugned -11- Comp. App. (AT) (Ins.) No. 81 of 2024
Order, is completely out of jurisdiction of the Adjudicating Authority and the
Adjudicating Authority should not have dealt with this aspect at all.
26. The Appellant pleaded that the crux of the dispute revolves around the
issue as to whether or not the First Restructuring approval as continued on
29.09.2020 was given effect to and was being performed with additional facts of
payment of Rs. 317.02 Crores made to the Respondent No. 2 and PFC during
the pendency of the Company Petition establishes that the Corporate Debtor
could not have been disregarded by the Adjudicating Authority to arrive at a
finding that the Corporate Debtor is insolvent.
27. The Appellant emphasised that the present alleged dues under the
restructuring approval according to the Respondent No. 2 should be calculated
and an opportunity should be granted to the Corporate Debtor to repay the same
within a specified timeframe and the Corporate Debtor is ready and willing to
forthwith make payment of a sum of Rs. 103 Crores which is lying to the credit
of its TRA account.
28. Concluding his arguments, the Appellant summarised that the
Adjudicating Authority failed to consider his pleadings made before the
Adjudicating Authority in respect of validity of the both restructuring approvals,
alleged default falling within the period specified under Section 10A of the
Code and complete viability of the Corporate Debtor and therefore, the
impugned order need to be set aside.
-12-
Comp. App. (AT) (Ins.) No. 81 of 2024
29. Per contra, the Respondent No. 2 denied all the averments of the
Appellant, treating such averments as misleading, mischievous and without any
substance.
30. The Respondent No. 2 submitted that the Adjudicating Authority has
gone through entire facts and the law in details and passed well-reasoned
speaking order contained in the impugned order dated 02.01.2024. The
Respondent No. 2 gave the background of the case and circumstances which led
to passage of impugned order.
31. The Respondent no. 2 submitted that he was compelled to file Section 7
application to protect his financial rights since the corporate debtor was not
repaying his obligation. The Respondent no. 2 submitted that he gave all the
opportunities to the Corporate Debtor and in fact approval the restructuring plan
of the Corporate Debtor vide dated 21.02.2020 which could not be complied by
the Corporate Debtor. The Respondent No. 2 also submitted that in order to
further facilitate the corporate debtor for its revival, the second restructuring
approval was given to the corporate debtor on 29.09.2020, however the
corporate debtor miserably failed to meet pre implementation conditions and
therefore there was no restructuring agreement in existence. The Respondent
No. 2 filed the application under Section 7 of the Code for default of
Rs. 2183.19 Crores and date of default was mentioned as 31.03.2018 and date of
NPA was 30.06.2018, enclosing several documents including, common loan -13- Comp. App. (AT) (Ins.) No. 81 of 2024
agreement dated 19.06.2013, Mortgage details, Deeds of hypothecation, pledge
deed, cost overrun facility etc.
32. It is the case of the Respondent No. 2 that the Corporate Debtor never
denied its liability of payments and in fact acknowledged the debts in Annual
Financial Statements of the Corporate Debtor. The Respondent No. 2 submitted
that in terms of the provisions contained in the Code, the Adjudicating Authority
is only required to ascertain whether there was debt and default took place in
excess of Rs. 1 Crore and the application was complete and in such eventuality
of meeting these conditions, the Adjudicating Authority is required to admit the
application filed under Section 7 of the Code. The Respondent no. 2 cited the
Judgment passed by Hon'ble Supreme Court of India in case of 'Innoventive
Industries ltd. vs. ICICI Bank [2 (2018) 1 SCC 407]' where Hon'ble Supreme
Court held that the Adjudicating Authority mainly only has to determine debt
and default.
33. The Respondent No. 2 submitted that the Lender's meeting was held on
17.02.2021 wherein it was noted that the Corporate Debtor had failed to satisfy
most of the pre-implementation conditions and they were cautioned to ensure
due satisfaction without further delay by 28.02.2021, failing which the
Restructuring Proposal would fail. The Corporate Debtor acknowledged its
failure to fulfil the pre-implementation conditions and wrote to the Respondent
No. 2 seeking an "extension of six months for implementation of the Resolution -14- Comp. App. (AT) (Ins.) No. 81 of 2024
Plan and extending the date for initial DRA creation from 28th February to 31st
August 2021 and shifting of date of payment of interest/principal from
31.03.2021 to 30.09.2021". The Respondent No. 2 stated that the Corporate
Debtor failed to fulfil the pre-implementation conditions of the Restructuring
Proposal, and therefore, the Restructuring Proposal did not fructify into a
restructuring agreement and hence were of no consequence.
34. The Respondent No. 2 strongly denied that the account of the Corporate
Debtor was restructured by the Respondent No. 2 and PFC and submitted that
during the meeting held on 11.11.2021, the lenders including the Respondent
No. 2, discussed the compliance of the pre-implementation conditions
mentioned in the Restructuring Proposal dated 29.09.2020 ("Ist Restructuring
Proposal") and the failure of the Corporate Debtor to fulfil the same by
28.02.2021. It is also highlighted that the minutes of the meeting had on
11.11.2021 recorded such discussions including the communication regarding
rejection of the Restructuring Proposal were also made available to the
Corporate Debtor, therefore, the submissions of the Appellant that the account
has been restructured or that the timelines were extended are false.
35. The Respondent No. 2 stated that averment of the Appellant regarding the
date of default being incorrect are also false and submitted that since the
Respondent No. 2 had rejected the 'Restructuring Proposal', the date 30.03.2018
was given as date of default as it was date when the Corporate Debtor defaulted -15- Comp. App. (AT) (Ins.) No. 81 of 2024
and date of 30.06.2018 was indicated on the date when the account of the
Corporate Debtor was declared as NPA.
36. The Respondent No. 2 also denied the averments made by the Appellant
that he was part of the management of the Corporate Debtor by virtue of
nominating his nominee Director on the Board of Director of the Corporate
Debtor and stated that it has no relevance to his application under Section 7 of
the Code.
37. The Respondent No. 2 also denied the assumptions and presumptions
about the financial viability of the corporate debtor as claimed by the Appellant.
The Respondent No. 2 further submitted that the repayment of the credit
facilities would be dependent on the operation of the Plant and fixation of the
tariff by the regulatory authorities and the Appellant was well aware that one of
the pre-implementation conditions for the Restructuring Proposal was approval
from the West Bengal Electricity Regulatory Commission fixing the tariff
charges by February 28, 2021, failing which the said Restructuring Proposal
would stand rejected. The Respondent No. 2 submitted that since the
Respondent failed to achieve the same, the restructuring proposal was not in
existence legally.
38. The Respondent No. 2 denied that the account of the Corporate Debtor
was restructured and reiterated that the Restructuring Proposal was approval
subject to condition that the Corporate Debtor would comply with stipulated -16- Comp. App. (AT) (Ins.) No. 81 of 2024
pre-implementation conditions, as contained in its approval letter, however since
the said pre- implementation conditions were not achieved by the Corporate
Debtor, the Restructuring Proposal failed and the same was duly communicated
to the Corporate Debtor. The Respondent No. 2 stated that Appellant indeed
requested for extension of time under the Restructuring Proposal, which was
never accepted by the Respondent No. 2.
39. The Respondent No. 2 mentioned that the Appellant is attempting to
mislead this Appellate Tribunal by submitting that the Respondent No. 2 and
PFC accepted the sum of Rs. 50 Crores under the said Restructuring Proposal
and reiterated that the Restructuring Proposal was categorically rejected by the
lenders on the grounds of failure on the part of the Respondent to meet the pre-
implementation conditions. The Respondent No. 2 also denied that the
Restructuring Proposal is binding or subsisting, as on date, as the same has long
been rejected by the Respondent No. 2 on account of failure to meet the pre-
implementation conditions until the expiry of the validity period of the
Restructuring Proposal. Further, the Appellant has contended that pursuant to
the demand of Respondent No. 2 to remit an amount of Rs. 50 Crores to the
Respondent No. 2 and PFC vide letter dated 16.12.2021, the Corporate Debtor
had issued a letter dated 24.12.2021 stating that payment of Rs. 50 Crores would
be deemed to be an acceptance of revival of the Restructuring Proposal and
hence, the Restructuring Proposal stood revived. The Respondent No. 2 -17- Comp. App. (AT) (Ins.) No. 81 of 2024
submitted that a defaulting borrower has no right in law to seek a unilateral
revival of a Restructuring Proposal. The Respondent No. 2 stated that on issue
of part payment of huge overdues, the Appellant also failed to reveal that the
Respondent No. 2 repeatedly in its communications, inter alia, dated 05.01.2022
and 20.01.2022 highlighted that the default continued and there was no deemed
revival of the Restructuring Proposal.
40. It is the case of the Respondent No. 2 that the Appellant is misleading this
Appellate Tribunal by incorrectly stating that the Corporate Debtor is not in
default as it has already paid all the amounts demanded by REC to be paid out
of the TRA of the Corporate Debtor during the pendency of the Section 7
Application. It has been submitted that the Respondent No. 2 had demanded
certain amounts lying in the TRA out of the revenue generated, in terms of the
Trust and Retention Account Agreement dated 18.07.2013, to recover in part, a
small portion of the huge overdues. Demand made for payouts out of the TRA
based on the revenue available in the account of the Corporate Debtor cannot be
construed to alter the repayment schedule already contractually entered into in
terms of the Original Loan Agreement and the argument of the Appellant in this
regard is absolutely baseless. It is the case of the Respondent No. 2 that filing
of the Section 7 Application does not create any moratorium on the financial
creditor to keep recovering its dues from the borrower, and the Respondent -18- Comp. App. (AT) (Ins.) No. 81 of 2024
No. 2 was under no legal restriction from seeking recovery of its dues during the
pendency of the Section 7 Application.
41. The Respondent No. 2 strongly objected to the averments of the
Appellant that the default period was covered under Section 10 A of the Code
and stated that since there was no restructuring proposal agreement validly
existed due to failure on the part of the Corporate Debtor, the default date was
correctly indicated in the application filed under Section 7 in part IV i.e.
30.03.2018, along with the date of 30.06.2018 when the account of the
Corporate Debtor was declared as NPA.
42. The Respondent No. 2 stated that in the Impugned Order, the
Adjudicating Authority assumed that the Second Restructuring Proposal had
been given effect to and noting the occurrence of default to even meet the
repayments under the Second Restructuring Proposal, the Adjudicating
Authority has held the Appellant to be in default and the default occurred on
31.03.2021; (i.e., outside the Section 10A period) and admitted the Section 7
Application. The Respondent No 2 reiterated that the Restructuring Proposal
had never fructified into an agreement and was never implemented and
therefore, the Appellant's argument that the date of default should be construed
on the basis of the date of interest payment set out under the First Restructuring
Proposal is absolutely misleading and baseless. The Respondent No. 2 further
explained that the Second Restructuring Proposal specifically stated that it was a -19- Comp. App. (AT) (Ins.) No. 81 of 2024
revised restructuring proposal having its own detailed terms and conditions,
which is effectively a novation of the terms under the First Restructuring
Proposal. Further, there was no provision in the Second Restructuring Proposal
saving any provision of the First Restructuring Proposal, including interest
payment obligations thereunder and in fact, Second Restructuring Approval has
its own separate table for the repayment schedule of principal and provisions for
interest payments.
43. The Respondent No. 2 also explained that the Second Restructuring
Proposal specifically deals with all the interest overdue of the Appellant upto
30.09.2020 (including interest obligations arising for quarter ending on
30.06.2020 which is claimed by the Appellant to have been defaulted upon
under First Restructuring Proposal), to be converted into optionally convertible
debentures, thereby proving wrong the theory of the Appellant of the non-
payment of interest in quarter ending 30.06.2020 being a default under First
Restructuring Proposal, which has continued even in the Second Restructuring
Proposal.
44. The Respondent No. 2 explained that there is no requirement under the
Code to recall the entire loan facilities before initiating of the CIRP under
Section 7. The Respondent No. 2 stated that non-payment of loan instalments,
both principal and interest, reflect an amount of default far in excess of Rs. 1
Crore and further gave the present status of overdues as on 02.01.2024 to be -20- Comp. App. (AT) (Ins.) No. 81 of 2024
Rs. 2588.23 Crores, including principal amount of Rs. 832.04 Crores, interest
amount of Rs. 1754.76 Crores and accrued interest of Rs. 1.43 Crores. Thus,
total outstanding amount of the Facilities as on 02.01.2024 is Rs. 3103.31
Crores.
45. Concluding his arguments, the Respondent No. 2 requested this Appellate
Tribunal to dismiss the appeal with exemplary cost.
Findings
46. In view of foregoing detailed discussion and after perusal of the record
made available, we find that following issues are pertinent to be decided in
order to take a conscious decision on the appeal:
(i) Whether the restructuring proposals dated 21.02.2020 and 29.09.2020,
were in existence and were binding.
(ii) Whether pre-implementation conditions as stipulated in the
restructuring proposals were mandatory and whether failure in its
compliance tantamounted to non-execution of the restructuring
approvals automatically.
(iii) Whether the date of default was covered under Period stipulated under
Section 10A of the Code.
(iv) Whether the payments of Rs. 50 Crores made by the Corporate Debtor
to the financial creditors i.e., the Respondent No. 2 and PFC resulted
in automatic extension of restructuring approvals.
-21- Comp. App. (AT) (Ins.) No. 81 of 2024
(v) Whether the financial viability of the Corporate Debtor as claimed by
the Appellant would have impacted the impugned order in deciding
the application filed under Section 7 of the code by the Respondent
No. 2.
47. Since all above issues are inter-related, inter-connected and depends upon
each other, we shall deal and decide all above issues and other issues raised in
the appeal in conjoint manner in subsequent discussions.
At the outset, it would be imperative to go through the provision of Section
"[10A. Suspension of initiation of corporate insolvency resolution process. Notwithstanding anything contained in sections 7, 9 and 10, no application for initiation of corporate insolvency resolution process of a corporate debtor shall be filed, for any default arising on or after 25th March, 2020 for a period of six months or such further period, not exceeding one year from such date, as may be notified in this behalf:
Provided that no application shall ever be filed for initiation of corporate insolvency resolution process of a corporate debtor for the said default occurring during the said period. Explanation. - For the removal of doubts, it is hereby clarified that the provisions of this section shall not apply to any default committed under the said sections before 25th March, 2020.]"
(Emphasis Supplied) -22- Comp. App. (AT) (Ins.) No. 81 of 2024
48. Thus, the period from the date 25.03.2020 to 24.03.2021, is the period
which is required to be excluded for the purpose of initiation of CIRP under
Section 7, 9 and 10. Section 10A of the Code also clearly mandates that no
application shall ever be filed for initiation of CIRP of a Corporate Debtor for
the said default occurring during the said period. It is significant to note that the
explanation provided under Section 10A of the Code stipulate that provision of
Section 10A shall not apply to any default committed under the said Sections
before 25.03.2020. Hence, date of default become critical.
49. We note that original common loan agreement was entered between the
Corporate Debtor and Respondent no. 2 and PFC on 19.06.2013. Due to failure
on part of the Corporate Debtor, first restructuring proposal was approved by
lenders on 21.02.2020. We have observed from the averments of all the parties
that even this first restructuring proposal could not proceed further due to non-
compliance of terms and conditions by the Corporate Debtor. In order to salvage
the Corporate Debtor, the lenders i.e. Respondent No. 2 and PFC approved
second restructuring proposal on 29.09.2020. Although the Appellant has
termed these proposals as agreements but the Respondent No. 2 has emphasised
that these were only restructuring proposals which were merely sanctioned by
the Respondent No. 2. We note that 2nd restructuring approval dated 29.09.2020
was subject to fulfilling pre-implementation conditions by the Corporate Debtor -23- Comp. App. (AT) (Ins.) No. 81 of 2024
by 28.02.2021 which never got fructified and therefore restructuring proposals
failed to take off.
50. Here we would like to refer to salient features of the original loan
agreement as well as salient features of two subsequent restructuring proposals
agreed by the Respondent No. 2.
51. We note that in the original sanction letter dated 22.12.2011 issued by the
Respondent No. 2 the detailed terms and conditions were elaborated including
(a) regarding repayment of loan, moratorium period and appropriation of receipt
and mode of payment, (b) Event of default, (c) TRA, (d) pre commitment
conditions which reads as under:
-24-
Comp. App. (AT) (Ins.) No. 81 of 2024 -25- Comp. App. (AT) (Ins.) No. 81 of 2024 -26- Comp. App. (AT) (Ins.) No. 81 of 2024
52. The original common loan agreement was signed on 19.06.2023 amongst
the Corporate Debtor, REC, the Respondent No. 2 herein (as 'REC', 'as
lenders agent', 'as Security agent') and PFC as another Financial Creditor.
The agreement mentioned amount of Rs. 1859 Crores as RTL facility and laid
down the drawdown schedule along with procedures for requesting drawdown,
Interest, Repayments, Conditions precedent for effectiveness of the agreement
and pre-disbursement of the conditions.
We note that due to several reasons, the Corporate Debtor could not repay
the outstanding dues to the Respondent No. 2 and thereafter Respondent No. 2 -27- Comp. App. (AT) (Ins.) No. 81 of 2024
communicated its approval to the restructuring proposal dated 21.02.2020 with
reference to Corporate Debtor Resolution Proposal letter dated 25.11.2019. As
per the Respondent No. 2 letter dated 21.02.2020, the restructuring proposal was
approved consisting of sustainable debt of Rs. 1460.30 Crores with fixed
interest rate of 11% with REC share in the RTL of Rs. 853.09 Crores, and
further details of balance outstanding along with restructuring were also
mentioned in the same letter. In clause 9 of the said letter dated 21.02.2020, the
REC recorded 'the detailed terms and conditions w.r.t approval of
restructuring proposal are placed at Annexure -1 shall also apply'.
We observe that the restructuring proposal approved by the Respondent
No. 2 dated 21.02.2020 could not succeed and second restructuring proposal
was approved by Respondent No. 2 on 29.09.2020 stating total outstanding
debts to be Rs. 3,427.21 Crores on cut off date of 30.09.2020. This second
restructuring approval letter contained details about various payments and
interest to be paid by the Corporate Debtor and further mentioned in clause 8
that 'detailed terms and conditions w.r.t. a proposed restructuring proposal as
mentioned above (considering the above-mentioned modifications/
amendments in the proposed structure and terms of restructuring proposal)
placed that annexure -1shall also apply'.
We also note that the Annexure-1 of 2nd Restructuring approval states first
clause as 'pre-conditions to effective implementation of the Resolution Plan' -28- Comp. App. (AT) (Ins.) No. 81 of 2024
and mentioned several such pre-conditions including tariff order for plant
approving, creation of initial DSRA for the project and so on. We observe from
the averments of the Respondent No. 2 that these vital pre-implementation
conditions were not complied by the Corporate Debtor and no approval of tariff
order by stipulated date was obtained by the Corporate Debtor and the
Corporate Debtor further failed to create initial DSRA.
53. It goes without saying that pre-implementation conditions are akin to
conditions precedent which are meant to be complied with before the agreement
is fructified. The Appellant has not refuted that the Corporate Debtor could not
meet such conditions precedent. The argument of the Appellant is that the first
restructuring proposal dated 21.02.2020 continued to be valid since in the
second restructuring proposals approval letter dated 29.02.2019, specifically
referred to first restructuring proposal. It is further the argument of the
Appellant that unless such letters are cancelled and recall letters are issued by
the lenders, the restructuring approval letters continued to be valid and result
into deemed agreements.
In this connection we observe that on the failure of the Corporate Debtor
to fulfil its obligation to the original common loan agreement and subsequently,
further failure to comply with the first restructuring proposal dated 21.02.2020
and further failure to comply with the second restructuring approval dated
29.09.2020, the Appellant, at this stage, cannot take the plea of continuation of -29- Comp. App. (AT) (Ins.) No. 81 of 2024
all agreements/proposals. Normally, when the restructuring proposal is agreed
upon, the same is in supersession to the previous loan agreement/restructuring
proposal. Here, it is critical to understand that pre-implementation condition are
conditions precedent, which are meant to be followed and it cannot be the case
of the borrower that despite his failure to fulfil the conditions precedent, the
restructuring proposal should be deemed to be valid, continuing and further
deemed to be converted into agreement. It may be gathered that if the conditions
precedent of any restructuring proposal is not met with, this would
automatically result into non-fructification of restructuring proposal and original
loan agreement will get restored and will continues to survive. In the present
case, undisputedly the Corporate Debtor could not make the required payments
to the lenders i.e. the Respondent No. 2 as well as PFC and also could not meet
with pre-implementation conditions and therefore, the restructuring approval
ceased to remain alive and the only valid agreement which survived was the
common loan agreement dated 19.06.2013. We answer the issue no. 1 & 2
accordingly.
54. Here we would also note details of order of Hon'ble Calcutta High Court
which were referred by the Appellant during pleadings seeking inter alia a writ
of mandamus against the Respondent No. 2 to extend time for implementing the
Restructuring Proposal until March 2022, passed an order holding that : -30-
Comp. App. (AT) (Ins.) No. 81 of 2024
"there was therefore no arbitrary or unfair action on the part of the respondent nos.3 and 4 in cancelling the restructuring offer" and that "the institution of proceedings by PFC and REC under the provisions of the Insolvency and Bankruptcy Code, 2016 before the National Company Law Tribunal cannot be faulted."
The Division Bench of the Hon'ble Calcutta High Court in the appeal
filed by the Corporate Debtor, being MAT No. 626 of 2021 made a limited
modification to the order dated 02.07.2021 and directed the lenders to address
the tariff order dated 31.05.2021 received by the Corporate Debtor along with
the extent of fulfilment of pre-implementation conditions, while inter alia
holding that :
"The settlement of the tariff or, the Tariff Order, being a pre-condition towards the restructuring arrangement arrived at in the meeting dated 17th February, 2021, with the pronunciation of the Tariff Order by the Commission on the 31st day of May 2021, such pre-condition stood answered. It is not within the domain of R3 and R4 acting as lenders to wait any further beyond the Tariff Order pronounced by the Commission. It is evident that the restructuring exercise arrived at the said consortium meeting dated 17th February, 2021 has not worked out."
-31- Comp. App. (AT) (Ins.) No. 81 of 2024
It has been brought to our notice that on 11.11.2021 Lenders' meeting
was held pursuant to the order of the Hon'ble Calcutta High Court dated
07.10.2021, wherein lenders after considering the tariff order, noted the failure
of the Corporate Debtor in meeting several pre-implementation conditions of the
Restructuring Proposal, and again notified the failure of the Restructuring
Proposal.
Thus, we find that orders of the Hon'ble Calcutta High Court does not
help the cause of the Appellant and therefore, has no impact on this appeal
before us.
55. Now, we will deal the issue regarding default period falling within period
specified under Section 10A of the Code or otherwise. At this juncture, we
would like to take into account part IV of the application made by the
Respondent No. 2 while filing the Section 7 application which reads as under: -32-
Comp. App. (AT) (Ins.) No. 81 of 2024
56. Thus, it is evident that the Respondent No. 2 clearly indicated date of
default to be 31.03.2018, which is not covered under Section 10A of the Code. -33-
Comp. App. (AT) (Ins.) No. 81 of 2024
Incidentally, the Respondent No. 2 also gave date of NPA of Corporate Debtor
i.e., 30.06.2018, which is also out of purview of Section 10A of the Code.
57. It will also be pertinent to note the finding of the Adjudicating Authority
on this issue which can be seen as under:
"The terms and conditions as well as the sanction letter does not provide that in case of the failure of the repayment plan, the date of default shall be reckoned from a date prior to the sanction of the plan. It does not have a pre-empting or a remedial clause to that effect. Thus, the date of default cannot now be assumed to be outside this restructured plan.
Date Principal Interest 31st March, 20221 28.37 Crores 77.81 Crores 30th June, 2021 7.09 Crores 38.09 Crores 30th September, 2021 7.09 Crores 38.32 Crores 31st December, 2021 7.09 Crores 38.12 Crores 31st March, 2022 7.09 Crores 37.10 Crores 30th June, 2022 7.09 Crores 37.32 Crores 30th September, 2022 7.09 Crores 37.53 Crores Total 70.91 Crores 304.29 Crores
In the supplementary affidavit filed by the Corporate Debtor it has been affirmed that against the requirement of repayment above, the following payment have been made in the manner shown herein:
Date Amount 24th December, 2021 50 Crores 12th July, 2022 50 Crores 13th September, 2022 50 Crores 22nd September, 20 Crores -34- Comp. App. (AT) (Ins.) No. 81 of 2024
2022 Total 170 Crores
From the above two tables it is evident that the Corporate Debtor has made a payment of 170 Crore till 22 September 2022 as against the total requirement of Rs 375.2 Crore. The important part however is that the first payment of Rs.50 Crore was made on 24" of December 2021, whereas it was supposed to be made by 31" March 2021 as per the revised sanctioned letter (supra). The default can thus be seen to have taken place on 31s March 2021 itself, which is outside the 10A period, though by a whisker..."
(Emphasis Supplied)
58. We observe that although the Respondent No. 2 has given date of default
as 31.03.2018 the date on which the Corporate Debtor failed to meet its first
obligation as 'per original common loan agreement dated 19.06.2013 as
amended on 30.10.2015 in part IV of the Section 7 application, but the
Adjudicating Authority has treated as 31.03.2021 as date of default as per
Second Restructuring Approval letter according to which, the first payment was
to be made by 31.03.2021 whereas the first payment of Rs. 25 Crores was made
on 21.12.2021, hence the Adjudicating Authority held that the date of default
which was not covered under period stipulated under Section 10 A of the Code
since last date covered under Section 10A was 24.03.2021. -35-
Comp. App. (AT) (Ins.) No. 81 of 2024
Thus, the date of default as indicated in Part IV by the Appellant is
31.03.2018 based on first default as per original common loan agreement. The
Adjudicating Authority has considered 31.03.2021 as a date of default based on
the second restructuring approval dated 29.09.2020. We have already noted that
as per Section 10A of the Code, the period is specified is from 25.03.2020 to
24.03.2021. Thus, either of the dates i.e., 31.03.2018 or 31.03.2021 are clearly
out of purview of Section 10A of the Code. Thus, issue No. 3 answered
accordingly.
59. As regard, the pleading of the Appellant that it's the First Restructuring
Proposal dated 21.02.2020 which is valid and in existence since the statutory
restructuring proposal dated 29.09.2020 gave its reference in its approval letter
issued by the Respondent No. 2. In this connection, we note that the original
common loan agreement was entered into between the Corporate Debtor and the
Respondent No. 2 along with PFC on 19.06.2013 which was amended on
30.10.2015. Since, there were financial issues to meet its obligations by the
Corporate Debtor, first restructuring approval was issued on 21.02.2020, which
also failed and therefore the Respondent No. 2 along with PFC issued Second
Restructuring Approval on 29.09.2020. we have already discussed that the
Second Restructuring Approval letter contained specific pre-implementation
conditions and failure in fulfilling these stipulations by the Corporate Debtor
would automatically make such approval letter to be non existent. -36-
Comp. App. (AT) (Ins.) No. 81 of 2024
We are of the opinion that in such eventuality, the original common loan
agreement gets revived. In any case the plea of the Appellant that the original
common loan agreement as well as restructuring approval letter should not be
taken into account and only the first restructuring approval letter should be
taken into account and therefore a date of default according to first restructuring
approval letter should be the date which falls within the specific period of
Section 10A of the Code, is not convincing.
We could not find any sound reasoning as to why only the alleged default
under First Restructuring Proposal should be construed as the original date of
default, ignoring default under the novated Second Restructuring Approval or
the defaults under the Original Loan Agreement and therefore, we do not find
any merit in the pleadings of the Appellant about alleged default to fall within
the period specified under Section 10 A of the Code.
60. Another plea of the Appellant is that the payment made by the Corporate
Debtor to the Respondent No. 2 and PFC of Rs. 50 Crores in December, 2021
should be deemed revival of restructuring approval and also that the Appellant
had issued the letter dated 24.12.2021 in response to the Respondent No. 2 and
PFC letter dated 16.12.2021 which explicitly mentioned 'your receipt of the
payment of the said sum of Rs. 50 Crore will be deemed and constructed by us
to be an acceptance by you of the proposal contained herein'. -37-
Comp. App. (AT) (Ins.) No. 81 of 2024
We wonder whether such type of unilateral conditions by one party can
result into automatic binding force on other party and become agreement. We
have noted that there has been huge outstanding dues which have been flagged
by the Respondent No. 2 and PFC from time to time and the Respondent No. 2
and PFC have been issuing the demand letters to the Corporate Debtor. The
money remitted in pursuant to said demand letters cannot be deemed renewal of
restructuring approval, which could not survive due to failure on the part of the
Corporate Debtor in fulfilling its obligations regarding pre implementation
conditions.
61. It is worth emphasising that the Restructuring proposal is always offered
by the borrowers and accepted by the lenders on certain predetermined and pre-
specified terms and conditions including repayment, interest, tenure, haircut, if
any, etc., It cannot be the case of the Appellant that merely indicating self
imposed caveat while remitting the money in response to demand letter by the
lenders, such restructuring proposal should be treated as automatic
novation/renewal.
62. Significantly, we have noted from the submissions of the Respondent No.
2 that such plea of the Appellant regarding existence and continuation of default
under first restructuring proposal is wrong as the Corporate Debtor itself has
submitted in I.A. No. 1020/KB/2020 filed by the them before the Adjudicating
Authority in which the Corporate Debtor sought reliance solely on the Second -38- Comp. App. (AT) (Ins.) No. 81 of 2024
Restructuring Proposal submitting that the Corporate debtor was required to
make payment from 31.03.2021, without contending that there was any payment
obligations or default continuing from first restructuring proposal.
63. In view of preceding discussions, we do not find any force in the pleading
of the Appellant on this issue and therefore we answer issue No. 4 accordingly.
64. As regard, the pleading of the Appellant that since the loan was not
recalled by the Respondent No. 2 he is not entitled to initiate CIRP proceeding
under Section 7 of the Code. However, the Appellant has not given any legal
basis for the same with reference to the Code and therefore, do not merit
consideration. In fact, there is no such requirement under the Code to recall the
entire loan facilities before seeking initiation of corporate insolvency resolution
process under Section 7.
65. Now, we take up last issue raised by the Appellant regarding financial
viability of the Corporate Debtor based on which Section 7 application of the
Respondent No. 2 should have been rejected. We would like to recapture from
pleadings of the appellant that the Corporate Debtor has raised bills of
Rs. 916.95 Crores from WBSEDCL and during Financial Year 2022-23, the
Corporate Debtor earned EBITDA of Rs. 308 Crores and therefore, the
company was solvent. During averments, the Appellant also agreed to pay
outstanding amounts as per restructuring approvals around Rs. 103 Crores lying
in the credit of TRA account.
-39-
Comp. App. (AT) (Ins.) No. 81 of 2024
In contrast, we have noted that the total outstanding dues of Respondent
No. 2 and PFC as on 02.01.2024 was Rs. 3103.31 Crores. We also observe that
there has been continuous and repeated failure on the part of the Corporate
Debtor to meet its obligation in making payment of principals and interest as per
original common loan agreement and also failure to meet obligations as per first
and second revised Restructuring Approvals. In backdrop of all these
information, we do not find that so-called claim made by the Appellant about
viability of the Corporate Debtor has any legal or factual force to impact the
outcome of Section 7 application as contained in the Impugned Order.
We therefore, answer the Issue No. 5 accordingly.
66. Incidentally, we observe that the Appellant has taken the plea that the
Adjudicating Authority should not have gone in the details regarding the
execution part of the first restructuring approval by way of payment or default
since this was out of jurisdiction of the Adjudicating Authority and should have
been dealt by Civil Court. On the other hand, interestingly, we find the pleading
of the Appellant that the Adjudicating Authority although mentioned about the
First Restructuring Approval, however, did not discuss or adjudicated on the
same. We find this to be contrary.
Here, we will clarify that the Adjudicating Authority has all the rights and
authority to examine all such documents which has direct or indirect bearing on
the application filed under Section 7 of the Code.
-40-
Comp. App. (AT) (Ins.) No. 81 of 2024
In any case, such arguments of the Appellant has no impact on the
validity of the Impugned Order.
67. Thus, we do not find any substance in the Appeal and we further do not
find any error in the Impugned Order on any ground raised in the Appeal by the
Appellant.
68. In fine, the appeal fails and stand dismissed. No Costs. Interlocutory
Application(s), if any are Closed.
[Justice Rakesh Kumar Jain] Member (Judicial)
[Mr. Naresh Salecha] Member (Technical)
Sim/sr
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free