Nitant Verma vs Concept Horizon Infra Private Limited ...
- CitationCompany Appeal (AT) (Insolvency) No. 1335 of 2022
Ratio decidendi
The rule this decision rests on
The Appellate Tribunal's reasoning rests on the following principle: where, after admission of a Section 7 application and commencement of the corporate insolvency resolution process, the applicant allottees no longer wish to pursue the proceeding and the allottees, acting through an association, have entered into a conciliation agreement with the corporate debtor for completion of the project, and the construction is being funded by the promoter under the supervision of the Resolution Professional with necessary regulatory approvals obtained, there is no reason to continue the CIRP, and the Tribunal may close it while granting liberty to the requisite number of allottees to initiate a fresh Section 7 proceeding should a cause be made out.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
IN THE MATTER OF: Nitant Verma ...Appellant
Versus
Concept Horizon Infra Pvt. Ltd. & Ors. ...Respondents
Present: For Appellant: Mr. Abhijeet Sinha, Sr. Advocate with Ms. Nattasha Garg, Mr. Anubhav Dubey, Mr. Thakur Ankit, Advocates. For Respondents: Mr. Rishi Singh, Ms. Reema Advocates for R-1 (IRP).
With
Company Appeal (AT) (Insolvency) No. 1364 of 2022 & I.A. No. 4246, 4247 of 2022 & 172 of 2025
IN THE MATTER OF: Orizzonte Social Welfare Society ...Appellant
Versus
Concept Horizon Infra Pvt. Ltd. & Ors. ...Respondents
Present: For Appellant: Mr. Arup Sinha, Ms. Arham Tanvir, Mr. Uday Arora, Mr. Shivam Srivastava, Mr. Dhairya Verenkar, Advocates. For Respondents: Mr. Rishi Singh, Ms. Reema Advocates for R-1 (IRP).
ORDER
(Hybrid Mode)
10.07.2025: This Appeal has been filed by the Suspended Director of
the Corporate Debtor - M/s Concept Horizon Infra Pvt. Ltd. dated 14.10.2022
by which order NCLT, New Delhi Bench (Court-II) has admitted Section 7 2
application filed by Meena Porwal and 65 others claiming to be allottees of the
Corporate Debtor where their case was that they had advanced term loans of
varying amounts to the Corporate Debtor under identical Buyback
Agreements and assured returns, however, default had been committed by
the Corporate Debtor. The Adjudicating Authority after hearing the
Applicants and the Corporate Debtor, admitted Section 7 application and
appointed an IRP.
2. In the appeal notices were issued on 14.11.2022. Notices were served
on Respondent who appeared before the Tribunal on 25.01.2023 and prayed
for time to file Reply. Replay affidavit has been filed by Respondent Nos. 2, 3,
12, 20, 59, 61 and 63. Other Respondents having not appeared, this Court
on 02.05.2023 directed for substituted served by publication in newspapers.
Publication was already affected, which was noticed in the order dated
02.05.2023. Out of the Respondents who initiated Section 7 proceeding only
few have filed Reply Affidavit, as noted above. The IRP had appeared and filed
Status Report.
3. When the Appeal was taken on 12.07.2023, learned counsel for the
Appellant submitted that developer is ready to fund the construction as well
as take other steps as required to be taken for construction. On 12.07.2023
following order was passed:
"ORDER
12.07.2023: Learned Counsel for the Appellant submits that there is already an order passed on
Company Appeal (AT) (Ins.) No.1335 & 1364 of 2022 3
15.11.2022 in Comp. App. (AT)(Ins.) No. 1364/2022 that steps be taken to carry on construction with the co-operation of ex-management and ex-employees by the IRP.
2. Learned Counsel for IRP who is present in the Court submits that RERA registration has already been lapsed and that there are no funds available to carry out construction.
3. Learned Counsel for the Promoter Shri Abhijeet Sinha submits that Developers are ready to fund the construction as well as other steps required to be taken for start of construction.
4. Let IRP take appropriate steps to enable the construction to go on. The project being the Real Estate Project, completion of construction shall be beneficial to all.
Let appeal be listed after six weeks. The IRP may file the status Report by the next date.
List this appeal on 28.08.2023.
Stay on the constitution of CoC shall continue."
4. The IRP has filed Status Report, last being Status Report dated
24.02.2025. The Appellant has filed an Affidavit on 14.05.2025, where
necessary reports including NOC from Airport Authority, Fire Department,
Environment Department has been brought on the record.
5. Both the above appeals arise out of the order passed by the Adjudicating
Authority on Section 7 application filed by Meena Porwal and 65 others.
Company Appeal (AT) (Ins.) No.1335 & 1364 of 2022 4
Applicants' case in Section 7 application i.e. C.P. (IB) No. 1915 of 2019 was
that they have advanced term loans of varying amounts to the Corporate
Debtor under identical Buyback Agreements attached to the application and
to secure the repayment obligations under the Buyback Agreements, a
security interest was created in favour of each of the Applicant in the form of
contingent allotment. The Corporate Debtor has appeared before the
Adjudicating Authority and opposed submitting that the Applicants does not
fulfil the threshold as required under proviso to Section 7 Sub-section (1).
The Adjudicating Authority admitted the CIRP by order dated 14.10.2022.
6. Orizzonte Social Welfare Society has filed Company Appeal (AT) (Ins.)
No.1364 of 2022, which is society of homebuyers with respect to project
Orizzonte. In their appeal they have made following prayers:
"a. Set aside the Impugned Order dated 14.10.2022 passed by the Ld. National Company Law Tribunal, Bench II at Delhi in CP (IB) NO.62/CB/2021, titled as in CP (IB) No. 1915 of 2019, titled as "Smt. Meena Porwal & Ors. Vis. M/s. Concept Horizon Infra Private Limited";
b. Stay the operation and effect of the Impugned Order dated 14.10.2022 passed by the Ld. National Company Law Tribunal, Bench II at Delhi.in CP (IB) NO.62/CB/2021, titled as in CP (IB) No. 1915 of 2019, titled as "Smt. Meena Porwal & Ors. Vis. M/s. Concept Horizon Infra Private Limited";
Company Appeal (AT) (Ins.) No.1335 & 1364 of 2022 5
c. Dismiss the application filed by the Respondent Nos. 2 to 66 under Section 7 of the Code being CP(IB)- 1915/2019 for not complying with the second proviso to Section 7;
d. Pass any other order that this Tribunal may deem fit."
7. Thus, the Welfare Society of homebuyers is also aggrieved by the order
initiating CIRP. The learned counsel appearing for the Appellant in Company
Appeal (AT) (Ins.) No.1364 of 2022 submits that the members of the Society
wants that their units be handed over to them and they also support the
construction to be carried out in accordance with law after obtaining renewal
of registration and other necessary regulatory requirements. Learned counsel
for the Welfare Society submits that no construction has yet started.
8. We have heard Shri Abhijeet Sinha, learned senior counsel for the
Appellant in Company Appeal (AT) (Ins.) No.1335 of 2022, Shri Aurp Sinha,
learned counsel for the Appellant in Company Appeal (AT) (Ins.) No.1364 of
2022. We have also heard learned counsel appearing for the IRP as well as
learned counsel appearing for the Intervener - Homebuyers.
9. Learned counsel for the Appellant appearing in Company Appeal (AT)
(Ins.) No.1335 of 2022 submits that present is a case where the reverse CIRP
has been directed by order of this Tribunal directing the Promoter to fund the
CIRP. It is submitted that steps regarding construction are being taken and
necessary approval have also been obtained. It is further submitted that the
Respondents who had initiated the Section 7 proceeding now themselves are
Company Appeal (AT) (Ins.) No.1335 & 1364 of 2022 6
agreeable that construction be carried out by the Promoters and even the
Respondents who initiated Section 7 are not in favour of continuance of CIRP.
10. Learned counsel appearing for the Welfare Association submits that
some of the Applicants who initiated the CIRP process have now joined the
Association and Association has entered into a settlement with the Promoters
for carrying out the construction. It is submitted that the Association consists
of large number of homebuyers i.e. more than 259 members who are allottees
and application under Section 7 was initiated by 66 allottees only some of
which have already joined the Association. It is submitted that the Welfare
Association which has filed Company Appeal (AT) (Ins.) No.1364 of 2022 is
opposing the CIRP and prayed for setting aside CIRP since the Welfare
Association support the construction so that units be completed and handed
over to the allottees.
11. Learned counsel for the IRP submits that under the orders of this Court,
IRP has taken steps for commencement of construction. It is submitted that
necessary approvals and test reports have been obtained and Promoter have
also entered into agreement with the new developer who has to carry out
construction work. It is submitted that RERA registration has lapsed,
application for renewal of which has already been made and on account of
non-receiving of the renewal of registration, construction could not be
proceeded with.
Company Appeal (AT) (Ins.) No.1335 & 1364 of 2022 7
12. We have considered the submissions of learned counsel for the parties
and perused the record.
13. These two appeals have been filed challenging the order admitting
Section 7 application, which was filed by 66 Applicants who had claimed that
they had advanced term loan of various amounts to the Corporate Debtor
under identical Buyback Agreements and to secure the repayment obligations
under the Buyback Agreements security interest was created in form of
contingent allotment.
14. As noted above, the application under Section 7 filed by Meena Porwal
and 65 other applicants. Reply Affidavit has been filed by Meena Porwal and
certain other Respondents, as noted above. It is useful to notice the Reply
Affidavit which was filed by Meena Porwal, Respondent No.2 herein. A short
affidavit of only 4 paragraphs has been filed by Respondent No.2 which has
been styled as Reply Affidavit, which affidavit is as follows:
"AFFIDAVIT
I, Meena Porwal, D/o Sh. Surya Prakash Toshniwal, age 44 years, residing at 102/115, Silver Oaks Apartments, DLF Phase-1, Guru gram, Haryana- 122002, do hereby solemnly affirm and declare as under: -
1. I booked a unit having 460 sft. in the Project "ORIZZONTE" (herein after referred as "Project") being developed by M/s Concept Horizon Infra Pvt Ltd./Respondent No. 1 and the Respondent No. 1
Company Appeal (AT) (Ins.) No.1335 & 1364 of 2022 8
issued a Memorandum of Understanding (MOU) dated 15-07-2015.
2. I along with other persons who had booked a unit in the Project had filed a Petition under Section 7 of the Insolvency and Bankruptcy Code, 2016 ("IBC") bearing no. CP (IB)/1915/2019 against the Respondent No. I before the Ld. National Company Law Tribunal, Delhi.
3. That, during the pendency of aforesaid proceedings, several allottees of the Project formed an association and got it registered with a Registrar of Societies under the name "Orizzonte Social Welfare Society", ("Association") having registration no.: GBN/06315/2021-2022. It has come to my knowledge that the said association acting on behalf of all the Allottees / members, has entered into a Conciliation Agreement dated 07.07.2022 with the Respondent No. 1 agreeing to and allowing the Respondent No. 1 to complete construction of the Project. Further in terms of the said Conciliation Agreement, the Respondent No. l has undertaken to complete construction and handover units within three years from the date of its registration with the RERA.
4. In view of the above fundamental change in circumstances and in the larger interest of completion of the Project, I do not wish to pursue the proceedings under Section 7 of the IBC against the Respondent No. l any further."
Company Appeal (AT) (Ins.) No.1335 & 1364 of 2022 9
15. The above Affidavit clearly gives the case of the Respondent that several
allottees of the Project formed an association and got it registered under the
name Orizzonte Social Welfare Society. In Para 3 of the above affidavit, it has
been mentioned that Association has acted on behalf of all the Allottees /
members, and they have entered into a Conciliation Agreement dated
07.07.2022 with the Corporate Debtor agreeing to allow the Corporate Debtor
to complete construction of the Project. The above stand taken by the
Respondents, who had initiated the proceeding clearly indicate that the
Respondents who were applicant before the Adjudicating Authority are also
in favour of construction to be carried out by the Corporate Debtor and
allottees' Welfare Society has filed Appeal praying for same relief i.e. closure
of CIRP. Although, Affidavit has been filed by few of the Respondents, as
noted above, but at the time of hearing none appeared for the Respondents to
oppose the appeals.
16. Construction by the fund of Promoter under the supervision of IRP has
already been directed by this Tribunal, as noted above. A detailed Status
Report and Affidavit have been brought on record which indicate that various
necessary steps taken towards commencement of construction and obtaining
no objection from various authorities. NOC dated 06.05.2025 from Greater
Noida Authority has been brought on the record.
17. In facts of the case and submissions as noted above, we see no reason
to continue the CIRP any further. The construction of the project may
continue with the funding by the Promoter as submitted before us. The CIRP
Company Appeal (AT) (Ins.) No.1335 & 1364 of 2022 10
is closed. We, however, grant liberty to the requisite number of allottees to
initiate any fresh proceeding under Section 7, if any cause for initiating the
proceeding is made out. IRP shall be paid his fees and reasonable expenses
incurred in the CIRP process so far by the Corporate Debtor. With the
aforesaid, both the appeals are disposed of.
[Justice Ashok Bhushan] Chairperson
[Barun Mitra] Member (Technical) Archana/nn
Company Appeal (AT) (Ins.) No.1335 & 1364 of 2022
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free