Navkar Builders Limited vs Niyojit Infratech Private Limited
- CitationCompany Appeal (AT) (Insolvency) No. 800 of 2022
Ratio decidendi
The rule this decision rests on
Where the corporate debtor has disputed the operational creditor's claim, supported by a notice invoking an arbitration clause issued before the operational creditor's demand notice, and where the disputed claim rests on the absence of a completion certificate for the work, a pre-existing dispute exists between the parties and an application under Section 9 cannot be admitted on that claim. Where the parties' contract contains an arbitration clause and the dispute over the claimed amount falls within it, the operational creditor's remedy lies in arbitration and not in insolvency proceedings.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
NATIONAL COMPANY LAW APPELLATE TRIBUNAL, PRINCIPAL BENCH, NEW DELHI Company Appeal (AT) (Insolvency) No. 800 of 2022 IN THE MATTER OF: Navkar Urbanstructure Ltd. ...Appellant Versus Niyojit Infratech Pvt. Ltd. ...Respondent Present: For Appellant: Mr. Pavan Godiwala, Mr. M.S. Vishnu Sankar, Advocates For Respondent: ORDER
22.08.2022: Heard Learned Counsel for the Appellant.
This appeal has been filed by the Appellant ('Operational Creditor') against
the order dated 28.04.2022 passed by the Adjudicating Authority by which
application filed under Section 9 by the Appellant has been rejected.
2. The 'Corporate Debtor' received a Work Order from one M/s. 'Annu Infra
Construct India Pvt. Ltd.' for trenching, ducting, backfilling supply and
installation of manholes etc. in the state of Bihar. The 'Corporate Debtor'
assigned part of the Work to Appellant by agreement dated 30.11.2018.
3. The notice dated 12.01.2021 u/s 8 of the Code, (dispatched on
25.01.2021) was issued by the Appellant to the 'Corporate Debtor demanding
amount due and payable on account of service provided to the 'Corporate Debtor'
by the 'Operational Creditor'. The Corporate Debtor has issued notice dated
22.01.2021 invoking Arbitration Clause under the agreement. Notice u/s 8 was
issued by the Operational Creditor on 25.01.2021 to the 'Corporate Debtor'
which was replied by the Corporate Debtor vide reply dated 09.02.2021.
Company Appeal (AT) (Insolvency) No. 800 of 2022 1
4. In the reply notice, the claim of the Appellant was denied stating that no
money could be claimed by Operational Creditor before obtaining the Completion
Certificate for the work stated in Letter of Intent (LOI). The reply also referred to
the notice dated 22.01.2021 by which Operational Creditor was informed about
the Arbitration Clause in LOI dated 30.11.2018.
5. Section 9 application was filed by the Operational Creditor claiming an
amount of Rs. 8,29,54,798/-. The Corporate Debtor filed a detailed reply to
section 9 application.
6. After hearing the parties, by impugned order dated 28.04.2022 the
Adjudicating Authority dismissed Section 9 application noticing that Section 8
notice was posted by the Operational Creditor on 25.01.2021 whereas Corporate
Debtor vide notice dated 25.01.2021 has invoked Arbitration Clause.
7. The Appellant challenging the order contended that the Appellant was not
present only on the date when the order was passed whereas he appeared on
earlier dates. He submits that he could not file any rejoinder to the reply filed
by the Corporate Debtor due to certain valid reason which have not been taken
note of by the Adjudicating Authority. He further submits that notice invoking
arbitration was received after Section 8 notice was issued.
8. We have considered the submissions of the Appellant and perused the
record.
9. In para 13,17 and 18 of the reply, following averments have been
specifically made:-
Company Appeal (AT) (Insolvency) No. 800 of 2022 2 "13. It is stated that the petitioner was
supposed to complete the work as aforesaid
by March 31,2019. However, the same was
incomplete and whatever work was done
was not satisfactory of the Authorities and
therefore for the same no completion
certificate and/or NOC was issued by the
competent Authority. The Petitioner at all
material points of time knew about Payment
Clause of both the Agreements.
17. Pursuant thereto, the Corporate
Debtor had issued a notice inviting the
arbitration for adjudication of the alleged
claim made by the petitioner and for
adjudication of the damage suffered to the
Corporate Debtor due to non completion of
work in accordance with the Letter of Intent or
Work Order done by the petitioner. A copy of
letter send on January 22, 2021 is annexed
and marked as annexure 'H' at Pg. 61 of the
said Petition.
Company Appeal (AT) (Insolvency) No. 800 of 2022 3
18. It is noted that the said purported
notice under Section 8 of the Insolvency and
Bankruptcy Code, 2016 was received after
issuance of the arbitration notice and the same
was replied to by the Corporate Debtor vie its
letter dated February 9, 2021. A copy of the
reply dated February 9, 2021 is annexed hereto
and marked 'C'. It is relevant to mention herein
that both alleged that the notice of invocation
annexed and marked as annexure 'H' at Pg.61
of the said Petition is a reply to the purported
notice under Section 8 of the Insolvency &
Bankruptcy Code, 2016."
10. The Corporate Debtor in reply to Section 8 notice as well as in reply to
Section 9 application has categorically pleaded that there is Arbitration Clause
in the contract between the parties. Notice dated 22.01.2022 was issued by the
Corporate Debtor Invoking Arbitration Clause and the Operational Creditor
issued notice dated 12.01.2021 only on 25.01.2021 when it demanded amount
from the Corporate Debtor.
11. The Corporate Debtor in its reply has clearly stated that no amount can
be claimed by the Appellant to be due on the Corporate Debtor since no
Completion Certificate regarding the work of the Appellant was ever issued.
Company Appeal (AT) (Insolvency) No. 800 of 2022 4 When Completion Certificate regarding Work Order was never issued, the
amount claimed by the Appellant is disputed and the Adjudicating Authority has
rightly taken the view that in view of the pre-existing dispute between the parties
the application u/s 9 cannot be admitted.
12. There being Arbitration Clause in the agreement between the parties. The
Appellant is always at liberty to pursue his claim in the Arbitration.
13. We are satisfied that there is no good ground to entertain this appeal.
There is no merit in the appeal. The appeal is dismissed.
[Justice Ashok Bhushan] Chairperson
[Justice M.Satyanarayana Murthy] Member (Judicial)
[Mr. Barun Mitra] Member (Technical)
Shashi/nn
Company Appeal (AT) (Insolvency) No. 800 of 2022 5
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free