Mrs. Reeta Dhawan vs Atul Kumar Kansal Resolution ...
- CitationComp. App. (AT) (Ins) No. 1017 of 2023
Ratio decidendi
The rule this decision rests on
An order of the Adjudicating Authority that does not record findings on each prayer made in an application, and that confines itself to the claims admitted by the resolution professional, is a non-speaking order and is liable to be set aside; the Adjudicating Authority is bound to decide an application by recording reasons addressing each prayer raised in it, having regard to the pleadings and the evidence on record.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
Comp. App. (AT) (Ins) No. 1017 of 2023 & I.A. No. 3486, 3487, 3488 of 2023, 1709 of 2024
IN THE MATTER OF: Mrs. Reeta Dhawan ...Appellant
Versus
Atul Kumar Kansal Resolution Professional Universal Buildwell Pvt. Ltd. ...Respondent Present: For Appellants : Mr. Bharat Gupta, Adv. For Respondent : Mr. Swapnil Gupta, Vaibhav Mendiratta, Abhinav Mishra, Adv. for RP
ORDER
Per: Justice Rakesh Kumar Jain (Oral)
15.05.2024: This appeal is directed against the order dated
23.05.2023 by which an application bearing I.A. No. 2008 of 2023
filed by the Appellant has been dismissed by the Adjudicating
Authority (National Company Law Tribunal, New Delhi Bench).
2. The grievance of the Appellant is that the impugned order is
totally non-speaking as it has not dealt with the various prayers
made by the Appellant in the application and has confined its order
with the claim which has been admitted by the RP and has also
made a reference to the email dated 15.02.2023 which has also
been sent by the RP to the Appellant.
3. Counsel for the Appellant has drawn our attention to the
contents of the application bearing I.A. No. 2008 of 2023 much
less to the prayer which read as under:-
"The RP/CoC for effective and adequate processing of the claim of the Applicant/Financial Creditor dated 01.06.2020 lodged with the RP and in the light of the details contained in para no. 8 above and after due consideration of documents annexed therewith."
4. Since, the details of the reliefs are mentioned in Para 8 of the
application, therefore, the said paras are also reproduced as
under:-
"8. That the applicant/Financial Creditor had submitted their claim to the resolution professional (in short RP) and the claims are under: -
CLAIM NO. 1 i. Space rentals w.e.f November 2011 till January 2014 @ 59.80 per sqft x 670 sqft = Rs 40,066/- x 27 (Months) Rs 10,81,782/- (Rs Ten Lakhs Eighty-One Thousand, Seven Hundred Eighty-Two only)- Till January 31st 2014 ii. Space rentals w.e.f 1st February 2014 till January 31st 2017 @ 68.77 per sqft x 670 sqft (15% escalation) = Rs 16,58,986/ - Rs 46076 x 36 (Months) = Rs 16,58,736/-
(Rs Sixteen Lakhs, Fifty-Eight Thousand, Nine Hundred and Eighty-Six only)- Till January 31st 2017. iii. Space rentals w.e.f 1 st February 2017 till January 31st 2020 @ Rs 79.08 per sqft x 670 sqft (15% escalation) = Rs 19,07, 532/- 52,987/ Rs - x36 (Months) Rs 19,07,532/- (Rs Nineteen Lakhs, Seven Thousand, Five Hundred and Thirty-Two only)- Till January 31st 2020. iv. Space rentals w.e.f 1st February 2020 till 31st May 2020 @ Rs 90.942 per sqft x 670 sqft (15% escalation) = Rs 60,931x4= Rs 62 2,43,724/ - Rs 90.942/- X 4 (Months) = Rs 2,43,724/- (Rs Two Lakhs, Forty-Three Thousand, Seven Hundred and Twenty-Four only)- Till May 31st 2020.
v. Rs 48,92,004/- (Rest Forty-Eight Lakhs, Ninety-Two Thousand and four only) is payable towards space rentals as on 31.05.2020. The further payment shall be due till actual handing over of flat no. 218 with due registration thereof.
vi. The space rentals shall be continued to be payable till the actual handing over of the flat to the FC.
CLAIM NO.2 i. Plus, overdue payment w.e.f April 2008 till July 2008 @ Rs 52 per month, i.e Rs 34,840/ -x 4(Months) =Rs 1,39,360/-.
ii. Plus Outstanding rentals differentials for Rs 21 per sqft for February-March 2008 totaling to =Rs. 28,140/-Plus Outstanding for August 1st 2008 till 3rd August 2008 @ Rs 52 per sqft 1161x3 =Rs 3483/-
iii. Amount paid by FC to CD for alleged administrative charges, stamp duty and registration charges for conveyance deed =Rs 1,01,0007- Total claim under this head:
Rs 2,71,983/- (Rs Two Lakhs, Seventy-One Thousand Nine Hundred and Eighty-Three only)
CLAIM No.3 i. Actual handing over of possession of flat no. 237 and executing the registered sale deed of the flat no. 218 in the Universal Trade Tower to the FC or in lieu thereof Rs 1,00,00,000/- (Rs One Crore only) which is the market value of the flat.
CLAIM NO. 4 i. Since there is various breaches and material breaches of the terms and conditions of space buyer agreement therefore in terms of the undertaking, the CD is liable to pay the penalty to the petitioner to the extent of 1.70 times of the principal amount which comes at =Rs 17,85,000/-
CLAIM NO. 5 House Taxes The amount is payable as the same was agreed between the parties and as the lease agreement of the flat of FC was executed by CD in favour of the entity (their own sister concerns) and as per clause 5 of Lease agreement dated 18th July 2007 and as per extended lease dated 24.01.2011 Rs 1,03,000/ - paid by FC to MCG on 31.03.2018 Rs 4382/- paid by FC to MCG on 31.03.2018 Rs 7236/- on 03.07.2019 Total: Rs l,14,618/-(Receipts as proof enclosed)
CLAIM No. 6 Interest @18% per annum on the overdue amount till realization of the same"
5. Counsel for the Appellant has submitted that the
Adjudicating Authority has not looked into the claims of the
appellant in regard to the rent, conveyance, house taxes etc. and
has only confined itself to the claim which has been accepted by
the RP and also to the email dated 15.02.2023 which too was sent
by the RP denying the claim of the Appellant in regard to the rent,
whereas according to the Appellant, evidence has been brought on record to show that not only the Appellant is entitled to rent in
terms of Builder Buyer Agreement but also there are authorities to
cite that the RP has the competence to register the conveyance
deed also.
6. On the other hand, Counsel appearing on behalf of the RP
has candidly submitted that though the Appellant has made
various prayers in para 8 of the application but all have taken into
consideration by the Adjudicating Authority while passing the
impugned order though it has not been mentioned in so many
words.
7. We have heard Counsel for the parties and after perusal of
the record, are of the considered opinion that this matter requires
a relook by the Adjudicating Authority for the purpose of recording
a finding on each prayers sought in the application after taking
into consideration the pleadings as well as the evidence brought
on record. As according to us, the impugned order is totally non-
speaking.
8. In view thereof, the appeal succeeds and the impugned order
is hereby set aside. I.A. No. 2008 of 2023 is hereby restored and
the matter is remanded back to the Adjudicating Authority to decide the application again by recording reasons while dealing
with the prayers made in the application.
9. The parties are directed to appear before the concerned
Adjudicating Authority on 10th June, 2024.
10. The Adjudicating Authority who was seized of the matter is
requested to decide the matter as early as possible but preferably
within two months from the date of appearance of the parties. It is
made clear that we have not made any observation regarding merit
of the case and all the contentions are kept open for the
Adjudicating Authority to decide.
[Justice Rakesh Kumar Jain] Member (Judicial)
[Mr. Indevar Pandey] Member (Technical)
Sheetal/Ravi
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free