Mr. V. Nagarajan Resolution ... vs M/S. Meenakshi Energy Ltd
- CitationCompany Appeal (AT) (Insolvency) No. 42 of 2018
Ratio decidendi
The rule this decision rests on
The handing over or showing of documents by a corporate debtor to a party in arbitral proceedings does not, of itself, amount to a violation of the moratorium order under the Insolvency and Bankruptcy Code, 2016.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
Mr. V. Nagarajan Resolution Professional in respect of M/s. Cethar Ltd. ...Appellant
Vs.
M/s. Meenakshi Energy Ltd. ...Respondent
Present: For Appellant: - Mr. R. Subramanian, Advocate
For Respondent:- Mr. Arijit Mazumdar and Mr. Rishav Banerjee, Advocates.
ORDER
01.02.2018 ─ This appeal has been preferred by the 'Resolution
Professional' of M/s Cethar Limited against the order dated 18th
January, 2018 passed by the Adjudicating Authority (National Company
Law Tribunal), Single Bench, Chennai, in Company Application No.
71/IB/2017 in Company Petition No. 511/IB/2017, which reads as
follows: -
"ORDER
Counsel for Applicant/RP filed CA/71/IB/17 in
CP/511/17 raising an issue in the Application that
has been filed by the Respondent before the Arbitral
Tribunal for production of the certificates on
completion of the project. The Arbitral Tribunal vide
Contd/-.................
-2-
its order dated 09.12.2017 has given direction to the
Applicant to produce the certificates in relation to the
completion of the project in a sealed cover. It has been
submitted by the Counsel for the Applicant that the
Applicant is under the CIR process and any
application cannot be filed before any Court in the
light of the provisions of section 14 read with 60 of
the IBC, 2016, because the Applicant (Corporate
Debtor) will not be able to exercise the 'right of unpaid
vendor lien'.
Counsel for the Respondent submitted that the
Arbitral Tribunal has passed a detailed order. The
Arbitral Tribunal is also conscious of the fact that in
case the Corporate Debtor departs with the
certificates of the completion of the Project, there may
be financial implications. The Arbitral Tribunal while
passing the order observed that "an interim direction
is to avoid any controversy on the aspect, whether all
the certificates obtained and in the custody of the
claimant are made available. Further, the question
whether any condition regarding the payment of the
Company Appeal (AT) (Insolvency) No. 42 of 2018 -3-
amounts said to be due to the claimant, after the
initiation of Arbitration Proceedings, has to be
imposed, may have also to be considered". In view of
these observations, the Applicant may raise the issue
before the Arbitral Tribunal for consideration.
Accordingly, the Application stands disposed of."
2. We have heard learned counsel appearing on behalf of the
'Insolvency Resolution Professional' and Mr. Arijit Mazumdar, Advocate
who has appeared on behalf of the Respondent.
3. Having heard learned counsel for the parties, we are of the opinion
that the handing over or showing any document to any party will not
amount to violation of order of 'Moratorium'.
4. In view of such observation, learned counsel for the 'Resolution
Professional' sought permission to withdraw this appeal. Prayer is
allowed. The appeal is dismissed as withdrawn.
(Justice S.J. Mukhopadhaya) Chairperson
(Justice Bansi Lal Bhat) Member(Judicial) Ar/uk
Company Appeal (AT) (Insolvency) No. 42 of 2018
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.