Miss Lucy
← All judgments

Mohit Arora vs Manish Aneja & Ors

National Company Law Appellate Tribunal29 August 2025Ashok Bhushan

Ratio decidendi

The rule this decision rests on

Where a flat buyer's agreement fixes a period for handing over possession, with the qualifiers of force majeure, intervention of statutory authorities, receipt of an occupation certificate and timely payment by allottees, those qualifiers are to be read harmoniously with the operative possession clause, and an occupation certificate is not a precondition whose absence suspends the developer's obligation to hand over possession where the developer has not completed construction, since the occupation certificate can only issue after completion, so a developer cannot shield itself behind its non-receipt. Default by some allottees in paying instalments does not defeat a Section 7 application by allottees who have themselves paid their consideration and against whom the corporate debtor has defaulted in handing over possession, since it is not necessary that every applicant prove default against itself, and any allottee who is a financial creditor may join an application founded on default to any financial creditor. Non-handing over of possession beyond the contractual period, where the project remains incomplete, is a continuing default, and a Section 7 application founded on such default is rightly admitted, the corporate debtor not being entitled to benefit from its own inaction in completing the project. Reverse insolvency resolution under which the promoter completes the project is not to be directed where the allottees who have initiated the Section 7 proceedings oppose it and the project remains incomplete, the Tribunal declining such a direction in those circumstances and leaving the corporate debtor to be resolved under the CIRP process.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

NATIONAL COMPANY LAW APPELLATE TRIBUNAL,PRINCIPAL BENCH, NEW DELHICompany Appeal (AT) (Insolvency) No. 1163 of 2024

[Arising out of Order dated 04.06.2024 passed by the Adjudicating Authority (National Company Law Tribunal), Court-V, New Delhi Bench in C.P. IB (IBC) No.657/ND/2021]

IN THE MATTER OF: Mohit Arora (Suspended Director of Revital Reality Pvt. Ltd.) ...Appellant

Versus

Manish Aneja & Ors. ...Respondents

Present: For Appellant: Mr. Abhijeet Sinha, Sr. Advocate with Mr. Ishan Dewan, Mr. V. Siddharth and Mr. Shreyans Jain, Advocates. For Respondents: Mr. Rishabh Jain, Advocate for RP. Ms. Pooja M. Saigal, Sr. Advocate with Mr. Palash S. Singhai, Mr. S. Sharma, Ms. Riddhi Jain and Mr. Nivesh Dixit, Advocates for R-1 to R-165. Ms. Vibha Makhija, Sr. Advocate with Mr. Nikhil Kumar Jha, Advocates for Applicant in I.A. No.7226/2024 and I.A. No.2767/2025.

JUDGMENT

Ashok Bhushan, J.

This Appeal by Suspended Director of the Corporate Debtor - M/s

Revital Reality Pvt. Ltd. has been filed challenging the order dated

04.06.2024 passed by the Adjudicating Authority (National Company Law

Tribunal), Court-V, New Delhi Bench admitting Section 7 application filed by

Cont'd.../ 2

Respondent Nos. 1 to 165, who had filed application under Section7 for

initiating CIRP against the Corporate Debtor. Aggrieved by the order dated

04.06.2024, this appeal has been filed.

2. Brief facts necessary to be noticed for deciding this appeal are:

2.1 State Government Haryana vide Town and Country Planning

Department Notification dated 19.08.2013 issued "Affordable Housing

Policy 2013". Under the said policy, the Corporate Debtor was

granted license by the Director General, Town and Country Planning,

Haryana, Chandigarh, on 19.12.2014 for construction and

development of an affordable group housing colony.

2.2 Building plan under the name and sign of 'Basera' was

launched by the Corporate Debtor. In the project, allotments were

made to several allottees. Project consisted of 15 towers. Units were

booked from 2014 to 2017. In the project situated at Sector 79B

Manesar Urban Complex, Gurugram, Haryana, Respondent Nos.1 to

165 were allotted different units and allotment letters were issued in

favour of the Respondents and Flat Buyer's Agreement was entered

between the Corporate Debtor and Respondent No.3, Mr. Ajay

Vashnavi on 02.06.2016, in favour of Respondent No.2, Mr. Ankur

Khetan Flat Buyer's Agreement was executed on 10.12.2015 and on

12.05.2016 in favour of Mr. Vishal Kumar. Similarly, Flat Buyer's

Agreements were executed in favour of other Respondents. As per the

Company Appeal (AT) (Insolvency) No.1163 of 2024 3

Flat Buyer's Agreement, the Corporate Debtor represented to the

Allottees that possession of the units will be handed over in four years

from date of approval of building plan and date of environmental

clearance whichever is later. In the present case, environmental

clearance was granted on 22.01.2016. The Respondents herein made

payments towards the consideration. Respondents had paid about

90% to 95% of the sale consideration and some of the Respondents

have paid their full sale consideration.

2.3 A Section 7 application was filed by 172 unitholders on

13.10.2021 against the Corporate Debtor seeking initiation of CIRP.

The applications pleaded that Principal Amount due to the Financial

Creditor is Rs.31,22,62,342/-. It was pleaded in the application that

certain letters of allotment and Flat Buyer's Agreement of three flat

buyers was annexed with the Section 7 application. Referring to

Clause 3.1 and 3.5 of the Flat Buyer's Agreement, it was pleaded that

the Corporate Debtor was to handover the possession by 22.01.2020.

Several emails were sent to the Financial Creditor enquiring about the

progress and status of construction, to which replies were given by the

Corporate Debtor and Corporate Debtor committed default, having

committed breach of the agreement with the flat buyers. In the

Section 7 application, date of default has been mentioned as

22.01.2020.

Company Appeal (AT) (Insolvency) No.1163 of 2024 4

2.4 In Section 7 application reply was filed by the Corporate Debtor.

Corporate Debtor in addition to reply filed an affidavit dated

22.08.2022 before the Adjudicating Authority bringing on record the

status of project. It was pleaded that out of total 15 towers having

residential units, Tower 1 and 2 are fully complete. Details of status

of the construction was mentioned in the Affidavit. A settlement

proposal was also offered to the homebuyers and applicants.

2.5 The Adjudicating Authority passed various orders in the Section

7 proceeding asking the Financial Creditors to take instructions on

the settlement proposal of the Corporate Debtor. The Financial

Creditors, however, informed the Adjudicating Authority that proposal

submitted by the Corporate Debtor is not acceptable. The

Adjudicating Authority proceeded to hear the parties and by the

impugned order has admitted Section 7 application. The Adjudicating

Authority, in the impugned order held that the Corporate Debtor

having not offered possession to the Respondents - unit holders

within 48 months from 22.01.2016, default has been committed. The

arguments raised on behalf of the Corporate Debtor that unless

Occupation Certificate is received there is no obligation to offer

possession was considered and rejected. The Corporate Debtor also

raised submission that application is barred by Section 10A of the I&B

Code, which too was considered and not accepted. The Adjudicating

Authority admitted Section 7 application and appointed Shri Gaurav

Company Appeal (AT) (Insolvency) No.1163 of 2024 5

Katiyan as Resolution Professional. Aggrieved by order admitting

Section 7 application, the Suspended Director of the Corporate Debtor

has filed this appeal.

2.6 The appeal came to be heard by this Tribunal on 12.06.2024,

thereafter on 02.07.2024. On 02.07.2024, following interim order was

passed:

"In the meantime, CoC may proceed to hold its meeting, however, no Form G shall be issued till the next date."

Parties completed their pleadings and parties were heard on

06.08.2025.

3. We have heard Shri Abhijeet Sinha, learned senior counsel for the

Appellant, Ms. Pooja M. Saigal, learned senior counsel appearing for the

Respondents - Financial Creditors. Ms. Vibha Makhija, learned senior

counsel has appeared for the Applicant in I.A. No. 7226/2024, Mr. Nikhil

Kumar Jha has appeared for Applicant in I.A. No. 2767/2025 and Mr.

Rishabh Jain has appeared for the Resolution Professional.

4. Shri Abhijeet Sinha, learned counsel for the Appellant in support of

the Appeal submits that the Adjudicating Authority erred in admitting

Section 7 application. There was no default on the part of the Corporate

Debtor as per the agreement between the parties. Learned counsel for the

Appellant referred to Clause 3.1 and 3.5 of the Flat Buyer's Agreement and

Company Appeal (AT) (Insolvency) No.1163 of 2024 6

submitted that offer of possession within four years was subject to force

majeure circumstances, intervention of statutory authorities, requirement of

Occupation Certificate and allottees making timely payment of instalments.

It is submitted that the present is a case where under the orders of the

statutory authorities including orders of the Court and Tribunal, for 89 days

there was stay on the construction. It is submitted that the possession

could have been offered to the allottees only after receipt of the Occupation

Certificate. No Occupation Certificate having yet been received, there can be

no offer of possession. The Adjudicating Authority had not appropriately

considered the Clause 3.1 and 3.5 of the Flat Buyer's Agreement. It is

submitted that the Adjudicating Authority has unduly relied on the

judgment of Hon'ble Supreme Court in Ireo Grace Realtech Pvt. Ltd. vs.

Abhishek Khanna & Ors., 2021 (2) SCR 1, which judgment is in context

of Consumer Protection Act and was on the deficiency of service, which is a

concept applicable to Consumer Protection Act and not to the I&B Code. It

is submitted that the agreement between the parties have to be read as it is

and allottees for discrepancy of service and for other reliefs are free to take

proceedings before the State RERA Authorities and other Authorities but

unless there is default on part of the Corporate Debtor proceedings for

insolvency commencement cannot be initiated against the Corporate Debtor.

Only a handful of allottees (initially there were 172 Applicants) have filed the

application for putting the Company into insolvency whereas there are 976

units and majority of the homebuyers are not in favour of the insolvency. It

is submitted that in the insolvency of a real estate project seldom there is

Company Appeal (AT) (Insolvency) No.1163 of 2024 7

resolution and completion of construction. It is submitted that the

timeframe for offering possession was subject to timely payment of

instalment by the unitholders. Before the Adjudicating Authority, the

Corporate Debtor has brought on record details of outstanding amount of

various unitholders who were in default and payment of their consideration.

Learned counsel for the Appellant has referred to the details of 56 allottees

amongst the Applicants who has initiated the Section 7 application, where

according to the Appellant, there are huge amount of default. It is

submitted that dues with reference to 27 unitholders are more than Rs.1

Lakh. It is submitted that timely payment by the allottees was relevant

consideration for determining default on the part of the Corporate Debtor.

The Adjudicating Authority has not adverted to the said pleading, thus, the

conclusion of the Adjudicating Authority that there is default in not offering

possession by the Corporate Debtor is not in accordance with law. It is

submitted that the period of 89 days counted from 22.01.2020, it falls

within the prohibited period under Section 10A, hence, the Section 7

application ought not to have been entertained. Corporate Debtor has

placed orders passed by Court, Tribunal and Statutory Authority whereby

construction was halted for 89 days. Learned counsel, however, submitted

that Appellant proceed on assumption that threshold as allowed to allottees

is fulfilled and no arguments are being addressed on said issue, although

several of the Respondents who has initiated proceeding under Section 7

were themselves in default. It is submitted that the Appellant has filed an

application IA No.6177 of 2024 seeking direction of reverse insolvency

Company Appeal (AT) (Insolvency) No.1163 of 2024 8

process under which the Appellant can complete the construction under the

supervision of the IRP. It is submitted that the Appellant has given proposal

to the allottees for construction and most of the allottees agreed and given

consent letters in favour of the Corporate Debtor.

5. Ms. Pooja M. Saigal, learned senior counsel appearing for the

Respondents - allottees refuting the submission of learned counsel for the

Appellant submits that environmental clearance certificate having been

issued on 22.01.2016, four years' period came to an end and default was

committed by the Corporate Debtor on 22.01.2020. The Corporate Debtor

has failed to procure Occupation Certificate till date. The submission of the

Appellant that unless Occupation Certificate is received Corporate Debtor

cannot be said to have committed any default, if the interpretation of the

Appellant is accepted of various clauses of Flat Buyer's Agreement as

contended, there will never be default on part of the Corporate Debtor. It is

submitted that the application was filed by the Applicants in 2021 and as on

date about four years have elapsed, however, till date neither construction

has been completed nor possession has been offered. It is submitted that

before the Adjudicating Authority, the Corporate Debtor itself has filed an

affidavit which indicate that all towers except 1 and 2 Tower were not

constructed, even according to the Appellant's case. The project under

which the allottees were allotted units was an affordable group housing

project in which carpet area of flat is 310 sq. ft. onwards. Most of the

allottees who were allotted flats have taken financial assistance for making

Company Appeal (AT) (Insolvency) No.1163 of 2024 9

payment of the consideration and for last more than five years they are

waiting for their units to be handed over. The project is not in habitable

condition. The Corporate Debtor has neglected the units and failed to make

endeavours to complete the construction in order to qualify enough to

obtain the Occupation Certificate. The possession of the units is still not

delivered, even after more than five years from 22.01.2020 on which date

possession was to be offered to the allottees. Even if, allowance of 89 days is

granted to the Appellant during which construction was halted and given a

grace period of further six months, the default is continuing and when

default is continuing in nature, Appellant cannot be heard to say that since

there was no default on 22.01.2020, application under Section 7 deserve to

be rejected. The threshold of the allottees was fully complete, even after

settlement with few allottees, there were 142 members who fulfil the

minimum threshold. The submission of the Appellant that allottees have

defaulted in payment of their instalment, it is submitted that some of the

unitholders has paid 100% of their consideration and most of them have

paid 90-95% of their consideration. Unitholders have also paid amounts to

the Corporate Debtor as per the demand letters issued from time to time. It

is submitted that even as on date construction is not complete and project is

standing stand still. It is submitted that for resolution of the Corporate

Debtor insolvency process is eminent and the unitholders can get their units

through mechanism as provided in the I&B Code. The Adjudicating

Authority after considering all aspects of the matter has correctly admitted

the Section 7 application. The submission of the Appellant is wrong that

Company Appeal (AT) (Insolvency) No.1163 of 2024 10

several hundred people are already offered possession. There is no

Occupation Certificate, it cannot be accepted that units are complete to be

offered.

6. Ms. Vibha Makhija, learned senior counsel submits that approx. 200

homebuyers have given their consent letter, who are Applicant in IA No.7226

of 2024, accepting the resolution plan given by the Promoters. It is

submitted by learned counsel that homebuyers are interested in completion

of project and insolvency of the Corporate Debtor shall cause hardship for

the unitholders to get possession of their units. The suspended

management has provided a plan in which the construction shall be

completed within stipulated time under supervision of a committee having

homebuyers as members and Resolution Professional. It is submitted that

on the application filed by handful of homebuyers the Corporate Debtor

cannot be put under insolvency.

7. Another IA No.2767 of 2025 has been filed by one Pawan Kumar

Kaushik, a unitholder who has also referred to the resolution plan

submitted by the Promoters. It is submitted that before the Adjudicating

Authority also 180 homebuyers have filed an application for deferment. The

plan provided by the suspended management need to be accepted in which

their 70% amount will be used for construction.

8. We have considered the submissions of learned counsel for the parties

and perused the record.

Company Appeal (AT) (Insolvency) No.1163 of 2024 11

9. We have already noticed above that project in question i.e. 'Basera' is

a project under Affordable Housing Scheme floated by Government of

Haryana in 2013. Licences were granted to the Corporate Debtor in the year

2014 and the building plan approved. As per the scheme of the Government

of Haryana, development of colony under Affordable Housing Scheme was to

be done so that unitholders will get small units of 310 sq ft and more. All

the applicants were allotted different units in different towers. There is no

dispute between the parties that the four years' period under which

construction was to be completed and units to be handed over to the unit

holders commenced on 22.01.2016 on which date environmental clearance

was granted. As noted above, issue that the Applicants (Respondent herein)

who had filed application under Section 7 fulfil the necessary threshold

being more than 100 allottees is not being questioned. We, thus, need to

proceed on the premise that Section 7 application was filed by the

Applicants who fulfil the threshold as provided under Section 7 proviso.

10. The submission which has been pressed by learned counsel for the

Appellant is that there was no default on the part of the Corporate Debtor so

as to initiate insolvency resolution process against the Corporate Debtor.

The submission which has been pressed by learned counsel for the

Appellant is that as per the Flat Buyer's Agreement entered between the

Corporate Debtor and the unitholders period of 48 months under which the

Corporate Debtor has to offer the possession was subject to four conditions

i.e. (i) force majeure circumstances; (ii) intervention of statutory authorities;

Company Appeal (AT) (Insolvency) No.1163 of 2024 12

(iii) requirement of Occupation Certificate; and (iv) completion of obligation

by allottees including timely payment of their instalments. Submission of

learned counsel for the Appellant is that the Adjudicating Authority has

completely ignored the contractual clauses between the parties, hence, has

come to the erroneous conclusion that default has been committed by the

Corporate Debtor.

11. The clauses of Flat Buyer's Agreement which falls for consideration

and has been relied by learned counsel for the Appellant are clause 3.1 and

3.5. We need to need to notice Clause 3.1 and 3.5 from the Flat Buyer's

Agreement dated 10.12.2015 entered between the Corporate Debtor and Mr.

Ankur Khetan, which was part of the Section 7 application filed by the

Respondents. Clause 3.1 and 3.5 are as follows:

"3.1 Subject to Force Majeure circumstances, intervention of Statutory Authorities, receipt of occupation certificate and Allottee/Buyer having timely complied with all its obligations, formalities or documentation, as prescribed by Developer and not being in default under any part hereof and Flat Buyer's Agreement , including but not limited to the timely payment of installments of the other charges as per the payment plan, Stamp Duty and registration charges, the Developer proposes to offer possession of the Said Flat to the Allottee/Buyer within a period of 4 (four) years from the date of approval of building plans or grant of environment clearance, (hereinafter

Company Appeal (AT) (Insolvency) No.1163 of 2024 13

referred to as the ''Commencement Date"), whichever is later.

3.5 The Developer shall endeavor to handover possession of the Said Flat within a period of four years (48 months) from the Commencement Date, subject to timely payment by the AIlottee/Buyer towards the basic sale price and other charges, as demanded in terms of this Agreement. The time frame for possession provided hereinabove is tentative and shall be subject to force majeure and timely and prompt payment of all installments and completion of formalities required."

12. The submission which has been pressed by learned counsel for the

Appellant is that 4 years' period which is provided in Clause 3.1 was subject

to force majeure, intervention of statutory authorities, requirement of

Occupation Certificate and allottees making timely payment of instalments.

The submission of the Appellant is that details of 89 days during which

construction was halted along with relevant orders was produced before the

Adjudicating Authority. It is submitted that in event 89 days period is

extended, the default shall fall within the period prohibited under Section

10A. It is well settled principle of construction of contract that all clauses of

the contract has to be given a harmonious construction and parties' intent

need to be find out from the clauses of the contract.

13. Two clauses i.e. 3.1 and 3.5 of the Flat Buyer's Agreement are

relevant. We need to first take up the submission of timely payment of

Company Appeal (AT) (Insolvency) No.1163 of 2024 14

instalments by the allottees, which according to Appellant was not done by

the Respondents. A chart showing default on the part of 56 allottees out of

171 allottees has been referred to by learned counsel for the Appellant,

according to which there are more than Rs.1 Lakh dues of 27 allottees.

14. The present is a case where it is the submission of the Appellant that

all applicants who have filed Section 7 application are in default. Learned

counsel for the Appellant during submission has referred to 56 allottees who

according to the Appellant are in default. In this context, we notice the

judgment of Hon'ble Supreme Court in "Manish Kumar vs. Union of India,

(2021) 5 SCC 1" where the Hon'ble Supreme Court had occasion to

elaborately consider the provision of Section 7 of the I&B Code in reference

to the allottees who initiate proceeding under Section 7 against a real estate

company. It was held by the Hon'ble Supreme Court that it is not necessary

that all Applicants who have initiated proceeding under Section 7 need to

prove that default has been committed with respect to each of them by the

Corporate Debtor. It is submitted that any allottee, who is Financial

Creditor of the Corporate Debtor for default of any other Financial Creditor

by virtue of explanation to Section 7(1) can initiate proceeding. Thus, in a

case where Corporate Debtor commits default, failing to handover

possession of unit to allottee who is a Financial Creditor and has paid his

100% consideration, no capital can be made by making submission by the

Corporate Debtor that there are some other allottees who are party to the

application who had not paid their 100% consideration. In this context, we

Company Appeal (AT) (Insolvency) No.1163 of 2024 15

refer to Para 170 and 171 of the judgment of Hon'ble Supreme Court in

Manish Kumar's case, which is as follows:

"170. It is indisputable that in order to successfully move an application under Section 7 that there must be a default which must be in a sum of Rs 1 crore. It is equally clear that the amount of Rs 1 crore need not be owed by the corporate debtor in favour of the applicant. It must be noted that the Explanation existed even prior to the provisos being inserted. It is open to a financial creditor, to move an application in the company of another financial creditor or more than one other financial creditor. In fact, a perusal of the Rules, which we have already extracted, would indicate that irrespective of the number of applicants the court fee would remain Rs 25,000. This answers the alleged vagueness about court fees where the provisos are given effect to. Thus, dehors the impugned provisos in terms of the Explanation in Section 7(1), a financial debt need not be owed to the applicant and as joint application by more than one applicant was and is contemplated, the resultant position would be that any number of applicants, without any amount being due to them, could move an application under Section 7, provided that they are financial creditors and there is a default in a sum of Rs 1 crore even if the said amount is owed to none of the applicants but to any another financial creditor. This position has not undergone any change even with the insertion of the provisos. In other words, even though the provisos require that in the case of a

Company Appeal (AT) (Insolvency) No.1163 of 2024 16

real estate project, being conducted by a corporate debtor, an application can be filed by either one hundred allottees or allottees constituting one-tenth of the allottees, whichever is less, if they are able to establish a default in regard to a financial creditor and it is not necessary that there must be default qua any of the applicants. We have taken an extreme example to illustrate how the Code can possibly be worked.

171. In practice, it may be unlikely, however, that persons would come together as applicants under the Code, if they are real estate allottees, particularly knowing what the admission of application under Section 7 entails, and the destiny of an application which has reached the stage of compulsory winding up under Section 33. However, taking a more likely example viz. of the corporate debtor operating in the real estate sector and an allottee moving an application upon there being amounts due to him, prior to the amendment, undoubtedly, a single allottee could set the ball in motion and all he had to satisfy is default to him or any other financial creditor. The change that is brought about is only that apart from establishing the factum of default, he must present the application endorsed by the requisite number introduced by the proviso. Since, default can be qua any of the applicants, and even a person, who is not an applicant, and the action is, one which is understood to be in rem, in that, the procedures, under the Code, would bind the entire set of stakeholders, including the whole of the allottees, we

Company Appeal (AT) (Insolvency) No.1163 of 2024 17

can see no merit in the contention of the petitioner based on the theory of default, rendering the provisions unworkable and arbitrary."

15. Thus, the submission of the Appellant that some of the allottees have

not made timely payment of their instalments cannot be accepted to ignore

the default committed by the Corporate Debtor against those applicants who

have made payment of their full consideration and claiming default in not

handing over possession by the time given in the Flat Buyer's Agreement.

16. The second limb of the argument of the Appellant is that Clause 3.1

clearly stipulate that offering the possession is subject to requirement of

Occupation Certificate. The Adjudicating Authority has examined the said

submission in Para 13 of the order. The averment made by the Corporate

Debtor was not accepted observing that "If such a contention of the Corporate

Debtor is taken into consideration, then, it would lead the tendency of

intentional prolonged delays on the part of the Corporate Debtor for an

uncertain period in order to avoid handing over the possession to the

respective allottees".

17. The Occupation Certificate is issued by the Regulatory Authority to a

Corporate Debtor after completion of the construction. In a case where

Corporate Debtor does not complete construction, it cannot shield itself on

the ground that no Occupation Certificate has been issued, therefore, its

obligation to handover possession shall not commence. Clause 3.5, as

noted above contemplate handing over possession within 48 months from

Company Appeal (AT) (Insolvency) No.1163 of 2024 18

the commencement date subject to force majeure and timely payment of all

instalments. When we read Clause 3.1 and 3.5 together, period of 48

months has been contemplated for handing over possession subject to only

force majeure and payment of instalments. No case of force majeure except

halting of construction for 89 days has been contended, which falls in the

expression 'intervention of statutory authorities'. Clause 3.5 does not stand

any fetter in handing over possessing or receipt of Occupation Certificate.

18. We now need to notice Affidavit dated 22.08.2022 which was filed by

the Corporate Debtor before the Adjudicating Authority where status of

project has been given. According to own case of the Corporate Debtor out

of total 15 Towers only Tower 1 and 2 are fully complete and rest 13 Towers

were yet to be completed. In Para 9, a detailed chart outlining the status of

project has been given. In Para 10 of the Affidavit following has been stated:

"10. In view of the ongoing work and continuous measures being taken by the CD to complete the project timely, the said project is endeavoured to be completed by June 2023. However, till date total No. of 452 units have been offered for possession. Copies of photographs reflecting the status of the project/towers is annexed herein as Annexure R-1.

A detailed chart reflecting the status of possession offers is reproduced herein below for ready reference:"

SR. PHASES TOWER TOWER TOTAL POSSESSION EXPECTED NO. NO CONFIGU NO OF OFFERED DAT OF RATION FLATS POSSESSION

Company Appeal (AT) (Insolvency) No.1163 of 2024 19

1 Phase 1 Tower 1 G+12 130 130 Possession on going 2 Tower 2 G+12 130 130 Possession on going 3 Phase 2 Tower 3 G+14 120 48 Possession on 4 Tower 11 G+13 112 48 going 5 Tower 12 G+14 120 48 6 Tower 13 G+14 120 48 7 Phase 3 Tower 4 G+14 150 Possession will be offered in September 2022 8 Tower 6 G+17 144 Possession will be offered in Oct 2022 9 Tower 7 G+17 144 Possession offered in Oct 2022 10 Tower 8 G+17 144 Possession offered in Nov 2022 11 Tower 9 G+15 128 Possession in Dec 2022 12 Tower 5 G+15 128 Possession in Feb 2023 13 Phase 4 Tower 10 G+14 150 Possession in May 2023 14 Tower 14 G+15 128 Possession in June 2023 15 Tower 15 G+15 128 Possession in April 2023 TOTAL 1976 452

According to, thus, own case of the Corporate Debtor, possession was

to be handed over by June, 2023.

19. At this stage, we also need to notice I.A. No.6177 of 2024 filed by the

Appellant. In which application the Appellant has made following prayers:

"PRAYER

In view of the facts and circumstances of the case and in the interest of justice this Hon'ble Appellate Tribunal may graciously be pleased to:

Company Appeal (AT) (Insolvency) No.1163 of 2024 20

a) Direct the Respondent No. 166 to take such necessary steps as may be required to continue the Corporate Debtor as a going concern, including by continuing the constructions activities;

b) Permit the ex-management of the Corporate Debtor to assist the Respondent No. 166 in completing the construction activities under the supervision of the Respondent No. 166;

c) Pass directions to the complete the Project by Promoter in reverse insolvency mechanism;

d) Pass any other order (s) which this Tribunal may deem fit."

20. The application itself indicates that construction of the project is not

complete and Appellant seeks leave of the Court to proceed with the

construction of the project under the supervision of the IRP. In the

application, it has been submitted that Appellant is negotiating with one

M/s Raveneek Homes for joint development of concerned land. It is useful

to notice that a reply has been filed by the Resolution Professional in IA

No.6177 of 2024 where the Resolution Professional has stated that HRERA

registration has already expired in November, 2020 and further there is

dispute with Directorate of Town and Country Planning, Haryana (DTCP) on

renewal of licence and the Corporate Debtor has filed a Writ Petition. It was

further pleaded that the Corporate Debtor claim to offered possession

without obtaining Completion Certificate/ Occupation Certificate and also

Company Appeal (AT) (Insolvency) No.1163 of 2024 21

without having basic amenities. It is useful to extract Para 5(a) and (b) of

the reply, which is as follows:

"a. The contents of para 8(a) are denied in toto. It is denied that Resolution Professional placed any negative agenda for discontinuance of construction before CoC. The same is evident from the notice, agenda and explanatory statement to 2nd CoC meeting. Copy of notice, agenda and explanatory statement of 2nd CoC meeting is annexed herewith as Annexure-RI. It is also transpires from reading of minutes of 2nd CoC meeting that CoC noted that HRERA registration of the project has already expired in November, 2020 and no money can be collected from real estate allottees without renewal of HRERA. The CoC also noted that there is ongoing dispute with Directorate of Tower and Country Planning, Haryana (DTCP) on renewal of licence fee and writ petition is already filed by the Corporate Debtor. The CoC also noted that there will be more pilferage or wastage of resources of the Corporate Debtor in piecemeal construction activity.

b. With regard to contents of para 8(b), (c) & (d), it is submitted that Corporate Debtor offered possession of flats without obtaining CC/OC and also without having basic amenities such as permanent electricity connection, without having any permanent solution of water supply and sewerage treatment. The monthly expenses as mentioned in para 8(b), (c) & (d) are dead loss the Corporate Debtor due to illegal possession offered by the ex-management."

Company Appeal (AT) (Insolvency) No.1163 of 2024 22

21. The above clearly indicate that registration of the project is not there

from November, 2020 and project is still incomplete. In this appeal an

additional affidavit has been filed by the Appellant dated 23.11.2024

annexing resolution plan with respect to 'Basera' project. The resolution

plan proposed to be a resolution plan along with financial proposal and term

of plan. Para 6.3.1 gives the timeline chart, which provides as follows:

"6.3.1 Timeline Chart

The Promoters proposes to implement this Resolution Plan within a period in accordance with the Implementation Schedule and other terms contained in this Resolution Plan.

To implement of the Resolution Plan in the following manner ("Implementation Schedule"):

S.No. Activity Indicative Timeline 1. Approval of the E Resolution Plan by the NCL 2. Obtaining approvals E+180 days from various authorities 3. Possession of flats to E+730 days to Home Buyers E+1095

22. The above timeline which is given by the Appellant itself indicate that

from the date of approval of the resolution plan between 730 days to 1095

days' possession of flats will be given to the homebuyers. Thus, according to

the Appellant still there will be 2-3 years in handing over possession to the

homebuyers.

Company Appeal (AT) (Insolvency) No.1163 of 2024 23

23. All the above facts which have been brought along with the Affidavit

by the Appellant either before the Adjudicating Authority as well as before

this Tribunal can be looked into to come to the conclusion as to whether the

Corporate Debtor needs resolution under CIRP.

24. We may also notice the judgment of this Tribunal in "Shailendra

Agarwal vs. Asit Upadhyaya & Ors., Company Appeal (AT) (Ins.) No.327

of 2025" decided on 23.04.2025 where it was observed that not handing

possession by the Corporate Debtor to the allottees is a continuing default

committed by the Corporate Debtor. The above was a case also where

Section 7 application was filed by the allottees alleging default on the part of

the Corporate Debtor in handing over possession and refunding the amount

to the allottees. It is useful to notice following observations in Para 31 of the

judgment:

"31. ......It also mentions that the act of non- handing of possession on the part of the corporate debtor resulted in default on the part of the corporate debtor and since the possession of the units has not been handed over till day, it resulted in continuing default/recurring cause of action in terms of section

22 of the limitation act in 1963. Further in part V of the CP, in the list of documents to be attached there is clear mention of documents which show continuing default committed by the CD. The Respondents-

allotees had attached the copy of RERA publication dated 24.12.2022 for this project showing default committed by the CD. Respondents-allotees has also

Company Appeal (AT) (Insolvency) No.1163 of 2024 24

attached the statement of accounts as on 30.06.2022 of Nikhil Home Associates. We find that documents filed and the sequence of events clearly brings out the fact that the default is continuing and we cannot come to an inference that there is absence of pleadings. The judgement cited is therefore of no avail to the Appellants."

25. We have noticed above that Appellant has filed IA No.6177 of 2024

seeking direction to complete the project by Promoters in reverse insolvency

mechanism. In the appeal no order was passed by this Tribunal accepting

the prayers made in the application although a group of allottees who had

filed IA No.7266 of 2024 and another IA, as noted above, supporting the

Promoters of the Corporate Debtor prayed that the resolution plan of the

Promoter be accepted and they may be permitted to carry on construction.

The Respondent herein who has filed the Section 7 application opposed the

said prayer tooth and nail. It is submitted that the Corporate Debtor had

neglected to construct project and project is in inhabitable condition. Even

after expiry of more than five years from the date when possession was to be

given to the unitholders project is neither complete nor can be completed by

the Promoters in near future. In the present case, we, thus, are not inclined

to pass any direction for Reverse Insolvency Resolution Process, as prayed

by the Promoters.

26. There can be no dispute to the proposition that that in several cases

this Court has directed for completion of the project under the Reverse

Insolvency Process. Judgment of this Tribunal in "Flat Buyers

Company Appeal (AT) (Insolvency) No.1163 of 2024 25

Association of Winter Hills - 77, Gurgaon vs. Umang Realtech P. Ltd.,

2020 SCC OnLine NCLAT 1199" has been relied. The most of the cases

where Reverse Insolvency was directed are cases where all stakeholders

were substantially agreed with the proposal of construction. Present is a

case where Applicants who has initiated proceedings under Section 7 have

objected to the prayers made by the Promoter to permit them to carry on the

construction.

27. It is submitted that the present is a case where the Corporate Debtor

is to be resolved by CIRP process only and the resolution plan has to be

obtained as per the CIRP process. It is submitted that in view of the interim

order passed by this Tribunal directing the Resolution Professional not to

issue Form G on 02.07.02024 further steps are not yet been taken and this

Court may direct the Resolution Professional to issue Form G and obtain a

compliant resolution plan for resolution of the Corporate Debtor.

28. We having noticed the facts present in Section 7 application, affidavit

filed before the Adjudicating Authority and this Tribunal and application

filed before this Tribunal in the present appeal, we come to the conclusion

that project 'Basera' is still incomplete and no case has been made out to

permit the Promoter to complete the project. The Adjudicating Authority

having already initiated the CIRP process by admitting Section 7 application,

the Corporate Debtor needs to be resolved in accordance with the process

prescribed in the I&B Code and CIRP Regulations, 2016.

Company Appeal (AT) (Insolvency) No.1163 of 2024 26

29. In facts of the present case, specially the fact that project is not yet

complete as per own case of the Appellant and Appellant in its resolution

plan itself has shown that it will take 2-3 years in handing over possession

to the homebuyers. The submission advanced by leaned counsel for the

Appellant that there is no default on the part of the Corporate Debtor cannot

be accepted. The real estate projects are project which are undertaken by

the Corporate Debtor to complete with the amount received from the

allottees. Timelines given in the Flat Buyer's Agreement has to be given

meaning and purpose. The Corporate Debtor cannot be allowed to take

benefit of his own inaction and act of not completing the project.

Submission of the Appellant that since Occupation Certificate was not

issued, it could not give possession to the homebuyers cannot be accepted.

Completion of the construction is precondition for obtaining Occupation

Certificate, thus, precondition having not been completed by the Corporate

Debtor, it cannot hide its default on the pretext that due to non-receipt of

the Occupation Certificate possession cannot be handed over, hence, there

is not default on the part of the Corporate Debtor.

30. Taking into consideration the overall facts and circumstances, no case

has been made out to interfere with the initiation of insolvency resolution

process of the Corporate Debtor. The project which is not complete even

after about a decade from the date when allotment was made in favour of

the allottees, the Corporate Debtor needs resolution as per the I&B Code

and the CIRP Regulations, 2016.

Company Appeal (AT) (Insolvency) No.1163 of 2024 27

31. In result, we dismiss the appeal. Discharge the interim order dated

02.07.2024. The period from 02.07.2024 till date shall be excluded from the

CIRP process. The Resolution Professional to proceed with the CIRP process

and after issuing Form G take steps for early resolution of the Corporate

Debtor as early conclusion of the CIRP is required in the facts of the present

case. Subject to above, the appeal is dismissed.

[Justice Ashok Bhushan] Chairperson

[Barun Mitra] Member (Technical)

NEW DELHI

29th August, 2025

Archana

Company Appeal (AT) (Insolvency) No.1163 of 2024

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free