Mohit Arora vs Manish Aneja & Ors
- CitationCompany Appeal (AT) (Insolvency) No. 1163 of 2024
Ratio decidendi
The rule this decision rests on
Where a flat buyer's agreement fixes a period for handing over possession, with the qualifiers of force majeure, intervention of statutory authorities, receipt of an occupation certificate and timely payment by allottees, those qualifiers are to be read harmoniously with the operative possession clause, and an occupation certificate is not a precondition whose absence suspends the developer's obligation to hand over possession where the developer has not completed construction, since the occupation certificate can only issue after completion, so a developer cannot shield itself behind its non-receipt. Default by some allottees in paying instalments does not defeat a Section 7 application by allottees who have themselves paid their consideration and against whom the corporate debtor has defaulted in handing over possession, since it is not necessary that every applicant prove default against itself, and any allottee who is a financial creditor may join an application founded on default to any financial creditor. Non-handing over of possession beyond the contractual period, where the project remains incomplete, is a continuing default, and a Section 7 application founded on such default is rightly admitted, the corporate debtor not being entitled to benefit from its own inaction in completing the project. Reverse insolvency resolution under which the promoter completes the project is not to be directed where the allottees who have initiated the Section 7 proceedings oppose it and the project remains incomplete, the Tribunal declining such a direction in those circumstances and leaving the corporate debtor to be resolved under the CIRP process.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
[Arising out of Order dated 04.06.2024 passed by the Adjudicating Authority (National Company Law Tribunal), Court-V, New Delhi Bench in C.P. IB (IBC) No.657/ND/2021]
IN THE MATTER OF: Mohit Arora (Suspended Director of Revital Reality Pvt. Ltd.) ...Appellant
Versus
Manish Aneja & Ors. ...Respondents
Present: For Appellant: Mr. Abhijeet Sinha, Sr. Advocate with Mr. Ishan Dewan, Mr. V. Siddharth and Mr. Shreyans Jain, Advocates. For Respondents: Mr. Rishabh Jain, Advocate for RP. Ms. Pooja M. Saigal, Sr. Advocate with Mr. Palash S. Singhai, Mr. S. Sharma, Ms. Riddhi Jain and Mr. Nivesh Dixit, Advocates for R-1 to R-165. Ms. Vibha Makhija, Sr. Advocate with Mr. Nikhil Kumar Jha, Advocates for Applicant in I.A. No.7226/2024 and I.A. No.2767/2025.
JUDGMENT
Ashok Bhushan, J.
This Appeal by Suspended Director of the Corporate Debtor - M/s
Revital Reality Pvt. Ltd. has been filed challenging the order dated
04.06.2024 passed by the Adjudicating Authority (National Company Law
Tribunal), Court-V, New Delhi Bench admitting Section 7 application filed by
Cont'd.../ 2
Respondent Nos. 1 to 165, who had filed application under Section7 for
initiating CIRP against the Corporate Debtor. Aggrieved by the order dated
04.06.2024, this appeal has been filed.
2. Brief facts necessary to be noticed for deciding this appeal are:
2.1 State Government Haryana vide Town and Country Planning
Department Notification dated 19.08.2013 issued "Affordable Housing
Policy 2013". Under the said policy, the Corporate Debtor was
granted license by the Director General, Town and Country Planning,
Haryana, Chandigarh, on 19.12.2014 for construction and
development of an affordable group housing colony.
2.2 Building plan under the name and sign of 'Basera' was
launched by the Corporate Debtor. In the project, allotments were
made to several allottees. Project consisted of 15 towers. Units were
booked from 2014 to 2017. In the project situated at Sector 79B
Manesar Urban Complex, Gurugram, Haryana, Respondent Nos.1 to
165 were allotted different units and allotment letters were issued in
favour of the Respondents and Flat Buyer's Agreement was entered
between the Corporate Debtor and Respondent No.3, Mr. Ajay
Vashnavi on 02.06.2016, in favour of Respondent No.2, Mr. Ankur
Khetan Flat Buyer's Agreement was executed on 10.12.2015 and on
12.05.2016 in favour of Mr. Vishal Kumar. Similarly, Flat Buyer's
Agreements were executed in favour of other Respondents. As per the
Company Appeal (AT) (Insolvency) No.1163 of 2024 3
Flat Buyer's Agreement, the Corporate Debtor represented to the
Allottees that possession of the units will be handed over in four years
from date of approval of building plan and date of environmental
clearance whichever is later. In the present case, environmental
clearance was granted on 22.01.2016. The Respondents herein made
payments towards the consideration. Respondents had paid about
90% to 95% of the sale consideration and some of the Respondents
have paid their full sale consideration.
2.3 A Section 7 application was filed by 172 unitholders on
13.10.2021 against the Corporate Debtor seeking initiation of CIRP.
The applications pleaded that Principal Amount due to the Financial
Creditor is Rs.31,22,62,342/-. It was pleaded in the application that
certain letters of allotment and Flat Buyer's Agreement of three flat
buyers was annexed with the Section 7 application. Referring to
Clause 3.1 and 3.5 of the Flat Buyer's Agreement, it was pleaded that
the Corporate Debtor was to handover the possession by 22.01.2020.
Several emails were sent to the Financial Creditor enquiring about the
progress and status of construction, to which replies were given by the
Corporate Debtor and Corporate Debtor committed default, having
committed breach of the agreement with the flat buyers. In the
Section 7 application, date of default has been mentioned as
22.01.2020.
Company Appeal (AT) (Insolvency) No.1163 of 2024 4
2.4 In Section 7 application reply was filed by the Corporate Debtor.
Corporate Debtor in addition to reply filed an affidavit dated
22.08.2022 before the Adjudicating Authority bringing on record the
status of project. It was pleaded that out of total 15 towers having
residential units, Tower 1 and 2 are fully complete. Details of status
of the construction was mentioned in the Affidavit. A settlement
proposal was also offered to the homebuyers and applicants.
2.5 The Adjudicating Authority passed various orders in the Section
7 proceeding asking the Financial Creditors to take instructions on
the settlement proposal of the Corporate Debtor. The Financial
Creditors, however, informed the Adjudicating Authority that proposal
submitted by the Corporate Debtor is not acceptable. The
Adjudicating Authority proceeded to hear the parties and by the
impugned order has admitted Section 7 application. The Adjudicating
Authority, in the impugned order held that the Corporate Debtor
having not offered possession to the Respondents - unit holders
within 48 months from 22.01.2016, default has been committed. The
arguments raised on behalf of the Corporate Debtor that unless
Occupation Certificate is received there is no obligation to offer
possession was considered and rejected. The Corporate Debtor also
raised submission that application is barred by Section 10A of the I&B
Code, which too was considered and not accepted. The Adjudicating
Authority admitted Section 7 application and appointed Shri Gaurav
Company Appeal (AT) (Insolvency) No.1163 of 2024 5
Katiyan as Resolution Professional. Aggrieved by order admitting
Section 7 application, the Suspended Director of the Corporate Debtor
has filed this appeal.
2.6 The appeal came to be heard by this Tribunal on 12.06.2024,
thereafter on 02.07.2024. On 02.07.2024, following interim order was
passed:
"In the meantime, CoC may proceed to hold its meeting, however, no Form G shall be issued till the next date."
Parties completed their pleadings and parties were heard on
06.08.2025.
3. We have heard Shri Abhijeet Sinha, learned senior counsel for the
Appellant, Ms. Pooja M. Saigal, learned senior counsel appearing for the
Respondents - Financial Creditors. Ms. Vibha Makhija, learned senior
counsel has appeared for the Applicant in I.A. No. 7226/2024, Mr. Nikhil
Kumar Jha has appeared for Applicant in I.A. No. 2767/2025 and Mr.
Rishabh Jain has appeared for the Resolution Professional.
4. Shri Abhijeet Sinha, learned counsel for the Appellant in support of
the Appeal submits that the Adjudicating Authority erred in admitting
Section 7 application. There was no default on the part of the Corporate
Debtor as per the agreement between the parties. Learned counsel for the
Appellant referred to Clause 3.1 and 3.5 of the Flat Buyer's Agreement and
Company Appeal (AT) (Insolvency) No.1163 of 2024 6
submitted that offer of possession within four years was subject to force
majeure circumstances, intervention of statutory authorities, requirement of
Occupation Certificate and allottees making timely payment of instalments.
It is submitted that the present is a case where under the orders of the
statutory authorities including orders of the Court and Tribunal, for 89 days
there was stay on the construction. It is submitted that the possession
could have been offered to the allottees only after receipt of the Occupation
Certificate. No Occupation Certificate having yet been received, there can be
no offer of possession. The Adjudicating Authority had not appropriately
considered the Clause 3.1 and 3.5 of the Flat Buyer's Agreement. It is
submitted that the Adjudicating Authority has unduly relied on the
judgment of Hon'ble Supreme Court in Ireo Grace Realtech Pvt. Ltd. vs.
Abhishek Khanna & Ors., 2021 (2) SCR 1, which judgment is in context
of Consumer Protection Act and was on the deficiency of service, which is a
concept applicable to Consumer Protection Act and not to the I&B Code. It
is submitted that the agreement between the parties have to be read as it is
and allottees for discrepancy of service and for other reliefs are free to take
proceedings before the State RERA Authorities and other Authorities but
unless there is default on part of the Corporate Debtor proceedings for
insolvency commencement cannot be initiated against the Corporate Debtor.
Only a handful of allottees (initially there were 172 Applicants) have filed the
application for putting the Company into insolvency whereas there are 976
units and majority of the homebuyers are not in favour of the insolvency. It
is submitted that in the insolvency of a real estate project seldom there is
Company Appeal (AT) (Insolvency) No.1163 of 2024 7
resolution and completion of construction. It is submitted that the
timeframe for offering possession was subject to timely payment of
instalment by the unitholders. Before the Adjudicating Authority, the
Corporate Debtor has brought on record details of outstanding amount of
various unitholders who were in default and payment of their consideration.
Learned counsel for the Appellant has referred to the details of 56 allottees
amongst the Applicants who has initiated the Section 7 application, where
according to the Appellant, there are huge amount of default. It is
submitted that dues with reference to 27 unitholders are more than Rs.1
Lakh. It is submitted that timely payment by the allottees was relevant
consideration for determining default on the part of the Corporate Debtor.
The Adjudicating Authority has not adverted to the said pleading, thus, the
conclusion of the Adjudicating Authority that there is default in not offering
possession by the Corporate Debtor is not in accordance with law. It is
submitted that the period of 89 days counted from 22.01.2020, it falls
within the prohibited period under Section 10A, hence, the Section 7
application ought not to have been entertained. Corporate Debtor has
placed orders passed by Court, Tribunal and Statutory Authority whereby
construction was halted for 89 days. Learned counsel, however, submitted
that Appellant proceed on assumption that threshold as allowed to allottees
is fulfilled and no arguments are being addressed on said issue, although
several of the Respondents who has initiated proceeding under Section 7
were themselves in default. It is submitted that the Appellant has filed an
application IA No.6177 of 2024 seeking direction of reverse insolvency
Company Appeal (AT) (Insolvency) No.1163 of 2024 8
process under which the Appellant can complete the construction under the
supervision of the IRP. It is submitted that the Appellant has given proposal
to the allottees for construction and most of the allottees agreed and given
consent letters in favour of the Corporate Debtor.
5. Ms. Pooja M. Saigal, learned senior counsel appearing for the
Respondents - allottees refuting the submission of learned counsel for the
Appellant submits that environmental clearance certificate having been
issued on 22.01.2016, four years' period came to an end and default was
committed by the Corporate Debtor on 22.01.2020. The Corporate Debtor
has failed to procure Occupation Certificate till date. The submission of the
Appellant that unless Occupation Certificate is received Corporate Debtor
cannot be said to have committed any default, if the interpretation of the
Appellant is accepted of various clauses of Flat Buyer's Agreement as
contended, there will never be default on part of the Corporate Debtor. It is
submitted that the application was filed by the Applicants in 2021 and as on
date about four years have elapsed, however, till date neither construction
has been completed nor possession has been offered. It is submitted that
before the Adjudicating Authority, the Corporate Debtor itself has filed an
affidavit which indicate that all towers except 1 and 2 Tower were not
constructed, even according to the Appellant's case. The project under
which the allottees were allotted units was an affordable group housing
project in which carpet area of flat is 310 sq. ft. onwards. Most of the
allottees who were allotted flats have taken financial assistance for making
Company Appeal (AT) (Insolvency) No.1163 of 2024 9
payment of the consideration and for last more than five years they are
waiting for their units to be handed over. The project is not in habitable
condition. The Corporate Debtor has neglected the units and failed to make
endeavours to complete the construction in order to qualify enough to
obtain the Occupation Certificate. The possession of the units is still not
delivered, even after more than five years from 22.01.2020 on which date
possession was to be offered to the allottees. Even if, allowance of 89 days is
granted to the Appellant during which construction was halted and given a
grace period of further six months, the default is continuing and when
default is continuing in nature, Appellant cannot be heard to say that since
there was no default on 22.01.2020, application under Section 7 deserve to
be rejected. The threshold of the allottees was fully complete, even after
settlement with few allottees, there were 142 members who fulfil the
minimum threshold. The submission of the Appellant that allottees have
defaulted in payment of their instalment, it is submitted that some of the
unitholders has paid 100% of their consideration and most of them have
paid 90-95% of their consideration. Unitholders have also paid amounts to
the Corporate Debtor as per the demand letters issued from time to time. It
is submitted that even as on date construction is not complete and project is
standing stand still. It is submitted that for resolution of the Corporate
Debtor insolvency process is eminent and the unitholders can get their units
through mechanism as provided in the I&B Code. The Adjudicating
Authority after considering all aspects of the matter has correctly admitted
the Section 7 application. The submission of the Appellant is wrong that
Company Appeal (AT) (Insolvency) No.1163 of 2024 10
several hundred people are already offered possession. There is no
Occupation Certificate, it cannot be accepted that units are complete to be
offered.
6. Ms. Vibha Makhija, learned senior counsel submits that approx. 200
homebuyers have given their consent letter, who are Applicant in IA No.7226
of 2024, accepting the resolution plan given by the Promoters. It is
submitted by learned counsel that homebuyers are interested in completion
of project and insolvency of the Corporate Debtor shall cause hardship for
the unitholders to get possession of their units. The suspended
management has provided a plan in which the construction shall be
completed within stipulated time under supervision of a committee having
homebuyers as members and Resolution Professional. It is submitted that
on the application filed by handful of homebuyers the Corporate Debtor
cannot be put under insolvency.
7. Another IA No.2767 of 2025 has been filed by one Pawan Kumar
Kaushik, a unitholder who has also referred to the resolution plan
submitted by the Promoters. It is submitted that before the Adjudicating
Authority also 180 homebuyers have filed an application for deferment. The
plan provided by the suspended management need to be accepted in which
their 70% amount will be used for construction.
8. We have considered the submissions of learned counsel for the parties
and perused the record.
Company Appeal (AT) (Insolvency) No.1163 of 2024 11
9. We have already noticed above that project in question i.e. 'Basera' is
a project under Affordable Housing Scheme floated by Government of
Haryana in 2013. Licences were granted to the Corporate Debtor in the year
2014 and the building plan approved. As per the scheme of the Government
of Haryana, development of colony under Affordable Housing Scheme was to
be done so that unitholders will get small units of 310 sq ft and more. All
the applicants were allotted different units in different towers. There is no
dispute between the parties that the four years' period under which
construction was to be completed and units to be handed over to the unit
holders commenced on 22.01.2016 on which date environmental clearance
was granted. As noted above, issue that the Applicants (Respondent herein)
who had filed application under Section 7 fulfil the necessary threshold
being more than 100 allottees is not being questioned. We, thus, need to
proceed on the premise that Section 7 application was filed by the
Applicants who fulfil the threshold as provided under Section 7 proviso.
10. The submission which has been pressed by learned counsel for the
Appellant is that there was no default on the part of the Corporate Debtor so
as to initiate insolvency resolution process against the Corporate Debtor.
The submission which has been pressed by learned counsel for the
Appellant is that as per the Flat Buyer's Agreement entered between the
Corporate Debtor and the unitholders period of 48 months under which the
Corporate Debtor has to offer the possession was subject to four conditions
i.e. (i) force majeure circumstances; (ii) intervention of statutory authorities;
Company Appeal (AT) (Insolvency) No.1163 of 2024 12
(iii) requirement of Occupation Certificate; and (iv) completion of obligation
by allottees including timely payment of their instalments. Submission of
learned counsel for the Appellant is that the Adjudicating Authority has
completely ignored the contractual clauses between the parties, hence, has
come to the erroneous conclusion that default has been committed by the
Corporate Debtor.
11. The clauses of Flat Buyer's Agreement which falls for consideration
and has been relied by learned counsel for the Appellant are clause 3.1 and
3.5. We need to need to notice Clause 3.1 and 3.5 from the Flat Buyer's
Agreement dated 10.12.2015 entered between the Corporate Debtor and Mr.
Ankur Khetan, which was part of the Section 7 application filed by the
Respondents. Clause 3.1 and 3.5 are as follows:
"3.1 Subject to Force Majeure circumstances, intervention of Statutory Authorities, receipt of occupation certificate and Allottee/Buyer having timely complied with all its obligations, formalities or documentation, as prescribed by Developer and not being in default under any part hereof and Flat Buyer's Agreement , including but not limited to the timely payment of installments of the other charges as per the payment plan, Stamp Duty and registration charges, the Developer proposes to offer possession of the Said Flat to the Allottee/Buyer within a period of 4 (four) years from the date of approval of building plans or grant of environment clearance, (hereinafter
Company Appeal (AT) (Insolvency) No.1163 of 2024 13
referred to as the ''Commencement Date"), whichever is later.
3.5 The Developer shall endeavor to handover possession of the Said Flat within a period of four years (48 months) from the Commencement Date, subject to timely payment by the AIlottee/Buyer towards the basic sale price and other charges, as demanded in terms of this Agreement. The time frame for possession provided hereinabove is tentative and shall be subject to force majeure and timely and prompt payment of all installments and completion of formalities required."
12. The submission which has been pressed by learned counsel for the
Appellant is that 4 years' period which is provided in Clause 3.1 was subject
to force majeure, intervention of statutory authorities, requirement of
Occupation Certificate and allottees making timely payment of instalments.
The submission of the Appellant is that details of 89 days during which
construction was halted along with relevant orders was produced before the
Adjudicating Authority. It is submitted that in event 89 days period is
extended, the default shall fall within the period prohibited under Section
10A. It is well settled principle of construction of contract that all clauses of
the contract has to be given a harmonious construction and parties' intent
need to be find out from the clauses of the contract.
13. Two clauses i.e. 3.1 and 3.5 of the Flat Buyer's Agreement are
relevant. We need to first take up the submission of timely payment of
Company Appeal (AT) (Insolvency) No.1163 of 2024 14
instalments by the allottees, which according to Appellant was not done by
the Respondents. A chart showing default on the part of 56 allottees out of
171 allottees has been referred to by learned counsel for the Appellant,
according to which there are more than Rs.1 Lakh dues of 27 allottees.
14. The present is a case where it is the submission of the Appellant that
all applicants who have filed Section 7 application are in default. Learned
counsel for the Appellant during submission has referred to 56 allottees who
according to the Appellant are in default. In this context, we notice the
judgment of Hon'ble Supreme Court in "Manish Kumar vs. Union of India,
(2021) 5 SCC 1" where the Hon'ble Supreme Court had occasion to
elaborately consider the provision of Section 7 of the I&B Code in reference
to the allottees who initiate proceeding under Section 7 against a real estate
company. It was held by the Hon'ble Supreme Court that it is not necessary
that all Applicants who have initiated proceeding under Section 7 need to
prove that default has been committed with respect to each of them by the
Corporate Debtor. It is submitted that any allottee, who is Financial
Creditor of the Corporate Debtor for default of any other Financial Creditor
by virtue of explanation to Section 7(1) can initiate proceeding. Thus, in a
case where Corporate Debtor commits default, failing to handover
possession of unit to allottee who is a Financial Creditor and has paid his
100% consideration, no capital can be made by making submission by the
Corporate Debtor that there are some other allottees who are party to the
application who had not paid their 100% consideration. In this context, we
Company Appeal (AT) (Insolvency) No.1163 of 2024 15
refer to Para 170 and 171 of the judgment of Hon'ble Supreme Court in
Manish Kumar's case, which is as follows:
"170. It is indisputable that in order to successfully move an application under Section 7 that there must be a default which must be in a sum of Rs 1 crore. It is equally clear that the amount of Rs 1 crore need not be owed by the corporate debtor in favour of the applicant. It must be noted that the Explanation existed even prior to the provisos being inserted. It is open to a financial creditor, to move an application in the company of another financial creditor or more than one other financial creditor. In fact, a perusal of the Rules, which we have already extracted, would indicate that irrespective of the number of applicants the court fee would remain Rs 25,000. This answers the alleged vagueness about court fees where the provisos are given effect to. Thus, dehors the impugned provisos in terms of the Explanation in Section 7(1), a financial debt need not be owed to the applicant and as joint application by more than one applicant was and is contemplated, the resultant position would be that any number of applicants, without any amount being due to them, could move an application under Section 7, provided that they are financial creditors and there is a default in a sum of Rs 1 crore even if the said amount is owed to none of the applicants but to any another financial creditor. This position has not undergone any change even with the insertion of the provisos. In other words, even though the provisos require that in the case of a
Company Appeal (AT) (Insolvency) No.1163 of 2024 16
real estate project, being conducted by a corporate debtor, an application can be filed by either one hundred allottees or allottees constituting one-tenth of the allottees, whichever is less, if they are able to establish a default in regard to a financial creditor and it is not necessary that there must be default qua any of the applicants. We have taken an extreme example to illustrate how the Code can possibly be worked.
171. In practice, it may be unlikely, however, that persons would come together as applicants under the Code, if they are real estate allottees, particularly knowing what the admission of application under Section 7 entails, and the destiny of an application which has reached the stage of compulsory winding up under Section 33. However, taking a more likely example viz. of the corporate debtor operating in the real estate sector and an allottee moving an application upon there being amounts due to him, prior to the amendment, undoubtedly, a single allottee could set the ball in motion and all he had to satisfy is default to him or any other financial creditor. The change that is brought about is only that apart from establishing the factum of default, he must present the application endorsed by the requisite number introduced by the proviso. Since, default can be qua any of the applicants, and even a person, who is not an applicant, and the action is, one which is understood to be in rem, in that, the procedures, under the Code, would bind the entire set of stakeholders, including the whole of the allottees, we
Company Appeal (AT) (Insolvency) No.1163 of 2024 17
can see no merit in the contention of the petitioner based on the theory of default, rendering the provisions unworkable and arbitrary."
15. Thus, the submission of the Appellant that some of the allottees have
not made timely payment of their instalments cannot be accepted to ignore
the default committed by the Corporate Debtor against those applicants who
have made payment of their full consideration and claiming default in not
handing over possession by the time given in the Flat Buyer's Agreement.
16. The second limb of the argument of the Appellant is that Clause 3.1
clearly stipulate that offering the possession is subject to requirement of
Occupation Certificate. The Adjudicating Authority has examined the said
submission in Para 13 of the order. The averment made by the Corporate
Debtor was not accepted observing that "If such a contention of the Corporate
Debtor is taken into consideration, then, it would lead the tendency of
intentional prolonged delays on the part of the Corporate Debtor for an
uncertain period in order to avoid handing over the possession to the
respective allottees".
17. The Occupation Certificate is issued by the Regulatory Authority to a
Corporate Debtor after completion of the construction. In a case where
Corporate Debtor does not complete construction, it cannot shield itself on
the ground that no Occupation Certificate has been issued, therefore, its
obligation to handover possession shall not commence. Clause 3.5, as
noted above contemplate handing over possession within 48 months from
Company Appeal (AT) (Insolvency) No.1163 of 2024 18
the commencement date subject to force majeure and timely payment of all
instalments. When we read Clause 3.1 and 3.5 together, period of 48
months has been contemplated for handing over possession subject to only
force majeure and payment of instalments. No case of force majeure except
halting of construction for 89 days has been contended, which falls in the
expression 'intervention of statutory authorities'. Clause 3.5 does not stand
any fetter in handing over possessing or receipt of Occupation Certificate.
18. We now need to notice Affidavit dated 22.08.2022 which was filed by
the Corporate Debtor before the Adjudicating Authority where status of
project has been given. According to own case of the Corporate Debtor out
of total 15 Towers only Tower 1 and 2 are fully complete and rest 13 Towers
were yet to be completed. In Para 9, a detailed chart outlining the status of
project has been given. In Para 10 of the Affidavit following has been stated:
"10. In view of the ongoing work and continuous measures being taken by the CD to complete the project timely, the said project is endeavoured to be completed by June 2023. However, till date total No. of 452 units have been offered for possession. Copies of photographs reflecting the status of the project/towers is annexed herein as Annexure R-1.
A detailed chart reflecting the status of possession offers is reproduced herein below for ready reference:"
SR. PHASES TOWER TOWER TOTAL POSSESSION EXPECTED NO. NO CONFIGU NO OF OFFERED DAT OF RATION FLATS POSSESSION
Company Appeal (AT) (Insolvency) No.1163 of 2024 19
1 Phase 1 Tower 1 G+12 130 130 Possession on going 2 Tower 2 G+12 130 130 Possession on going 3 Phase 2 Tower 3 G+14 120 48 Possession on 4 Tower 11 G+13 112 48 going 5 Tower 12 G+14 120 48 6 Tower 13 G+14 120 48 7 Phase 3 Tower 4 G+14 150 Possession will be offered in September 2022 8 Tower 6 G+17 144 Possession will be offered in Oct 2022 9 Tower 7 G+17 144 Possession offered in Oct 2022 10 Tower 8 G+17 144 Possession offered in Nov 2022 11 Tower 9 G+15 128 Possession in Dec 2022 12 Tower 5 G+15 128 Possession in Feb 2023 13 Phase 4 Tower 10 G+14 150 Possession in May 2023 14 Tower 14 G+15 128 Possession in June 2023 15 Tower 15 G+15 128 Possession in April 2023 TOTAL 1976 452
According to, thus, own case of the Corporate Debtor, possession was
to be handed over by June, 2023.
19. At this stage, we also need to notice I.A. No.6177 of 2024 filed by the
Appellant. In which application the Appellant has made following prayers:
"PRAYER
In view of the facts and circumstances of the case and in the interest of justice this Hon'ble Appellate Tribunal may graciously be pleased to:
Company Appeal (AT) (Insolvency) No.1163 of 2024 20
a) Direct the Respondent No. 166 to take such necessary steps as may be required to continue the Corporate Debtor as a going concern, including by continuing the constructions activities;
b) Permit the ex-management of the Corporate Debtor to assist the Respondent No. 166 in completing the construction activities under the supervision of the Respondent No. 166;
c) Pass directions to the complete the Project by Promoter in reverse insolvency mechanism;
d) Pass any other order (s) which this Tribunal may deem fit."
20. The application itself indicates that construction of the project is not
complete and Appellant seeks leave of the Court to proceed with the
construction of the project under the supervision of the IRP. In the
application, it has been submitted that Appellant is negotiating with one
M/s Raveneek Homes for joint development of concerned land. It is useful
to notice that a reply has been filed by the Resolution Professional in IA
No.6177 of 2024 where the Resolution Professional has stated that HRERA
registration has already expired in November, 2020 and further there is
dispute with Directorate of Town and Country Planning, Haryana (DTCP) on
renewal of licence and the Corporate Debtor has filed a Writ Petition. It was
further pleaded that the Corporate Debtor claim to offered possession
without obtaining Completion Certificate/ Occupation Certificate and also
Company Appeal (AT) (Insolvency) No.1163 of 2024 21
without having basic amenities. It is useful to extract Para 5(a) and (b) of
the reply, which is as follows:
"a. The contents of para 8(a) are denied in toto. It is denied that Resolution Professional placed any negative agenda for discontinuance of construction before CoC. The same is evident from the notice, agenda and explanatory statement to 2nd CoC meeting. Copy of notice, agenda and explanatory statement of 2nd CoC meeting is annexed herewith as Annexure-RI. It is also transpires from reading of minutes of 2nd CoC meeting that CoC noted that HRERA registration of the project has already expired in November, 2020 and no money can be collected from real estate allottees without renewal of HRERA. The CoC also noted that there is ongoing dispute with Directorate of Tower and Country Planning, Haryana (DTCP) on renewal of licence fee and writ petition is already filed by the Corporate Debtor. The CoC also noted that there will be more pilferage or wastage of resources of the Corporate Debtor in piecemeal construction activity.
b. With regard to contents of para 8(b), (c) & (d), it is submitted that Corporate Debtor offered possession of flats without obtaining CC/OC and also without having basic amenities such as permanent electricity connection, without having any permanent solution of water supply and sewerage treatment. The monthly expenses as mentioned in para 8(b), (c) & (d) are dead loss the Corporate Debtor due to illegal possession offered by the ex-management."
Company Appeal (AT) (Insolvency) No.1163 of 2024 22
21. The above clearly indicate that registration of the project is not there
from November, 2020 and project is still incomplete. In this appeal an
additional affidavit has been filed by the Appellant dated 23.11.2024
annexing resolution plan with respect to 'Basera' project. The resolution
plan proposed to be a resolution plan along with financial proposal and term
of plan. Para 6.3.1 gives the timeline chart, which provides as follows:
"6.3.1 Timeline Chart
The Promoters proposes to implement this Resolution Plan within a period in accordance with the Implementation Schedule and other terms contained in this Resolution Plan.
To implement of the Resolution Plan in the following manner ("Implementation Schedule"):
S.No. Activity Indicative Timeline 1. Approval of the E Resolution Plan by the NCL 2. Obtaining approvals E+180 days from various authorities 3. Possession of flats to E+730 days to Home Buyers E+1095
22. The above timeline which is given by the Appellant itself indicate that
from the date of approval of the resolution plan between 730 days to 1095
days' possession of flats will be given to the homebuyers. Thus, according to
the Appellant still there will be 2-3 years in handing over possession to the
homebuyers.
Company Appeal (AT) (Insolvency) No.1163 of 2024 23
23. All the above facts which have been brought along with the Affidavit
by the Appellant either before the Adjudicating Authority as well as before
this Tribunal can be looked into to come to the conclusion as to whether the
Corporate Debtor needs resolution under CIRP.
24. We may also notice the judgment of this Tribunal in "Shailendra
Agarwal vs. Asit Upadhyaya & Ors., Company Appeal (AT) (Ins.) No.327
of 2025" decided on 23.04.2025 where it was observed that not handing
possession by the Corporate Debtor to the allottees is a continuing default
committed by the Corporate Debtor. The above was a case also where
Section 7 application was filed by the allottees alleging default on the part of
the Corporate Debtor in handing over possession and refunding the amount
to the allottees. It is useful to notice following observations in Para 31 of the
judgment:
"31. ......It also mentions that the act of non- handing of possession on the part of the corporate debtor resulted in default on the part of the corporate debtor and since the possession of the units has not been handed over till day, it resulted in continuing default/recurring cause of action in terms of section
22 of the limitation act in 1963. Further in part V of the CP, in the list of documents to be attached there is clear mention of documents which show continuing default committed by the CD. The Respondents-
allotees had attached the copy of RERA publication dated 24.12.2022 for this project showing default committed by the CD. Respondents-allotees has also
Company Appeal (AT) (Insolvency) No.1163 of 2024 24
attached the statement of accounts as on 30.06.2022 of Nikhil Home Associates. We find that documents filed and the sequence of events clearly brings out the fact that the default is continuing and we cannot come to an inference that there is absence of pleadings. The judgement cited is therefore of no avail to the Appellants."
25. We have noticed above that Appellant has filed IA No.6177 of 2024
seeking direction to complete the project by Promoters in reverse insolvency
mechanism. In the appeal no order was passed by this Tribunal accepting
the prayers made in the application although a group of allottees who had
filed IA No.7266 of 2024 and another IA, as noted above, supporting the
Promoters of the Corporate Debtor prayed that the resolution plan of the
Promoter be accepted and they may be permitted to carry on construction.
The Respondent herein who has filed the Section 7 application opposed the
said prayer tooth and nail. It is submitted that the Corporate Debtor had
neglected to construct project and project is in inhabitable condition. Even
after expiry of more than five years from the date when possession was to be
given to the unitholders project is neither complete nor can be completed by
the Promoters in near future. In the present case, we, thus, are not inclined
to pass any direction for Reverse Insolvency Resolution Process, as prayed
by the Promoters.
26. There can be no dispute to the proposition that that in several cases
this Court has directed for completion of the project under the Reverse
Insolvency Process. Judgment of this Tribunal in "Flat Buyers
Company Appeal (AT) (Insolvency) No.1163 of 2024 25
Association of Winter Hills - 77, Gurgaon vs. Umang Realtech P. Ltd.,
2020 SCC OnLine NCLAT 1199" has been relied. The most of the cases
where Reverse Insolvency was directed are cases where all stakeholders
were substantially agreed with the proposal of construction. Present is a
case where Applicants who has initiated proceedings under Section 7 have
objected to the prayers made by the Promoter to permit them to carry on the
construction.
27. It is submitted that the present is a case where the Corporate Debtor
is to be resolved by CIRP process only and the resolution plan has to be
obtained as per the CIRP process. It is submitted that in view of the interim
order passed by this Tribunal directing the Resolution Professional not to
issue Form G on 02.07.02024 further steps are not yet been taken and this
Court may direct the Resolution Professional to issue Form G and obtain a
compliant resolution plan for resolution of the Corporate Debtor.
28. We having noticed the facts present in Section 7 application, affidavit
filed before the Adjudicating Authority and this Tribunal and application
filed before this Tribunal in the present appeal, we come to the conclusion
that project 'Basera' is still incomplete and no case has been made out to
permit the Promoter to complete the project. The Adjudicating Authority
having already initiated the CIRP process by admitting Section 7 application,
the Corporate Debtor needs to be resolved in accordance with the process
prescribed in the I&B Code and CIRP Regulations, 2016.
Company Appeal (AT) (Insolvency) No.1163 of 2024 26
29. In facts of the present case, specially the fact that project is not yet
complete as per own case of the Appellant and Appellant in its resolution
plan itself has shown that it will take 2-3 years in handing over possession
to the homebuyers. The submission advanced by leaned counsel for the
Appellant that there is no default on the part of the Corporate Debtor cannot
be accepted. The real estate projects are project which are undertaken by
the Corporate Debtor to complete with the amount received from the
allottees. Timelines given in the Flat Buyer's Agreement has to be given
meaning and purpose. The Corporate Debtor cannot be allowed to take
benefit of his own inaction and act of not completing the project.
Submission of the Appellant that since Occupation Certificate was not
issued, it could not give possession to the homebuyers cannot be accepted.
Completion of the construction is precondition for obtaining Occupation
Certificate, thus, precondition having not been completed by the Corporate
Debtor, it cannot hide its default on the pretext that due to non-receipt of
the Occupation Certificate possession cannot be handed over, hence, there
is not default on the part of the Corporate Debtor.
30. Taking into consideration the overall facts and circumstances, no case
has been made out to interfere with the initiation of insolvency resolution
process of the Corporate Debtor. The project which is not complete even
after about a decade from the date when allotment was made in favour of
the allottees, the Corporate Debtor needs resolution as per the I&B Code
and the CIRP Regulations, 2016.
Company Appeal (AT) (Insolvency) No.1163 of 2024 27
31. In result, we dismiss the appeal. Discharge the interim order dated
02.07.2024. The period from 02.07.2024 till date shall be excluded from the
CIRP process. The Resolution Professional to proceed with the CIRP process
and after issuing Form G take steps for early resolution of the Corporate
Debtor as early conclusion of the CIRP is required in the facts of the present
case. Subject to above, the appeal is dismissed.
[Justice Ashok Bhushan] Chairperson
[Barun Mitra] Member (Technical)
NEW DELHI
29th August, 2025
Archana
Company Appeal (AT) (Insolvency) No.1163 of 2024
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free