Marvel Landmark Pvt Ltd vs Jay Nihalani & Ors
- CitationCompany Appeal (AT) (Insolvency) No. 2227 of 2024
Ratio decidendi
The rule this decision rests on
A tribunal may recall its own order, passed without hearing one party on the merits, where that order was obtained by the other party's suppression of material facts and misrepresentation to the tribunal; such a recall is an exercise of inherent power to prevent abuse of its process and is not a review of the order on its merits. A recall is not confined to procedural irregularity alone: where the order was founded on a misrepresentation made to the tribunal by one party, and the absent party was not heard on the merits, the tribunal may restore the matter for merits adjudication, the absence of the other party being explained by a bona fide medical emergency of its counsel and not being wilful.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
[Arising out of the Impugned Order dated 18.11.2024 passed by the Adjudicating Authority, National Company Law Tribunal, Mumbai Bench in I.A. No. 4881 (MB)/2024 in CP (IB) No. 4320 of 2019]
In the matter of: Marvel Landmarks Pvt Ltd. Office No. 301-302, Jewel Tower, Lane No. 5, Koregaon Park, Pune, Pune, Maharashtra, India-411 001 ...Appellant
Versus
1. Jay Nihalani B1/27, Kubera Colony, NIBM Road, Kondhwa, Pune - 411048
2. Sanjay Sabharwal B-25, 2nd Floor, Marian Vihar, New Delhi 110028
3. Nirmala Parmar 8 Hill Range Society, Phase Two Anand Marg, Deolali Camp, Nashik 422401
4. Ankit Ashok Laungani 402, Satnam Society, Plot No.83, 29th Road, Behind Agarwal Nursing Home, Bandra (West) Mumbai 400050
5. Ram Krishan Chopra 24-A, Hills and Dales, Undri, Pune -- 411 060 6. Rustom Cyrus Dadachanji 1031 Clover Highlands, Building No. 10, Flat 31, Undri-Pisoli Road, Next to NIBM Post office, Kondhwa Pune- 411 048. 7. Chitra Sharma Flat No. 103, Block C-2, Waterlily, Adani Shantigram, Near Vaishnodevi Circle, S. G Road, Gandhinagar- 382421
8. Chetlapalli Radhakrishna Flat No. 1213, Clover Highlands Near NIRM, Kondhwa, Pune- 411048.
9. Shankar Bhima Nadoni B-1/ 2 Todkar Garden, Bibvewadi Kondhwa Road, Pune 411037.
10. Tanjana Sehgal Plot No.90, Sahney Sujan Park, Lullanagar Pune 411 040 11.
11. Sameer Vilas Raikar 213, Krutarth Society, Off Pune Satara Road Near, Citipride Multiplex, Pune- 417037.
12. Swati Abhijit Phadiya B 402, Konark lndraya Phase 2, Undari Road, Kondhwa, Pune- 411048. ...Respondents
Present:
For Appellant : Mr. Abhijeet Sinha, Sr. Advocate with Mr. Dhyal Deshpandy and Mr. Amit Arsiwala, Advocates.
For Respondents : Mr. Chaitanya Nikte and Mr. Anuj Tiwari, Advocates.
JUDGMENT
(Hybrid Mode)
Per: Barun Mitra, Member (Technical)
The present appeal filed under Section 61 of Insolvency and Bankruptcy
Code 2016 ('IBC' in short) by the Appellant arises out of the Order dated
18.11.2024 (hereinafter referred to as 'Impugned Order') passed by the
Page 2 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024 Adjudicating Authority (National Company Law Tribunal, Mumbai Bench, Court
VI) in IA/4881(MB) /2024 in Company Petition (IB) No. 4320/2019. By the
impugned order, the Adjudicating Authority has recalled its earlier order dated
06.04.2024 disposing of this Company Petition. Aggrieved by the restoration of
the Company Petition 4320/2019 by this impugned order, the present appeal
has been preferred by the Appellant.
2. The sequence of events which require to be noticed by this Tribunal for
consideration of the matter at hand are as outlined herein. The Corporate
Debtor-Appellant had entered into Agreements to Sale with the Respondents-
Homebuyers/Financial Creditors for purchase of residential units in the Marvel
Isola J Building Project. Since the residential units could not be constructed and
possession could not be handed over on time, the Respondents had filed a
Section 7 petition for initiation of Corporate Insolvency Resolution Proceedings
('CIRP' in short) on 30.11.2019. The Corporate Debtor raised questions on the
maintainability of the Section 7 petition, inter alia, including the ground that the
Respondents had failed to meet the requirements laid down by the 2nd proviso
to Section 7(1) of the IBC which had come into effect with an amendment in the
IBC during 2020 which prescribed minimum threshold of 100 allottees or 10%
of the total allottees in a Section 7 petition. The Section 7 petition was taken up
for hearing by the Adjudicating Authority several times by Bench III and then got
transferred to Bench VI. When the matter came up for hearing before Bench VI
on 24.04.2024, it was listed for final hearing on 15.05.2024. When the matter
came up for hearing on 15.05.2024, the Respondents sought an adjournment.
The same was allowed by the Adjudicating Authority by way of last chance and
Page 3 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024 was adjourned to 04.06.2024. Since the Respondents did not appear before the
Adjudicating Authority again on 04.06.2024, the Adjudicating Authority
disposed of the Company Petition No. 4320 of 2019 and the two IAs on the
ground that the present Respondents therein did not comply with the amended
law setting up requisite percentage/number of allottees to make them eligible to
continue with the Company Petition. Subsequently, on 14.09.2024, the present
Respondents filed an application IA No.4881 of 2024 under Rule-11 of the NCLT
Rules, 2016 seeking recall of the order of 04.06.2024. The matter was heard by
the Adjudicating Authority on 18.11.2024 on which date the impugned order
was passed recalling the order dated 04.06.2024 and restoring the Company
Petition and the two IAs. Aggrieved by this order, the Appellant- Corporate Debtor
has come up in appeal.
3. We have heard Shri Abhijeet Sinha, Ld. Sr. Advocate for Appellant and
Shri Chaitanya Nikte, Ld. Advocate representing the Respondent.
4. The Ld. Sr. Counsel for the Appellant assailing the impugned order
contended that the Adjudicating Authority having already passed an order on
merits in the Company Petition on 04.06.2024 and dismissed it, the same could
not have been reheard on merits by the Adjudicating Authority, basis a recall
application filed by the present Respondents before the Adjudicating Authority.
The order of 04.06.2024 was an appealable order and the same not having been
challenged within the prescribed period of limitation had already attained
finality. It was asserted that the powers of the Adjudicating Authority in the
context of recall under Rule 11 of NCLT Rules was limited and did not extend to
review of its own order or judgement. In the instant case, however, in the guise
Page 4 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024 of an IA filed under Rule 11 of NCLT Rules, which rule only permits recall of the
order, the Respondent has managed to seek review of the order of 04.06.2024
which is not permissible. Submission was also pressed that the order passed by
the Adjudicating Authority on 04.06.2024 was clearly decided on the merits of
dispute between both parties particularly with regard to maintainability of the
petition of the Respondents. The Adjudicating Authority in its orders had
categorically held that the Company Petition was not maintainable as it did not
comply with the requirements under 2nd proviso to Section 7(1) of the IBC. The
Adjudicating Authority by allowing the recall application and rehearing the
matter on maintainability issue committed a mistake as it did not have the power
to re-examine the merits of the case while hearing a recall application.
5. In support of their contention, reliance was placed on the judgement of
this Tribunal in Union Bank of India Vs Dinkar T. Venkatasubramanian &
Ors in CA(AT) (Ins.) No. 729 of 2020 where it has been held that power of recall
is not power of the Tribunal to rehear the case to find out any apparent error in
the judgment which is the scope of a review of a judgment. Attention was also
adverted to the judgment of the Hon'ble Apex Court in My Palace Mutually
Aided Co-operative Society Vs B. Mahesh and Others [2022 SCC Online SC
1063] wherein it was held that Civil Courts in exercising their inherent powers
under Section 151 of the Code of Civil Procedure (CPC), cannot exercise
substantive jurisdiction to unsettle already decided issues. A Court having
jurisdiction over the relevant subject matter has the power to decide and may
come either to a right or a wrong conclusion but the same is binding on the
Page 5 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024 parties until it is set aside by an appellate court or through other remedies
provided in law. It was pointed out that Rule 11 of the NCLT Rules, 2016 is pari
materia to Section 151 of CPC and hence an application for recall cannot
supplant the substantive provisions of appeal as contained in IBC.
6. It is also contended by the Appellant that there is no mention in the order
of 04.06.2024 that the company petition was being dismissed on grounds of non-
prosecution. The impugned order wrongly held that the Adjudicating Authority
in its order dated 04.06.2024 dismissed the petition for non-prosecution. It was
emphasised that the right course of action for restoration of an application on
grounds of non-prosecution is provided under Rule 48(2) of the NCLT Rules
which however is required to be made within 30 days from the date of dismissal.
On the other hand, the present IA has been filed well beyond the period of 30
days. To circumvent the period of limitation set out in Rule 48(2), the
Respondents have invoked Rule 11. The ground for seeking recall was therefore
not violation of the principles of natural justice but on merits which is not
permissible.
7. Making rival contentions, submission was made by the Ld. Counsel for
the Respondent that the Company Petition No. 4320 of 2019 had been heard 31
times. The Respondents were represented by their counsel regularly in these
hearings until the matter was transferred from Bench-III to Bench-VI of the
Adjudicating Authority. Bench VI heard the matter twice in quick succession
within a span of twenty days. During the hearing on 15.05.2024, the junior
counsel of the present Respondents had sought adjournment since the hearing
Page 6 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024 could not be not be attended by the senior. The matter was adjourned and
admittedly fixed for final hearing on 04.06.2024 on which date too, the hearing
could not be attended by the counsel of the Respondents. The absence of the
counsel on both these dates was not intentional but was on account of serious
life-threatening medical complication suffered by the wife of the Ld. Counsel
during that period. It was pointed out that for good measure they attached the
medical certificate of the doctor with their IA No. 4881 of 2024 which clearly
shows that as on 04.06.2024 also, the counsel's wife was under treatment in the
hospital. There were compelling circumstances for the absence of the counsel
during the two crucial hearings held on 15.05.2024 and 04.06.2024. Due to the
prolongation of the critical and emergent medical condition of the wife of the
counsel, the Respondents were not able to communicate with their counsel even
thereafter. However as soon as it came to their knowledge that the Adjudicating
Authority had passed an order on 04.06.2024, they filed the recall application
IA No 4881 of 2024. Since the Adjudicating Authority had passed the order on
04.06.2024 in their absence, this had prejudicially affected their rights as
allottees. Hence, in the interest of justice, the recall application was filed by them
before the Adjudicating Authority. It was also asserted that it is a well settled
dictum that a litigant should not suffer injustice for no fault of theirs. Being
bonafide litigants, their valuable rights and interests cannot be sacrificed on
account of a genuine handicap faced by their counsel in registering their
presence before the Adjudicating Authority on the relevant dates of hearing. In
support of their contention, attention was adverted to the judgment of the
Hon'ble Supreme Court in Secretary, Department of Horticulture,
Page 7 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024 Chandigarh Vs Raghu Raj in Civil Appeal No. 6142 of 2008 wherein it was
held that a litigant should not suffer on account of default or non-appearance of
the advocate. It was also mentioned that the Hon'ble Supreme Court in Rafiq &
Anr. Vs Munshilal & Anr. (1981) 2 SCC 788 had also held that a party should
not suffer for the inaction on the part of the lawyer. In any case, it was contended
that in the present matter the non-appearance of the advocate was also bonafide
having been propelled by circumstances of medical emergency.
8. It was also vehemently contended that the Corporate Debtor had misled
the Adjudicating Authority on 04.06.2024 into believing that there are 288 unit-
holders in Marvel Isola J Building Project, while the correct position was that in
this Building Project where the Respondents were to get their units, there were
only 44 units. It was pointed out that the MAHARERA Certificate also clearly
showed that there were 44 flats in this building project. Hence, with 12
Applicants in CP No. 4320 of 2019, the 10% threshold criteria stood fulfilled
making the Company Petition maintainable. On the other hand, taking
advantage of the absence of the Respondents-Allottees during the hearing, the
Appellants succeeded in misleading the Adjudicating Authority into believing
that the project consisted of 282 residential flats and the Company Petition
having been filed by only 12 allottees, the 10% threshold was not fulfilled. This
was a clear case whereby the Corporate Debtor had suppressed material
information from the Adjudicating Authority which led to the erroneous finding
on the part of the Adjudicating Authority that the Company Petition was not
maintainable. It was vehemently asserted that this concealment and
Page 8 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024 misrepresentation of facts was a fraud played upon the Adjudicating Authority
to obtain a favourable order. In the given circumstances, when the Corporate
Debtor had obtained orders of the Adjudicating Authority by suppression of fact
and making misleading statements, the Adjudicating Authority was well within
its jurisdiction to exercise its inherent powers under Rule 11 of NCLT Rules.
9. We have duly considered the arguments advanced by the Learned Counsel
for both the parties and perused the records carefully.
10. To arrive at our analysis and findings, at the outset, it would be useful and
constructive to note the order of the Adjudicating Authority dated 04.06.2024
which is as extracted below:
1. Heard Counsel for the CD on the main CP and two IAs. There is no representation from the FC. It has been stated by the Counsel for the CD that there are originally 282 unit-holders for the Housing Project, namely, 'Marvel Isola J Building'. However, there are only 12 Applicants who have filed the CP as FCs. The application was filed on 29.11.2019. There is no record to show that the Applicants have complied with the amended law to make the requisite percentage/number of the unitholders to make them eligible to continue with the present C.P.
2. Counsel for CD also submits that RERA has granted extension for completion of the Project up to 30.12.2024 and based on which, the construction has been initiated again. Based on instructions received from his client, he also submits that construction will be completed within the said period. In view of the above, we find that the application lacks the requisite number/ percentage of the unit holders to be eligible to continue the C.P. and hence, the CP is disposed of. The IA Nos. 1750/2021 & 1755/2021 are also consequently disposed of.
(Emphasis supplied)
11. Having noted the order of 04.06.2024, we now proceed to notice the
prayers of the Respondents as made out in IA No. 4881 of 2024 which had been
Page 9 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024 filed under Rule 11 of the NCLT Rules, 2016 seeking recall of the order of
04.06.2024. The prayers in the said application are as reproduced below:
a) "That this Hon'ble Tribunal be pleased to recall the Order dated 04/06/2024 passed by this Hon'ble Tribunal in Company Petition No. 4320 of 2019 and IA No.1750 of 2021 and IA No. l755 of 2021;
b) This Hon'ble Tribunal be pleased to urgently list the Company Petition No. 4320 of 2019 alongwith all the Interlocutory Application for hearing and final disposal.
c) Any other order in the interest of justice may kindly passed."
12. That the above IA 4881of 2024 had sought to invoke the Rule 11 of NCLT
Rules is also borne out from the letter addressed to the NCLT Registry by the Ld.
Counsel of the present Respondents which is as reproduced below:
"To, The Registrar, National Company Law Tribunal, Mumbai Bench Sir, I, the undersigned on behalf of Applicants in the aforesaid matter is filing an IA under section 60(5) of the insolvency and bankruptcy code 2016 r/w rule 11 of the national company law tribunal rules, 2016 for seeking recall of the order dated 04/06/2024 in cp no.4320 of 2019 passed by this hon'ble tribunal
Thanking You, Yours Faithfully, Advocate for Applicant Chaitanya B. Nikte"
From the prayers contained in IA No. 4881 of 2024 and the forwarding letter to
the NCLT Registry with respect to this IA, it is clear that the Respondents had
filed a recall application by invoking Rule 11 of the NCLT Rules. Given that the
Respondents had sought to rely on the inherent powers of the Tribunal under
NCLT Rule 11 and not NCLT Rule 48(2) while filing the IA No. 4881 of 2024 we,
Page 10 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024 therefore, do not find it necessary to dilate our views on the applicability of Rule
48(2) of NCLT Rules in the present factual matrix.
13. It is, however, the case of the Appellant that the Adjudicating Authority in
its order of 04.06.2024, had arrived at a specific finding that the Company
Petition was not maintainable. The dismissal of the Company Petition was
therefore not on grounds of non-prosecution but was a decision on merits. It is
the contention of the Appellant that the statutory provisions of the IBC do not
permit the Adjudicating Authority to revisit its own findings of fact or law in any
order delivered by it. Having already dismissed the Company Petition on
04.06.2024, the Adjudicating Authority, basis a recall application, cannot revisit
the Company Petition on the ground that the dismissal was incorrect or that it
had been incorrectly adjudicated because of disputed facts once having
dismissed it. It was asserted that the impugned order has sought to review its
earlier order of 04.06.2024 which is not permissible in a recall application and
therefore needs to be set aside.
14. When we look at the impugned order, we find that the Adjudicating
Authority in paragraph 2 therein has clearly taken note of the objections of the
present Appellant that the power of recall is not a power of the Tribunal to be
exercised for finding out any apparent errors and that the Adjudicating Authority
does not have any power of review. In this context, the Adjudicating Authority
has also taken cognizance of the judgment of this Tribunal in
Venkatasubramanian supra at para 20 wherein this Tribunal has observed on
the aspect of power of recall as follows:
Page 11 of 18
Company Appeal (AT) (Insolvency) No. 2227 of 2024 "....power to recall its judgment is inherent in this Tribunal since inherent power of the Tribunal are preserved, powers which are inherent in the Tribunal as has been declared by rule 11 of the National Company Law Appellate Tribunal Rules, 2016. Power of recall is not power of the Tribunal to rehear the case to find out any apparent error in the judgment which is the scope of a review of a judgment. Power of recall of a judgment can be exercised by this Tribunal when any procedural error is committed in delivering the earlier judgment; for example: necessary party has not been served or necessary party was not before the Tribunal when judgment was delivered adverse to a party. There may be other grounds for recall of a judgment. Well known ground on which a judgment can always be recalled by a court is ground of fraud played on the court in obtaining judgment from the court. We, for the purpose of answering the questions referred to us, need not further elaborate the circumstances where power of recall can be exercised."
The above judgement while drawing a distinction between recall and review also
clearly outlined some of the circumstances as to when a judgment can be
recalled.
15. We may now proceed to examine whether there were sufficient grounds
for recall of the order of 04.06.2024 in the present factual matrix. It would be
useful at this juncture to examine the findings of the Adjudicating Authority as
returned in the order of 04.06.2024. A plain reading of the above order, which
has already been reproduced at para 10 above, clearly indicates that only the
Counsel for the present Appellant-Corporate Debtor who was present before the
Adjudicating Authority on 04.06.2024. The order also records the submission
made by the Counsel for the Corporate Debtor that the Marvel Isola J Building
Housing Project had 282 unit holders and that there is no record to show that
the applicants had complied with the eligibility laid down in the amended
provision of the IBC. Basis these submissions made by the Counsel for the
Page 12 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024 Corporate Debtor, the Adjudicating Authority had returned the finding that the
Company Petition stands disposed since the Respondents lacked the requisite
number/percentage of unit holders to be eligible to continue the Company
Petition.
16. After perusing the order of 04.06.2024, there is no ambiguity in our mind
that the Adjudicating Authority in passing the order on 04.06.2024 had
preponderantly relied on the submissions made by the Counsel of the Corporate
Debtor on whether the Appellants were compliant with the 2nd proviso to Section
7(1) of the IBC to file the Company Petition No. 4320 of 2019. Per contra, when
we look at the material on record placed before us, we find that the Respondents
in the said Company Petition had categorically informed the Corporate Debtor
on affidavit that they were in compliance with the 2nd proviso to Section 7(1) of
the IBC. It was vehemently contended by the Respondents that in their Rejoinder
affidavit to the Reply filed by the Corporate Debtor in the Company Petition, at
paragraphs 4(iv) to 4(vii) it had been categorically pleaded that they were fully
compliant with the amended Section 7 of IBC. This fact has been reiterated by
the Respondents in their Recall application which is placed at pages 810 to 811
of Appeal Paper Book ("APB" in short). For reasons of clarity, we are extracting
the categorical pleadings made by the Respondents in their Rejoinder affidavit
to the Reply filed by the Corporate Debtor on the Company Petition as captured
in the Recall application:
"iv. I say that, the Corporate Debtor has registered a "real estate project"
under the MAHARERA portal by the name of "MARVEL ISOLA J BUILDING" wherein the Corporate Debtor has mentioned total number
Page 13 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024 of apartments in the said project as "44". I say that, all the 12 applicants of the captioned company petition are allottees of the abovementioned real estate project namely "Marvel Isola J Building" having a separate RERA Registration No. P52100001843. Hereto, annexed and marked as Annexure-4 is a copy of the RERA Registration certificate of the real estate project "Marvel Isola J Building" and Annexure-5 is a copy of the RERA Application made by the Corporate Debtor extracted from the MAHARERA portal with regards to the real estate project "Marvel Isola J Building".
v. I say that, in addition to the above, the Director of co-promoter of the said project who is also the Director of the Corporate Debtor and who has signed the Affidavit in Reply on behalf of the Corporate Debtor, has also submitted an affidavit dated 17/07/2017 before the MAHARERA wherein the "Marvel Isola J Building" has been categorically identified as a spate project. Hereto, annexed and marked as Annexure-6 is a copy of the Affidavit dated 17/07/2017 submitted to MAHARERA.
vi. I say that, in the Application made by the Corporate Debtor for registration of the said project "Marvel Isola J Building", the Corporate Debtor has categorically mentioned the total number of flats/apartments in the said project which are '44' in number. Further, the Corporate Debtor has also mentioned in the said application the total number of Booked Apartments i.e. the total number of Allotted Apartments which is 25. Therefore, in view of the Amendment Act, of 2020 the total number of allottees are 25 and there are total 12 applicants in the captioned company petition which comes to 48% of the total allottees. I further say that, even for the sake of calculation if all the 44 apartments are considered as allotted even then the applicants shall form 27% of 44 allottees which are the total number of apartments in the said project. Therefore, the applicants are conveniently more than the minimum requirement of 10% as per the amendment act of2020.
vii. I say that, accordingly the present company petition filed by the applicants is well in compliance of the Amendment Act of 2020 and as such requires no modification whatsoever. Therefore, this Hon'ble Tribunal is well within its jurisdiction to entertain and dispose off the captioned company petition on its own merits and the same is not deemed to be withdrawn as the captioned company petition complies with the Amendment Act of 2020."
(Emphasis supplied)
Page 14 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024
17. From the above narration, it becomes clear that the Adjudicating Authority
was misled by the present Appellant-Corporate Debtor for they suppressed the
fact that the present Appellants-Homebuyers in their Reply affidavit to the
Rejoinder filed by the Corporate Debtor had clearly articulated that they were
compliant with the eligibility terms laid down in the 2nd proviso to Section 7(1)
of the IBC along with supporting documents including MAHARERA certificate to
buttress their claim. Instead, the Corporate Debtor wrongfully apprised the
Adjudicating Authority during the hearing that the said project consisted of 282
flats and there being only 12 allottees as Respondents, they did not meet the
requisite percentage of allottees required to file the Company Petition.
18. We are, therefore, of the considered view that a misrepresentation was
made to the Adjudicating Authority by the Corporate Debtor for inspite of being
aware that their submission before the Adjudicating Authority was not based on
correct facts which tantamount to feeding of misleading facts to the Adjudicating
Authority. We do not wish to express any opinion as to whether the
misrepresentation was negligent, reckless, innocent or done with some oblique
motive except for holding this to be a case of misrepresentation which had
consequences of deflecting the course of judicial proceedings. It is a universally
accepted position that the justice delivery system is expected to administer
justice fairly and to the satisfaction of all concerned. In the present
circumstances, where the Adjudicating Authority has been made to rely on
distorted facts which the Adjudicating Authority became aware of belatedly, the
Page 15 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024 Adjudicating Authority can always invoke its inherent powers in order to protect
itself and to prevent an abuse of its process.
19. We also find that the Adjudicating Authority has also in the impugned
order distinguished the facts of the case in Venkatasubramanian supra from
the present one on the ground that in that case the order was based on the recall
of the final order passed after hearing both the parties on merit unlike the
present case where the order of 04.06.2024 was held as one which was not
passed on merits and had been passed without hearing the Respondents. It is
amply clear that the Company Petition was not heard on merits since it was not
decided in the presence of both parties. We must add here that the absence of
the Ld. Counsel of the Respondent-allottees was not wilful, deliberate or
intentional but was occasioned by critical medical conditions of the wife of the
Ld. Counsel. We also notice that even on 04.06.2024 when the Adjudicating
Authority had passed the order disposing of the Company Petition No. 4320 of
2019, the wife of the Counsel was still in hospital which is a factum not contested
by the Appellants either. It was of course submitted by the Appellants that
medical grounds cannot be stretched for so long a period to be viewed as a
genuine ground for delay. However, keeping in mind the facts and
circumstances, we are reasonably satisfied with the explanation offered by the
Respondents for their absence and would like to give benefit of doubt to them.
20. We have no quarrel with the ratio in the judgment delivered by the Hon'ble
Apex Court in My Palace Mutually Aided Co-operative Society supra that
Civil Courts in exercising their inherent powers cannot exercise substantive
Page 16 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024 jurisdiction to unsettle already decided issues. Be that as it may, the same
judgment at paragraph 35 has also clarified that it does not doubt the
proposition of law that fraud nullifies all proceedings, or that the Court has
power to recall an order which was passed due to a fraud played on the Court.
The order of 04.06.2024 was passed by the Adjudicating Authority by predicating
on the mis-statement made by the Corporate Debtor. As the order of 04.06.2024
had been obtained by the Appellants by suppressing material fact and by taking
advantage of the absence of the Respondents, the Adjudicating Authority had
therefore rightly recalled the order of 04.06.2024 which it had passed on
incorrect and false submissions without going into merits. The Adjudicating
Authority in such circumstances would have been failing in its duty of justice
dispensation if it did not exercise its inherent powers as a remedial measure to
jettison such manipulation, manoeuvring and misrepresentation. In the absence
of the allottees being represented by their Counsel, the Corporate Debtor should
have been fair to the allottees in pointing out to the Bench VI of the Adjudicating
Authority that the pleadings in the matter had already been completed and that
the present Respondent in their Rejoinder therein had depicted how they met
the amended law of Section 7. Instead, the Corporate Debtor took undue
advantage of the absence of the allottees and misrepresented the correct facts
causing miscarriage of justice. In the above circumstances, the Adjudicating
Authority did not commit any mistake in holding that the order dated 04.06.2024
was passed only on the submissions of the Corporate Debtor without getting into
the merits of the matter. Since, the order was not on merits and was passed
Page 17 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024 without hearing the present Respondents, the Adjudicating Authority recalled
the order of 04.06.2024 and restored the Company Petition.
21. For the foregoing reasons, we are convinced with the reasoning of the
Adjudicating Authority in recalling the order of 04.06.2024 and restoring the
Company Petition and the IA No.1750 of 2024 and 1755 of 2021 for examination
on merits. While affirming the decision of the Adjudicating Authority of
restoration of the Company Petition and the two IAs supra, we also add that
none of our discussion above be viewed as expression of any opinion by us on
the merits of the Company Petition. The Appeal is disposed of on the above
terms. No order as to costs.
[Justice Ashok Bhushan] Chairperson
[Barun Mitra] Member (Technical)
[Arun Baroka] Member (Technical)
Place: New Delhi Date: 21.01.2025
Abdul/ Harleen
Page 18 of 18 Company Appeal (AT) (Insolvency) No. 2227 of 2024
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.