M/S. Sumeet Industries Limited Through ... vs Dakshin Gujarat Vij Company Limited
- CitationCompany Appeal (AT) (Insolvency) No. 251 of 2026
Ratio decidendi
The rule this decision rests on
The Adjudicating Authority's dismissal is sustained on the ground that the appellant has not conclusively established that the appropriation of the security deposit was effected after commencement of CIRP in violation of Section 14; where the decision to adjust the security deposit was taken by the competent authority before the moratorium date, and the subsequent accounting reflection in later bills is consequential only, the adjustment is not a moratorium breach. A Resolution Professional's acceptance of a creditor's admitted claim after adjustment, with knowledge of the adjustment and without objection during CIRP, together with the approval of the resolution plan on that basis, precludes later reopening of that adjustment through an application filed after plan approval, as this would modify the approved plan contrary to the finality principle in Ebix Singapore. An application for reversal of an adjustment, filed by a Resolution Professional after the CoC has approved the plan and without CoC mandate, cannot be validated by a Monitoring Committee, which lacks the statutory powers of the CoC to ratify such action.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
(Arising against the impugned order dated 27.11.2025 passed by the National Company Law Tribunal, Ahmedabad Bench in I.A. No. 47(AHM)/ 2024 in Company Petition (IB) No. 38 of 2020].
IN THE MATTER OF:
SUMEET INDUSTRIES LIMITED Through its Resolution Professional, Mr. Satyendra Prasad Khorania, having registered office at 402, OK Plus, DP Metro Pillar No. 94, New Sanganer Road, Jaipur-302019 ...Appellant
Versus
1. DAKSHIN GUJARAT VIJ COMPANY LIMITED Through its Managing Director Having registered office at: Urja Sadan, Nana Varachha Road, Kapodara Char Rasta, Surat-395006
2. Eagle Group Through Authorised Signatory ...Respondent No.1 Mr. Radheshyam B. Jaju Office Address at: 201, Orleans, Sosyo Circle, Udhna Mangdalla Road, Surat, Gujarat- 395002 ...Respondent No.2
Present: For Appellant: Mr. Ajit Kumar Sinha, Sr. Advocate with Mr. Srijan Sinha, Mr. Himanshu Chaubey, Mr. Siddharth Garg, Ms. Lihzu Shiney Konyak, Ms. Nitya Prabhakar and Mr. Rishi Chouksey, Advocates. For Respondent: Ms. Srishti Khindaria, Advocate for R1.
Adv. Saumitra Chaturvedi, Advocate for R2/SRA. JUDGMENT
(25th May, 2026)
INDEVAR PANDEY, MEMBER (T)
The present Appeal has arisen out of the order dated 27.11.2025
passed by the National Company Law Tribunal, Ahmedabad Bench
(Adjudicating Authority) in I.A. No. 47/2024 in CP(IB) No. 38/2020,
whereby the application filed by Appellant-Sumeet Industries Limited
(Corporate Debtor) through its Resolution Professional Mr. Satyendra
Prasad Khorania, came to be dismissed. Through the said application, the
Appellant had sought directions against Dakshin Gujarat Vij Company
Limited (DGVCL)/ Respondent No.1 herein, for restoration of the
Security Deposit amounting to Rs.8,30,25,606/, which according to the
Appellant had been illegally adjusted by the Respondent No.1 after
commencement of the Corporate Insolvency Resolution Process ("CIRP"),
and further sought re-credit/refund of an amount of Rs.3,78,78,845.48/-
, which had allegedly been appropriated by the Respondent No.1 towards
pre-CIRP electricity dues in violation of the moratorium imposed under
Section 14 of the Insolvency and Bankruptcy Code, 2016 (hereinafter
referred to as 'Code'). The Eagle Group which is the Successful Resolution
Applicant (SRA) in the aforesaid CIRP has been Arrayed as Respondent
No.2. Aggrieved by dismissal of its application by the Adjudicating
Authority, Sumeet Industries Limited/ Corporate Debtor has filed this
appeal through the Resolution Professional before this Appellate Tribunal.
Page 2 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 Brief Facts of the Case
2. The facts relevant for deciding this matter are as given below:
i. Proceedings against the Corporate Debtor were originally initiated
by IDBI Bank through an application filed under Section 7 of the
Insolvency and Bankruptcy Code, 2016, which came to be registered
as CP (IB) No. 38/NCLT/AHM/2020 before the Ld. Adjudicating
Authority.
ii. The CD was drawing electricity from the Respondent No.1. For the
month of November 2022, the Energy Bill dated 02.12.2022 was
issued by the Respondent No.1 for an amount of
Rs.10,70,96,739.44/-. This included total monthly bill amount;
outstanding arrears; and delayed payment penalty.
iii. The aforesaid electricity dues for November 2022 were not cleared
within the stipulated period, and accordingly, the Respondent No.1
on 14.12.2022 issued a statutory disconnection notice under
Section 56 of the Electricity Act, 2003, directing the Corporate
Debtor to clear the outstanding dues within fifteen days from the
date of issuance of the notice and further warning that, in the event
of non-payment, the electricity supply would be disconnected
without further notice upon expiry of the said period, i.e., on or after
29.12.2022.
Page 3 of 49
Company Appeal (AT) (Ins.) No. 251 of 2026 iv. Adjudicating Authority vide its order dated 20.12.2022 admitted
the Sec 7 petition filed by the IDBI Bank and initiated CIRP against
Sumeet Industries Limited/Corporate Debtor. Consequent upon
admission, the Adjudicating Authority by order dated 15.02.2023
confirmed appointment of Mr. Satyendra P. Khorania as Resolution
Professional.
v. Following commencement of CIRP, a public announcement came
to be issued on 28.12.2022 inviting claims from all creditors of the
Corporate Debtor in accordance with the provisions of the IBC and
CIRP Regulations. The Interim Resolution Professional (IRP) through
a communication dated 29.12.2022, informed the Respondent No.1
regarding initiation of CIRP against the Corporate Debtor and
specifically requested the Respondent to submit its claims relating
to the period prior to the insolvency commencement date. The
Respondent was further informed that uninterrupted electricity
supply was necessary for keeping the Corporate Debtor operational
as a going concern during CIRP and was therefore requested not to
discontinue the electricity supply.
vi. The Respondent No.1 on 02.01.2023 issued another Energy Bill
for the month of December 2022 reflecting a net payable amount of
Rs.6,56,60,308/-. Significantly, the said bill also reflected that an
"advance payment/security deposit adjustment" amounting to INR
8,29,34,548/- had been appropriated by the Respondent No.1.
Page 4 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 vii. Pursuant to the public announcement inviting claims, the
Respondent No.1 on 06.01.2023 submitted its proof of claim in
Form-B before the Resolution Professional together with calculation
sheets, consumer ledger report, December 2022 Energy Bill and
Adjustment Details Report. After adjustment of Security Deposit of
Rs.8,30,25,606/- the Respondent No.1 filed its net claim amount to
Rs.3,03,78,845/-.
viii. The Corporate Debtor thereafter made payment of
Rs.6,56,60,308/- on 11.01.2023 towards the December 2022
electricity bill. However, according to the Appellant, the Respondent
No.1 illegally appropriated the entire amount towards dues for the
whole month of December 2022 including dues relating to the period
prior to 20.12.2022, i.e., the insolvency commencement date. It was
specifically alleged that an amount of Rs.3,78,78,845.48/- paid after
initiation of CIRP was unlawfully adjusted against pre-CIRP dues in
violation of Section 14 of the IBC.
ix. Along with the May 2023 electricity bill dated 01.06.2023 an
Adjustment Report was issued by the Respondent No.1. The said
report reflected credit towards interest on the security deposit at the
rate of 4.25% for Financial Year 2022-23 amounting to
Rs.2,37,52,721/- and also reflected deduction and deposit of TDS
with the Income Tax Department. According to the Appellant, if
interest was calculated on the security deposit amount of
Rs.8,30,25,606/- at the rate of 4.25%, it corresponded to Page 5 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 approximately 273 days, thereby demonstrating that the
Respondent continued treating the security deposit as subsisting till
29.12.2022.
x. After noticing the alleged adjustment, the Resolution Professional
on 03.06.2023 addressed a detailed communication to the
Respondent No.1 raising objection to the deduction of security
deposit after commencement of CIRP and sought clarification
regarding the basis on which the adjustment had been carried out
despite operation of the statutory moratorium. The Respondent No.1
on the other hand on 23.11.2023 demanded payment of alleged
outstanding electricity dues pertaining to the CIRP period and
threatened disconnection of electricity supply in the event of non-
payment.
xi. The Resolution Plan of the Corporate Debtor, Sumeet Industries
Limited, was approved by the Committee of Creditors ("CoC") on
21.10.2023. The Appellant on 05.01.2024 filed I.A. No. 47/2024
before the Ld. Adjudicating Authority seeking directions against the
Respondent to restore the security deposit amount and refund/re-
credit amounts allegedly adjusted against pre-CIRP dues in violation
of Section 14 of the IBC.
xii. During pendency of the said application, the Respondent again
issued a notice dated 15.01.2024 threatening discontinuation of
electricity supply unless payment of Rs.1,76,76,153/- was made
Page 6 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 within fifteen days. Aggrieved by the said notice and apprehending
further disconnection, the Corporate Debtor approached the Hon'ble
Gujarat High Court by filing Special Civil Application No. 1425 of
2025 seeking protection against disconnection and continuation of
electricity supply.
xiii. The Ld. Adjudicating Authority by order dated 16.07.2024
approved the Resolution Plan submitted by Eagle Group.
xiv. After the approval of Resolution Plan, Ld. Adjudicating Authority
vide the impugned order dated 27.11.2025 dismissed I.A. No.
47/2024 primarily on the grounds that the Resolution Professional
had accepted the Respondent's residual claim of Rs.3,03,78,845/-
after adjustment of the security deposit, that the filing of
proceedings before the Gujarat High Court amounted to forum
shopping, and that the application had been filed after approval of
the Resolution Plan. Aggrieved by the said findings and dismissal of
its application, The RP has preferred the present Appeal before this
Appellate Tribunal.
Submissions of the Appellant/ RP of Sumeet Industries Ltd.
3. Ld. Counsel for the Appellant submits that the present Appeal has
been validly instituted by the Corporate Debtor through its Resolution
Professional, Mr. Satyendra Prasad Khorania. The institution and
continuation of the present proceedings have been duly authorised by the
Monitoring Committee in its 3rd Meeting dated 20.12.2025, wherein a Page 7 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 conscious decision was taken authorising the Chairman to sign, file and
pursue the present Appeal, engage legal counsel in consultation with the
Successful Resolution Applicant and bear litigation expenses through the
SRA in accordance with the Approved Resolution Plan. It is further
submitted that I.A. No. 47 of 2024 had originally been filed on 05.01.2024,
much prior to approval of the Resolution Plan on 16.07.2024, at a stage
when the Resolution Professional was exercising statutory powers under
Sections 18 and 25 of the IBC for preservation and recovery of the assets
of the Corporate Debtor. Even subsequent to approval of the Resolution
Plan, the Monitoring Committee effectively steps into the shoes of the
Resolution Professional and is competent to continue proceedings initiated
for recovery of assets belonging to the Corporate Debtor. Reliance is placed
upon the judgment of this Hon'ble Tribunal in Mehsana Urban Co-
operative Bank Ltd. v. Swastik Ceracon Ltd., Comp. App. (AT) (Ins.) No.
1956 of 2025 decided on 12.03.2026, wherein it has been categorically
held that jurisdiction under Section 60(5)(c) of the IBC continues even after
approval of the Resolution Plan and proceedings for recovery of amounts
wrongfully adjusted during CIRP remain maintainable.
4. He submits that the present proceedings do not in any manner seek
reopening, modification or alteration of the Approved Resolution Plan. The
limited relief sought by the Appellant is restoration of amounts illegally
appropriated by the Respondent in contravention of Section 14 of the IBC.
The amounts in question were fully disclosed in the Information
Memorandum and were consciously factored into the Resolution Plan
Page 8 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 submitted by the Successful Resolution Applicant. It is submitted that
Clauses 9.1.16 and 9.1.17 of the Approved Resolution Plan specifically
preserve and authorise continuation of legal proceedings against the
Respondent for recovery of such amounts for the benefit of the Corporate
Debtor and all stakeholders. The very incorporation of these clauses
clearly demonstrates that the issue was never treated as settled upon
approval of the Resolution Plan. Clause 9.1.16 specifically records the
prayer that DGVCL reverse the pre-CIRP adjustment made against
payments effected by the IRP for running the Corporate Debtor as a going
concern, whereas Clause 9.1.17 expressly preserves the right of the
Resolution Applicant to initiate legal proceedings regarding wrongful
adjustment of the Security Deposit. The stand taken by the Respondent
that approval of the Resolution Plan extinguishes the present cause of
action is therefore wholly untenable and contrary to the express terms of
the Approved Plan itself.
5. It is submitted that the Respondent's defence that the Security
Deposit amounting to Rs.8,30,25,606/- stood appropriated on
14.12.2022, i.e. prior to commencement of CIRP on 20.12.2022, is entirely
false, unsupported and contrary to the documentary record. The
Respondent has failed to produce even a single contemporaneous
accounting record, ledger entry, debit advice, communication, adjustment
memo or financial statement evidencing any such appropriation on
14.12.2022. The bald assertion made by the Respondent is merely an ipse
dixit unsupported by legally admissible evidence. In absence of any
Page 9 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 contemporaneous record establishing actual appropriation prior to
commencement of CIRP, the Respondent cannot be permitted to defeat the
statutory protection available under Section 14 of the IBC.
6. Ld. Counsel submits that in an attempt to fill the complete
evidentiary vacuum surrounding the alleged adjustment, the Respondent
has sought to rely upon an Office Note dated 14.12.2022. The said reliance
is wholly misconceived and legally unsustainable. The Office Note merely
records an internal proposal requiring "further deliberation and decision"
and does not evidence any concluded or effectuated adjustment. The
document at best reflects an internal discussion and not an actual
appropriation of the Security Deposit. It is submitted that the said Office
Note was never communicated to the Corporate Debtor and no
contemporaneous action was taken pursuant thereto. More importantly,
the said document was produced for the first time only through an affidavit
dated 12.08.2025, i.e. more than two and a half years after the alleged
adjustment. Such highly belated production itself creates serious doubt
regarding its authenticity and evidentiary value. Had the appropriation
genuinely occurred on 14.12.2022, contemporaneous accounting records
and formal adjustment entries would necessarily have existed and been
immediately produced before the Learned Adjudicating Authority.
7. Ld. Counsel further submits that the Respondent's own
contemporaneous records completely demolish its stand that adjustment
of the Security Deposit had occurred prior to commencement of CIRP.
Firstly, the deduction of TDS amounting to Rs.2,63,919/- and
Page 10 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 corresponding reflection in Form 26AS clearly establish that the
Respondent itself treated the Security Deposit as subsisting and operative
at least till 29.12.2022. The act of calculating, crediting and depositing
TDS on accrued interest is wholly inconsistent with the Respondent's plea
that the Security Deposit had already been adjusted six weeks earlier on
14.12.2022. Secondly, the Respondent's own Form-B dated 06.01.2023
records that adjustment of the Security Deposit was processed only on
06.01.2023, i.e. seventeen days after commencement of CIRP. This
statutory document maintained by the Respondent itself conclusively
proves that the appropriation was post-CIRP in nature. Thirdly, the
electricity invoice dated 02.01.2023 constitutes the very first document
reflecting reduction of the Security Deposit to "0" and simultaneously
records an adjustment entry of Rs.8,29,34,546/-. Had the adjustment
genuinely taken place on 14.12.2022, the Security Deposit would not have
continued to appear in subsequent records till January 2023. These facts
were specifically placed on record by the Appellant in the detailed
Rejoinder dated 07.06.2024. However, despite existence of overwhelming
documentary evidence, the Learned Adjudicating Authority erroneously
recorded in Paragraph 16 of the Impugned Order that no evidence
regarding such credit had been produced.
8. He submits that the Security Deposit amounting to
Rs.8,30,25,606/- constitutes an asset of the Corporate Debtor and
immediately upon commencement of CIRP on 20.12.2022 came under the
full protection of the moratorium imposed under Section 14 of the IBC.
Page 11 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 Section 14(1)(c) expressly prohibits any action to foreclose, recover or
enforce any security interest created by the Corporate Debtor in respect of
its property during the moratorium period. Reliance is placed upon the
judgment of the Hon'ble Supreme Court in Central Transmission Utility
of India Ltd. v. Sumit Binani (2026 INSC 284 decided on 23.03.2026),
wherein it has been categorically held that no enforcement or
appropriation of a security deposit is permissible once the moratorium
takes effect, even if such security could otherwise have been invoked prior
to CIRP. The Hon'ble Supreme Court further reiterated the principle laid
down in Bharti Airtel Ltd. v. Aircel Ltd., (2024) 4 SCC 668, that no
form of set-off can be exercised during CIRP except where contractual set-
off had already been completed prior to commencement of CIRP. The
Respondent's alleged adjustment clearly falls outside this limited
exception. The Hon'ble Supreme Court additionally observed that
permitting such set-offs would defeat the pari passu distribution
mechanism embedded within the IBC framework. Similar principles were
also affirmed by this Hon'ble Tribunal in Central Transmission Utility
of India Ltd. v. Summit Binani and Others, 2024 SCC OnLine NCLAT
1382 and Corob India Pvt. Ltd. Through its Authorized Signatory v.
Birendra Kumar Agrawal and Others, 2024 SCC OnLine NCLAT 1267,
wherein unilateral appropriation of deposits during moratorium was held
impermissible. The Respondent has failed to distinguish any of these
binding precedents.
Page 12 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026
9. Ld. Counsel submits that the Respondent has further unlawfully
appropriated an amount of Rs.3,78,78,845.48/- out of payments made by
the Corporate Debtor during the CIRP period towards alleged pre-CIRP
dues. The payments made by the Corporate Debtor during CIRP, including
payment dated 11.01.2023, were specifically intended for discharge of
current operational liabilities so as to ensure continuity of essential
electricity supply and maintain the Corporate Debtor as a going concern.
However, the Respondent illegally appropriated Rs.3,78,78,845.48/- from
such CIRP-period payments towards liabilities relating to the period prior
to commencement of CIRP. Such conduct is wholly impermissible in law.
Firstly, appropriation of CIRP-period payments towards pre-CIRP liabilities
constitutes indirect recovery during the operation of moratorium and
therefore directly violates Section 14 of the IBC. Payments made during
CIRP for current operational requirements cannot be diverted towards
satisfaction of historical dues. Secondly, the Respondent has effectively
secured a double recovery. The Respondent had already submitted Form-
B before the Resolution Professional claiming the same pre-CIRP dues and
thereafter participated in the resolution process as an Operational
Creditor, ultimately receiving an amount of Rs.7.24 lakhs under the
Approved Resolution Plan. Having already participated in the insolvency
resolution mechanism and received distribution under the Resolution
Plan, the Respondent cannot additionally appropriate CIRP-period
payments towards the very same pre-CIRP liabilities.
Page 13 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026
10. He submitted that the Corporate Debtor vide letter dated 30.11.2023
specifically informed the Respondent that the electricity bill for December
2022 had already been paid and despite such payment, the Respondent
had illegally adjusted an amount of Rs.3,03,78,845.60/- relating to the
pre-CIRP period. Through the said communication, the Corporate Debtor
expressly requested the Respondent to credit the said amount against
current outstanding dues. Despite receipt of such objection and despite
being fully aware of the legal embargo created by Section 14 of the IBC,
the Respondent failed to rectify the wrongful appropriation.
11. Regarding the allegation of Forum shopping raised by the
Respondent Ld. Counsel submits that the same is entirely misconceived.
The Writ Petition filed before the Hon'ble Gujarat High Court, SCA No.
1425 of 2024, arose from an altogether distinct cause of action and sought
entirely different reliefs. The said Writ Petition was necessitated by the
second notice issued under Section 56 of the Electricity Act dated
15.01.2024 during CIRP, whereby the Respondent demanded payment of
Rs.17,67,61,531.14/- within fifteen days while simultaneously
threatening disconnection of electricity supply. The reliefs sought in the
writ proceedings pertained to protection against coercive disconnection
and invocation of writ jurisdiction on account of violation of statutory and
constitutional safeguards.
12. Ld. Counsel submits that in contrast, the present Appeal concerns
the first Section 56 Notice dated 14.12.2022 issued prior to
commencement of CIRP and specifically challenges the illegality of Page 14 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 subsequent post-CIRP appropriations of the Security Deposit and CIRP-
period payments in violation of Section 14 of the IBC. The causes of action,
statutory framework, reliefs sought and jurisdictions invoked in both
proceedings are therefore entirely distinct and independent.
13. He further submits that the Impugned Order suffers from grave and
fundamental errors of fact as well as law, each of which independently
renders the order unsustainable and collectively warrants interference by
this Appellate Tribunal. The Learned Adjudicating Authority has failed to
appreciate the documentary evidence placed on record by the Appellant
and has overlooked binding legal principles governing the operation of
Section 14 of the IBC.
14. It is submitted that the factual findings recorded in Paragraph 16 of
the Impugned Order are demonstrably erroneous and contrary to the
material available on record. The Appellant had specifically produced the
Adjustment Report and Energy Bill dated 01.06.2023 recording payment
of interest at 4.25% till 29.12.2022, Form 26AS reflecting deduction of TDS
on the Security Deposit, the first Section 56 Notice demanding the entire
outstanding amount, the invoice dated 02.01.2023 showing deduction of
the Security Deposit only after commencement of CIRP, and the detailed
Rejoinder dated 07.06.2024 explaining all relevant facts and chronology in
detail. Despite such extensive documentary evidence, the Learned
Adjudicating Authority erroneously proceeded on the basis that no
evidence regarding continued existence of the Security Deposit had been
Page 15 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 produced. The Impugned Order is therefore vitiated by complete non-
consideration of material evidence placed on record and warrants
interference by this Tribunal.
Submissions of the Respondent No.1/DGVCL
15. Ld. Counsel for Respondent No.1, Dakshin Gujarat Vij Company
Limited ("DGVCL"), submitted that the present Appeal filed by the
Appellant is wholly misconceived, devoid of merit and is liable to be
dismissed at the threshold itself. It was submitted that the Resolution Plan
in respect of the Corporate Debtor, Sumeet Industries Limited, already
stands approved by the Committee of Creditors ("CoC") on 21.10.2023 and
thereafter received approval from the Adjudicating Authority on
16.07.2024. It was further submitted that pursuant to the approval of the
Resolution Plan, the Successful Resolution Applicant ("SRA") has already
taken over the management and control of the Corporate Debtor and the
Resolution Plan also appears to have been implemented, as reflected from
Paragraph 5 of the Reply filed by the SRA. In such circumstances, the
present Appeal is nothing but an attempt to unsettle a concluded CIRP
and to deprive DGVCL of its legitimate and settled dues, which is
impermissible in law.
16. The Respondent No. 1 raised a bill of Rs. 10,71,63,833.44/- for the
month of November, 2022. The Corporate Debtor paid an amount of Rs.
4,45,00,000/- against such bill, leaving an outstanding amount of Rs.
6,25,96,739.44/-. Against such outstanding arrears, on 14.12.2022, the
Page 16 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 Respondent No. 1 decided to adjust the security deposit amount of Rs.
8,30,25,606/- leaving a balance security deposit of Rs.2,04,28,866.56/.
17. Corporate Debtor was admitted into the CIRP on 21.12.2022. The
Respondent No. 1 bifurcated the billing for the month of December into
two parts, first being the period prior to the initiation of CIRP (01.12.2022
to 20.12.2022) and second period post the initiation of CIRP (20.12.2022
to 31.12.2022). The total bill amount for December 2022 was Rs.
7,86,57,116.68/- out of which Rs. 5,08,07,712/- was for the period prior
to the initiation of CIRP (01.12.2022 to 20.12.2022) and Rs.
2,77,81,462.52/- was for the period post the initiation of CIRP (20.12.2022
to 31.12.2022).
18. The Respondent No. 1 adjusted the balance security deposit of Rs.
2,04,28,866.56/- against the dues of the period prior to the initiation of
CIRP (01.12.2022 to 20.12.2022) of Rs. 5,08,07,712/-, further leaving a
balance of Rs. 3,03,78,845.60/- as unpaid dues for the Pre CIRP period
and the same remained due and payable to the Respondent No. 1 from the
Corporate Debtor.
19. Ld. Counsel further submitted that the Hon'ble Supreme Court in
Ebix Singapore v. Committee of Creditors of Educomp Solutions Ltd.
has categorically held that the Code contains no provision permitting
modification, withdrawal or reopening of a Resolution Plan after the same
attains binding force under Section 31(1) of the Code. It was submitted
that the Hon'ble Supreme Court, particularly in Paragraphs 157 to 159,
164 to 166 and 221 to 224 of the judgment, has clearly laid down that the Page 17 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 jurisdiction of the Adjudicating Authority is confined only to examining
compliance with Section 30(2) prior to approval of the Resolution Plan and
once the Plan is approved, even such limited jurisdiction stands
exhausted. It was emphasized that the Hon'ble Supreme Court has further
clarified that Section 31(1) cannot be interpreted to mean that a Resolution
Plan remains indeterminate or open to modification or withdrawal.
Therefore, once finality has attached to the Resolution Plan, particularly
after approval by the Adjudicating Authority, the same cannot be reopened
through the present proceedings.
20. Ld. Counsel further submitted that the Hon'ble Supreme Court in
Paragraph 221 of the aforesaid judgment has specifically observed that
permitting withdrawal or modification of a Resolution Plan after
submission before the Adjudicating Authority would create an additional
tier of negotiations not contemplated or regulated by the statute. It was
therefore argued that the present attempt of the Appellant and the RP to
revisit settled claims and adjustments after approval and implementation
of the Plan is contrary to the scheme and object of the IBC.
21. Ld. Counsel submitted that in the present case, the Resolution
Professional had filed IA No. 47 of 2024 after approval of the Resolution
Plan by the CoC and that too without any authorization or mandate from
the CoC. It was further submitted that despite the Adjudicating Authority
recording findings against the RP on this aspect, the same has not been
challenged in the present Appeal, nor was any rejoinder filed by the RP
Page 18 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 when the issue regarding lack of authority was specifically raised by
DGVCL in its reply.
22. Ld. Counsel further submitted that the RP has not challenged
several crucial findings recorded in the Impugned Order. It was pointed
out that the Adjudicating Authority has already recorded findings that: (a)
the RP had accepted the Energy Bill of December 2022 along with
adjustment details and admitted the claim form of DGVCL; (b) the RP had
accepted the adjusted amount and continued making monthly payment
bills thereafter; (c) the claim of DGVCL had already been considered under
the Resolution Plan and approved by the CoC; (d) both the Information
Memorandum ("IM") and the Resolution Plan proceeded on the basis of
DGVCL's claim after adjustment of the security deposit; (e) IA No. 47 of
2024 was filed after approval of the Plan by the CoC; (f) there was no
mandate from the CoC for reclassification or for seeking refund of the
security deposit and the subsequent approval of the Monitoring Committee
could not validate earlier unauthorized actions of the RP, especially when
no Monitoring Committee existed at the relevant time; (g) the RP had also
filed parallel proceedings before the Hon'ble High Court after approval of
the Plan and without approval from the competent authority; (h) the RP
was simultaneously seeking reversal of the security deposit adjustment
while also retaining the claim amount already settled under the Plan,
thereby depriving DGVCL of its legitimate dues; and (i) the RP failed to
produce any evidence regarding the alleged credit in its account and the
Page 19 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 bills only reflected adjustment. It was submitted that all these findings
have attained finality.
23. Ld. Counsel submitted that the entire case of the Appellant is based
upon an erroneous factual assumption that the adjustment of the security
deposit was made after initiation of the CIRP. It was submitted that this
assumption itself is fundamentally incorrect. Ld. Counsel clarified that the
adjustment towards pre-CIRP dues was made by DGVCL on 14.12.2022,
which was prior to the commencement of CIRP on 21.12.2022. It was
submitted that this fact is clearly borne out from the office note of DGVCL
at Page 236 as well as from the affidavit filed before the Adjudicating
Authority at Page 235. It was further submitted that the Impugned Order
itself specifically records this factual position in Paragraph 13 at Page 88.
Thus, the adjustment was admittedly pre-CIRP in nature and cannot be
assailed on the ground urged by the Appellant.
24. Ld. Counsel further submitted that the Corporate Debtor had
furnished a security deposit of approximately Rs.8.30 crores with DGVCL,
which remained available with DGVCL during November and December
2022. It was submitted that the details regarding adjustment of the said
amount against electricity dues had already been set out by DGVCL in
Paragraphs 15 to 20 of its reply. After such adjustment, the net pre-CIRP
dues payable by the Corporate Debtor stood reduced to Rs.3.03 crores.
Accordingly, DGVCL filed its Claim Form-B on 06.01.2023 only for the net
amount of Rs.3.03 crores after enclosing complete adjustment details and
the corresponding bill which reflected the security deposit balance as "Nil". Page 20 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 It was submitted that the IRP accepted the said claim without any
objection and with complete knowledge of all relevant facts and
documents.
25. Ld. Counsel submitted that thereafter the Resolution Plan was
approved and DGVCL ultimately received only Rs.7.24 lakhs against its
admitted claim of Rs.3.03 crores. Therefore, both the adjustment as well
as the admitted claim have attained finality and cannot now be reopened
after conclusion of the CIRP process.
26. Ld. Counsel further relied upon Paragraph 100 of the judgment in
Ebix Singapore v. Committee of Creditors of Educomp Solutions Ltd.
wherein the Hon'ble Supreme Court emphasized that sanctity of the
insolvency process and procedural certainty are essential to the
functioning of the Code. It was submitted that the RP, having accepted
DGVCL's adjusted claim, permitted the IM and Resolution Plan to proceed
on that basis and allowed the CoC to approve the Plan accordingly, is now
estopped from turning around and seeking reversal of the very same
adjustment. It was argued that such conduct amounts to approbation and
reprobation and cannot be permitted. It was further submitted that the
present attempt is effectively aimed at denying DGVCL its legitimate claim
despite the same having already been accepted throughout the CIRP
process. It was also submitted that the SRA had proceeded strictly on the
basis of the IM and has no right to seek any undue enrichment by
reopening settled issues.
Page 21 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026
27. Ld. Counsel further submitted that the Adjudicating Authority has
expressly recorded at Page 89 of the Impugned Order that IA No. 47 of
2024 had been filed by the RP without any authorization from the CoC. It
was emphasized that this finding has not been challenged in the Appeal
and therefore stands conclusive and binding. It was submitted that after
approval of the Plan by the CoC, the RP could not have independently
initiated such proceedings.
28. Ld. Counsel further placed reliance upon the judgment of the
Hon'ble Supreme Court in Greater Noida Industrial Development Authority
v. P.S. Soni and submitted that the Hon'ble Supreme Court has held that
the RP is under a statutory obligation to collate all claims and the
Information Memorandum prepared on that basis forms the foundation on
which resolution applicants submit their plans. It was submitted that in
the present case DGVCL had filed Claim Form-B on 06.01.2023 for ₹3.03
crores after adjusting the security deposit and disclosing the same as "Nil",
with the adjustment having already been carried out on 14.12.2022, i.e.,
seven days before initiation of CIRP. The IRP/RP accepted the said claim
without objection, prepared the IM on that basis, the SRA submitted its
Resolution Plan accordingly and the CoC approved the Plan on the same
footing. Hence, the RP is bound by its own acceptance and cannot now
seek to reopen the issue.
29. Ld. Counsel further submitted that the RP is now attempting to
selectively reverse the adjustment while simultaneously ignoring the
consequence that the original claim amount of DGVCL would also have to Page 22 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 be restored in entirety. It was submitted that if such reversal is accepted,
DGVCL's status as a secured creditor to the extent of Rs.8.30 crores would
also revive, which position was never presented before the CoC during
CIRP. Such restoration would necessarily vitiate the Resolution Plan itself
and compel reopening of the entire CIRP process. It was therefore argued
that the conduct of the RP lacks bona fides and is legally untenable.
30. Ld. Counsel submitted that in light of the aforesaid facts and settled
legal position, there exists no statutory, inherent or residuary jurisdiction
to interfere with the Impugned Order dated 27.11.2025 passed by the
Adjudicating Authority. It was submitted that DGVCL's legitimate dues
cannot be defeated by an application which itself was filed without
authority and after conclusion of the CIRP process. It was further
submitted that security deposit is statutorily recognized and the issue
concerning interest had already been dealt with by DGVCL before the
Adjudicating Authority by way of affidavit at Pages 223 and 228-229,
particularly Paragraphs 12 and 13 thereof, after consideration whereof the
contentions of the RP stood rejected.
31. Ld. Counsel further submitted that issuance of the Disconnection
Notice dated 14.12.2022 does not in any manner preclude adjustment of
the security deposit. It was submitted that the statutory period of fifteen
days prescribed under the Electricity Act is relevant only for the purpose
of disconnection of electricity supply and not for adjustment of security
deposit. It was argued that even after adjustment of the security deposit,
disconnection proceedings could still continue for any outstanding Page 23 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 amount. Further, the Disconnection Notice itself contemplates adjustment
against part payment and therefore such adjustment does not invalidate
or nullify the notice.
32. Ld. Counsel submitted that the Appellant has relied upon the
judgment of the Hon'ble Supreme Court in CTUIL v. Sumit Binani. However,
the said judgment is wholly distinguishable on facts. It was submitted that
in the said case the adjustment had admittedly been carried out after
initiation of CIRP and after filing of the original claim form without any
adjustment. Further, the RP therein had immediately disputed the
adjustment and the Information Memorandum also contained details
regarding the disputed amounts. Therefore, the factual matrix of the said
case is entirely different from the present matter.
33. Ld. Counsel further submitted that the SRA has relied upon the
judgment of this Appellate Tribunal in Mehsana Urban Cooperative Bank
Ltd. v. Swastik. It was submitted that the said decision is also
distinguishable as in that matter the adjustment was made after initiation
of CIRP and after filing of claims for the full amount without disclosing any
mutual set-off or adjustment. It was further submitted that the claims
therein had already been admitted and amounts were provided under the
Resolution Plan. Moreover, the subject matter there related to dividend
amounts and not electricity dues governed by the Electricity Act, 2003. It
was argued that the said judgment does not deal with a situation where
the RP had expressly accepted the adjustment, admitted only the net claim
Page 24 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 amount and thereafter proceeded with the IM and Resolution Plan on that
basis.
34. Ld. Counsel lastly submitted that unlike the present matter, there
was no issue in the aforesaid cases regarding reopening of an already
concluded Resolution Plan. Therefore, the said judgments have no
applicability to the facts of the present case and do not assist the Appellant
or the SRA in any manner. He therefore requested for dismissal of the
appeal.
Submissions of the Respondent No.2/SRA
35. Ld. Counsel for Respondent No. 2/ Successful Resolution Applicant
(SRA) submitted that he is supporting the Appellant who is seeking
reversal of the post-CIRP appropriation of the Security Deposit amounting
to INR 8,30,25,606/- by Respondent No. 1, Dakshin Gujarat Vij Company
Limited ("DGVCL"), and also seeking re-credit of INR 3,78,78,845.48/-
which had been appropriated from CIRP-period payments towards pre-
CIRP dues. It is submitted that both these amounts formed part of the
asset pool of the Corporate Debtor and were specifically reflected in the
Information Memorandum. These amounts had also been factored into the
Approved Resolution Plan submitted by the SRA. Therefore, the unilateral
appropriation of the said amounts by DGVCL has caused direct and
irreversible prejudice to the SRA and the stakeholders of the Corporate
Debtor.
Page 25 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026
36. Ld. counsel submits that DGVCL's sole defence was that the
adjustment of the Security Deposit had allegedly been carried out vide an
Office Note dated 14.12.2022, i.e., seven days prior to commencement of
CIRP on 21.12.2022. However, according to the Respondent No. 2, this
plea stands completely demolished by DGVCL's own records and
documents.
37. It was further submitted that DGVCL's own Form-B receipt dated
06.01.2023 records that the adjustment was processed on 06.01.2023,
i.e., seventeen days after commencement of CIRP. Further, the Section 56
notice dated 14.12.2022 demanded the entire gross outstanding amount
without giving any deduction or adjustment towards the Security Deposit,
thereby clearly establishing that no actual appropriation had taken place
on that date. The counsel further argued that even the Office Note relied
upon by DGVCL merely referred to "further deliberation and decision" and
did not record any final or concluded act of appropriation. The said Office
Note was never communicated to the Corporate Debtor and was only
produced belatedly through an affidavit dated 12.08.2025.
38. He further submitted that DGVCL had additionally appropriated an
amount of INR 3,78,78,845.48/- from a post-CIRP payment dated
11.01.2023 towards the very same pre-CIRP dues which had already been
claimed through Form-B dated 06.01.2023.
39. Ld. counsel submits that the objection raised by DGVCL regarding
the locus of the Resolution Professional and Monitoring Committee was
Page 26 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 completely baseless both factually and legally. It was submitted that the
3rd Monitoring Committee Meeting held on 20.12.2025 specifically
authorised the Chairman to file and pursue the present Appeal before this
Hon'ble Tribunal, with all litigation expenses being borne by the SRA.
Further, I.A. No. 47/2024 had been filed on 05.01.2024, which was prior
to approval of the Resolution Plan on 16.07.2024. Therefore, at the
relevant time, the Resolution Professional was fully empowered under
Sections 18 and 25 of the IBC to take all necessary steps for protection
and preservation of the assets of the Corporate Debtor. It was further
argued that even after approval of the Plan, the Monitoring Committee
continued to possess the necessary locus for implementation of the Plan
and protection of the Corporate Debtor's assets. The SRA had also been
impleaded as a formal party by order of this Tribunal itself and was the
real party in interest, since its financial entitlements exceeding Rs.12
crores were directly affected. Thus, any technical objection regarding the
mode or nomenclature of filing stood cured.
40. Ld. counsel relied upon the judgment of this Appellate Tribunal in
Mehsana Urban Co-operative Bank Ltd. v. Swastik Ceracon Ltd.
decided on 12.03.2026, wherein it was held that the NCLT retains
jurisdiction under Section 60(5)(c) of the IBC even after approval of the
Resolution Plan to adjudicate disputes arising out of insolvency
proceedings. It was further held therein that an application filed by an SRA
after Plan approval for recovery of assets adjusted during CIRP in violation
of the moratorium is maintainable. The counsel submitted that Section
Page 27 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 61(1) of the IBC confers a right of appeal upon "any person aggrieved",
which expression is broad and cannot be interpreted narrowly. Thus, both
the Corporate Debtor acting through the Monitoring Committee and the
SRA were clearly entitled to maintain the present proceedings. Reliance is
also placed upon the judgment of the Hon'ble Supreme Court in Central
Transmission Utility of India Ltd. v. Sumit Binani decided on
23.03.2026, which has also been relied upon by Appellant.
41. Ld. counsel further submitted that Clauses 9.1.16 and 9.1.17 of the
Approved Resolution Plan specifically authorised the Resolution
Professional and Monitoring Committee to continue and prosecute all
litigations and legal proceedings initiated during CIRP or in furtherance of
the Resolution Plan for the benefit of the Corporate Debtor and all
stakeholders. Hence, the present Appeal was fully contemplated and
protected under the Approved Plan itself.
42. Ld. counsel submits that the Security Deposit continued to remain
an asset of the Corporate Debtor beyond 20.12.2022 and any
appropriation after that date was expressly prohibited under Section
14(1)(c) of the IBC, which bars all actions for foreclosure, recovery or
enforcement of any security interest against the assets of the Corporate
Debtor after commencement of CIRP.
43. Ld. counsel further submits that the Office Note dated 14.12.2022
relied upon by DGVCL could not constitute a valid order of appropriation.
Reliance was again placed upon Mehsana Urban Co-operative Bank (supra)
wherein this Tribunal held that an internal office noting without Page 28 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 implementation cannot amount to adjustment of the Corporate Debtor's
asset. It was argued that the Electricity Act, 2003 itself prescribes a
statutory mechanism for passing orders by competent authorities and an
internal, uncommunicated office note does not satisfy any such legal
requirement. The counsel further submitted that DGVCL's own argument
that the 15-day period under Section 56 of the Electricity Act was only for
disconnection and not for adjustment actually defeats its own case
because the Section 56 notice itself demanded the full outstanding amount
without any deduction towards the Security Deposit, thereby proving that
no appropriation had occurred on 14.12.2022. It was further argued that
the said 15-day period expired only on 29.12.2022, i.e., after
commencement of CIRP, and therefore any subsequent action stood
prohibited by virtue of Section 14 read with Section 238 of the IBC.
44. Ld. counsel submits that the contention of DGVCL that the
Resolution Professional stood estopped by acceptance of the adjusted
claim and that approval of the Resolution Plan barred reopening of the
issue was legally unsustainable. It was argued that there can never be any
estoppel against a statute and any act which is void ab initio under Section
14 of the IBC cannot be validated merely because the Resolution
Professional initially accepted the claim. The counsel pointed out that
objections had in fact been raised by the Resolution Professional through
letter dated 03.06.2023 and the Corporate Debtor itself had demanded
restoration of the amounts through letter dated 30.11.2023. Therefore,
Page 29 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 there was no acquiescence or waiver on part of the Corporate Debtor or
the SRA.
45. He further submitted that the present proceedings do not amount to
reopening or modification of the Approved Resolution Plan, rather, the
present proceedings seek recovery of assets which always belonged to the
Corporate Debtor and which were required to vest in the SRA under the
Approved Plan. Thus, the judgment of the Hon'ble Supreme Court in Ebix
Singapore Pvt. Ltd. v. Committee of Creditors of Educomp Solutions Ltd.
dealing with finality of Resolution Plans has no application to the facts of
the present case. He also submitted that DGVCL's argument that its claim
was duly reflected in the Information Memorandum and claim process and
therefore the matter stood concluded upon approval of the Resolution Plan
is fundamentally flawed. It was argued that consideration of DGVCL's
claim during CIRP does not authorise DGVCL to unilaterally appropriate
amounts in violation of the IBC. It was further submitted that if DGVCL's
argument were accepted, there would have been no necessity for inclusion
of Clauses 9.1.16 and 9.1.17 in the Approved Resolution Plan. The very
inclusion of these clauses demonstrates that all stakeholders consciously
intended recovery proceedings and litigation concerning such assets to
continue even after Plan approval.
46. Ld. Counsel finally argues that in the light of the aforesaid
submissions and the binding principles laid down in Central Transmission
Utility of India Ltd. v. Sumit Binani and Mehsana Urban Co-operative
Page 30 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 Bank Ltd. v. Swastik Ceracon Ltd., present Appeal is maintainable and the
same be allowed.
Analysis and Findings
47. We have heard the counsels and gone through the records of the
case including written submissions of the parties.
48. The sole issue which arises for consideration in the present Appeal
is: 'Whether Respondent No.1-Dakshin Gujarat Vij Company Limited
("DGVCL") illegally appropriated the Security Deposit amounting to INR
8,30,25,606/- and wrongly adjusted CIRP-period payments amounting to
INR 3,78,78,845.48/- towards pre-CIRP dues in violation of Section 14 of
the Code".
49. Before dealing with the rival submissions, it is necessary to notice
the relevant facts emerging from the record. The Corporate Debtor was
admitted into CIRP on 20.12.2022, and simultaneously the moratorium
under Section 14 of the Code came into operation. The electricity supply
to the Corporate Debtor was being provided by DGVCL and substantial
electricity dues had accumulated against the Corporate Debtor. Electricity
bills dated 01.11.2022 and 02.12.2022 reflected continuing arrears and
delayed payment charges. Since the outstanding dues remained unpaid,
DGVCL issued a disconnection notice dated 14.12.2022 under Section 56
of the Electricity Act, 2003, calling upon the Corporate Debtor to clear the
outstanding dues within fifteen days, failing which the electricity supply
was liable to be disconnected.
Page 31 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026
50. The Appellant along with Respondent No. 2/SRA have argued that
despite commencement of CIRP on 20.12.2022 and moratorium imposed
thereafter, DGVCL appropriated the Security Deposit of Rs.8,30,25,606/-
against pre-CIRP dues through the electricity bill dated 02.01.2023 and
further reflected the same in Form-B filed on 06.01.2023. It has also been
alleged that CIRP-period payments amounting to Rs.3,78,78,845.48/-
were illegally adjusted towards pre-CIRP dues. It is their case that the
Office Note dated 14.12.2022 relied upon by DGVCL does not constitute a
concluded act of appropriation and merely records internal deliberation. It
has further been argued that the disconnection notice dated 14.12.2022
demanded the entire gross outstanding amount without deduction of the
Security Deposit, thereby demonstrating that no adjustment had actually
taken place before commencement of CIRP. According to the Appellant,
such adjustment amounts to indirect recovery during moratorium and is
therefore prohibited under Section 14 of the IBC. The Appellant has relied
upon the electricity bill dated 02.01.2023, the Form-B dated 06.01.2023,
the alleged continuation of interest on the Security Deposit till 29.12.2022,
and the deduction of TDS upon such interest, to contend that the Security
Deposit continued to remain alive even after commencement of CIRP.
Reliance has also been placed upon judgments including Central
Transmission Utility of India Ltd. v. Sumit Binani and Bharti Airtel Ltd. v.
Aircel Ltd. to contend that unilateral appropriation or set-off after
commencement of CIRP is impermissible in law.
Page 32 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026
51. Per contra, the Respondent No.1 has contended that the decision to
appropriate the Security Deposit had already been taken on 14.12.2022
itself, i.e., prior to commencement of CIRP, through an internal Office Note.
According to the Respondent, the subsequent reflection of such
adjustment in the electricity bill dated 02.01.2023 and in Form-B dated
06.01.2023 was only a consequential accounting exercise and not the
actual date of appropriation. The Respondent has further contended that
the Resolution Professional was fully aware of the adjustment during the
CIRP period itself since the Respondent's claim along with adjustment
details formed part of the CIRP record. It has also been argued that the
Resolution Plan has already been approved on 16.07.2024 and
implementation has commenced, and therefore reopening the issue at this
stage would disturb the commercial finality attached to the approved
Resolution Plan.
52. The Appellant has relied upon the electricity bill dated 02.01.2023
and Form-B dated 06.01.2023 to argue that the appropriation was
admittedly post-CIRP. However, these documents merely indicate the stage
at which the adjustment came to be reflected in the billing and claim
records. They do not conclusively establish that the underlying decision
regarding appropriation itself was taken for the first time after 20.12.2022.
53. The Respondent, on the other hand, has consistently relied upon the
internal Office Note dated 14.12.2022 to contend that the decision
regarding adjustment of the Security Deposit had already been taken prior
to commencement of CIRP. The document forms part of the
Page 33 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 contemporaneous internal record maintained by DGVCL prior to initiation
of CIRP. The said Office Note also gains significance because it precedes
the CIRP commencement date of 20.12.2022 as well as the expiry of the
period granted under the Section 56 notice. In commercial functioning of
public utility entities, administrative decisions and their eventual
accounting implementation do not necessarily occur simultaneously.
Therefore, merely because the consequential reflection of adjustment
appeared subsequently in the bill dated 02.01.2023 or Form-B dated
06.01.2023 cannot, by itself, conclusively establish that the underlying
decision regarding appropriation was first taken after commencement of
CIRP.
54. The office Note dated 14-12-2022 is extracted below:
"DAKSHIN GUJARAT VIJ COMPANY LIMITED CIN U40102GJ2003SGC042909 Regd. & Corporate Office "Urja Sadan", Nana Varachha Road, Kapodra Char Rasta, SURAT- 395 006 Kadodara Division, 66 KV Substation Compound, Kadodara- 394327 Telephone (02622) 275911
Office Note: Dt.: 14 Dec 2022
Sub: Non-Payment of energy bills for the month of Nov-2022 by EHT consumer M/s Sumeet Industries Limited bearing HT Cons No. 11921.
In connection to above, M/s Sumeet Industries Limited is EHT consumer of DGVCL, Kadodara Division having contract demand of 13000 KVA bearing HT Cons No. 11921. This office has issued energy bill for the month of Nov-2022 amounting to Rs. 107096739.44 on Dtd 02.12.2022. M/s Sumeet Industries Limited is consistently failing to pay the full amount of its monthly energy bills by the due date, making it liable for disconnection as per applicable rules. The details are as under:
Page 34 of 49
Company Appeal (AT) (Ins.) No. 251 of 2026 S. No. Particulars Amount
1. Energy bill for the month of 67259893.71 Nov-2022 billed in Dec-2022
2. Outstanding Arrears 39088298.15
3. Delayed Payment Charge 748547.58
4. Total Arrears of energy bill 107096739.44
As per the consumer ledger, a Security Deposit of Rs.8,30,25,606/-
is available with DGVCL. Referencing Corporate Office Circular No. DGVCL/GM(F&A)/HT-SD-Adjustment/2020-21/06635 dated 30.04.2021, adjustment of the security deposit is permitted at the time of TDC, especially for HT consumers with substantial arrears.
In light of the above, the following option is presented for consideration:
Adjustment of the Security Deposit against the outstanding arrears of the energy bills.
The matter is put up for deliberation and necessary decision.
(Signed on 14-12-2022) S.A (Rev) Division Office, Kadodara.
(Signed on 14/12/2022) Note: Adjust SD as per norms Ex. Engineer (O&M) DGVCL, Division Office, Kadodara"
55. We can see from the office Note above that it was initiated by S.A.
(Rev) on 14-12-2022 furnishing the details about outstandings of the
Corporate Debtor amounting to Rs.10,70,96,739.44/- for the month of
November, 2022 which is payable in December, 2022. The note proposed
adjustment of Security Deposit (SD) against the outstanding arrears of the
energy bills. The officer puts up the note for deliberation and necessary
decision. The Executive Engineer in his noting on the note sheet, orders
for adjustment of SD as per norms. The aforesaid office note was submitted
Page 35 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 through an affidavit submitted by the Exe. Engineer on 12.08.2025 in
compliance with the directions of the Adjudicating Authority. The relevant
para 3 of the aforesaid affidavit is extracted below:
"3. In compliance with the direction contained in the aforesaid order, I am filing the present affidavit placing on record the file noting indicating that the decision to adjust the security deposit of the consumer, as available with the electricity distribution company, against the past unpaid electricity bills was taken on 14.12.2022. A copy of relevant page of the file containing official noting is annexed herewith and marked as Annexure -A. The original file shall be produced at the time of hearing of the application for perusal of the Hon'ble Tribunal."
56. We note the following from the aforesaid documents:
(i) The Executive Engineer has approved the Note submitted by the SA and has ordered adjustment of SD as per norms; and
(ii) Executive Engineer has also undertaken to produce the original file containing the note sheet to the Adjudicating Authority at the time of hearing.
57. The Appellant has relied upon the last sentence of the office note
recorded by SA (Rev) dated 14.12.2022 which reads as follows:
"The matter is put up for deliberation and necessary decision"
The Appellant argues that no decision could be taken on that date as the
matter required deliberation. We are not in agreement with this argument
of the Appellant. It is undisputed that the Executive Engineer (EE) is the
competent Authority to order the adjustment of the Security Deposit. He
Page 36 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 after due consideration, has ordered the adjustment of SD as per norms.
This decision of EE cannot be questioned vis-à-vis his authority to take
such decision as Competent Authority. The deliberation in administrative
parlance is deliberation by the Authority competent to take such decision,
accordingly, in this case the Competent Authority (EE) has ordered
adjustment of SD towards outstanding dues. This document has been
submitted by the competent authority (EE) through an affidavit before the
Adjudicating Authority and its veracity has not been under question. The
EE has also undertaken to produce the original file having the aforesaid
office note before the Adjudicating Authority as and when required. In the
functioning of the executive branch once a decision is taken by the
competent authority, the decision becomes binding and comes into effect.
In this case the security deposit was already lying with the Respondent
No.1 and subsequent actions are to be taken by commercial/ accounting
branch relate to making corresponding entries in the records. As the next
bill for December, 2022 was due in January, 2023 only, the said
adjustments of security deposit is duly reflected in the bill dated
02.01.2023. We therefore find no discrepancy in the submission of
Respondent No.1 regarding the date of adjustment of security deposit,
which in our view has been correctly stated as 14.12.2022.
58. The Appellant has also relied upon the disconnection notice dated
14.12.2022 issued under Section 56 of the Electricity Act to contend that
as per the aforesaid section the disconnection was to be effective 15 days
from the date of issue of notice i.e. on 29.12.2022, and therefore the
Page 37 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 deduction could not have effected before that date. As the entire gross
outstanding amount was demanded in the disconnection notice,
appropriation could have taken place on the last date i.e. 29.12.2022, if
the payment was not made by them. It is to be noted herein that
disconnection notice is a statutory notice, which is issued to the
consumers in default, giving them time to make payments of outstanding
dues to prevent disconnection. The disconnection notice issued under
Section 56 of the Electricity Act forms part of the overall recovery
mechanism relating to electricity dues. Mention of the gross outstanding
amount in such notice does not necessarily negate the Respondent's stand
that an internal decision regarding adjustment had already been initiated
or approved. The decision to adjust the Security Deposit, on the other hand
is a commercial decision based upon the past payment behaviour of the
consumer and is not linked to the statutory notice for disconnection under
Section 56 of the 'Electricity Act'. There is no legal or administrative bar
on initiation of both these actions independently and concurrently. We
therefore find no infirmity in the actions of the Respondent No.1.
59. We now take a look at the computation of the claim filed by the
Respondent No.1 in the CIRP Proceedings. The Corporate Debtor was
admitted into the CIRP on 21.12.2022. The Respondent No. 1 raised a bill
of Rs. 10,71,63,833.44/- for the month of November, 2022 against which
the Corporate Debtor paid an amount of Rs. 4,45,00,000/, leaving an
outstanding amount of Rs. 6,25,96,739.44/-. This amount was adjusted
on 14.12.2022 from the security deposit of CD lying with Respondent No.1
Page 38 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 amounting to Rs. 8,30,25,606/- leaving a balance security deposit of Rs.
2,04,28,866.56/.
60. The Respondent No. 1 bifurcated the billing for the month of
December into two parts, first being the period prior to the initiation of
CIRP (01.12.2022 to 20.12.2022) and second period post the initiation of
CIRP (20.12.2022 to 31.12.2022). The total bill amount for December 2022
was Rs. 7,86,57,116.68/- out of which Rs. 5,08,07,712/- was for the
period prior to the initiation of CIRP (01.12.2022 to 20.12.2022) and Rs.
2,77,81,462.52/- was for the period post the initiation of CIRP (20.12.2022
to 31.12.2022). The Respondent No.1 adjusted the balance security
deposit of Rs. 2,04,28,866.56/- against the dues of the period prior to the
initiation of CIRP (01.12.2022 to 20.12.2022) of Rs. 5,08,07,712/-, further
leaving a balance of Rs. 3,03,78,845.60/- as unpaid dues for the Pre CIRP
period and the same remained due and payable to the Respondent No. 1
from the Corporate Debtor. The Respondent No.1 filed its claim before the
Adjudicating Authority in Form-B on 06.01.2023 for this amount of
Rs.3,03,78,845.60/- which was admitted by the Resolution Professional.
After the approval of the Resolution Plan by the Adjudicating Authority,
the Respondent No.1 received an amount of Rs.7.24 lakhs under the
approved resolution plan against the aforesaid admitted claim in the CIRP
proceedings.
61. The Appellant has further relied upon the alleged calculation of
interest on the Security Deposit till 29.12.2022 and the corresponding TDS
deduction reflected in Form 26AS. According to the Appellant, such
Page 39 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 accounting treatment conclusively proves that the Security Deposit
continued to subsist beyond commencement of CIRP. However, we find
merit in the Respondent's explanation that interest calculation and TDS
reconciliation are annual/quaterly accounting exercises and cannot
conclusively determine the precise date of the underlying appropriation
decision. The appellant has made its own calculations, which in its view
suggest that the aforesaid security deposit was adjusted after the initiation
of CIRP on 20.12.2022. As we have already noted that date of adjustment
of security deposit is to be considered as the date of approval by the
competent authority. Further the claim submitted by the Respondent No.1
which had been duly accepted by the Resolution Professional and
approved in the resolution plan was based upon the calculations of the
Respondent No.1, which was never disputed by the Appellant till the plan
approval by the CoC on 21.10.2023. Its only after the approval of the
resolution plan by the CoC that the Appellant files the IA No. 47 of 2024
on 05.01.2024, before the Adjudicating Authority. We are not persuaded
by the arguments of the Appellant at this stage. He could have included
the claim of Respondent No.1 in the contingent claim category from the
beginning and could have advised SRA/Respondent No.2 who is
supporting the appeal, to provide "NIL" or a token amount in the plan.
62. Another important aspect is the conduct of the Resolution
Professional during the CIRP. The record clearly shows that DGVCL filed
its Form-B claim on 06.01.2023 along with the December 2022 Energy Bill
and adjustment details. The Resolution Professional accepted the claim
Page 40 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 form; admitted the claim; and continued making monthly electricity
payments thereafter. The material on record further shows that the
Information Memorandum and Resolution Plan proceeded on the basis of
DGVCL's claim after adjustment of the Security Deposit and the dues of
the Corporate Debtor for the remaining dues of December 2022 post CIRP
initiation on 20.12.2022. Thereafter, the Information Memorandum was
prepared, the resolution process continued. The Resolution Plan was
approved by Committee of Creditors (CoC) on 21.10.2023 and ultimately
by the Adjudicating Authority on 16.07.2024. The Successful Resolution
Applicant has already taken over management of the Corporate Debtor and
implementation of the Resolution Plan has commenced. The application
I.A. No. 47 of 2024 was filed before the Adjudicating Authority after
approval of the Resolution Plan by the CoC, despite the fact that the
Appellant/RP was fully aware of the adjustment of the security deposit by
the DGVCL and related issues.
63. We further note that the RP had filed the aforesaid I.A. after the
approval of the plan by the CoC, pending its consideration of the
Adjudicating Authority. The CoC was fully operation in this period but the
RP did not seek the approval or the mandate from CoC before initiating IA
No. 47 of 2024 to initiate action qua admitted claims which were already
settled in the resolution plan. It is the submission of the RP that the
Monitoring Committee has ratified such decision of the RP. We note that
the CoC is a creature of the Act, while the Monitoring Committee derives
its existence from the CIRP Regulations. A decision, which should have
Page 41 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 been taken with the concurrence or at least the knowledge of CoC, could
not be ratified by the Monitoring committee, which does not have the
statutory powers like the CoC.
64. The material placed on record further shows that the Resolution
Applicant and the stakeholders were fully aware of the issue regarding
DGVCL even during CIRP. In fact, specific clauses were incorporated in
the Resolution Plan preserving the right to pursue proceedings against
DGVCL. This itself demonstrates that the dispute was not hidden,
suppressed, or discovered subsequently after plan approval.
65. The Appellant has also argued that the present proceedings merely
seek restoration of monies and do not amount to reopening of the
Resolution Plan. However, we are unable to accept the contentions of the
Appellant and ignore the practical consequences of the relief sought. The
amounts involved exceeds Rs.12 crores. At a stage where the Resolution
Plan has already attained finality and implementation has commenced,
any direction for restoration of such substantial amounts would
necessarily impact the financial assumptions and settled commercial
rights arising out of the approved Resolution Plan. This would amount to
modification of the plan after the approval of the same by the Adjudicating
Authority.
66. The Appellant has also contended that the Resolution Professional
had locus to file and maintain the present proceedings and that clauses
9.1.16 and 9.1.17 of the Resolution Plan specifically preserved the right to
Page 42 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 pursue proceedings against DGVCL. While there may not be absolute merit
in the Respondent's technical objections regarding maintainability, we find
that the ultimate dismissal of the application by the Adjudicating Authority
was not solely founded upon locus or forum shopping. The core findings
recorded by the Adjudicating Authority are based upon appreciation of
facts, timing of the alleged appropriation, conduct of the parties during
CIRP, and the effect of the approved Resolution Plan. Therefore, even
assuming that the proceedings were maintainable, the Appellant was still
required to conclusively establish illegality in the Respondent's actions,
which in our considered view has not been done.
67. We also find that the allegations relating to wrongful adjustment of
CIRP-period payments amounting to Rs.3,78,78,845.48/- have not been
supported by a clear and conclusive financial reconciliation. The
transactions between the parties formed part of a running commercial
account involving current charges, arrears, delayed payment charges,
security deposit adjustments, and operational dues. It was necessary on
the part of Appellant to provide a clear and detailed reconciliation was
necessary before any finding of illegal double recovery or unjust
enrichment could have been returned against the Respondent. On the
other hand, Respondent No.1/DGVCL has furnished their calculations
based on two energy bills for November and December, 2022 in a clear and
succinct manner based on which their claim was admitted by the RP. The
Adjudicating Authority considered these allegations of Appellant found no
Page 43 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 sufficient ground to grant the relief sought. We do not find the said
conclusion to be arbitrary or contrary to the material available on record.
68. The Appellant has also argued that the Adjudicating Authority
wrongly observed that the filing of the writ petition before the Hon'ble
Gujarat High Court amounted to forum shopping. It is true that the writ
petition arose from the subsequent Section 56 notice dated 15.01.2024
and sought protection against threatened disconnection of electricity
supply during CIRP. However, both proceedings substantially arose out of
the same continuing dispute between the parties concerning electricity
dues, adjustment of payments, security deposit, and continuation of
electricity supply during CIRP. In any event, even if the observations
regarding forum shopping are kept aside, the same do not affect the
independent findings recorded by the Adjudicating Authority on merits.
69. The Appellant has relied upon various cases in their support. We
now proceed to examine them in the present factual matrix.
70. In Central Transmission Utility of India Ltd. v. Sumit Binani
(2026 INSC 284), the Hon'ble Supreme Court held that appropriation of a
security deposit after commencement of moratorium would be
impermissible under Section 14 of the IBC. However, the said judgment
proceeded on the basis that the post-CIRP appropriation stood clearly
established from the record. In the present case, the findings are to the
contrary as the security deposit has been adjusted based on the decision
taken on 14.12.2022, prior to commencement of CIRP, and the subsequent
Page 44 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 reflection in the electricity bill dated 02.01.2023 and Form-B dated
06.01.2023 was merely consequential accounting treatment.
71. In Bharti Airtel Ltd. v. Aircel Ltd., reported in (2024) 4 SCC 668,
the Hon'ble Supreme Court observed that unilateral set-off during CIRP
would defeat the scheme and pari passu principle under the IBC. However,
in the said case, the set-off sought to be exercised during the subsistence
of moratorium was not dependent upon any disputed prior decision or pre-
CIRP appropriation process. In the present case, the adjustment of
security deposit has taken place based on the Office Note dated
14.12.2022 and therefore the dispute is essentially factual in nature.
Moreover, the present case also involves an approved Resolution Plan
which has already attained finality, unlike the factual background in
Bharti Airtel. Therefore, the ratio of the said judgment does not assist the
Appellant in the peculiar facts of the present matter.
72. In Corob India Pvt. Ltd. through its Authorized Signatory v.
Birendra Kumar Agrawal and Others, reported in 2024 SCC OnLine
NCLAT 1267, this Tribunal considered the legality of unilateral
appropriation of deposits during the moratorium period and held such
action to be impermissible under the IBC framework. However, the said
judgment was rendered in the context of an admitted adjustment made
during CIRP and did not involve a disputed factual issue regarding whether
the appropriation decision itself had been taken prior to commencement
of CIRP. The ratio of the aforesaid judgment is not directly applicable to
the present case.
Page 45 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026
73. The Respondent has relied upon the judgment of the Hon'ble
Supreme Court in Ebix Singapore Pvt. Ltd. v. Committee of Creditors
of Educomp Solutions Ltd., reported in (2022) 2 SCC 401, to contend
that once a Resolution Plan is approved by the CoC and thereafter attains
approval under Section 31 of the IBC, the same cannot ordinarily be
reopened or altered. The relevant paragraphs 166 and 167 of the judgment
are extracted below:
'166. The binding nature, as between the CoC and the successful resolution applicant, of the resolution plan submitted for approval by the adjudicating authority is further evidenced from the fact that the CoC issues an Lol to a successful resolution applicant stating that it has been selected as the successful resolution applicant and its plan would be submitted to the adjudicating authority for its approval. The successful resolution applicant is typically required to accept the Lol unconditionally and submit a PBG. Sequentially, the issuance of an Lol is followed by its unconditional acceptance by the successful resolution applicant. In AMTEK Auto¹, this Court thwarted a similar attempt by a successful resolution applicant who had relied on certain open-ended clauses in its resolution plan to seek a direction compelling the CoC to negotiate a modification to its resolution plan. The resolution plan had been approved by the adjudicating authority and the resolution applicant's IA was not entertained. The resolution applicant had then sought to challenge the approval of the resolution plan under Section 61(3) IBC by seeking the same relief. This Court rejected the claim and observed that: (SCC p. 475, para 30) "30. To assert that there was any scope for negotiations and discussions after the approval of the resolution plan by the CoC would be plainly contrary to the terms of IBC."
167. Regulation 38(3) mandates that a resolution plan be feasible, viable and implementable with specific timelines.
A resolution plan whose implementation can be withdrawn at the behest of the successful resolution applicant, is
Page 46 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 inherently unviable, since open-ended clauses on modifications/withdrawal would mean that the plan could fail at an undefined stage, be uncertain, including after approval by the adjudicating authority. It is inconsistent to postulate, on the one hand, that no withdrawal or modification is permitted after the approval by the adjudicating authority under Section 31, irrespective of the terms of the resolution plan; and on the other hand, to argue that the terms of the resolution plan relating to withdrawal or modification must be respected, in spite of the CoC's approval, but prior to the approval by the adjudicating authority. The former position follows from the intent, object and purpose of IBC and from Section 31, and the latter is disavowed by IBC's structure and objective. IBC does not envisage a dichotomy in the binding character of the resolution plan in relation to a resolution applicant between the stage of approval by the CoC and the approval of the adjudicating authority. The binding nature of a resolution plan on a resolution applicant, who is the proponent of the plan which has been accepted by the CoC cannot remain indeterminate at the discretion of the resolution applicant. The negotiations between the resolution applicant and the CoC are brought to an end after the CoC's approval. The only conditionality that remains is the approval of the adjudicating authority, which has a limited jurisdiction to confirm or deny the legal validity of the resolution plan in terms of Section 30(2) IBC. If the requirements of Section 30(2) are satisfied, the adjudicating authority shall confirm the plan approved by the CoC under Section 31(1) IBC.'
74. We note from the above, that the Hon'ble Supreme Court has
specifically emphasized that once negotiations between the CoC and the
Successful Resolution Applicant conclude and the Resolution Plan is
approved by the CoC, the commercial terms underlying the Plan attain
binding character and cannot remain uncertain or indeterminate
thereafter. In the present case, the Resolution Professional, CoC, and the
Successful Resolution Applicant were fully aware during CIRP of DGVCL's
adjusted claim, the appropriation of the Security Deposit, and the details Page 47 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 of the claim filed by the Respondent. The Resolution Plan approved by the
CoC on 21.10.2023 was based on full awareness of facts of the case by the
concerned stakeholders. The same resolution plan was thereafter
approved by the Adjudicating Authority on 16.07.2024. It is a case where
the claims have been admitted and treated in the resolution plan with full
knowledge of concerned stakeholders. The Ebix Singapore (supra) fully
supports the contention of the Respondent No.1 that any changes to the
resolution plan at this stage would be contrary to the binding agreement
between the parties, and the completed resolution process cannot now be
indirectly reopened through the present proceedings by the Appellant.
75. Upon an overall consideration of the factual matrix, we find that the
Appellant has failed to conclusively establish that the appropriation of the
Security Deposit was affected after commencement of CIRP in violation of
Section 14 of the IBC. The material on record indicates that the
Respondent No.1 had taken a decision regarding adjustment of security
deposit through the Office Note dated 14.12.2022 prior to commencement
of CIRP. The effect of such decision was immediate as the security deposit
was lying with the Respondent No.1. It was subsequently reflected in the
next billing cycle for which the bill was issued on 02.01.2023 and Form-B
dated 06.01.2023.
76. We further note that the Resolution Professional, CoC, and
subsequently the Successful Resolution Applicant were fully aware of the
adjusted claim position during CIRP. The Resolution Plan came to be
approved and thereafter implemented on that basis. Once the CoC, in Page 48 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026 exercise of its commercial wisdom, approved the Resolution Plan after
considering the financial provisions and claims placed before it, the same
cannot ordinarily be unsettled at a later stage except within the limited
framework permissible under the IBC, particularly in light of the principles
of finality emphasized in Ebix Singapore (supra). In the facts of the present
case, any such action would amount to amendment to the approved
resolution plan which would be in the teeth of Ebix (supra) and the factual
matrix of the case.
77. In view of the findings above, we are of the opinion that the Appellant
has failed to establish any legal or factual infirmity in the Impugned Order
passed by the Adjudicating Authority. The findings recorded by the
Adjudicating Authority are based upon proper appreciation of the factual
matrix, the conduct of the parties during CIRP, and the legal principles
governing insolvency proceedings.
78. We accordingly hold that the Impugned Order dated 27.11.2025
passed in I.A. No. 47/2024 in CP(IB) No. 38/2020 does not suffer from any
infirmity The Appeal is accordingly dismissed. No order as to costs.
[Justice Ashok Bhushan) Chairperson
1.
[Mr. Indevar Pandey] Member (Technical)
Place: New Delhi
Harleen/ Pragya (LRA) Page 49 of 49 Company Appeal (AT) (Ins.) No. 251 of 2026
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free