M.K. Ranjitsinh vs Union Of India
- SCC(2021) 15 SCC 1
- Neutral2021 INSC 258
- SCR[2021] 4 SCR 81
Ratio decidendi
The rule this decision rests on
1. The State and Central Government have a constitutional duty under Article 21 of the Constitution, informed by ecocentric principles and the doctrine of public trust, to take steps to preserve endangered bird species from extinction, and in fulfilling this duty to prioritize the protection of rare species even where doing so incurs additional costs to power transmission. 2. In balancing sustainable development with species protection, where technical feasibility permits, power transmission infrastructure must be modified or laid underground in priority and potential habitats of endangered species, and where feasibility is uncertain, the matter must be evaluated on a case-by-case basis by technical experts rather than applying a uniform approach. 3. All low-voltage overhead power lines currently existing in the priority and potential habitats of the Great Indian Bustard must be converted to underground lines, and all future low-voltage power lines in these habitats must be laid underground without exception. 4. Where high-voltage overhead power lines cannot be feasibly converted to underground lines after technical assessment, the installation of bird divertors is a mandatory condition to be attached to all new power transmission contracts, and divertors must be immediately installed on existing overhead lines pending completion of feasibility assessments for undergrounding. 5. The costs incurred in protecting endangered bird habitats through power line mitigation may be borne by electricity utilities under their corporate social responsibility obligations under the Companies Act 2013, by the State through Compensatory Afforestation Fund available under the Compensatory Afforestation Fund Act 2016, or by regulatory approval of cost pass-through to consumers subject to competent regulatory authority approval. 6. Where habitat conservation requires protection of breeding grounds from predation, such areas must be secured through appropriate fencing and maintained free from power supply infrastructure.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
IN THE SUPREME COURT OF INDIA
CIVIL ORIGINAL JURISDICTION
I.A. NO.85618 OF 2020
IN
WRIT PETITION (CIVIL) NO.838 OF 2019
M.K. Ranjitsinh & Ors. .…. Petitioner(s)
Versus
Union of India & Ors. ….Respondent(s)
ORDER
1. The writ petition is filed in the nature of public Signature Not Verified Digitally signed by Sanjay Kumar Date: 2021.04.19 interest seeking to protect two species of birds namely the 16:20:14 IST Reason:
Great Indian Bustard (‘GIB’ for short) and the Lesser
1 Florican, which is on the verge of extinction. The existence of
overhead power lines is stated to have become a hazard due
to which the said species of birds on collision are getting
killed. In the pending writ petition, the application in I.A.
No.85618/2020 is filed seeking interim directions to direct
the State of Rajasthan (respondents No.5 and 6) and State of
Gujarat (respondents No.9 to 11) to ensure predator proof
fencing, controlled grazing in the enclosure development and
to direct the said respondents not to permit installation of
overhead power lines and also not permit further
construction of windmills and installation of solar
infrastructure in priority and potential habitat as identified
by the Wildlife Institute of India. The petitioner is also
seeking a direction to the respondents to install divertors for
the powerlines which has been listed in the application.
2. The very subject matter indicates that though such
directions are sought against the respondents, the litigation
is not adversarial in nature as it is community interest. In
fact, the petitioners being environmentalists, are seeking to
protect the rare birds which are dwindling in number. It is
contended that GIB is one of the heaviest flying birds in the
2 world, about a meter in height and wing span of around
seven feet. It has disappeared from 90 per cent of habitat
except parts of Rajasthan and Gujarat which is to be
protected. According to the petitioners, overhead power lines
are the biggest threat to the survival of the GIBs. The
Wildlife Institute of India (WII) in its Report “Power Line
Mitigation, 2018” has stated that every year 1 lakh birds die
due to collision with power lines. The Report concluded that
unless power line mortality is mitigated urgently, extinction
of GIBs is certain. Surveys conducted by Wildlife Institute of
India (WII) in Thar covering 80 km of power lines repeated 7
times over a year found 289 carcasses of around 30 species,
including the Great Indian Bustard (GIB). The study
estimated 3 bird mortalities/km/month for lowtension
lines, 6 bird mortalities/km/month for hightension lines,
and about 1 lakh birds/per year within a 4200 sq.km area
in/around Desert National Park, Rajasthan. In terms of
GIB, 6 mortalities have been recorded in Thar during 2017
20, all due to hightension transmission lines – some of
them connected to wind turbine. Therefore, petitioner seeks
undergrounding all future overhead power lines; selected
3 power lines in priority GIB habitat and installation of
divertors in potential habitat.
3. In fact, it is admitted by the Ministry of Power, Union
of India in their affidavit dated 15.03.2021 as follows:
“The Great Indian Bustard (“GIB”) lacks frontal vision. Due to this, they cannot detect powerlines ahead of them, from far. As they are heavy birds, they are unable to manoeuvre across power lines within close distances. Thus, they are vulnerable to collision with power lines. In case of low voltage lines, electrocution is often the cause of death due to smaller phase to phase separation distance. High voltage lines do not cause death due to electrocution but cause death due to collision.”
4. But, this Court while considering IA Nos.1433 and
1477 of 2005 in the case of T.N. Godavarman
Thirumulpad Vs. Union of India & Ors. (2012) 3 SCC 277
has observed as hereunder:
“17. Environmental justice could be achieved only if we drift away from the principle of anthropocentric to ecocentric. Many of our principles like sustainable development, polluterpays principle, intergenerational equity have their roots in anthropocentric principles. Anthropocentrism is always human interest focussed and that nonhuman has only instrumental value to humans. In other words, humans take precedence and human responsibilities to nonhuman based benefits to 4 humans. Ecocentrism is naturecentred where humans are part of nature and nonhumans have intrinsic value. In other words, human interest does not take automatic precedence and humans have obligations to nonhumans independently of human interest. Ecocentrism is therefore lifecentred, naturecentred where nature includes both humans and nonhumans. The National Wildlife Action Plan 20022012 and the Centrally Sponsored Integrated Development of Wildlife Habitats Scheme, 2009 are centred on the principle of ecocentrism.”
In that context while taking note of the contention of the
State relating to lack of funds, reference was made to the
Centrally Sponsored Integrated Development of Wildlife
Habitats Scheme, 2009 which provides for financial
sharing between Centre and State. Though taken note in
the context of conservation of wild buffalo the pattern of
funding was taken note in para23 which provides for
100% central assistance in respect of GIB, for both
recurring and nonrecurring items of expenditure.
5. Further this Court in the case of Centre for
Environmental Law, World Wide Fund – India Vs.
Union of India & Ors., (2013) 8 SCC 234 while
considering the protection and conservation of endangered
5 species has observed as hereunder:
“45. We may point out that there has been wide ranging discussions and deliberations on the international platforms and conferences for re building of certain principles laid down in the earlier conventions on the Principles of Sustainable Development. The United Nations Commission on Environment and Development defined the “sustainable development” as follows:
“Sustainable development is the development that meets the needs of the present without compromising the ability of future generations to meet their own needs.” (World Commission on Economic Development [WCED], 1987 : 43)
46. Sustainable development, it has been argued by various eminent environmentalists, clearly postulates an anthropocentric bias, least concerned with the rights of other species which live on this earth. Anthropocentrism is always human interest focussed thinking that non human has only instrumental value to humans, in other words, humans take precedence and human responsibilities to nonhuman are based on benefits to humans. Ecocentrism is nature centred, where humans are part of nature and nonhumans have intrinsic value. In other words, human interest does not take automatic precedence and humans have obligations to nonhumans independently of human interest.
Ecocentrism is, therefore, lifecentred, nature centred where nature includes both humans and nonhumans.”
6 “48. Article 21 of the Constitution of India protects not only the human rights but also casts an obligation on human beings to protect and preserve a species becoming extinct, conservation and protection of environment is an inseparable part of right to life. In M.C. Mehta v. Kamal Nath [(1997) 1 SCC 388] , this Court enunciated the doctrine of “public trust”, the thrust of that theory is that certain common properties such as rivers, seashores, forests and the air are held by the Government in trusteeship for the free and unimpeded use of the general public. The resources like air, sea, waters and the forests have such a great importance to the people as a whole, that it would be totally unjustified to make them a subject of private ownership. The State, as a custodian of the natural resources, has a duty to maintain them not merely for the benefit of the public, but for the best interest of flora and fauna, wildlife and so on. The doctrine of “public trust” has to be addressed in that perspective.
49. We, as human beings, have a duty to prevent the species from going extinct and have to advocate for an effective species protection regimes. NWAP 20022016 and the Centrally sponsored scheme, 2009 indicate that there are many animal species which are close enough to extinction and some of the other species have already disappeared from this earth. No species can survive on the brink of extinction indefinitely and that the continued existence of any species depends upon various factors like humananimal conflict, epidemics, forest fire and other natural calamities, etc.”
The State as well as the Central Government therefore, 7 have a duty cast to preserve the endangered species and
as such the expenses incurred will have to be provided by
them either under the schemes available or by
earmarking the same in such manner. Needless to
mention that in the instant case the preservation is by
undergrounding the powerlines and in that context if cost
is incurred, it would also be permissible to pass on a
portion of such expenses to the ultimate consumer
subject to approval of the Competent Regulatory
Authority.
6. The respondents though are sensitive to the issue,
have contended that the highvoltage lines do not cause
GIB deaths due to electrocution but cause death due to
collision. It is contended that the underground high
voltage line is not technically feasible due to several
factors such as (i) high cost (ii) high downtime to repair
any failed cable (iii) nonavailability of cables at 765 Kv
level and (iv) increase in the number of joints with length
of run. The petitioners/applicants in order to controvert
the same and contend that the undergrounding of high
8 voltage line is not a novel move but has been undertaken
in other cases, have referred to the tender notification
issued by Power Transmission Corporation of
Uttarakhand Limited for 220 KV transmission line and
the one issued by Delhi Transport Limited for 220 KV
underground cable.
7. In addition, the petitioners have also referred to the
invitation of public comments for laying underground
cable transmission line of 220 KV by the Government of
India, Ministry of Road Transport and Highways. The
report published by the Power Grid Corporation is
referred to indicate that the undergrounding of 220 KV
power line is possible and is being done in India. It is
specifically contended that the 10 km long power lines
were made underground by GETCO for the safety of
Greater Flamingos in the Khadir Region of Kutch.
Similar such instances of underground power lines being
laid is also referred by Mr. Shyam Divan, learned senior
counsel for the petitioner. Ms. Aishwarya Bhati, learned
ASG and Dr. Manish Singhvi, learned senior counsel
9 appearing on behalf of the respondents however sought
to indicate that the instances referred, wherein the tender
notifications were issued for underground power lines
cannot be made comparable in all cases inasmuch as the
same would be possible depending on the area, terrain
and the distance for which such cable line is to be laid
which cannot be of universal application.
8. In that background, keeping in view, the sustainable
development concept and on striking a balance the
protection of the rare species of birds is essentially to be
made, the effort being to save every bird while at the
same time allowing transmission of power in an
appropriate manner. Even as per the study/survey
conducted by the Wildlife Institute of India, it would not
be feasible to lay underground power cables in certain
areas and the conversion of the already existing cables
also cannot be made in certain locations. In such of the
locations, it is recommended that ‘bird divertors’ be
installed on the existing power lines and the
undergrounding of the new power line wherever
technically feasible in the vicinity of the habitats of the
10 rare species of birds be undertaken.
9. The report dated 11.07.2019 was submitted by the
Wildlife Institute before the National Green Tribunal to
that effect and para 4.2 of the report reads as hereunder:
“4.2. Mitigate all power transmission lines passing through priority bustard habitats identified by WII (Please refer Annexure 10) by undergrounding cables (where technically/technologically feasible) or installing bird divertors to make them prominent to birds. The priority areas where this intervention is required has been mapped by the Wildlife Institute of India and a technicalcumfinancial proposal has been submitted to RVPNL for necessary approvals from Rajasthan Energy Department for mitigation. This action must be expeditiously implemented in the shortterm (13 years), as powerline mortality is currently the biggest threat to the species.”
10. In addition to the death of the birds due to collision
and electrocution, the conservation strategy also requires
protecting the eggs of the said species of birds and the
same being transferred to breeding centres for the
purpose of hatching. In that regard, for conservation, the
habitat restoration and for making it predator proof,
appropriate fencing is to be provided to the breeding
11 grounds. In that regard, pictorial representation of the
priority and potential area is indicated in Annexure A7
(page 74) of I.A. No.85618/2020 which is also depicted
here below.
11. In the above background, there cannot be
disagreement whatsoever that appropriate steps are
required to be taken to protect the said species of birds.
In that view, insofar as the existing overhead powerlines
are concerned the respondents shall take steps forthwith
to install divertors and in respect of existing overhead
powerlines all future cases of installing the transmission
lines a study shall be conducted with regard to the
feasibility for the lines to be laid underground. In all such
cases where it is feasible, steps shall be taken to lay the
transmission line underground. For the lines to be laid in
future if as per the technical report the overhead line
alone is feasible and the same is ratified by the
Committee, in such event the installation of the divertors
shall also be a condition attached in the contract to be
entered with generating companies. Insofar as, the cost
incurred in the said process, the concerned respondents
12 No. 5 to 8 and 9 to 11 shall work out and provide for the
same and the respondents No.1 to 4 aid in this regard. It
would be open to them to muster the resources in
accordance with law. In cases where the power
generators are required to bear the additional amount
adding to the cost of production, it would be open to
regulate the manner in which the cost would be mitigated
in accordance with contractual terms. Irrespective of the
cost factor the priority shall be to save the near extinct
birds.
12. In fact, a few suggestions were made in the course of
arguments, as to how financial resources can be mobilised.
One of the options that could be explored, is to invite the
attention of each electricity utility engaged in the generation
of power, to Section 135 of the Companies Act, 2013, which
imposes corporate social responsibility upon companies
having a specified net worth or turnover or net profit.
Section 166(2) of the Companies Act, 2013 ordains the
Director of a Company to act in good faith, not only in the
best interest of the Company, its employees, the
13 shareholders and the community, but also for the protection
of environment. The word “environment”, though not
defined in the Companies Act, has to be given the meaning
assigned to it under the Environment (Protection) Act, 1986.
Section 2(a) of the Environment (Protection) Act, 1986,
defines the word “environment” to include the “inter
relationship which exists among and between water, air and
land, and human beings, other living creatures, plants, micro
organisms and property”
Moreover, with the implementation of the Compensatory
Afforestation Fund Act, 2016 (CAF, 2016), substantial
funds are available with the National and State
Authorities. Sections 4, 5 and 6 of the Act, provide for
the utilisation of the fund for measures to mitigate
threats to wildlife. The State of Rajasthan has already set
up a Compensatory Afforestation Fund Management and
Planning Authority (CAMPA) on 12.11.2009. Rule 5(2)(i)
of these Rules permit the use of the State Fund for the
improvement of wildlife habitat. It appears, according to
the petitioners that a sum of Rs.47,436 crores, out of a
14 total of Rs.54,685 crores CAMPA Fund have been
transferred by the Union Environment Ministry to the
States for afforestation projects.
13. With regard to the conservation of the habitat to
secure the safety of the eggs laid by the birds, the area
earmarked and indicated as islands and shown in
AnnexureA7 and in light colour in sketch here below
shall be fenced and protected from invasion by predators
so that the eggs laid in these areas are protected. The
power supply line regarding which underground passage
is to be made should also avoid these areas.
14. In the light of the contentions urged on this aspect
of the matter, we are conscious that the laying of the
underground power line more particularly of highvoltage
though not impossible, would require technical
evaluation on casetocase basis and an omnibus
conclusion cannot be reached laying down a uniform
method and directions cannot be issued unmindful of the
fact situation. Though that be the position the
consensus shall be that all low voltage powerlines to be
laid in the priority and potential habitats of GIB shall in
15 all cases be laid underground in future. In respect of low
voltage overhead powerlines existing presently in the
priority and potential habitats of GIB, the same shall be
converted into underground powerlines. In respect of
highvoltage powerlines in the priority and potential
habitats of GIB, more particularly the powerlines referred
in the prayer column of I.A. No.85618/2020 and
indicated in the operative portion of this order shall be
converted into underground power line. The potential
and priority area in Kutch and Thar respectively are as
per the sketch shown below:
16 17
While considering the laying of underground power line
the said habitats shall be kept in perspective and steps be
taken for the safety of the GIB in the said habitat.
15. As already taken note above, the laying of high
voltage underground power line would require expertise to
assess the feasibility of the same. For this specific
purpose of assessing the feasibility after taking into
consideration all technical details, we deem it proper to
constitute a committee consisting of the following
members:
(i) Dr. Rahul Rawat, Scientist, Room No.021, Block14,
Ministry of New and Renewable Energy, CGO Complex, Lodi Road, New Delhi.
(ii) Dr. Sutirtha Dutta, Scientist, Wildlife Institute of India, Dehradun.
(iii) Dr. Devesh Gadhavi, Deputy Director, The Corbett Foundation.
The above committee may also obtain technical
reports if need be, from experts in the field of electricity
18 supply to arrive at their decision. The Government of India
shall provide all assistance to the Committee.
16. The details of the powerlines from Kutch for
installation of bird divertors is as follows:
a) List of powerlines from Kutch for Capacity installation of divertors
1) Kukdau to Vingaber (8.86 Km) Unknown
2) Vingaber to Lala (4.84 Km) Unknown
3) Agriculture area near highway NH Unknown 41 (0.53 KM)
4) Agriculture area near highway NH Unknown 41 (0.86 KM)
5) Khirsara village to Khotara town Unknown (3.42 Km)
6) Prajau Substation to Prajau Village Unknown on road side (2.81 Km)
7) Part of Bhamedi to Naliya (4.44 Km) Unknown
8) Part of Fulay vandh to Naliya Unknown Jakhau Road (10.9 Km)
9) Part of Kothara Naliya line (9.1 Km) Unknown
10) Part of KotharaNaliya Line (6.90 Unknown km)
11) Part of Vanku to Fulay Vandh Unknown (6.25 km)
The details of the powerlines for installation of
divertors from Rajasthan are as follows:
b) List of powerlines for Capacity installation of divertors from Rajasthan 1) Jaisalmer – Ramgarh 1 (40 Km) 132 kv 2) Jaisalmer – Ramgarh 2 (40 Km) 132 kv
19
3) Askandra (Pokran to Askandra ) 132 kv (30 Km)
4) Askandra (Pokran to Askandra ) 132 kv (20 Km)
5) Amarsagar – Ramgarh (40 Km) 220 kv
6) Amarsagar – Lilo (8 Km) 220 kv
7) Amarsagar – Phalodi (54 Km) 220 kv
8) Amarsagar – Phalodi (71 Km) 220 kv
9) Ramgarh Dechu (49 Km) 220 kv
10) Ramgarh Dechu (43 Km) 220 kv
11) Ramgarh Dechu (50 Km) 220 kv
12) Akai – Ramgarh (55 Km) 400 kv
13) Tejuva – Kuchadi (138 km) 33 kv
14) Kaladongar (70 Km) 33 kv
15) Mokla – Habur – Sanu (301 km) 33 kv
16) Tejuva – Kuchadi (25 km) 132 kv
17) Kaladongar (47 km) 132/220 kv
18) Mokla – Habur – Sanu (43 km) 132/220 kv
19) Chandan Via Bhagu ka Gaon to 33 kv Mohangarh (70 km)
20) Amarsagar – Ramgarh (40 km) 220 kv
21) Amarsagar – Ludarva (4 km) 33 kv
The details of the powerlines to be converted to
underground subject to feasibility, if not, to immediately
install divertors;
Lines from Kutch
a) List of powerlines from Kutch for Capacity undergrounding
1) 220 KV GETCO line next to breeding 220 KV site 13 cables (3.19 Km)
2) Bhachunda GIB habitat to Sandhav Unknown River line (2.1 Km)
3) Bhanada to Valram Society (6.1 Km) 66 KV
4) GETCO Substation to Dhanawada – Unknown Nanawada (9.81 Km)
20
5) GETCO Substation to Kothara Unknown Mothala Road (9.69 Km)
6) Jakhau to Prajau road substation Unknown (10.9 Km)
7) Jakhau to Sindhodi (8.39 Km) Unknown
8) Jakhau to Sindhodi (8.53 Km) Unknown
9) Jakhau to Sindhodi (8.57 Km) Unknown
10) JakhauVanku Road to Prajau Road Unknown substation (3.43 Km)
11) Kalatalav Khirsara Road (9.0 Km) Unknown
12) Khirsara Kothara (8.20 Km) Unknown
13) Khirsara to Kothara River Unknown Wastelands (2.24 Km)
14) Kunathiya GETCO to Bitta & around 220 kv Adani Solar (6.65)
15) Kunathiya GETCO to Tera (7.32 Km) 66 KV
16) Kunathiya GETCO towards Rava 66 KV (3.34 km)
17) Lala to Jakhau (11.6 Km) Unknown
18) Line near Khorsara (2.77 Km) Unknown
19) Line near Lala village (1.45 Km) Unknown
20) NaliyaKothara Road (6.58 Km) Unknown
21) NaliyaKothara Highway (15.0 Km) Unknown
22) NaliyaKothara Highway Line (15.7 Unknown km)
23) NaliyaKothara Road to Prajau (9.15 Unknown Km)
24) NaliyaKothara Road to VankuLala 66 KV Road (10.8 km)
25) Prajau Road (5.57 Km) Unknown
26) Prajau to NaliyaJakhau Road Unknown
27) Prajau Road line passing through Unknown Naliya Grasslands (4.43 km)
28) Prajau Road substation to Naliya Unknown Kothara Road substation
29) Prajau village to Prajau Road (5.82 Unknown Km)
30) Part of Bhamedi to NaliyaJakhau Unknown Road (8.19 km)
31) Part of Fulay Vandh to Naliya Unknown
21 Jakhau Highway (8.27 Km)
32) Part of KotharaNaliya (8.82 Km) Unknown
33) Part of KotharaNaliya line (9.36 km) Unknown
34) Part of Vanku to Fulay Vandh line (1 Unknown km)
35) Khirsara to Highway River Unknown Wastelands (1.59 Km)
36) Kunathiya GETCO to Bhanada 66 KV Village via Agri Farms (12.1 km)
Lines from Rajasthan
b) List of powerlines from Rajasthan Capacity for undergrounding
1) KanoiSalkha (21 Km) 33 kv
2) SamDhanana (45 Km) 33 kv
3) TejuvaKuchr (17 Km) 33 kv
4) Khuchri horizontalparallel (21 Km) 33 kv
17. The respondents No.5, 6 and 9 to 11 while arranging
to lay the powerlines underground in respect of the
powerlines, the feasibility of which is not in doubt shall
proceed with the work right away. However, in cases where
the respondents find that there are issues relating to
feasibility, the matter shall be referred to the committee
with all relevant material and particulars. The committee
shall assess the matter and arrive at a conclusion as to
whether the underground powerline is feasible or not.
Based on the report to be rendered by the committee the
further action shall be taken by the respondent.
22
18. In all cases where the overhead powerlines exist as
on today in the priority and potential GIB area the
respondents shall take steps forthwith to install divertors
pending consideration of the conversion of the overhead
cables into underground powerlines. In all such cases
where it is found feasible to convert the overhead cables
into underground powerlines the same shall be undertaken
and completed within a period of one year and till such
time the divertors shall be hung from the existing
powerlines.
19. Ordered accordingly.
..…………....................CJI.
(S. A. Bobde)
…..…………....................J. (A.S. Bopanna)
..…..………......................J. (V. Ramasubramanian)
New Delhi, April 19, 2021
23
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free