J.K. Paper Fibre Resources vs Sunit Jagdishchandra Shah Resolution ...

National Company Law Appellate Tribunal5 March 2025Ashok Bhushan

Ratio decidendi

The rule this decision rests on

Where the Committee of Creditors has, before the expiry of the 330-day outer limit, taken a considered decision to seek further extension of the CIRP period to complete consideration of pending resolution plans, and the Adjudicating Authority has granted such extension prior to approving the plan, the Adjudicating Authority may approve a resolution plan after 330 days; the Essar Steel judgment does not wholly exclude extension beyond 330 days where only a short period remains to complete the process. An Operational Creditor whose aggregate dues are not less than 10% of the debt is entitled to notice of CoC meetings and to attend and express views, but has no right to vote; the failure to furnish such a creditor with the detailed valuation report, where the CoC has considered and minuted the reasons for sharing only fair value and liquidation value and the valuation reports were placed before the voting members, does not amount to a material irregularity causing prejudice to that creditor. Non-publication of Form-G on the websites of the Corporate Debtor and IBBI is not a ground for interference at the instance of an Operational Creditor who did not raise the objection when the expressions of interest were received and who has no demonstrated prejudice, since the requirement principally bears on prospective resolution applicants. Section 30(2)(b) is satisfied where the amount provided for operational creditors under the plan is not less than their liquidation entitlement under Section 53; where the liquidation value available to operational creditors is nil, a plan providing a positive sum to them complies with the provision, and an operational creditor bound by a plan approved by more than 66% of the voting share cannot resist it on that ground. The scope of review of a resolution plan by the Adjudicating Authority and the Appellate Authority is confined to the matters in Section 30(2) (and, on appeal, Section 61(3)); so long as the statutory provisions of the IBC and the CIRP Regulations are complied with, the commercial wisdom of the CoC, here reflected in a 97.36% approval, cannot be substituted by the Adjudicating Authority, which may not examine the merits of the plan save where it is contrary to express provisions of law or the public interest.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

NATIONAL COMPANY LAW APPELLATE TRIBUNALPRINCIPAL BENCH, NEW DELHICompany Appeal (AT) (Insolvency) No. 76 of 2025

[Arising out of the Impugned Order dated 27.11.2024 passed by the Adjudicating Authority, National Company Law Tribunal, Ahmedabad Bench-II in IA(Pan)/6(AHM)2024 in CP(IB)/9(AHM)2021] In the matter of: J.K. PAPER FIBRE RESOURCES Through its Partner Mr. Jitendra K. Shah 6th Floor, Elite Square 274 Perin Nariman Street, Fort, Mumbai 400 001 ...Appellant Versus Sunit Jagdishchandra Shah Resolution Professional of Shree Rajeshwaranand Paper Mills Limited. 801-802, 8th Floor, Abhijeet 1, Nr. Milhakhali Six Roads, Navrangpura, Ahmedabad 380009 Gujarat ...Respondents

Present: For Appellant : Mr. Romy Chako, Sr. Advocate with Mr. Ajay Kumar Tiwari, Advocates. For Respondent : Ms. Honey Satpal, Mr. Yash Dhyani, Ms. Pooja Singh and Mr. Akash Agarwalla, Advocates.

JUDGMENT

(Hybrid Mode)

Per: Barun Mitra, Member (Technical)

The present appeal filed under Section 61 of Insolvency and Bankruptcy

Code 2016 ('IBC' in short) by the Appellant arises out of the Order dated 27.11.2024 (hereinafter referred to as 'Impugned Order') passed by the

Adjudicating Authority (National Company Law Tribunal, Ahmedabad Bench-

II) in IA No 6 of 2024 in CP(IB)/9(AHM)2021. By the impugned order, the

Adjudicating Authority has approved the resolution plan of the Corporate

Debtor as submitted by the Resolution Professional. Aggrieved by the

impugned order, the present appeal has been preferred by the Appellant-

Operational Creditor.

2. The sequence of events which are necessary to be noticed for deciding

the present appeal are as follows:

 On 07.12.2022, the CIRP of the Corporate Debtor was initiated and IRP

was appointed.

 The IRP constituted the CoC comprising of two Secured Financial

Creditors and two Unsecured Financial Creditors. The first CoC meeting

was held on 13.01.2023.

 On 10.03.2023, the Form-G was published by the IRP inviting EOIs.

 On 05.06.2023, the CIRP period of 180 days had expired. The

Resolution Professional ("RP" in short) filed an application before the

Adjudicating Authority for extension of CIRP period for 90 days which

was allowed on 19.06.2023.

 In the 14th CoC meeting held on 29.08.2023, the CoC resolved to extend

the CIRP period beyond 270 days. This was allowed by the Adjudicating

Authority on 06.10.2023.

Page 2 of 15 Company Appeal (AT) (Insolvency) No. 76 of 2025  On 19.10.2023, the 17th CoC meeting directed the RP to file application

for extension of CIRP period as it wanted to discuss the resolution plan

submitted by Mercury Terra Firma.

 On 30.12.2023, the Adjudicating Authority allowed extension of CIRP

period upto 10.12.2023, while also directing the RP to expedite the CIRP

process.

 The 19th CoC meeting held on 01.11.2023 decided to reissue Form-G.

Accordingly, the RP republished Form-G on 03.11.2023.

 The CoC considered the EOIs received in the 21st and 22nd CoC

meetings. Since the 23rd CoC meeting held on 04.12.2023 was still

considering the resolution plans and needed further time for

consideration and the CIRP period was expiring on 10.12.2023, the RP

moved the Adjudicating Authority for seeking further extension of CIRP

for a period of 60 days.

 Extension of CIRP period upto 20.02.2024 was allowed on 08.01.2024

by the Adjudicating Authority.

 On 29.01.2024 the CoC approved the resolution plan submitted by

Mercury Terra Firma which was approved with 97.36% voting.

 The Adjudicating Authority passed the impugned order on 27.11.2024

approving the resolution plan.

 Aggrieved by the impugned order approving the resolution plan, the

present appeal has been preferred by the Appellant- Operational

Creditor.

Page 3 of 15 Company Appeal (AT) (Insolvency) No. 76 of 2025

3. Making his submissions, the Ld. Counsel for the Appellant submitted

that the Adjudicating Authority approved the resolution plan in violation of

Section 12 of the IBC by allowing repeated extensions of CIRP even beyond

330 days. Extension had been allowed beyond the period of 330 days without

adequate justification. It was submitted that the Hon'ble Supreme Court in its

judgment in Committee of Creditors of Essar Steel India Vs Satish Kumar

Gupta in Civil Appeal No. 8766-67 of 2019 clearly provided that the

resolution process was required to be completed within the outer limit of 330

days from insolvency commencement date including extensions. Highlighting

other procedural and material irregularities, it was submitted that the RP had

re-published the Form-G on 03.11.2023 only in the newspapers and not on

the website of IBBI or the Corporate Debtor which amounted to non-

compliance of Regulation 36-A(2) of the IBBI (Insolvency Resolution Process

for Corporate Persons) Regulations, 2016 ("CIRP Regulations" in short). It is

also contended that the RP did not circulate the valuation report of the

Corporate Debtor either to the Appellant or to other members of the CoC but

only furnished bare figures of fair value and liquidation value. In the absence

of valid and detailed valuation reports, the CoC would have been handicapped

to exercise its commercial wisdom judiciously. However, the Adjudicating

Authority has overlooked these procedural irregularities in approving the

resolution plan.

4. It was also pointed out that the RP had admitted Rs 7,40,60,531/- as

against Rs 7,61,15,758/- claimed by the Appellant and that the aggregate

admitted claim of all Operational Creditors put together worked out to Rs Page 4 of 15 Company Appeal (AT) (Insolvency) No. 76 of 2025 18,34,60,969/-. However, as against a composite claim of Rs 18.34 Cr. of the

Operational Creditors, the Successful Resolution Applicant has offered only

Rs 60 lakhs for payment to Operational Creditors which was shockingly low.

The resolution plan therefore prejudiced the interests of Operational Creditors

and amounted to non-compliance with Section 30(2)(b) of IBC.

5. Refuting the contentions raised by the Appellant, the Ld. Counsel for

the Respondent submitted that the resolution plan could have been

challenged only on the grounds laid down under Section 61(3) of the IBC but

no such grounds have been substantiated by the Appellant in the present

appeal. On the contention that the RP had only shared naked figures of fair

value and liquidation value instead of providing the detailed valuation report,

it was submitted that the 17th CoC meeting had after due deliberations

recorded the reasons for not sharing the full valuation report with the

Appellant. In any case, the Appellant being an Operational Creditor having no

voting rights it was of no consequence whether the detailed valuation report

was placed before them or not since it was the members of the CoC who were

required to exercise their commercial wisdom on the valuation reports placed

before them. Moreover, the Appellant had participated in the CoC meetings

but not having raised any objections earlier on this count cannot do so now.

6. It was also contended that in terms of the judgment of the Hon'ble

Supreme Court in Essar Steel supra, the Adjudicating Authority was

empowered to complete the resolution process by extending the 330 day time-

line. It was submitted by the Respondent that the Adjudicating Authority had

also rejected objections taken by the Suspended Management against Page 5 of 15 Company Appeal (AT) (Insolvency) No. 76 of 2025 extension of time-lines. It was contended that the Appellant has failed to

explain how it was aggrieved by the resolution plan which had been approved

by the Adjudicating Authority after allowing extended time-lines. The

Appellant had been a regular participant in the CoC meetings but never

opposed the extension of CIRP time-lines. Not having raised such objections

earlier, the Respondent cannot raise this issue at this belated stage. It was

also pointed out that the Respondent cannot complain about the treatment

meted out to the Operational Creditors in the resolution plan since they had

received more than the minimum entitlement in terms of liquidation value

which was kept at Nil for Operational Creditors. It was also pointed out that

when the resolution plan had been approved by the CoC with 97.36% voting,

the Adjudicating Authority had no option to traverse beyond the commercial

wisdom of the CoC. In any case, it was vehemently contended that the

resolution plan already stands implemented and therefore cannot be reversed

when the Appellant has failed to make out any ground as to how the resolution

plan was non-compliant of Section 30(2) of IBC.

7. We have duly considered the arguments advanced by the Learned

Counsel for both the parties and perused the records carefully.

8. The short point for our consideration is whether there were material

irregularities in the exercise of powers by the RP in the CIRP proceedings;

whether the claims of the Operational Creditors did not receive their dues or

whether there was any contravention of the provisions of law.

Page 6 of 15 Company Appeal (AT) (Insolvency) No. 76 of 2025

9. Coming to the contentions raised by the Appellant with regard to

material and procedural irregularities, we find that the Appellant has assailed

the impugned order approving the resolution plan on the ground that the plan

was approved by the Adjudicating Authority after expiry of 330 days of CIRP

period at a time when this outer time-line could not have been breached in

terms of the Essar judgment.

10. There is no doubt that in terms of Section 24(3)(c) of the IBC, it is the

duty of the RP to give notice to the Operational Creditors or their

representatives regarding the CoC meetings if the amount of their aggregate

due is not less than 10% of the debt. It is also well settled that such

Operational Creditors whose aggregate due is not less than 10% of the debt

have a right to watch the proceedings of the CoC and express their views in

the meetings without however any right to vote. In the present case, there is

no denial of the fact that the Appellant received notice of the CoC meetings

from the RP. As the Appellant was kept informed of the CoC meetings and

records show their regular participation in such meetings, they had full

knowledge of the CIRP proceedings. They were therefore equally aware of the

extensions of CIRP time-lines approved by the CoC but these extensions by

the CoC were not questioned by them at the appropriate time. The issue was

neither agitated before the Adjudicating Authority at the right point of time

and is now being raked up belatedly.

11. Further when we look at the material on record, it is an undisputed fact

that the resolution plan in the present case was approved by the Adjudicating

Authority beyond 330 days. Be that as it may, we also notice that the Page 7 of 15 Company Appeal (AT) (Insolvency) No. 76 of 2025 Adjudicating Authority had already approved the extension of CIRP period on

08.01.2024 which date was before 29.01.2024 when the plan was approved.

In the present case, the 23rd CoC meeting on 04.12.2023 had taken note of

the fact that it was in an advanced stage of considering the resolution plans

before it and since the extended CIRP period was getting expired on

10.12.2023, the CoC approved seeking further extension of CIRP period.

Clearly enough, CoC having taken a considered decision in this regard, this

constituted sufficient grounds for the Adjudicating Authority to extend further

time beyond 330 days for completion of the CIRP process. The Essar

judgment supra which has been relied upon by the Appellant does not come

to their rescue since this judgment does not completely rule out the possibility

of CIRP extension beyond 330 days particularly so when a short period is left

for completion of CIRP.

12. In such circumstances, we are not persuaded to accept the contention

of the Appellant that the resolution plan could not have been approved by the

Adjudicating Authority since the CIRP timeline had stood exhausted.

13. Yet another perceived irregularity contended by the Appellant is that

though Regulation 35(2) of the CIRP Regulations makes it incumbent on the

part of the RP to provide fair value, liquidation value and valuation report to

every member of the CoC, the same was not done.

14. To appreciate the above allegation better, we need to look at the minutes

of the 17thCoC meeting wherein this issue was discussed in details which is

as extracted hereunder:

"Agenda 7) Any other matters relevant to the present case subject to approval of Chairman.

Page 8 of 15 Company Appeal (AT) (Insolvency) No. 76 of 2025 One of the CoC members i.e. Riddhi Siddhi GlucoBiols Limited represented by their authorised representative required and insisted the RP to provide them the Valuation Reports of the Corporate Debtor to share ahead with prospective buyers.

The RP informed that he can only share the Fair Value & Liquidation Value of the Corporate Debtor. The RP drew their attention to the regulations of the IBC, 2016 that as per the Regulation 35(2) of the Insolvency and Bankruptcy Board of India (Insolvency Resolution Process for Corporate Persons) Regulations, 2016 which is quoted below:

"After the receipt of resolution plans in accordance with the Code and these regulations, the resolution professional shall provide the fair values and the liquidation value to every member of the committee in electronic form, on receiving an undertaking from the member to the effect that such member shall maintain confidentiality of the fair value and the liquidation value and shall not use such values to cause an undue gain or undue lass to itself or any other person and comply with the requirements under sub-section (2) of section 29"

The RP even informed the CoC members that such liquidation value and fair value were already sent and shared with all the CoC members. He further informed that CoC members also cannot share the values with anyone as they have provided the undertaking as per the Regulation 35(2) of the Insolvency and Bankruptcy Board of India (Insolvency Resolution Process for Corporate Persons) Regulations, 2016 and Section 29 of the Insolvency & Bankruptcy Code, 2016."

15. When we look at the above 17th CoC meeting proceedings, we find

that the issue of sharing of the detailed valuation report had been raised

therein by one of the CoC members - Riddhi Siddhi GlucoBiols Limited. We

find that the CoC had considered this issue in the meeting and minuted the

reasons for only sharing the bare figures of the fair value and liquidation

value of the Corporate Debtor. Besides the fact that this matter was duly

Page 9 of 15 Company Appeal (AT) (Insolvency) No. 76 of 2025 considered, deliberated and decided upon by the CoC in its commercial

wisdom, it is also pertinent to note that since the Operational Creditor had

no right to vote in the meeting of the CoC, they cannot be said to have

suffered from any prejudice for not being provided with the valuation report.

Whether the detailed valuation report was placed before the Appellant or

not was immaterial since it was the members of the CoC who were required

to exercise the commercial wisdom on the valuation reports placed before

them and not the Appellant who did not have the right to exercise their vote.

The bogey of non-sharing of the detailed valuation report as a ground

evidencing material or procedural irregularity therefore lacks force.

16. Even the ground raised by the Appellant that Form-G had not been

published on the websites of the Corporate Debtor and IBBI lacks force of

contention since this is again another much belated complaint. It does not

lie in their mouth to agitate this matter now when they had slept over this

issue all along when the EoIs were received. Further, non-publication of

Form-G has a bearing on the interests of the potential resolution applicants

who have not raised any such complaint. The Appellant in their capacity as

Operational Creditor cannot rightfully claim that their interests were

prejudicially affected on this count. Moreover, it is ironical that on the one

hand the Appellant has been expressing concern over CIRP timelines having

been crossed and yet a belated complaint is being thrown up pushing the

plan approval process into disarray.

17. Yet another contention of the Appellant was that the plan was wrongly

approved by the Adjudicating Authority without the plan conforming to the

Page 10 of 15 Company Appeal (AT) (Insolvency) No. 76 of 2025 statutory provision as contained in Section 30(2)(b) of the IBC. This argument

was premised on the ground that the Appellant as Operational Creditor had

not been allocated amount as per their entitlement under Section 30(2)(b) of

IBC.

18. To decide on the tenability of the above argument, we may first notice

the provisions contained in Section 30(2)(b) of the IBC which reads as follows:

Section 30: Submission of resolution plan.

30. (2) The resolution professional shall examine each resolution plan received by him to confirm that each resolution plan--

(a) provides for the payment of insolvency resolution process costs in a manner specified by the Board in priority to the payment of other debts of the corporate debtor;

(b) provides for the payment of debts of operational creditors in such manner as may be specified by the Board which shall not be less than-

(i) the amount to be paid to such creditors in the event of a liquidation of the corporate debtor under section 53; or

(ii) the amount that would have been paid to such creditors, if the amount to be distributed under the resolution plan had been distributed in accordance with the order of priority in sub-section(1) of section 53, whichever is higher, and provides for the payment of debts of financial creditors, who do not vote in favour of the resolution plan, in such manner as may be specified by the Board, which shall not be less than the amount to be paid to such creditors in accordance with sub-

section (1) of section 53 in the event of a liquidation of the corporate debtor.

Explanation 1.-For removal of doubts, it is hereby clarified that a distribution in accordance with the provisions of this clause shall be fair and equitable to such creditors.

19. From a plain reading of the above statutory provision, the entitlement

of an Operational Creditor is to receive the amount as provided under Section

30(2)(b) of IBC which is not less than the amount which the Appellant would Page 11 of 15 Company Appeal (AT) (Insolvency) No. 76 of 2025 have been entitled to receive in the event of a liquidation of the Corporate

Debtor under Section 53 of the IBC. When we see the material on record, we

find that the fair value of the Corporate Debtor was Rs 45.85 Cr and the

liquidation value was Rs 33.16 Cr with no amount specified for Operational

Creditors. On the other hand, when we see the plan features at para 15 of the

impugned order, the plan provides for Rs. 60 lakhs for Operational Creditors

which sum was clearly more than the liquidation value which was their

minimum entitlement. That being so, the resolution plan cannot be said to be

in dissonance with the provisions of Section 30(2)(b) of IBC.

20. Furthermore, the resolution plan having been approved by more than

66% of vote share by the CoC, such plan cannot be interfered with by the

Adjudicating Authority merely on the grounds that the Operational Creditors

were being paid Rs 60 lakhs at a time when no amount has been specified for

Operational Creditors in terms of liquidation value. We are of therefore of the

considered view that since the liquidation value in the present case is nil, the

Operational Creditors including the Appellant cannot have any grievance

against the amount being paid to them since the amount paid under the plan

to the Operational Creditors is clearly more than the liquidation value.

21. The resolution plan has been approved with a majority of 97.36% of vote

share. The plan having been approved by majority of votes, the Operational

Creditor is clearly bound by the approved resolution plan. We therefore are of

the considered view that the Adjudicating Authority did not commit any error

while approving the resolution plan after noting its satisfaction at para 26 of

Page 12 of 15 Company Appeal (AT) (Insolvency) No. 76 of 2025 the impugned order about the plan being in compliance of the provisions of

the IBC in terms of Section 30(2) of the IBC.

22. It may be useful to notice that Section 30 of the IBC which deals with

submission of Resolution Plan and sub-section (6) thereto states that "the

resolution professional shall submit the Resolution Plan as approved by the

Committee of Creditors to the Adjudicating Authority". In the present case, the

RP after approval of the plan by the CoC with 97.36% vote share filed an

application before the Adjudicating Authority seeking approval of the

Resolution Plan under Section 31 of the Code. Section 31 deals with approval

of Resolution Plan. Section 31(1) provides that if the Adjudicating Authority is

satisfied that the Resolution Plan as approved by the CoC under Section 30(4)

meets the requirements as referred to in Section 30(2), it shall by order

approve the resolution plan which shall be binding on the Corporate Debtor

and other stakeholders involved in the Resolution Plan. It is also pertinent to

note that the Adjudicating Authority has noted at para 20 of the impugned

order that the CoC has satisfied itself that the resolution plan meets the

requirement of being viable and feasible for revival of the Corporate Debtor.

That the CoC also expressed its satisfaction that the plan was in accordance

with Section 30 of the IBC and compliant with CIRP Regulations 38 has been

noticed at para 18 of the impugned order. Furthermore, the Adjudicating

Authority has noticed at para 26 of the impugned order that the plan was in

accordance with Sections 30 and 31 of the IBC and complies with Regulations

38 and 39 of CIRP Regulations.

Page 13 of 15 Company Appeal (AT) (Insolvency) No. 76 of 2025

23. Law is now well settled that the jurisdiction of the Adjudicating and

Appellate Authorities to interfere with approval of the resolution plan is

limited. The scope of judicial review is confined to the provisions contained in

Section 30(2) of the IBC for the Adjudicating Authority and Section 30(2) read

with Section 61(3) for the Appellate Authority. There is only limited review

which can be exercised by the Adjudicating Authority or the Appellate

Authority. There can be no fetters on the commercial wisdom of CoC. The

supremacy of commercial wisdom of CoC has been reaffirmed time and again

by the Hon'ble Supreme Court in a catena of judgements - K. Sashidhar v.

Indian Overseas Bank (2019) 12 SCC 150 ; Committee of Creditors of

Essar Steel India Limited v. Satish Kumar Gupta (2020) 8 SCC 531;

Maharashtra Seamless Limited v. Padmanabhan Venkatesh (2020) 11

SCC 467; Kalpraj Dharamshi v. Kotak Investment Advisors Limited,

(2021) 10 SCC 401 and Ghanashyam Mishra and Sons Private Limited

through the Authorized Signatory v. Edelweiss Asset Reconstruction

Company Limited through the Director (2021) 9 SCC 657.

24. So long the statutory provisions of the IBC and the CIRP Regulations

framed thereunder are complied with, it is the commercial wisdom of the

requisite majority of the CoC which is to negotiate and accept a resolution

plan. Once all the mandatory requirements have been duly complied with and

taken care of, judicial review cannot be extended to analyse and look into the

dissatisfaction evinced by any particular creditor or stakeholder. The

Adjudicating Authority cannot substitute its views with the commercial

wisdom of the CoC nor deal with the merits of Resolution Plan unless it is

Page 14 of 15 Company Appeal (AT) (Insolvency) No. 76 of 2025 found it to be contrary to the express provisions of law and against the public

interest. There is neither any material irregularity nor contravention of any

provisions of law by the CoC which has been justifiably substantiated by the

Appellant. In the present case when no valid grounds have been made out to

challenge the approval of the resolution plan, the legislative fiat of the IBC

that the Adjudicating Authority cannot trespass upon the business decision

of the CoC holds ground. We have no doubts in our mind that the plan has

been rightly approved by the Adjudicating Authority.

25. In result, we do not find any good ground to interfere with the

impugned order approving the resolution plan. There is no merit in the

appeal. The Appeal is dismissed. No costs.

[Justice Ashok Bhushan] Chairperson

[Barun Mitra] Member (Technical)

[Arun Baroka] Member (Technical)

Place: New Delhi Date: 05.03.2025

Abdul/Harleen

Page 15 of 15 Company Appeal (AT) (Insolvency) No. 76 of 2025

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.