International Road Dynamics South Asia ... vs D.A. Toll Road Pvt. Ltd
- CitationCompany Appeal (AT) (Insolvency) No. 72 of 2017
Ratio decidendi
The rule this decision rests on
The arbitration clause in the underlying agreement is not, by itself, a ground for rejecting an application under Section 9 of the Insolvency and Bankruptcy Code, 2016. A Section 9 application cannot be rejected merely because the corporate debtor is solvent. An application under Section 9 that combines claims arising out of separate agreements or work orders, carrying different amounts and different dates of default, is defective and not maintainable, since each distinct claim has its own cause of action and cannot be clubbed together to establish a default of debt. Where a claim is shown to be time-barred or the delay in moving the forum is unexplained, the claimant must explain the delay and laches; the court makes no finding on whether the Limitation Act, 1963 applies to proceedings under the Code. Where the material before the Adjudicating Authority shows a reconciliation between the parties that reduces the claimed default, and the claim is hit by limitation in part, the existence of a dispute as to the claim requires elaborate enquiry, which is not contemplated under the Code, and the application may be rejected on that basis.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
International Road Dynamics South Asia Pvt. Ltd. . ...Appellant
Versus
Reliance Infrastructure Ltd. ...Respondent
Company Appeal (AT) (Insolvency) No. 77 of 2017
IN THE MATTER OF:
International Road Dynamics South Asia Pvt. Ltd. .. .Appellant
Versus
D.A. Toll Road Pvt. Ltd. ...Respondent
Present: For Appellants: Shri Joydip Bhattacharya, Shri Surendra Kumar and Shri Mayank Sharma, Advocates
For Respondent: Shri Hasan Murtaza, Advocate
ORDER
01.08.2017 As both the appeals have been preferred by the appellant -
International Road Dynamics South Asia Pvt. Ltd., they were heard together and
disposed of by this common judgment.
2. In Company Appeal (AT) (Insolvency) No. 72 of 2017, the appellant has
challenged the order dated 29th March, 2017 passed by the learned Adjudicating
Authority (National Company Law Tribunal, Mumbai Bench, Mumbai) whereby the
application preferred by the appellant under Section 9 of the Insolvency &
Bankruptcy Code, 2016 (hereinafter referred to as the 'I & B Code') for initiation of Insolvency Resolution Process (IRP) against the respondent - Reliance
Infrastructure Ltd. ('Corporate Debtor') has been rejected.
3. In other case, Company Appeal (AT) (Insolvency) No. 77 of 2017, similar
application under Section 9 of the I & B Code preferred by the appellant against
the 'Corporate Debtor'- D.A. Toll Road Pvt. Ltd. has been rejected by the Learned
Adjudicating authority, Mumbai Bench, Mumbai by the impugned order dated 3rd
April, 2017.
4. In the case of Reliance Infrastructure Ltd., apart from the other grounds,
learned Adjudicating Authority while held that 'Operational Creditor' can initiate
'Arbitration proceedings', further held that the facts of the case do not warrant to
invoke Section 9 of the I&B Code.
5.. Learned counsel for' the appellant submits that there is no dispute in
existence. In such case, merely on the ground that there is an arbitration clause
in the agreement or that the 'Corporate Debtor' is solvent, the application under
Section 9 cannot be rejected, if otherwise complete.
6. Learned counsel for the respondent - Reliance Infrastructure Ltd. submitted
that there are existing disputes and the application preferred by the appellant under
Section 9 is not complete. According to him, claim with regard to three different
projects arising out of three different agreements have been mingled together to
show outstanding dues, without explaining the date of default. Further, according
to him some of the claims are time barred.
7. Having heard learned counsel for the parties, insofar as Company Appeal (AT)
(Insolvency) No. 72 of 2017 is concerned, while we hold that 'alternative remedy of
arbitration' cannot be a ground to reject an application under Section 9 and no
application under Section 9 can be rejected on the ground that 'Corporate Debtor'
is solvent. Though, we hold above, but for the reasons recorded below we are not
inclined to interfere with the impugned order dated 29th March, 2017.
8. From the notice dated 21st January, 2017 issued by the appellant under
Section 8 to 'Corporate Debtor' - Reliance Infrastructure Ltd., we find that the claim
has been made with regard to outstanding dues on account of 'three different
projects' arising out of three separate work orders. For example, with regard to 'GF
Toll Project', the total payment made by the 'Corporate Debtor' is Rs. 5,41,07,993/-
including the last payment of Rs. 1,06,55,322 made on 17th May, 2013 as pleaded
by appellant. The amount of Rs.2,84,52,328/- is shown to be due.
If the last payment made by the 'Corporate Debtor' on 17th May, 2013, then
why the appellant did not chose to move before any Forum for more than four years,
particularly when three years prescribed under the Limitation Act, 1963 for filing a
suit for money claim has not been explained. However, we make it clear that we
are not giving any specific finding on the question as to whether Limitation Act,
1963 is applicable or not in filing application for corporate resolution process under
the I&B Code, but certainly the claimant is required to explain the delay and laches.
9. The other claim relates to 'DS Toll Project' and 'NK Toll Projects', arising out
of two different work orders. With regard to 'DS Toll Project', it is stated that till date
entire amount of Rs. 28,31,430/- is due. The said amount has been added with
Rs.2,84,52,328/- in respect of 'GF Toll Project', which arise out of separate work
order.
10. We are of the view that different claim(s) arising out of different agreements
or work order, having different amount and different dates of default, cannot be
clubbed together for alleged default of debt, the cause of action is being separate.
For the said reasons, we hold that the joint application preferred by appellant under
Section 9 is defective, as distinct from incomplete, and, was not maintainable.
11. Learned counsel for the respondent also highlighted 'existence of dispute' in
regard to non-completion of the project within the time, and, the counter-claim as
made by the respondent - 'Corporate Debtor'. However, in absence of any document enclosed, showing dispute raised prior to issuance of Section 8 notice, we are not
deciding such issue.
For the reason aforesaid, we are not inclined to interfere with the impugned
order dated 29th March, 2017, though it is open to the appellant to move separate
application in respect of separate work orders/ contracts, if not barred by limitation
or delay and laches and if there is no dispute after following the procedure laid
down under I & B Code and Rules framed thereunder.
12. Insofar as the proceedings against 'D A Toll Road Pvt. Ltd.' is concerned, the
learned Adjudicating Authority by impugned order dated 3rd April, 2017 noticed the
relevant fact. It was noticed that the 'Corporate Debtor' - DA Toll Pvt. Ltd. was
making part payment from time to time in respect to invoices of the creditors, in
the process of which last payment was made on 26th September, 2013. Ever since,
no further payment was made by the 'Corporate Debtor' towards alleged claimed
amount of Rs.65,22,971/- which alleged to be outstanding. The learned
Adjudicating Authority while noticed that cause of action took place on 26th
September, 2013 and a reconciliation between the Creditor and Corporate Debtor
made on 13th August, 2015 stating that outstanding amount due to the Creditor is
Rs.25,03,900/- and beneath the said reconciliation statement, a note was entered
by an employee of debtor company namely Ajay Sharma stated that the bills on
hold come to Rs.40,19,071/- and bills were not brought forward into the books of
the debtor company to show that the total amount due was Rs.65,22,971/-, the
Tribunal accepted the plea taken on behalf of the appellant that since the
howing reconciliation has entered into between the parties on 13th August, 2015 showing-
an amount of Rs. 40,19,071/- needs to be credited in the debtor company's account
therefore, the outstanding amount of default of Rs.65,22,971/- has been doubted.
For the reason aforesaid, the learned Adjudicating Authority held that there is a dispute of claim and some part of such claim is hit by limitation, it needs elaborate
enquiry and not permitted under I&B Code, 2016
13. We find no merit in both the appeal(s).
14. In the result, no interference is called for. Both the appeals stand disposed
of with the observations as made above. However, there shall be no order as to
costs.
[Justice S.J. Mukhopadhaya] Chairperson
[Balvinder Singh] Member (Technical)
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free