Independent Sugar Corporation Limited vs Committee Of Creditor Of Hindusthan ...
- CitationCompany Appeal (AT) (Insolvency) No.516 of 2025
Ratio decidendi
The rule this decision rests on
Where the Supreme Court's direction under Section 31(4) IBC requires the CoC to reconsider a resolution plan, the Adjudicating Authority must decide all pending applications, including the plan approval application and objections going to the continuance of the Resolution Professional, rather than halting the plan process by interim order; an interim restraint that stalls the process so frustrates that direction and delays the corporate debtor's resolution, and so cannot be sustained. An order of the Adjudicating Authority that is clarified by a later order of the same authority is to be read in accordance with that clarification; so read, an earlier direction to the effect that no further steps be taken pursuant to a CoC resolution does not operate as a restraint on the process.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
NATIONAL COMPANY LAW APPELLATE TRIBUNAL, PRINCIPAL BENCH, NEW DELHI Company Appeal (AT) (Insolvency) No.516 of 2025 (Arising out of Order dated 11.03.2025 passed by the Adjudicating Authority (National Company Law Tribunal), Kolkata Bench, Kolkata in IVN. P (IBC)/5(KB)2025 in C.P.(IB)/369(KB)2020)
IN THE MATTER OF: Independent Sugar Corporation Ltd. ...Appellant
Versus
Committee of Creditors of Hindusthan National Glass & Industries Ltd. & Ors. ...Respondents
Present: For Appellant : Mr. Ritin Rai, Sr. Advocate with Mr. Rishav Banerjee, Mr. Utsav Trivedi, Ms. Pooja Chakrabarti, Ms. Kiran Sharma, Ms. Manini Roy, Mr. Mridul Godha and Ms. Nandini Acharya, Advocates. Mr. Yadnath Bhargavan, Mr Akshay Chandra, Advocates for Intervenor/Impleading Applicant. For Respondents : Mr. Siddhant Kant and Ms. Gayathri Balasubramanian, Advocates for R-1/CoC. Mr. Abhishek Anand and Mr. Mohit Gupta, Advocates for CoC. Mr. Krishnendu Datta, Sr. Advocate with Mr. Vikram Wadhera, Ms. Smriti Churiwal, Mr. Jaiveer Kant, Mr. Akhil Nene, Advocates for R-2/RP. Mr. Joy Saha, Ms. Liz Mathew, Sr. Advocates with Abhijeet Sinha, Mr. Bhagavathy and Ms. Aastha Vishwakarma, Advocates for R-3.
JUDGMENT
ASHOK BHUSHAN, J.
This Appeal has been filed challenging order dated 11.03.2025
passed by National Company Law Tribunal, Kolkata Bench in IVN. P
Company Appeal (AT) (Ins.) No.516 of 2025 1 (IBC)/5(KB)2025. The Appellant aggrieved by the order has come up in
this Appeal.
2. Brief background facts necessary to be noticed for deciding the
Appeal are:
i. Corporate Insolvency Resolution Process ("CIRP") was
initiated against Hindusthan National Glass & Industries Ltd.
- Corporate Debtor ("CD") vide order dated dated 21.10.2021.
Mr. Girish Sriram Juneja (Respondent No.2 herein) was
appointed as Interim Resolution Professional ("IRP"), who was
latter confirmed as Resolution Professional ("RP") of the CD.
ii. In the CIRP of the CD, three Resolution Plans were received,
i.e. by the Appellant, AGI Greenpac ("AGI") and Nirma
Chemical Works Private Limited. CoC on 28.10.2022
approved the Resolution Plan of AGI with 98% vote share. The
Resolution Plan of the Appellant received 88% vote share.
iii. The AGI - Resolution Applicant had submitted an Application
with the Competition Commission of India ("CCI") seeking
approval to enter into combination with the CD. The CCI on
15.03.2023 granted approval to AGI combination proposal
with the CD. There have been challenge to the order of CCI.
The NCLT rejected the Application on 28.04.2023. An Appeal
and various Applications were filed in Company Appeal (AT)
(Ins.) No.735 of 2023 before this Tribunal. This Tribunal vide
order dated 18.09.2023 upheld the approval granted to the
Company Appeal (AT) (Ins.) No.516 of 2025 2 AGI observing that prior approval was only 'directory'. The
Appellant also challenged CCI approval dated 15.03.2023
before the NCLAT, which order was upheld by NCLAT on
28.07.2023. The Appellant filed Civil Appeal before the
Hon'ble Supreme Court, challenging both the orders i.e.
28.07.2023 and 18.09.2023. The Hon'ble Supreme Court
vide its order dated 29.01.2025 set aside the approval
granted to the Resolution Plan of AGI, holding that approval
of CCI is mandatory before Resolution Plan can be approved
by the CoC. The Hon'ble Supreme Court by its judgment
dated 29.01.2025, issued following directions:
"155. The upshot of the above discussion are the following orders:
155.1. The AGI Greenpac's Resolution Plan is unsustainable as it failed to secure prior approval from the CCI, as mandated under the proviso to Section 31(4) of the IBC. Consequently, the approval granted by the CoC to the Resolution Plan dated 28.10.2022 without the requisite CCI approval, cannot be sustained and is hereby set aside and quashed.
155.2. Any action taken pursuant to the Resolution Plan shall stand nullified, and the rights of all stakeholders shall be restored as per status quo ante, prior to the approval of the Resolution Plan by the CoC on 28.10.2022.
155.3. Consequently, the CoC shall reconsider the Appellant's Resolution Plan and any other Resolution Plans which possessed the requisite CCI approval as on 28.10.2022 i.e., the date on which the CoC voted upon the submitted Resolution Plans."
Company Appeal (AT) (Ins.) No.516 of 2025 3 iv. On 30.01.2025, Insolvency and Bankruptcy Board of India
("IBBI") issued a show cause notice to the RP - Mr. Girish
Sriram Juneja . The Adjudicating Authority on 04.02.2025,
taking into consideration the direction of the Hon'ble
Supreme Court, directed the CoC to consider the Plan
submitted by H2 Bidder i.e. Appellant. The CoC in its
Meeting dated 04.02.2025 approved the Resolution Plan of
the Appellant and also resolved to file an Application seeking
extension of CIRP period. I.A. 269/KB/2025 has been filed
by RP, praying for various reliefs, including extension of
CIRP.
v. The Adjudicating Authority on 14.02.2025 framed certain
questions with respect to resolution process. On 14.02.2025,
the Adjudicating Authority observed that it hopes and trust
that till the matter is finally heard, no further steps would be
taken by the CoC or RP pursuant to the 'resolution' adopted
on 04.02.2025. The Applications were heard on 27.02.2025.
The RP also filed an Application before the Adjudicating
Authority seeking approval of Resolution Plan being IA (Reso
Plan) 6/KB/2025. An Appeal in this Tribunal was also filed
challenging order dated 27.02.2025, which was dismissed by
this Tribunal on 07.03.2025
vi. The Application - INV. P (IBC) No.5/KB/2025 was filed by
Soneko Marketing Pvt. Ltd., an Operational Creditor, praying
Company Appeal (AT) (Ins.) No.516 of 2025 4 for intervention. The said Application came for consideration
before the Adjudicating Authority on 11.03.2025, on which
date, following order was passed by the Adjudicating
Authority:
"IVN.P (IBC)/5(KB)2025
Heard Ld. Sr. Counsel for the parties on the interim relief.
Let reply affidavit be filed to this application by the respondent within a period of five days from today. Consequent upon filing of reply affidavit, rejoinder if any, be filed within next five days. Both the parties are hereby directed to supply advance copy to each side as stated above.
In the meantime, RP is hereby directed not to proceed with the decisions on any resolution plan. However, he will continue to run the CIRP process and keep the company is going concern. It is made clear that pleadings should be completed in all eventuality before the date fixed and no further adjournment will be given for hearing of this application. The matter will be heard on the date fixed.
Registry is hereby directed to list the matter on the top of Board. Ld. Sr. Counsel for the parties are hereby directed to remain present for hearing on the date fixed. Ld. Counsel for the parties are further directed to file written submission, if any, not more than three pages in support of their arguments.
List the matter on 26/03/2025 for hearing."
vii. Subsequent to the order dated 11.03.2025, the Adjudicating
Authority passed an order on 17.03.2025 in IA(IB)
No.269/KB/2025, where various reliefs were claimed,
including extension of CIRP period. The Adjudicating
Company Appeal (AT) (Ins.) No.516 of 2025 5 Authority in its order dated 17.03.2025 took the view that
post the IA(IB) No.269/KB/2025 was reserved for orders, the
CP-369/KB/2020 has been transferred to another Bench.
Hence, Adjudicating Authority refrained from commenting on
all other matters associated with the present case and the
same may be taken up before the Bench, where the matter is
transferred. The Adjudicating Authority however, on prayer
of the RP for clarification, granted following clarification in
paragraph 18:
"18. In regard to the prayer "a" of the application seeking clarification of the order dated 10.02.2025 we have already clarified in presence of all the parties that filing of IAs have not restrained and applications have already been filed by the CoC and RP which have been entertained by this Tribunal even after the order of 10.02.2025."
3. This Appeal has been e-filed on 24.03.2025 challenging the order of
Adjudicating Authority dated 11.03.2025. On 27.03.2025, the Appeal
was taken for consideration and on the request made by learned Counsel
for the Respondent, the matter was fixed for 28.03.2025. The Appeal was
heard on the said date and the order was reserved.
4. We have heard Shri Ritin Rai, learned Senior Counsel appearing for
the Appellant; Shri Joy Saha, learned Senior Counsel appearing for
Respondent No.3, who had filed the Application for Intervention Petition
No. IBC)/5(KB)2025. We have also heard Shri Krishnendu Datta, learned
Senior Counsel for the RP and learned Counsel appearing for the CoC/
Respondent No.1.
Company Appeal (AT) (Ins.) No.516 of 2025 6
5. Learned Counsel for the Appellant in support of the Appeal submits
that by order of the Hon'ble Supreme Court dated 29.01.2025, the
Hon'ble Supreme Court has directed for consideration of the Appellant's
Resolution Plan and any other Resolution Plan, which possessed the
requisite CCI approval as on 28.10.2022, i.e. the date on which the CoC
voted upon the Resolution Plan of AGI. In view of the direction of the
Hon'ble Supreme Court, it was obligatory on the CoC and the RP to
consider the Resolution Plan of the Appellant. After the order was passed
by the Hon'ble Supreme Court, a show cause notice dated 30.01.2025
was issued to the RP by IBBI, which show cause notice has no effect on
continuation of the RP in the present proceedings. Such initiation of
show cause notice result in automatic suspension of RP's Authorization
for Assignment ("AFA") granted to the RP, which debars the RP from
taking any fresh assignment. However, issuance of show cause notice,
does not prohibit the RP to continue with the existing engagement. After
the order of the Hon'ble Supreme Court various applications have been
filed by Operational Creditor, i.e. suspended Management, by filing
different Intervention Applications to stall the process of approval of
Resolution Plan. The Application - Inv. P (IBC)/5(KB)2025 was filed only
with the said object and Adjudicating Authority committed error in
passing an interim order on 11.03.2025, directing the RP not to proceed
with the decision on any Resolution Plans, which interim order is
unsustainable. It is submitted that the interim order passed by
Adjudicating Authority has effect of stopping the RP and the CoC from
complying the order of Hon'ble Supreme Court dated 29.01.2025. It is
Company Appeal (AT) (Ins.) No.516 of 2025 7 submitted that Adjudicating Authority itself by order dated 17.03.2025
clarified that filing of IAs have not restrained and Applications have
already been filed by the CoC and RP, which have been entertained by the
Tribunal even after the order of 10.02.2025 (correct date is 14.02.2025).
Learned Counsel for the Appellant submits that Appellant's only prayer in
this Appeal is that Adjudicating Authority may be directed to proceed with
the Plan approval application and all other Application/ Intervention
Applications and decide the same. Learned Counsel for the Appellant
submits that although by issue of show cause notice, there is no embargo
on the RP with respect to continuing with the existing assignment,
however, this Tribunal may direct the NCLT to treat all pending
Applications as objections to the Plan approval application and decide the
same, so that order of the Hon'ble Supreme Court dated 29.01.2025 be
implemented.
6. Shri Joy Saha, learned Senior Counsel appearing for Respondent
No.3 - Soneko Marketing Pvt. Ltd., who had filed Intervention Application
No.(IBC)/5(KB)2025, opposing the Appeal contends that the effect of
issuance of show cause notice by the IBBI is automatic suspension of AFA
of the RP. The AFA having been suspended automatically, the RP cannot
proceed, in the present proceedings. The Adjudicating Authority has
rightly restrained the RP from proceeding with the Resolution Plan.
Learned Counsel has relied on the judgment of High Court of Madras in
CA. V. Venkata Sivakumar vs. Insolvency and Bankruptcy Board of
India - (2024) SCC OnLine Mad 156 as well as judgment of High Court
Company Appeal (AT) (Ins.) No.516 of 2025 8 of Bomaby in Kairav Anil Trivedi vs. Insolvency and Bankruptcy
Board of India and ors. - (2024) SCC OnLine Bom 2572.
7. Learned Counsel for the CoC submits that the Resolution Plan
having been approved by the CoC on 04.02.2025, Application for approval
of Resolution Plan needs to be considered. It is submitted that
Intervenors, dissenting secured Financial Creditors and Suspended
Management are trying to stall the CIRP by filing one after another
Intervention Applications. It is submitted that by issuance of show cause
notice, the RP is not prohibited from continuing the existing assignment.
The RP cannot take any new assignment in view of suspension of AFA.
Reference has been made to Regulation 7A of IBBI (Insolvency
Professional) Regulations, 2016.
8. We have considered the submissions of learned Counsel for the
parties and have perused the records.
9. The Appellant is aggrieved by the following part of the impugned
order i.e. "In the meantime, RP is hereby directed not to proceed with the
decisions on any resolution plan". The submission of the Appellant is that
all Intervention Applications and objections to the Resolution Plan need to
be considered simultaneously by the Adjudicating Authority and the
process need not be stopped. The issuance of show cause notice dated
30.01.2025 in no manner prohibit the RP to continue with the
assignment. In any view of the matter, the Hon'ble Supreme Court has
directed for consideration of Resolution Plan of the Appellant by the CoC
and RP submitted as on 28.10.2022.
Company Appeal (AT) (Ins.) No.516 of 2025 9
10. The submission canvassed before us by contesting parties is
regarding engagement of RP to continue in the process or not. Admittedly,
Intervention Petitions (IBC)/5(KB)2025 and other Applications are still
pending and have still not been finally decided. When the Hon'ble
Supreme Court had directed the CoC to reconsider the Resolution Plan of
the Appellant as on 28.10.2022, we are of the view that the Resolution
Plan Application along with all objections regarding continuance of the RP
in the CIRP, need to be finally decided by the Adjudicating Authority.
Stopping the process will further delay the resolution of the CD. We have
already noticed that IA 269/KB/2025 has already been filed by the RP for
extension of timeline of the CIRP. The Hon'ble Supreme Court having
directed for consideration of Resolution Plan of the Appellant, the
Adjudicating Authority has to consider and pass an appropriate order on
the said Application, which Application is also now pending for
adjudication.
11. Shri Joy Saha, learned Senior Counsel for Respondent No.3 has
submitted that Adjudicating Authority has already passed an order on
14.02.2025, where the Adjudicating Authority directed "we hope and
trust that till the matter is finally heard and disposed of, no further steps
would be taken by the CoC or RP pursuant to the 'resolution' adopted on
04/02/2025 and 10/02/2025". The submission is that the order dated
14.02.2025 being continuing and which order was never challenged, the
Adjudicating Authority has rightly passed the impugned order on
11.03.2025. We noticed above that Adjudicating Authority in its order
Company Appeal (AT) (Ins.) No.516 of 2025 10 dated 17.03.2025 in IA 269/KB/2025 has issued clarification. The
Adjudicating Authority, which had passed order on 14.02.2025, have
clarified that 'filing of IAs have not restrained and applications have
already been filed by the CoC and RP, which have been entertained by this
Tribunal even after the order of 10.02.2025 (correct date is 14.02.2025)'.
In view of the above clarification dated 17.03.2025, we are of the view that
order dated 14.02.2025, cannot be read in a manner as submitted by
Learned Counsel for Respondent No.3. Learned Counsel for Respondent
No.3 submitted that order was never challenged. However, Learned
Counsel for RP has contended that Application for clarification was
already filed being IA 269/KB/2025, which clearly covered the issue. We,
thus, are of the view that in view of the clarification order dated
17.03.2025, order dated 14.02.2025, cannot be read as any kind of
restraint put by the Adjudicating Authority.
12. The present is a case where CIRP has commenced as early as on
21.10.2021 and the process has not reached to its culmination. We are of
the view that in view of the order of the Hon'ble Supreme Court dated
29.01.2025, the Adjudicating Authority need to proceed with the
consideration of all pending Applications, including Plan approval
Application and Application - IVN. P (IBC)/5(KB)2025 and decide all
issues, including competency of the RP to participate in the ongoing
process. Applications being pending before the Adjudicating Authority,
we refrain ourselves from expressing any opinion on the submissions
regarding continuance of the RP as noticed above. Ends of justice will be
Company Appeal (AT) (Ins.) No.516 of 2025 11 served in disposing the Appeal by deleting the following directions from
the impugned order:
"....In the meantime, RP is hereby directed not to proceed with
the decisions on any resolution plan. ...."
13. We further are of the view that Adjudicating Authority may
proceed to consider all pending Applications, including Resolution Plan
approval Application, i.e. I.A. 269/KB/2025 and IVN. P (IBC)/5(KB)2025
and all other pending Applications and decide the same at the earliest in
accordance with law. The Appeal is disposed of accordingly. There shall
be no order as to costs.
[Justice Ashok Bhushan] Chairperson
[Barun Mitra] Member (Technical)
[Arun Baroka] Member (Technical)
NEW DELHI
4th April, 2025
Ashwani
Company Appeal (AT) (Ins.) No.516 of 2025 12
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free