Miss Lucy
← All judgments

Godrej & Boyce Mfg.Co Ltd vs Satec Envir Engineering India Pvt Ltd

National Company Law Appellate Tribunal6 May 2022

Ratio decidendi

The rule this decision rests on

In an application under Section 9 of the Insolvency and Bankruptcy Code, 2016, the adjudicating authority must reject the application where the corporate debtor has shown a pre-existing dispute, meaning a plausible contention requiring further investigation that is not a patently feeble legal argument or an assertion of fact unsupported by evidence, and that is not spurious, hypothetical or illusory; the existence of such a dispute need not be established by a pending suit or arbitration, since "dispute" under Section 5(6) includes a dispute as to the quality of goods or services. Where the operational creditor's claim is premised on payments to be made directly by a third-party end user under a comfort letter, the question whether the corporate debtor remains liable is a matter of the contractual and communicative record, and the mere existence of such direct-payment arrangements does not by itself displace a pre-existing dispute on the quality of supplied goods where that dispute is documented before the demand notice.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

NATIONAL COMPANY LAW APPELLATE TRIBUNAL PRINCIPAL BENCH, NEW DELHI COMPANY APPEAL (AT) (INSOLVENCY) No. 438 of 2022 (Arising out of Order dated 25.02.2022, passed by National Company Law Tribunal, Mumbai Bench, Court-III, in C.P. (IB) No. 982/(MB)/2020)

IN THE MATTER OF:

Godrej & Boyce Mfg. Co. Ltd. Pirojshahnagar, Vikhroli, Mumbai, Maharashtra - 400079. Through its Branch Commercial Manager Mr. Ajay Mathur ...Appellant

Versus

Satec Envir Engineering (India) Pvt. Ltd. Plot No. A/107 - 108, TTC Industrial Area, MIDC, Khairane, Thane - Belapur Road, Navi Mumbai, Thane, Mumbai - 400705. ...Respondent

For Appellant: Mr. Arun Kathpalia Sr. Advocate with Surekha Raman, Advocates. For Respondent: Ms. Milky Ghoshal, Advocate.

JUDGEMENT

[Per: Shreesha Merla, Member (T)]

1. Aggrieved by the Impugned Order dated 25/02/2022, passed by the

Learned Adjudicating Authority (National Company Law Tribunal, Mumbai

Bench, Court-III) in C.P. (IB) No. 982(MB)/2020, 'M/s. Godrej & Boyce

Manufacturing Co. Ltd.'/the 'Operational Creditor' preferred this Appeal under

Section 61 of the Insolvency and Bankruptcy Code, 2016, (hereinafter referred

to as 'The Code'). By the Impugned Order, the Adjudicating Authority has

dismissed the Application filed by the Appellant/'Operational Creditor' under

Section 9 of the Code against 'M/s. Satec Envir Engineering (India) Pvt.

Ltd.'/the 'Corporate Debtor', observing as follows: -2-

13. The Bench notes that in a letter dated 20.12.2018 addressed to IOCL, the Petitioner who are the contractors themselves had mentioned to IOCL, that the racking material due to exposure to rains and dust during installation and because of negligence and improper storage had corroded. Therefore, the Petitioner had strongly recommended that IOC should not use the racking system as the same is not certified for safe use.

14. It is clear to the Bench that and as admitted by Petitioner that there are serious problems with the racking system installed by them and also admits that the system has not yet undergone a safety audit and, therefore, was a non-certified weak racking. The Petitioner itself requested IOCL "not to use the system any further as the same has not been certified for safe use". The Petitioner ends the letter by saying that "Hope u find this in order and would ensure that the safety alert being raised is taken seriously and necessary correctives are undertaken without any further delay." The Bench notes that instead of rectifying the defective work, the Petitioner abandoned the Haldia project and did not carry out any work on the project.

15. The Bench also notes that both the work orders required 100% completion of the work as a pre-

condition for payment. Admittedly, the project has not been completed and that is the reason that the Petitioner cannot claim the payment for such defective and incomplete work. The Bench also notes that demand notice was issued by the Petitioner on 23.10.2019. However, there are genuine pre-existing disputes much prior to the issuance of the demand notice. It is well settled that an applicant u/s 9 of the IBC is required to be dismissed if genuine dispute exists between the parties. In recent Judgment of Hon'ble Supreme Court in Kay Bouvet Engineering Ltd us. Overseas Infrastructure Alliance (India) Private Limited 2021 SC OnLine SC 570, the Hon'ble Supreme Court developed upon the law relied upon its earlier judgment in Mobilox and held that:

"17... All that the adjudicating authority is required to see at this stage is, whether there is plausible contention which requires further investigation and that the dispute is not a patently feeble legal argument or an assertion of fact unsupported by evidence. It is important to separate the grain from the chaff and to reject a Company Appeal (AT) (Insolvency) No. 438 of 2022 -3-

spurious defence which is a mere bluster. It has been held that however, at this stage, the Court is not required to be satisfied as to whether the defence is likely to succeed or not. The Court also cannot go into the merits of the dispute except to the extent indicated hereinabove. It has been held that so long as a dispute truly exists in fact and is not spurious, hypothetical or illusory, the adjudicating authority has no other option but to reject the application."

16. In this Petition the Petitioner has clubbed the payments of two projects, one each at Bongaigaon and Haldia under two different work orders as part of a single Petition. This, as per the Bench, in terms of the clubbing of two claims under different work orders for different amount is not permissible. As per the pronouncement made by Hon'ble NCLAT in the matter of International Road Dynamics South Asia Put. Ltd. [Company Appeal (AT) (Insolvency) No. 72 of 2017] where the NCLAT had held the following:

"10. We are of the view that different claims) arising out of different agreements or work order, having different amount and different dates of default, cannot be clubbed together for alleged default of debt, the cause of action is being separate. For the said reasons, we hold that the joint application preferred by appellant under Section 9 is defective, as distinct from incomplete, and, was not maintainable."

2. Submissions of the Learned Sr. Counsel appearing on behalf of the

Appellant:

• It is submitted that the 'Corporate Debtor', engaged primarily in

executing Orders from the Government and the other customers for

Warehouse Development and three fabrications work Project

approached the Appellant for supply and installation of a Multitier

Racks for Heavy Duty Shelving for two separate work sites for the end

user i.e., Indian Oil Corporation Ltd. (IOCL) at Haldia, West Bengal and

Bongaigaon, Assam respectively.

Company Appeal (AT) (Insolvency) No. 438 of 2022 -4-

• A Purchase Order dated 18/05/2017, for the supply of Multitier Heavy

Duty Shelving amounting to Rs.1,43,94,240/- was issued for the Haldia

Project along with a corresponding Work Order dated 18/05/2017, for

the installation of the Multitier Heavy Duty Shelving amounting to

Rs.8,05,000/-. The payment terms for Purchase Order inter alia

comprised of 30% advance along with 'Advance Bank Guarantee', 60%

against Letter of Credit (LC) before dispatch and 10% against

commissioning.

• For the Project at Bongaigaon, a distinct Purchase Order dated

01/06/2017, for the supply of Multitier Heavy Duty Shelving

amounting to Rs.83,40,030/- accompanied with Work Order bearing

No. SEE/BJ/WO-038/2017-18 dated 01/06/2017, for the installation

of the Multitier Heavy Duty Shelving amounting to Rs.4,60,000/- were

issued by the Respondent. The payment terms for the Purchase Order

mirrored the Haldia site i.e., 30% advance along with 'Advance Bank

Guarantee', 60% against LC before dispatch and 10% against

commissioning and the payments terms for the Work Order was

identical to the terms in the Haldia site.

• It is submitted that the total value of the invoices raised by the

Appellant upon the 'Corporate Debtor' is Rs.2,45,51,513/- vide 34

invoices pertaining to the supply and installment at both Haldia and

Bongaigaon. Despite several requests the outstanding payments were

not made.

• On 07/12/17, the 'Corporate Debtor' vide an email admitted that an

amount of Rs.1,35,49,360.17/- was outstanding and due and payable

Company Appeal (AT) (Insolvency) No. 438 of 2022 -5-

for the IOCL Haldia site and an amount of Rs.83,40,030/- was

outstanding and due and payable for the Bongaigaon site.

• Learned Sr. Counsel drew our attention to the Comfort Letter issued by

IOCL on 23/01/2018 undertaking to release the payments to the tune

of Rs.42,41,947.64/-; the balance against completion of the erection of

the racking system and the rest i.e., Rs.63,62,921.47/- would be

released after completion of the job in totality with first preference to

the Appellant after due certification by the 'Corporate Debtor' and

acceptance of the PMC. It is submitted that in their email dated

07/02/2018, the Appellant pointed out discrepancies in the amounts

proposed to be paid by IOCL as mentioned in the Comfort Letter.

• Learned Sr. Counsel strenuously contended that there was no 'Pre-

Existing Dispute' and that the end user IOCL had given a Comfort Letter

only on account of the outstanding dues to be paid by the 'Corporate

Debtor'. Subsequently, there was correspondence between the parties

i.e., the Appellant and IOCL regarding deficit in the amounts mentioned

in the Comfort Letter. On 08/02/2018, IOCL addressed an email

stating that they cannot go beyond the Contractual Value mentioned in

their Work Order. On 13/02/2018, the Appellant addressed an email

to 'Engineering (India) Ltd.' (EIL) who were the Project Management

Consultants of IOCL to register the Appellant's complaint against the

'Corporate Debtor' as an amount of Rs.1.44Crs./- was still unpaid for

the Haldia site and Rs.89 Lakhs/- for Bongaigaon site.

• Thereafter there was communication on 03/05/2018, 16/08/2018,

09/02/2018, 20/02/2018 and on 23/01/2018 between the Appellant

and the IOCL. On 27/10/2018, there was a Meeting held between IOCL Company Appeal (AT) (Insolvency) No. 438 of 2022 -6-

and the Appellant and EIL and payment terms for the completion was

discussed. EIL addressed a letter dated 30/11/2018 informing the

Appellant inter alia, that some shortcomings were noticed in the

Inspection Report and requested the Appellant to deploy an experienced

engineer for rectification of the same. On December 20, 2018, the

Appellant addressed a letter to IOCL regarding the safety of the Godrej

Racking System installed at the IOCL factory. It was pointed out that

the racking material which was delivered, was lying outside in the open

without adequate protection and exposed to direct rain and dust. The

Appellant also stated that the same should be used after a safety check

to avoid any mishaps. On December 27, 2018, the Appellant addressed

a letter to IOCL that the request to start work as mentioned in the letter

dated 27/10/2018 has not been issued. Thereafter vide an email dated

14/01/2019, the Appellant informed EIL that it would not be possible

for the Appellant to execute the work without a formal Purchase Order

from IOCL.

• On 11/07/2019, the Appellant addressed an email to the 'Corporate

Debtor' that as per the Purchase Order terms, the advance payments of

only Rs.11,25,000/- was made (which is only to be 9% of the Order

Value) against a total due of Rs.37,63,200/- and that Rs.1,40,74,240/-

was overdue since last more than two years and that there was no

response from the 'Corporate Debtor'.

• The Appellant had issued a Demand Notice under Section 8 of the Code

claiming an amount of Rs.3,33,90,057/- on 23/10/2019. On

20/12/2019, the 'Corporate Debtor' replied to the Appellant's Demand

Notice stating that there was no 'Operational Debt' 'due and payable', Company Appeal (AT) (Insolvency) No. 438 of 2022 -7-

but had not raised any dispute prior to the issuance of the Demand

Notice nor placed any documents on record annexing to their Reply;

that there were any pending disputes between the 'Corporate Debtor'

and the Appellant herein.

• Learned Sr. Counsel contended that the Adjudicating Authority has

failed to consider that the 'Corporate Debtor' was raising a dispute after

the issuance of the Demand Notice merely as an afterthought and that

there was no 'Pre-Existing Dispute' between the parties and that merely

because there was a possibility of accepting direct payments from IOCL,

on account of the Comfort Letter given, the 'Corporate Debtor' cannot

be absolved of its Contractual Rights or obligations under the terms and

conditions of the Purchase Orders and Work Orders.

• It was only because IOCL was the end user that they had issued a

Comfort Letter dated 23/01/2018 stating that due to severe fund

crunch of the 'Corporate Debtor', IOCL was undertaking to release the

payments to the Appellant in respect of the supply and instalment work

for both Haldia and Bongaigaon sites.

• Learned Sr. Counsel submitted that the Adjudicating Authority has

wrongly observed that the contents of the letter dated 20/12/2018

addressed by the Appellant to IOCL signifies that there were disputes

with regard to the work carried by the Appellant. The Appellant had

completed the supply of all materials as per the Purchase Orders at

both the sites and there were no 'Pre-Existing Disputes' between the

parties.

Company Appeal (AT) (Insolvency) No. 438 of 2022 -8-

3. Submissions of the Learned Counsel appearing for the

Respondent/'Corporate Debtor':

• Learned Counsel for the 'Corporate Debtor' submitted that after 2018,

the 'Operational Creditor' had never contacted the 'Corporate Debtor'

and was directly in touch with IOCL, the end user and a Comfort Letter

dated 23/01/2018 was issued by IOCL to the 'Operational Creditor'

which signifies that a fresh contract was executed between them.

• Learned Counsel drew our attention to the letter dated 28/01/2018 in

support of her contention that the entire communication was between

IOCL and the Appellant with offers and counter offers having been

exchanged.

• It was further submitted that after rounds of negotiations, the Appellant

had finally accepted the amounts offered by IOCL and that there was

absolutely no privity of contract between the 'Corporate Debtor' and the

Appellant subsequent to 2018 and that disputes were raised by IOCL

which required rectification by the Appellant only.

4. The main point for consideration is whether there were any 'Pre-

Existing Disputes' between the 'Corporate Debtor' and the Appellant

herein/'Operational Creditor' and whether the Adjudicating Authority was

justified in dismissing the Section 9 Application.

5. Learned Sr. Counsel for the Appellant drew our attention to the

Purchase Order issued by the Appellant to the 'Corporate Debtor' to specify

that the payment terms are 30% advance payment, 50% against LC before

dispatch and 10% against commission.

6. For better understanding of the case, the letter dated 23/01/2018

addressed by IOCL to the Appellant is being reproduced as hereunder:

Company Appeal (AT) (Insolvency) No. 438 of 2022 -9-

(Emphasis Supplied)

7. From the aforenoted letter, it is clear that the 'Corporate Debtor' was

undergoing financial crunch on account of which the end user M/s. IOCL has

undertaken to make the payment to the tune of Rs.42,41,947.64/- against

completion of erection of the racking system and the balance would be

released after the completion of the job in totality, with due certification by Company Appeal (AT) (Insolvency) No. 438 of 2022 -10-

the 'Corporate Debtor'. It is the case of the 'Corporate Debtor' that this

communication signifies that it is the end user IOCL which has undertaken

to pay the amounts for and on behalf of the 'Corporate Debtor' and hence no

liability can be fastened upon them.

8. At this juncture, to understand whether there is any direct payments

made by IOCL/promised to be made by IOCL, we also reproduced subsequent

letter dated 07/02/2018 hereunder:

Company Appeal (AT) (Insolvency) No. 438 of 2022 -11-

(Emphasis Supplied)

9. From this letter, it is clear that the amount was to be paid directly by

IOCL to the Appellant and IOCL had undertaken to make good the deficit

amounts also.

10. The material on record evidences that on 03/05/2018, a Comfort Letter

was requested to be issued by the Appellant to IOCL against the Purchase

Order for the supply of instalment of Multitier Racks for Heavy Duty Shelving.

The correspondence dated 16/08/2018 between the Appellant and IOCL

further strengthens the argument of the Respondent that the payment would

be realized by IOCL after complete erection of system and the balance after

completion of entire racking system.

11. It is pertinent to mention that the communication dated 08/09/2018

and 20/10/2018 addressed by the Appellant to IOCL request that as per the

Comfort Letter, the total amount proposed as direct payment by IOCL to the

Appellant is to be released at the earliest.

Company Appeal (AT) (Insolvency) No. 438 of 2022 -12-

12. It is the case of the Respondent/'Corporate Debtor' that even for the

Review Meeting the 'Corporate Debtor' was not present and it was held

between IOCL and EIL and the Appellant herein. The Minutes too do not

record the presence of the 'Corporate Debtor'. From the aforenoted

communication, this Tribunal is of the considered view that the payments

were to be made, as per the Comfort Letter, by IOCL to the Appellant herein.

13. Now we address ourselves to the main issue as to whether there is any

'Pre-Existing Dispute' existing between the parties prior to the issuance of the

Notice mandated under Section 8 of the Code, based on the touchstone of the

ratio of the Hon'ble Supreme Court in 'Mobilox Innovations Pvt. Ltd.' Vs.

'Kirusa Software Pvt. Ltd.' (2018) 1 SCC 353, where in the Hon'ble Apex Court

has observed as follows:-

"40. It is clear, therefore, that once the operational creditor has filed an application, which is otherwise complete, the adjudicating authority must reject the application under Section 9(5)(2)(d) if notice of dispute has been received by the operational creditor or there is a record of dispute in the information utility. It is clear that such notice must bring to the notice of the operational creditor the "existence" of a dispute or the fact that a suit or arbitration proceeding relating to a dispute is pending between the parties. Therefore, all that the adjudicating authority is to see at this stage is whether there is a plausible contention which requires further investigation and that the "dispute" is not a patently feeble legal argument or an assertion of fact unsupported by evidence. It is important to separate the grain from the chaff and to reject a spurious defence which is mere bluster. However, in doing so, the Court does not need to be satisfied that the defence is likely to succeed. The Court does not at this stage examine the merits of the dispute except to the extent indicated above. So long as a dispute truly exists in fact and is not spurious, hypothetical or illusory, the adjudicating authority has to reject the application."

Company Appeal (AT) (Insolvency) No. 438 of 2022 -13-

14. The definition of the word 'dispute', is in fact, illustrative, the 'Corporate

Debtor' is not left with the only option of showing the 'existence of dispute' by

way of a pending Suit or Arbitration but can exercise its right to show that

goods and/or services supplied were substandard and deficient in quality.

15. Section 5(6) of the Code defines 'dispute' as follows:-

"5. Definitions.--In this Part, unless the context otherwise requires,--

................................ (6) "dispute" includes a suit or arbitration proceedings relating to-- (a) the existence of the amount of debt; (b) the quality of goods or service; or (c) the breach of a representation or warranty;"

16. Now we address ourselves to whether there was any 'Pre-Existing

Dispute' regarding quality/supply of the material by the Appellant. The

communication dated 30/11/2018 by EIL to the Appellant herein evidences

that there were some shortcomings listed namely the test certificate of the

materials were not found with the documents; that for fabrication/profiling of

racking materials, plates of different sizes has been used; and the Appellant

was requested to deploy their experienced engineer for rectification of the

shortcomings.

17. It is the case of the Appellant that the racking material was in

possession of IOCL and was lying outside in the open without adequate

protection being exposed to direct rain and dust and it is only on account of

negligence in storing the material that the paint was peeled off and there was

corrosion on the critical components.

18. The dispute between the parties is on account of the shortcomings

observed in the quality of the racking materials supplied to IOCL. The letter

dated 30/11/2018 addressed to the Appellant specifies that there are

discrepancies and the test certificates of all plates/materials is absent. As the

Company Appeal (AT) (Insolvency) No. 438 of 2022 -14-

letter dated 30/11/2018 is the main document emphasizing the dispute

raised, which is neither frivolous nor spurious, it is being reproduced

hereunder:

(Emphasis Supplied) Company Appeal (AT) (Insolvency) No. 438 of 2022 -15-

19. The Hon'ble Supreme Court in para 45 of 'Mobilox Innovations Pvt. Ltd.'

(Supra) has observed as follows:-

"45. Going by the aforesaid test of "existence of a dispute", it is clear that without going into the merits of the dispute, the appellant has raised a plausible contention requiring further investigation which is not a patently feeble legal argument or an assertion of facts unsupported by evidence. The defense is not spurious, mere bluster, plainly frivolous or vexatious. A dispute does truly exist in fact between the parties, which may or may not ultimately succeed, and the Appellate Tribunal was wholly incorrect in characterizing the defense as vague, got-up and motivated to evade liability."

20. For all the aforenoted reasons and the ratio of the Hon'ble Supreme

Court in 'Mobilox Innovations Pvt. Ltd.' (Supra) this Tribunal is of the

considered view that there is a 'Pre-Existing Dispute' and the aforenoted

correspondence establishes that 'a dispute truly exists in fact between the

Parties, which is not a patently feeble legal argument or an assertion of facts,

unsupported by evidence'.

21. Hence, we are of the view that the there is no illegality of infirmity in

the Order of the Adjudicating Authority and this Appeal fails and is

accordingly dismissed. No Order as to costs.

[Justice Ashok Bhushan] Chairperson

[Ms. Shreesha Merla] Member (Technical)

NEW DELHI 06th May, 2022

himanshu Company Appeal (AT) (Insolvency) No. 438 of 2022

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free