Entegra Limited vs Shree Maheshwar Hydel Power ...
- CitationComp. App. (AT) (Ins.) No. 1287
Ratio decidendi
The rule this decision rests on
A financial creditor that has acquired shares in the corporate debtor through invocation of pledge or partial conversion of debt into equity does not thereby lose its status as a financial creditor, and retains the independent right to file an application under Section 7 of the Insolvency and Bankruptcy Code, 2016. A recall notice issued by a lender demanding repayment of outstanding debts, which sets out the loan details, the defaults and the time within which payment is required, is not invalid in law merely because the lender was in management control of the corporate debtor, where the debts are shown by the record to be due and payable and the loan agreements are acknowledged by the borrower and its promoter. An application under Section 7 is not barred by limitation where the debt and default are established within the limitation period, including on the basis of acknowledgments in the corporate debtor's balance sheets and board minutes and disbursements under a loan agreement executed within three years of the application. The Adjudicating Authority's role under Section 7 is confined to determining the existence of a debt, the occurrence of default and the satisfaction of the minimum threshold, and to rejecting the application only where non-compliance with the Code is shown; a plea of malicious initiation under Section 65 is not established by the mere non-disbursal of an interest component where the record shows the lender's continued funding and the borrower's own admitted inability to pay.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
(Arising out of the Order dated 27.09.2022 passed by the National Company Law Tribunal Kolkata Bench in TP (IBC)/1(KB)2022, T.A.(IBC)/1(KB)2022, T.A. (IBC)/1(KB)2022)
IN THE MATTER OF:
Entegra Limited Niranjan 99 Marine Drive Mumbai - 400002 ...Appellant
Versus
1. Shree Maheshwar Hydel Power Corporation Ltd. Through Interim Resolution Professional, Apoorv Sarvaria, Registered office at: Abhayanchal Parisar, Post Mandaleshwar Mandelshwar - 451221, Madhya Pradesh Address for communication: Suite No. 1, 19 Park Area, Karol Bagh, Opposite Ajmal Khan Park, Central, NCT of Delhi-110005 Email ID: cirp.shreemaheshwar@gmail.com ...Respondent No. 1
2. Power Finance Corporation Ltd. Urjanidhi, 1, Barakhamba Lane, Connaught Place, New Delhi 110001 ...Respondent No. 2
Present
For Appellant: Mr. Abhishek Puri, Mr. Surbhi Gupta & Mr. Sahil Grewal, Advocates.
For Respondent: Mr. Ramji Srinivasan, Sr. Adv. with Mr. Deepak Khurana, Monalika, Adv. Mr. Gajanad Krodhiwal, Mr. Aditya Rathee & Mr. Shivam Rajpal, Adv. for RP/R1 -2- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
JUDGEMENT
(26.11.2024)
NARESH SALECHA, MEMBER (TECHNICAL)
Preliminary
1. The present appeal has been filed by Entegra Limited who is the
Appellant herein, for challenging the Order dated 27.09.2022 passed by the
National Company Law Tribunal, Kolkata Bench ('Adjudicating Authority')
in TP (IBC)/1(KB)2022, T.A.(IBC)/1(KB)2022, T.A. (IBC)/1(KB)2022 upon
reference and Order dated 08.10.2021 in TP 258 of 2019 in CP (IB)
111/7/NCLT/AHM/2018 with Inv. P. 53 of 2018, Inv. P 54 of 2018 and IA 60
of 2020 passed by the Adjudicating Authority, NCLT, Indore Bench, at
Ahmedabad (together referred to as "Impugned Judgment"), whereby two
judges of the Adjudicating Authority have admitted the petition filed under
Section 7 of the Insolvency and Bankruptcy Code, 2016 (hereinafter referred to
as "Code") against Respondent No. 1,
2. The Appellant is Promoter of the Respondent No. 1 i.e., Shree
Maheshwar Hydel Power Corporation Ltd. ('SMHPCL') who is the Corporate
Debtor and being represented through its IRP, is the Respondent No. 1 herein.
The Power Finance Corporation Ltd. ('PFC') is the Respondent No. 2, who is
the Financial Creditor of the Respondent No. 1.
-3-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
3. Heard the Counsel for the Parties and perused the records made available
including the cited judgements.
Submissions of the Appellant
4. It is the case of the Appellant that he is the Promoter of Respondent No. 1
holding 29,17,20,330 shares of face value of Rs. 10/- each which constituted
58.43% of the total paid up capital of the Respondent No. 1. The Appellant gave
the background of the Promoters, the Appellant, the Respondent No. 1 and its
genuine intentions to complete 400 MW power project in power starved
Madhya Pradesh. The Appellant stated that, it was he who initiated the project
and provided all initial funding which demonstrate his true desire for
implementation of the Project. The Appellant stated that looking to huge funds
requirement, he approached lenders. The Appellant stated that the project was
on right path but external factors like Narmada Bachao Andolan ('NBA') etc.
derailed the project, which was further aggravated due to short sighted approach
of the Lenders and their greed to recover money at the cost of the project itself.
The Appellant stated that the Lenders especially the Respondent No. 2 are fully
responsible for the present state of affairs of the Respondent No. 1. The
Appellant assured that given a chance again he will pull back the project and
complete the project.
5. In this background, the Appellant stated that the Respondent No. 2 filed
an application under Section 7 of the Code for initiation of Corporate -4- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Insolvency Resolution Process ('CIRP') in respect of Respondent No. 1 for
alleged default of Rs. 2789.42 Crores before the Adjudicating Authority, Indore
at Ahmedabad Bench on 16.02.2018 which was decided on 08.10.2021 with
split judgments and finally the Impugned Order on 27.09.2022 was delivered by
Member (Judicial) of Kolkata Bench.
6. The Appellant submitted that the Respondent No. 2 illegally converted
debt into equity and also illegally invoked pledged shares and according such
illegal acts of Respondent No. 2, the shareholding of the Appellant in
Respondent No. 1 was reduced from 58.43% to 12.29% of paid-up share capital
of Respondent No. 1.
7. The Appellant conceded that the Respondent No.2 has now cancelled the
shares held by the Respondent No. 2 on account of illegal conversion of
subordinate debt into equity on 18.12.2019 and restored the shares which were
invoked by the Respondent in favour of the Appellant on 23.09.2019.
8. The Appellant pleaded that the Project is very important, however, due to
NBA and other related issues, the project was pushed back and as a
consequence the German Financers brought in by the Appellant withdrew from
the project resulting in the project coming to a halt in 2001.
9. The Appellant submitted that looking to the national importance of the
project, Madhya Pradhesh (GoMP) sanctioned (a financial guarantee of Rs. 400
Crores) to enable the Respondent No. 1 to raise the public bonds Optionally -5- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Fully Convertible Debentures (OFCD). The Lenders were requested to provide
the balance funds required to complete the project and in this background, the
Respondent No. 2, as lead lender along with other lenders came forward to
finance Respondent No. 1.
10. The Appellant assailed the conduct of the Respondent No. 2 who tried to
fish in the troubled water and took advantage of precarious financial condition
of the project by putting unnecessary pre-condition for further funding for the
project forcing the Appellant and the Respondent No. 1 to arbitrary terms and
conditions which required changes in Article of Association ('AoA') to make it
subordinate to dictum of the lenders especially the Respondent No. 2.
11. The Appellant cited few such pre conditions which included condition
like consultation with the Respondent No. 2 as condition precedent in
appointment of the Chairman, the Managing Director and the Director Finance
('DF') of Respondent No. 1 and further stipulated that Lender's Nominee
Directors will be involved in the management of the Respondent No. 1.
Similarly, the Lender's Auditors would also be involved in periodic reviews of
various commercial transactions during the Trust and Retention Account
('TRA') transactions. The Appellant submitted that he had no option but to
accept such conditions of the Respondent No. 2 which took away effectively the
management of the Respondent No. 1 out of control of the Appellant and
therefore he can't be held responsible for failure of the Respondent No. 1. -6-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
12. The Appellant submitted that as per amended AoA, no decision could
take place without approval of atleast three out of four nominee Directors of the
Lenders which demonstrate that the management completely shifted to
'Management Team' comprising of the Chairman, Managing Director, and DF
of Respondent No. 1, all of whom were appointed with consent of Respondent
No. 2. The Appellant highlighted the few important changes in Articles in AoA
like to Article 2: Definition of "Pledged shares of S. Kumars", Article 89(2),
Article 105, 108, 109, 134, etc., which completely restricted the rights of the
Promoters and gave the Lenders especially the Respondent No. 2 complete
control of Respondent No. 1.
13. The Appellant castigated the Respondent No. 2 who is the real cause for
mismanagement of the project despite being in control since 2005 and did not
release the funds from TRA account at the right time and rather diverted funds
for servicing the interest payable to Respondent No. 2, putting the Respondent
No. 1 under financial distress.
14. It is the case of the Appellant that such unlawful actions of Respondent
No. 2 put the Project into jeopardy. The Appellant highlighted that although he
was not required to bring in any funds as the effective management of
Respondent No. 1 was taken over by the Respondent No. 2, still in interest of
the project, the Appellant arranged Rs. 377 Crores of Term Loan from SBI,
pumped in himself Rs. 155 Crores on Direct Equity and further organized -7- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Rs. 200 Crores of OTD from Strategic Investors, Rs. 217.50 Crores of OFCD
subscription from YES Bank and Rs 80 Crores of unsecured loan. The
Appellant tried to highlight that the Respondent No. 2 diverted more than 42%
of these funds to serve its own interest which resulted in further cost escalation
of the project.
15. The Appellant submitted that since the project was not going ahead as per
Plan, around 2014, GoMP constituted a High Level Committee ('HLC') for the
purpose of finding the way forward to complete the project, comprising of
representatives of GoMP, Ministry of Power ('MoP'), Government of India
('GoI') Promoters, Respondent No. 2 and Lenders and the committee gave its
Report on 02.05.2015 giving three scenarios of further course of action.
"(I) By 02.08.2015 the existing promoter will arrange Rs.600 crores as well as
debt of Rs.1100 Crores at concessional rates to achieve the stipulated electricity
tariff of Rs. 5.32.
II. NHPC/NHDC will take over the company and Respondent No. 2 will be
amenable to infusing equity or additional debt as well as lowering interest rate
for existing debt with support from lenders so that the tariff is at Rs. 5.32 per
unit.
III. Cancellation of PPA- M.P. Power Management Company limited cancels
the existing Power Purchase Agreement."
-8-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
16. The Appellant submitted that the Scenario-I could not be achieved due to
non co-operation of the Respondent No. 2 and subsequently, the Respondent
No. 2 unilaterally declared Option I as "failed" to pursue its own interpretation
of Option 2 by forcibly taking 51% of the shares of Respondent No. 1 in tandem
with other Lenders. The Appellant emphasized that as per HLC, the equity
holding of the Appellant sould not have been reduced below 26%.
17. The Appellant further submitted that Respondent No 2 continued to
sabotage various funding proposals initiated by the Appellant and further due to
restrictive clauses inserted in Amended AoA like 80B, 89(2), 108 and 109, 134,
Article 105(d) and 126, etc., it became difficult for the Appellant to find
investors or seek additional funds. The Appellant brought out that in the year
2011, a Strategic Investor at the request of the Appellant Promoter also invested
Rs.100 Crores to complete the project, however Respondent No. 2 being in
control of the TRA, chose not to release this fund for actual project works and
rather tried to divert these funds to subserve its own interest.
18. The Appellant submitted that the Respondent No. 2 declared the loan
accounts of Respondent No. 1 as NPA on 31.03.2012, while the Respondent
No. 1 was under control of Respondent No. 2.
19. The Appellant submitted that due to complete mismanagement by the
Respondent No. 2 the Appellant was forced to file a complaint to Registrar of
Company ('RoC') Ahmedabad seeking to conduct an inquiry under section -9- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
206(4) of the Companies Act, 2013 regarding conduct of affair of Respondent
No. l and as a result the RoC marked the Respondent No. 1 as "management
disputed" company on 29.04.2016 and initiated enquiry.
20. The Appellant assailed the conduct of Respondent No. 2 who despite
undergoing inquiry by the RoC, sought to invoke all the shares pledged by the
Appellant Promoters as "Security Agent" of all lenders on 19.05.2016 and
further, vide notice dated 18.12.2015 and 27.05.2016 sought partial conversion
of the subordinate loan of Rs. 375 Crores into equity shares to make the
Promoters as minority shareholders from majority shareholder. The Appellant
highlighted that notice itself contained the 30 days response time and despite
this provision, without waiting for completion of the timeline, transfer of share
were approved by nominee directors of the Lenders in the board meeting held
on 01.07.2016. The Appellant further stated that in the same meeting, the
Respondent No. 2 partially converted subordinate debt extended by the
Respondent No. 2 to Respondent No. 1 into equity and thereby the Respondent
No. 2 illegally asserted shareholding of 23.32% of Respondent No. 1.
21. The Appellant stated that based on his complaint, the RoC Gwalior on
21.10.2017, delivered the report under Section 206 of the Companies Act, 2013
whereby it was held that the lenders were responsible for violation of provisions
of Companies Act, 2013 and were responsible for unsatisfactory state of affairs
of Respondent No. 1, since, the management control of the Respondent No. 1 -10- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
was taken over by the Lenders especially the Respondent No. 2 w.e.f.
25.11.2005. The Appellant criticized the Respondent No. 2, who after getting
such adverse remarks from RoC, filed a frivolous application under Section 241
& 242 of the Companies Act, 2013 against the Promoters which has been
rejected at various legal fora including by the Hon'ble Supreme Court of India.
The Appellant stated that the Tribunal gave its order on 15.06.2017 in Company
Petition No. 175/ 241-242/ NCLT/ AHM/ 2017; this Appellate Tribunal gave its
order in Company Appeal (AT) No. 237 of 2017 on 12.03.2018 and the Hon'ble
Supreme Court of India passed the judgment on 18.05.2018 in Civil Appeal No.
5028 of 2018, holding the Respondent No. 2 as responsible for making mess of
the Respondent No. 1. The Appellant stated that the funds movement from
TRA account was completely regulated and controlled by Lenders especially the
Respondent No. 2 and thereby the Promoters had no executive powers in
conduct of the affair of the Respondent No. 1. The Appellant stated that the said
judicial orders held that invocation of shares and partial conversion of
subordinate debt into equity by the Respondent were illegal.
22. The Appellant submitted that the Additional Loan Agreement dated
27.04.2017 was executed by the Respondent No. 2, in contravention to the HLC
report regarding shareholding of the Promoters cannot be lowered than 26%.
The Appellant emphasized that the Respondent No. 2 had malicious intentions
to create default on part of Respondent No. 1 with respect to the Additional -11- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Loan Agreement dated 27.04.2017 through non-disbursal of the interest
component and referred to Notice of Drawdown dated 02.05.2017 issued to
Respondent No. 2, through which drawdown (disbursal) of Rs. 435 Crores was
sought, which was sanctioned by Respondent No. 2. The Appellant stated that
out of this sanctioned amount, Rs. 10 Crores was earmarked towards Interest/
Interest during Construction ('IDC') and Rs. 88 Crores towards Financial
Charges. However, Respondent No. 2, only disbursed Rs. 384. 59 Crores but did
not release the interest component, in an attempt to fraudulently and mala-fide
create a situation of default for Respondent No. 1. The Appellant mentioned that
disbursal of these amounts was entirely in the hands of Respondent No. 2, since
it was in control of the affairs of the Respondent No. 1 as also the TRA accounts
of Respondent No. 1.
23. The Appellant submitted that Respondent No. 2 issued Loan Recall
Notice dated 17.01.2018 on the manufactured and fraudulent ground of non-
payment of interest as ensuring payment of Interest during construction was the
obligation of Respondent No. 2 himself. The Appellant stated that on the basis
of the mala-fide Loan Recall Notice dated 17.01.2018, Respondent No. 2
fraudulently sought to initiate insolvency proceedings against Respondent No. 1
by filing the Insolvency Petition bearing No. CP (IB) 111/2018 before NCLT,
Ahmedabad on 16.02.2018 -12- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
24. The Appellant stated that this Appellate Tribunal taking a pragmatic
approach vide the order dated 19.05.2018 directed that the matter could be
resolved by GoMP and GOI and accordingly the GoMP constituted a task force
on 18.04.2019 to find a way out for implementation of project. The Appellant
stated that the Promoter vide Letters dated 03.08.2018 and 19.10.2018 issued to
Respondent No. 2, presented a concrete offer of funding from Cantor Fitzgerald
Europe on 16.10.2018 and one of pre-conditions for such investment was that
"All litigation to be put on hold" which was not agreed by the Respondent No.
2. The Appellant submitted that vide e-mail dated 05.11.2018, the
Promoter/Appellant also submitted a draft MoU to Respondent No. 2, however,
Respondent No. 2 re-drafted the terms and conditions of the MoU only in July
2019.
25. It is the case of the Appellant that despite no debt being due from the
Respondent No. 1, in the interest of the Project, the MoU was executed between
Respondent No. 2, the Respondent No. 1 and the Promoters (Appellant) on
22.07.2019. The Appellant emphasized that the term of the MoU was to subsist
till 12 months and only by this time if the MoU was not implemented, only then
MoU could have been terminated and the period between 22.07.2019 till
22.07.2020 was to be treated as a calm period to ensure that viability of the
Project can be assessed, AoA can be amended, the BoD is reconstituted, -13- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
ownership is reverted to the Promoter/Appellant, Settlement plans can be
executed and interim finance can be brought into the Company.
26. The Appellant submitted that by 5.12.2019, Respondent No. 2 had
already started pursuing the Insolvency Petition and did not withdraw it as
clearly contemplated under Clause 1 and Clause 9 of the MoU, but the
Respondent No. 2 and the remaining lenders were not returning the entire
shareholding of the Promoter which had been illegally invoked by Respondent
No. 2. The Appellant stated that similarly no assistance was being provided for
amendment to the AoA by Respondent No. 2. The Appellant stated that the new
investors sought to be brought in by the Promoter/Appellant lost interest in the
Respondent No. 1 and the Task Force decided that since the IBC petition was
being pursued by Respondent No. 2, it could per-force not do anything. This
clearly shows that failure to execute the MoU was solely on account of
Respondent No. 2.
27. The Appellant defended his action that in light of the this adverse attitude
of the Respondent No. 2, no occasion arose for the Promoter/Appellant to bring
in funds of Rs. 10 Crores into Respondent No. 1 as per Clause 3 of the MoU.
The Appellant emphasized that these clauses contemplated that only upon
appointment of new KMPs, the Promoters would make payment of Rs. 10
Crores to the Respondent No. 1 for the purposes of the day-to-day expenses of
the Respondent No. 1. The Appellant submitted that for the purposes of -14- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
executing the MoU, only Zero date was of significance (which was achieved on
07.09.2019 upon deposit of Rs. 1 Crores by the Promoter/Appellant). Thus, the
Appellant submitted that in view of Clause 11 of the MoU, no alleged debt is
even otherwise due by the Respondent No. 1 under the Loan Agreements and if
at all, the Respondent No. 2 could only seek for repayment/ settlement in terms
of the MoU which deferred the payment dates for all the Loan Agreement
mentioned in the subject Loan Recall Notice for a period of one year from
22.07.2019.
28. The Appellant stated that the control of the Respondent No. 1 remained
with Respondent No. 2 and other Lenders since 2005 and even after signing of
the MoU dated 22.07.2019, only the MD appointed by Respondent No. 2 was
replaced with MD appointed by the Appellant under the MoU i.e. Mr. ML
Gupta but due to repeated breach of the MoU by Respondent No. 2, Mr. ML
Gupta resigned on 28.02.2020.
29. The Appellant submitted that Section 7 application of the Respondent No.
2 was listed before the Hon'ble Bench comprising of Dr. Deepti Mukesh and
Virendra Kumar Gupta wherein after hearing parties, orders were reserved. On
08.10.2021, the Bench pronounced a split verdict since they could not arrive at a
consensus. Thereafter, for the purpose of reference under Section 419(5) of
Companies Act, 2013 draft issues were framed by the Judicial member. -15-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
30. The Appellant stated that issues framed for reference by the Judicial
Member and technical member were thereafter assigned to Special Benches of
NCLT, Kolkata comprising of a single judicial member by the President, NCLT,
New Delhi vide order dated 21.02.2022. however, the same could not be drafted
and pronounced as the said Special member demitted office. The matter was
thereafter referred to the Special Bench comprising of J. Rohit Kapoor, Member
(judicial) who heard the referred matter on 26.07.2022, 28.07.2022, 29.07.2022
and thereafter, reserved the order on 01.08.2022 and the impugned order was
pronounced on 27.09.2022 , admitting the Insolvency Petition filed by
Respondent No. 2 and rejecting the Intervention Application No. IA 53/ 2018 [
TA (IBC) No. 1/ KB/2022] and Application u/s 65 of the Code bearing no. IA
60 of 2020 [ TA (IBC) No. 2/ KB/ 2022 ].
31. The Appellant submitted that the Respondent No. 2 is not a "financial
creditor" under Section 7 of the Code and rather, if at all would be a "corporate
applicant" in terms of section 5(5) of the Code, as the Respondent No. 2 himself
was in control the affairs and the management of the Respondent No. 1 since
2005.
32. The Appellant submitted that the Code clearly mandates that where the
Applicant seeking to initiate insolvency process falls in the definition of a
"Corporate Applicant" under the Code, any application of initiation of CIRP
Process in case of any "default" by a Corporate Debtor has to be made under -16- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Section 10 of the Code, in terms of Section 10(3) of the Code, a special
resolution passed by shareholders of the corporate debtor has to be obtained for
filing of the application. It is the case of the Appellant that the Respondent No. 2
to escape scrutiny of the Adjudicating Authority has surreptitiously filed the
present petition under Section 7 of the Code.
33. The Appellant submitted that the Hon'ble Supreme Court in Embassy
Property Developments Pvt. Ltd. v. State of Karnataka [2019 SCC Online SC
1542 held that a person acting on behalf of the Company before various fora and
authorities and thereafter, sought to file an Insolvency Petition in the guise of a
"Financial Creditor" cannot do so. The Appellant submitted that the Section 7
application of Respondent No. 2 should have been dismissed as Respondent No.
2 was not a "Financial Creditor" and rather was admittedly a "related party" of
Respondent No. 1 at the time of filing the present insolvency application and
even thereafter. The Appellant refuted the allegation of the Respondent No. 2
that there was a "financial debt" in terms of few documents like, Loan
Agreement dated 04.12.1998, Amendatory and Restated Agreement dated
16.09.2005, Common Loan Agreement dated 29.09.2006, Subordinate Loan
Agreement dated 29.09.2006, Master Restructuring and Loan Agreement dated
22.06.2010 and Additional Loan agreement dated 27.04.2017.
34. The Appellant submitted that the argument of Respondent No. 2 that even
where some quantum of financial debt is found to be due and payable, the -17- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Section 7 application is maintainable is fallacious since there is no "financial
debt" and consequently no default has arisen on account of Respondent No. 1,
since, the Respondent No. 2 himself is responsible for mess of the Respondent
No. 1 and for non-payment of interest amounts under the Additional Loan
Agreement which was not disbursed by Respondent No. 2 and therefore, there is
no default by the Respondent No. 1 of any debt due and payable. The Appellant
submitted that there is no mention regarding date of occurrence of default
despite the clear instructions for providing these details as per the Form 1 and
date of default has not been mentioned in the Loan Recall Notice either.
35. The Appellant emphasized that an act of engineering by the Respondent
No. 2 a purported default by not disbursing the interest component sanctioned
by way of the Notice of Drawal, clearly tantamount to malafide initiation of the
CIRP in violation of Section 65 of the Code.
36. The Appellant submitted that various loan agreements have been entered
into by Respondent No. 2 while in complete control of the Respondent No. 1.
This Appellate Tribunal held that the Subordinate term loan agreement dated
29.09.2006 had been executed by Respondent No. 2 in violation to Proviso of
Section 63(3) of Companies Act. It is the case of the Appellant that all the
Loans in the present matter are intrinsically linked to each other and draw
reference from the preceding Loan Agreements, therefore, setting aside of even
one subsequent Loan Agreement, would completely invalidate all past loan -18- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
agreement, therefore, there can't be any debt due and default on part of
Respondent No. 1.
The Appellant argued that initiating Section 7 application based on such
illegal Loan Agreements, tantamount to malicious and fraudulent initiation of
Insolvency which is barred under Section 65 of the Code. The Appellant stated
that the Additional Loan Agreement dated 27.04.2017 was entered into by
Respondent No. 2 despite knowing that the said Agreements were void-ab-initio
and illegal, and therefore, no "financial debt" can be said to be due or payable
under such an illegal and invalid Agreement.
37. The Appellant submitted that the Recitals L-O of the Additional Loan
Agreement dated 27.04.2017 and the Sanction Letter dated 12.01.2017 clearly
indicate that the basis of the Additional Loan Agreement was the operation of
Scenario-II proposed by the HLC, but the Scenario No. II did not envisage the
Additional Loan Agreement by Respondent No. 2, rather Scenario-II suggested
real Equity infusion into Respondent No.1 Company by CPSU like
NHPC/NHDC to the extent of 51% and the promoters' holding not dropping
below 26%. The Appellant further argued that, therefore, all the Loan
Agreements are sham and collusive transactions carried out at the behest of
Respondent No. 2 wearing the cap of the Lender on one hand, the Lender-led
management on the other hand. The Appellant stated that BoD of the
Respondent No. 1 accepted these Loans and signed Loan Agreements while -19- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
wearing the hat of the "Borrower", therefore, these transactions cannot be
treated as "Financial Debt".
38. The Appellant sated that the Loans provided under Loan Agreements are
barred by Limitation especially since the Lenders declared the Respondent No.
1 an NPA on 31.03.2012 qua these loans, thereafter, much beyond the period of
3 years, Respondent No. 2 executed the Additional Loan Agreement dated
27.04.2017 with Respondent No. 1, to revalidate the Loans which already stood
time barred.
39. The Appellant submitted that the Minutes of Board meeting and the
Balance Sheets of the Respondent No. 1 were prepared by KMPs appointed by
Respondent No. 2 as the Lead lender and approved by the Board which was
completely under the control of Respondent No. 2 and other Lenders since
2005. Therefore, any such alleged acknowledgement in any Balance Sheet BoD
minutes cannot be relied upon. The Appellant reiterated that initiation of CIRP
is for ulterior purposes and Section 65 of the Code is applicable as CIRP is with
malicious intent for any purpose other than for resolution of the Corporate
Debtor.
40. Concluding his remarks, the Appellant strongly urged this Appellate
tribunal to dismiss the Impugned Order to protect the Respondent No. 1
(Corporate Debtor) and the Promoters of the Respondent No. 1. -20-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Submissions of Respondent No. 2
41. Per contra, the Respondent No. 2 denied all the averments made by the
Appellant treating these as misleading and malicious.
42. The Respondent No. 2 gave his version of series of events since 1995 to
present day and tried to present a complete picture to demonstrate complete
failure of the Appellant as Promoter, again and again, in all respect. The
Respondent No. 2 submitted that the Appellant failed to meet obligations of
original loan account, Service Level Agreement ('SLA'), Default Payment
Guarantee ('DPG') etc. The Respondent No. 2 stated that the Appellant could
not even meet MoU conditions despite Respondent no. 2 returning invoked
shares and returning partially debt converted shares and further appointing Mr.
M.L. Gupta as MD who was nominee of the Appellant. The Respondent No. 2
stated that the Appellant had neither any intention to revive the Respondent No.
1 nor financial and managerial capacity to do and therefore the Appellant has
chosen wrong path of blame game and accusing Lenders for fraud etc.,
43. The Respondent No. 2 stated that it is undisputed fact that from
01.10.2001 to 31.10.2005, the Project was completely stalled as the promoter
and the Respondent No. 1 failed to infuse requisite equity and funding in the
Project and thereby the Project suffered huge setback.
44. The Respondent No. 2 submitted that Appellant's contention that by
amendment of AoA, the composition of BoD of the Respondent No. 1 was tilted -21- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
in favour of Lenders, thereby the management control of the Corporate Debtor
was transferred to the Lenders is irrelevant and erroneous. To buttress his point,
the Respondent No. 2 highlighted that amendments to AoA were done with the
consent and approval of the shareholders including the Promoter during the
process of the revalidation of the financial facilities to the Respondent No. 1 and
all Lenders including GoMP were involved in the said process.
45. The Respondent No. 2 assailed the conduct of the Appellant and the
Respondent No. 1, who failed to maintain the financial discipline in terms of the
financing agreements and defaulted in repayment of interest and outstanding
amounts to the lenders. The Respondent No. 2 mentioned that till 2010, the
lenders (including the Respondent No. 2) had disbursed their total debt
commitment but there was a huge shortfall on the part of the Promoter of the
Respondent No. 1 in bringing in the requisite equity as a result of which the
Project completion got abnormally delayed. The Respondent No. 2 stated that if
the Appellant had timely infused funds and taken proper steps for the
implementation of the Project, there would not have been inordinate delay of
more than 20 years in implementation of the Project which itself reveals lack of
financial and managerial capacity of the Appellant. The Respondent No. 2
submitted that due to lack of commitment from Appellant and the Respondent
No. 1, the loan accounts of the Respondent No. 1 were classified as Non-
Performing Assets ('NPA') on 31.03.2012.
-22-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
46. The Respondent No. 2 submitted that there are several acknowledgments
of debt and default on part of the Respondent No. 1 for instance while the HLC
was preparing its report, on 17.11.2014, Debt was acknowledged in the Annual
Report/Balance Sheet of the Corporate Debtor for the FY 2013-14 and the said
balance sheet was signed by Sh. Mukul Kasliwal (Promoter) as one of Directors
of the Respondent No. 1. The Respondent No. 1 again acknowledged its
liability/debt in the meeting of the BoD of the Respondent No. 1 held on
29.09.2015, which was attended by the Promoter Sh. Mukul Kasliwal.
47. The Respondent No. 2 gave the background and the events compelling
lenders and the Respondent No. 2 to acquire equity due to operation of law
subsequent to invocation of pledged shares and partial conversion of debt into
shares. The Respondent No. 2 submitted that on 22.03.2016, in an attempt to
implement Scenario-II, a review meeting was held at MoP to discuss the issues
relating to revival of the project and inter-alia, discussed issue regarding
Endorsement of NHPC/NHDC as new 'Promoter' as suggested by HLC,
however, NHPC declined the suggestion and as such as an interim measure, the
Respondent No. 2 along with other lenders were persuaded to get involved in
affairs of the Respondent No. 2 to sustain the revival measures. The
Respondent No. 2 elaborated that the implementation of Scenario II was
envisaged by way of invocation of pledge in favour of various consortium
lenders, and exercise of the conversion right by Respondent No. 2, as entailed -23- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
under the SLA for partially converting Respondent No. 2 's subordinate debt
into equity, in order to acquire majority equity as per the mandate of the HLC
under Scenario-II. The Respondent No. 2 further clarified that on 19.05.2016, a
notice for Invocation of Pledge was issued to the Respondent No. 1 and its
Promoter/pledgor and only thereafter on 27.05.2016, Respondent No. 2 issued a
Notice to the Respondent No. 1 for partial conversion of subordinate debt into
equity.
48. The Respondent No. 2 stated that in this backdrop and by virtue of the
transfer of 6,57,46,779 equity shares of Rs. 10/- each and conversion of
subordinate loan of Rs. 66,10,00,000/- into 6,61,00,000 equity shares of Rs. 10/-
each, Respondent No. 2 became a shareholder of the Respondent No. 1 w.e.f.
from 01.06.2016, holding 13,18,46,779 equity shares of Rs. 10/- each,
constituting 23.32% of the entire shareholding of the Respondent No. 1. The
Respondent No. 2 mentioned that 7 of the Lenders namely PFC, REC, HUDCO,
Central Bank of India, Dena Bank, NICL, had cumulatively acquired 51%
shareholding of the Respondent No. 1, pursuant to the invocation of the pledged
shares and conversion of sub-ordinate loan into equity, which was due to
operation of law.
49. The Respondent No. 2 stated that the efforts of Lenders to revive the
Project were being blocked by the Promoter by way of frivolous complaints
filed with RoC, Gwalior against lenders including the Respondent No. 2 which -24- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
led the Respondent No. 1 being marked as "Management Disputed" company by
the RoC. The Respondent No. 2 elaborated that under these uncertain
conditions created by the Promoters, it became difficult to tie-up funds required
for completion of the Project and to run the day-to-day affairs of the Respondent
No. 1. The Respondent No. 2 stated that he was compelled to file a Petition
under Section 241, 242 & 244 of the Companies Act, 2013 bearing CP. No.
15/1241- 242/NCLT/AHM of 2017 before the NCLT seeking appropriate reliefs
inter-alia, for handing over of records of the Respondent No. 1 from the
erstwhile management, removal of 'Management Disputed' status of the
Corporate Debtor by the RoC.
50. The Respondent No. 2 denied allegation of the Appellant that additional
loan agreement was forced upon them and pointed out that the aforesaid
Additional Loan Agreement was supported by the Promoter Sh. Mukul Kasliwal
in the board meeting dated 02.03.2017, as recorded in the minutes of meeting
that "Shri Mukul Kasliwal specifically requested the Board to record that, the
sanctioning of additional loan to complete the project is a welcome step apart
from all the issues and concerns going on between the Lenders and Promoters
and Lenders will receive support from the promoters as well in view to complete
the project." The Respondent No. 2 emphasized that the Appellant is estopped
from questioning the said Loan Agreement & any argument to the contrary is hit
by doctrine of approbate and reprobate.
-25-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
51. The Respondent No. 2 also stated that Schedule II of the Additional Loan
Agreement acknowledges the already existing debt of Rs. 1750.93 Crore and
further the Recitals to the Additional Loan Agreement also acknowledged the
previous liabilities of the Respondent No. 1. The Respondent No. 2 highlighted
that Article 2.3(a) of the Additional -Loan Agreement states :-
"The Drawdown under this Agreement shall be subject to the satisfaction of each condition precedent set forth in Article IV hereof. Further, the obligation of the Additional Lender to make disbursement under this Agreement shall be subject to the Borrower performing its obligation and undertakings under this Agreement and the Borrower's compliance with the disbursement procedure stipulated hereunder, including, the submissions by the Borrower of all necessary information, documents, etc. to the satisfaction a/the Additional Lender."
The Respondent No. 2 stated that Article 4.1(ii)(a) provides that "validity
of the Additional Facility as well as its terms and conditions shall be subject to
Government Companies/Lenders holding majority equity in the Project .....
....... ..... "
52. The Respondent No. 2 stated that this negates the pleadings of the
Appellant about alleged management control by the Lenders and submitted that
they are bankers and has no interest in acquiring share capital of Respondent
No. 1 or its management. It is only due to gross failure of the Appellant and the
Respondent No. 1 and decision of MoP, GoI, as well as GoMP, taken in national -26- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
interest, to salvage the project, the Lenders including the Respondent No. 2
agreed to acquire equity by way of invoking pledged shares and partial
conversion of subordinates debts to equity.
53. The Respondent No. 2 stated that on account of acquisition of the
shareholding of Respondent No. 1 by the Lenders having been declared invalid,
further disbursals under the Additional Loan Agreement could not be made, as
the condition precedents as aforesaid for such disbursal could not be fulfilled.
The Respondent No. 2 stated that the interest of Rs. 10 Crores was due to be
payable by the Respondent No. 1 on 15.07.2017, i.e. after the NCLT's Order and
as such this amount could not be disbursed to the Respondent No. 1. The
Respondent No. 2 clarified that at the time of disbursal of Rs. 384 Crores, the
amount of Rs. 10 Crores had not become due for payment by Respondent No. 1,
and therefore, it was not disbursed along with Rs. 384 Crores and further
submitted that any allegations of default having been 'created' or engineered' is
incorrect and baseless as the Respondent No. 1 received the debt and defaulted
in payment of interest on the amounts already disbursed.
54. The Respondent No. 2 submitted that the Respondent No. 1 could not
comply with the terms, conditions and covenants of the Additional Loan
Agreement, based on which Respondent No. 2 had sanctioned the Additional
Debt, inter alia, including conditions provided under Article 2.3 (a) read with
Article IV of the Additional Loan Agreement, occurrence of events adversely -27- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
impacting the ownership of Government companies/ lenders (including
Respondent No. 2) etc., provided under Article 4.1 (ii) (a) and accordingly
Respondent No. 2 could not have, and did not disburse any further money out of
the Additional Facility to the Corporate Debtor. The Respondent No. 2 stated
that the additional loan was sanctioned as part of the revival measures in
accordance to the recommendation of HLC constituted by on the premise that
Government Companies/ Lenders shall hold majority equity in the project.
55. The Respondent No. 2 stated that the first interest payment was due. on
15.07.2017 in terms of Article 7.1(b) read with definition of 'Interest Payment
Dates' which was after the NCLT's Order dated 15.06.2017, the Respondent No.
1 failed to pay the same & subsequent instalments and therefore, Demand
Letters dated 06.07.2017, 01.10.2017 & 05.01.2018 were issued by Respondent
No. 2 to the Respondent No. 1 for non-payment of dues· under the Additional
Loan Agreement.
56. The Respondent No. 2 denied the assertion of the Appellant that
Respondent No. 2 did not make further disbursal of amount under the Draw
Down Notice ('DDN') dated 02.05.2017 and in effect 'created' default and
clarified that the said assertion signifies the reliance on the Additional Loan
Agreement by the Appellant, thus, the Appellant cannot seek to rely upon the
Additional Loan Agreement to the extent it provides for disbursal of amounts, -28- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
however in the same breath ignore the conditions attached to such disbursal or
event aver that the said agreement was not valid.
57. The Respondent No. 2 castigated the Appellant who while on the one
hand objects to the Lenders having previously received interest during
construction ('IDC') from Respondent No. 1 & on the other hand non-disbursal
of the said amount of Rs. 10 crores by the Lenders to Respondent No. 1, which
would then have come back to Lenders as IDC as aforesaid, is being objected
and the Respondent No. 2 submitted that, the defense of default by the appellant
is that the Lenders (especially Respondent No. 2) were not paying themselves
which is again approbation & reprobation.
58. The Respondent No. 2 submitted that in view of the continuous defaults
by the Respondent No. 1, the Respondent No. 2 issued recall notice dated
17.01.2018, demanding the Respondent No. 1 to make payment of the total
outstanding of Rs. 2139.20 Crores including outstanding interest amounts
payable as on 16.01.2018 (excluding costs/delayed charges/other charges etc.),
within 15 days of the receipt of the said notice. The Respondent No. 2 stated
that since the Respondent No. 1 did not make the required payment, the
Respondent No. 2 filed an application under Section 7 of the Code on
16.02.2018 for initiation of CIRP against the Respondent No. 1.
59. The Appellant elaborated that on 12.03.2018. this Appellate Tribunal
dismissed the Appeal filed by Respondent No. 2 against the NCLT's Order -29- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
dated 15.06.2017 and while dismissing the Appeal, inter alia, directed that the
Government of GoMP and GoI, need to urgently consider the way forward in
public interest to get the Project completed. The Respondent No. 2 submitted
that this Appellate Tribunal in the Order dated 12.03.2018 further held that the
Promoter/ Appellant had a responsibility and a duty to manage the Respondent
No. 1 as per the Companies Act in which they have failed. The Respondent No.
2 empathetically submitted that this Appellate Tribunal held categorically that
"the Promoter do not appear to be enthusiastic to get status quo ante restored in
the Articles not inspire confidence that if we strike down these amendments
made on 25.11.2005 (and subsequently) they can take charge and complete the
project which attracts public interest. Promoters have not brought to our
attention that at any time they opposed, or stood up to the gradual takeover."
60. The Respondent No. 2 clarified that in the judgement dated 12.03.2018,
this Appellate Tribunal held that primarily compliances w.r.t. the provisions of
the Companies Act, 2013 for conferring right to convert debt into equity, the
compliance of the Rules framed thereunder for effecting transfer of shares,
requirement of notice for invocation of pledge etc. under the Contract Act, were
not made and accordingly the acquisition of shareholding by the Lenders was
not as per the extant legal procedures and provisions. The Appellant submitted
that this was more on procedural issues and not w.r.t. legal rights of the
Respondent No. 2 to file Section 7 application and as such Section 7 application -30- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
was filed by Respondent No. 2 on 16.02.2018, which was finally admitted after
4 ½ years on 27.09.2022, due to the Promoter - Appellant adopting various
dilatory tactics before the Adjudicating Authority.
61. The Respondent No. 2 strongly refuted the argument raised by the
Appellant that the Section 7 application was 'fraudulent' and 'malicious' and
ought to have been dismissed by invoking Section 65 of the Code solely on the
ground that the Respondent No. 2 did not disburse the amount of Rs. 10 Crore
towards interest under the Additional Loan Agreement dated 27.04.2017 and the
Respondent No. 2, 'created' or 'engineered' a default. The Respondent No. 2
stated that the Appellant has not elaborated as to how ingredients of Section 65
are satisfied. The Respondent No. 2 submitted that in view of failure of the
Appellant-Promoter to implement Scenario-I stipulated in the HLC Report (by
having failed to arrange the committed additional equity of Rs. 600 Crore as
well as debt of Rs. 1100 Crore by 02.08.2015), the Lenders had to acquire
majority shareholding in the Respondent No. 1 by invocation of pledge and
conversion of debt for implementation of Scenario-II. The Respondent No. 2
stated that in order to meet the immediate fund requirements, an Additional
Loan Agreement was executed between Respondent No. 2 and the Respondent
No. 1 for loan of Rs. 600 Crores and disbursed Rs. 384.59 Crores under the said
Loan Agreement, however, further disbursal was prevented as the Appellant -31- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
challenged to the acquisition of shares by the Lenders on technical grounds and
it was decided in favour of the Appellant by legal fora.
62. The Respondent No. 2 stated that as per Article 2.3(a) of the said Loan
Agreement stipulated that "The Drawdown under this Agreement shall be
subject to the satisfaction of each condition precedent set forth in Article IV
hereof and the condition precedent under Article 4.1(ii)(a) provides that
"validity of the Additional Facility as well as its terms and conditions shall be
subject to Government Companies/Lenders holding majority equity in the
Project and based on which Respondent No. 2 had sanctioned the Additional
Loan, could not be complied with, on account of the Orders dated 15.06.2017
and 12.03.2018 passed by the NCLT and by this Appellate Tribunal.
Accordingly, in view of the terms of sanction as aforesaid, Respondent No. 2
could not have disbursed any further amount under the Additional Loan
Agreement to the Respondent No. 1.
63. The Respondent No. 2 emphasized that the Additional Loan Agreement
was executed much prior to this Appellate Tribunal's Order dated 12.03.2018,
and prior to NCLT Order's dated 15.06.2017 in the proceeding arising from the
Petition under Section 241-242 of the Companies Act, 2013. The Respondent
No. 2 stated that since, the acquisition of shareholding of Respondent No. 1 by
the Lenders had been declared invalid vide the said Orders, therefore, further
disbursal of Rs 10 crore towards interest under the Loan Agreement (which was -32- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
due on 15.07.2017) could not be made, as the aforesaid condition precedent of
Govt. Companies/ Lenders holding majority equity in the CD for such disbursal
could not be fulfilled. The Respondent No. 2 stated that the Appellant's
allegation of default having been 'created' or 'engineered' by Respondent No. 2
is baseless.
64. The Respondent No. 2 stated that on the one hand, the Appellant is
contending that money ought to have been disbursed under the SLA and on
other hand the Appellant is seeking to challenge the same SLA, which is
approbation and reprobation and which was welcomed by the Promoters the
Promoter Sh. Mukul Kasliwal himself as recorded in BoD Minutes.
65. The Respondent No. 2 submitted that apart from default under the
Additional Loan Agreement as aforesaid, the Respondent No. 1 was also in
default of the loans granted by Respondent No. 2 under the previous loan
agreements, and therefore, the same by itself, warranted admission of Section 7
Application i.e., debt towards Loan Facilities as on 15.01.2018, Rs. 1,018.19
Crore (principal amount) was due & outstanding from the Respondent No. 1.
The Respondent No. 2 stated that the Respondent No. 1 was also in default of its
liability of Rs. 318.49 crore towards Default Payment Guarantee and liability
towards Guarantee Fee, Facility Agent Fee, Security Agent Fee etc. The
Respondent No. 2 further informed that in addition to these, the Respondent No.
1 also defaulted in discharging its liability of Rs. 103.87 crore towards ZCB -33- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
issued by the Respondent No. 1 for conversion of interest liability on the
outstanding loan in terms of the sanction letter dated 02.03.2005 and the said
liability on is accruing on quarterly basis.
66. The Respondent No. 2 stated that during pendency of Section 7
Application, the GoMP decided to constitute a Task Force on 18.4.2019 for,
inter alia, examining the difficulties being faced by the Project, accordingly, to
give another opportunity to the Promoter and the Respondent No. 1 an MoU
was executed amongst Respondent No. 2, the Respondent No. 1 and Appellant
on 22.07.2019, under which the Appellant had to settle the dues of all the
lenders (PFC, HUDCO, SBI, IFCI, REC, OICL, NICL, GICL, CBoI, IDBI,
Dena Bank). Management of Respondent No. 1 was taken over by the Appellant
& Sh. M.L. Gupta as nominee of the Appellant was appointed as CMD of
Respondent No. 1. The Respondent No. 2 stated that on 06.08.2019, invoked
shares were returned to the Appellant and the same is recorded in the letter
dated 05.03.2020 issued by the Sh. M.L. Gupta the MD appointed by the
Appellant. Further, conversion of debt into equity done by PFC, was also
reversed & accepted by the Board of the Respondent No. 1.
67. The Respondent No. 2 submitted that the MoU stipulated that the
Appellant shall bring in an upfront amount of Rs. 10 crore within three weeks
from appointment of CMD of this choice i.e. by 27.08.2019 (the appointment
having been made on 06.08.2019) and this was first and foremost obligation of -34- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
the Appellant, independent of any other action by any of the parties. The
Respondent No. 2 stated that admittedly, only Rs. 1 Crore, that too in tranches,
was brought by the Appellant and the balance amount of Rs. 9 Crore was never
brought, thus the first default under the MoU was committed by the Appellant
on 27.08.2019 itself. The Respondent No. 2 stated that Clause 11 of the MoU
records that "While submitting the Settlement Plan, the Settlement Plan would
make provision with respect to the various Loans as are mentioned in the Loan
Recall notice dated 17.01.2018 and Schedule B................" thus, the MoU
clearly stipulated repayment of loan granted under the Additional Loan
Agreement dated 27.04.2017 as well as previous loan/liabilities. The Appellant
stated that Clause 22 of the MoU provided "In the event of failure to implement
the contents of this MoU in 12 (twelve) months from the Execution Date, this
MoU shall stand automatically terminated". The Respondent No. 2 submitted
that even as on 24.10.2019, the said amount of Rs 9 Crore had not been infused,
nor was any concrete settlement proposal given to the Lenders. The Respondent
No. 2 pointed out that even in the subsequent meeting of lenders held on
16.12.2019, the Appellant assured that it shall infuse the said amount of Rs. 9
Crore by end of December, 2020, which was also not done. The Respondent
No. 2 empathetically submitted that all these clearly demonstrate lack of will
and intention on part of the Appellant to fulfil MoU conditions and hence he
can't take shelter of MoU at this stage without fulfilling conditions on his part. -35-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
68. The Respondent No. 2 assailed the Appellant who filed an Application
under Section 65 of the Code on 17.03.2020, much after Original
Orders/Judgments were reserved in his Section 7 application by the predecessor
Bench on 28.02.2020 & therefore being highly belated (two years after filing of
Section 7 Application & that too when orders had been reserved) and filed
baseless Section 65 application as an afterthought to derail the Section 7
application of the Respondent No. 2.
69. The Respondent No. 2 sated that due to the Appellant's utter failure to
implement the MoU, the Task Force constituted by the GoMP was annulled by
the GoMP and it was recorded in the communication dated 27.04.2020 issued
by the Govt. stating that "the second option of suggestions to allow legal
process initiated by the Respondent No. 2 under the Code to reach a logical
conclusion was accepted, making the existence of the Task Force infructuous"
which was not been challenged by the Appellant and has attained finality.
70. The Respondent No. 2 reiterated that on 22.07.2020, upon expiry of one
year from the date of its execution, the MoU stood automatically terminated in
terms of Clause 22 thereof. Even by this date, the Appellant did not bring the
amount of Rs 9 Crores as stipulated in the MoU, which it could have, as his
Section 7 application was still pending and had not been admitted.
71. The Respondent No. 2 submitted that there was no dispute on aspect of
limitation between the Member Technical and the Member Judicial of the -36- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
NCLT, which is evident from the Orders dated 08.10.2021 passed by the said
two Members and the questions framed for reference to the Third Member.
Whilst the Judicial Member has held that the Section 7 Petition is not barred by
limitation, the Technical Member has not given any finding on limitation and no
question has been framed by either of the Members on limitation, therefore, the
issue of limitation attained finality on 08.10.2021 and thus, the present Appeal
insofar as it challenges the said Order on limitation is itself barred by limitation.
The Respondent No. 2 has taken this specific objection in the Reply to Appeal,
to which there is no rebuttal/rejoinder. The Respondent No. 2 stated that
without prejudice to the Application under Section 7 is not barred by limitation,
as the disbursement of debt of Rs. 384.59 crore under the Additional Loan
Agreement dated 27.04.2017 took place in the year 2017 and the Application u/s
Section 7 was filed on 16.02.2018 and the disbursement has been admitted by
the Respondent No. 1 in its Reply filed through Appellant. The Respondent No.
2 also submitted that w.r.t. the debt and default under the previous loan
agreements, the Respondent No. 2 has acknowledged the debt from time to time
and particulars of such acknowledgments have given to this Appellate Tribunal
in a Chart along with brief compilation of relevant documents on record, during
the course of hearing in present appeal on 19.09.2024.
72. The Respondent No. 2 castigated the argument of the Appellant is that the
acknowledgment dated 17.11.2014 i.e. the Balance Sheet of Respondent No. 1 -37- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
for FY 2013-14 was not filed with the Section 7 Application but was filed with
the written submissions. The Respondent No. 2 submitted that the Appellant's
contention is untenable in view of the recent judgment of the Hon'ble Supreme
Court in Axis Bank Ltd. v. Naren Sheth, (2024) 1 SCC 679, wherein it is held
that the documents relating to acknowledgment claiming benefit of Section 18
can be introduced and accepted at the Appellate stage. The Respondent No. 2
also sought to make reliance on the judgment in Asset Reconstruction Co.
(India) Ltd. v. Tulip Star Hotels Ltd., 2022 SCC OnLine SC 944 [Relevant
Paras 49, 62, 76-80] and judgement in the matter of Rajendra Narottamdas
Sheth v. Chandra Prakash Jain, (2022) 5 SCC 600, to buttress this point.
73. The Respondent No. 2 stated that the Annual Report 2013 -14 was filed
with the ROC & is part of public record and this Balance Sheet was signed by
Sh. Mukul Kasliwal (Promoter) as one of Directors of the Respondent No. 1.
The Respondent No. 2 stated that this Balance Sheet has been filed by the
Appellant himself as Annexure-QQ in CP No. 175/2017 (Petition u/s 241-242)
pending before the NCLT, therefore, the plea of the Appellant w.r.t.,
acknowledgement of figures in this balance sheet is erroneous.
74. The Respondent No. 2 also strongly refuted the Appellant's reliance on
the Order dated 12.03.2018 passed by this Appellate Tribunal and stated that it
is misplaced as the Order dated 12.03.2018 was passed by this Appellate
Tribunal in the proceeding arising from Section 241-242 of the Companies Act, -38- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
2013 and therefore has no bearing on the debt or default or Section 7
Application under the Code and cited the judgment of this Appellate Tribunal in
Jagmohan Bajaj v. Shivam Fragrances Pvt. Ltd. & Ors., [(2018) 210 Comp
Cas 84] in support of this pleadings.
75. The Respondent No. 2 stated that this Appellate Tribunal held that "the
Promoter do not appear to be enthusiastic to get status quo ante restored in the
Articles not inspire confidence that if we strike down these amendments made
on 25.11.2005 (and subsequently) they can take charge and complete the project
which attracts public interest.............." and further, in Para 51 of the Order
dated 12.03.2018, this Appellate Tribunal has observed that "The Project has
been delayed endlessly." The Respondent No. 2 submitted that in terms of the
aforesaid Order of this Appellate Tribunal, the Secretary (Power), GoI on
24.03.2018 convened a meeting, which was attended by Promoters, GoMP, PFC
& other Lenders and recorded in the said meeting that all concerned including
Promoters favored resolution of Corporate Debtor under Code.
76. The Respondent No. 2 stated that at five places acknowledgment of debt
has been made by the Respondent no. 1 i.e., on 17.11.2014 - Balance Sheet of
the Respondent No. 1 for Financial Year 2013-14, 29.09.2015- Minutes of
meeting of Board of Directors of Respondent No. 1, 02.03.2017- Minutes of
meeting of Board of Directors of Respondent No. 1, 27.04.2017- Additional -39- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Loan Agreement- Schedule II and 28.08.2017- Balance Sheet of the Respondent
No. 1 for Financial Year 2016-17
77. The Respondent No. 2 stated that on 11.04.2019, the Respondent No. 1,
through its Managing Director, filed an Affidavit in Reply to the Application
under Section 7 proceeding, pending before the Adjudicating Authority
emphasizing that resolution needs to be found for the Respondent No. 1 and the
said Reply was duly supported by the Board Resolution dated 22.02.2019
passed by the Respondent No. 1.
78. The Respondent No. 2 submitted that a Memorandum of Understanding
was executed amongst PFC, the Respondent No. 1 and Appellant on 22.07.2019
('MoU'), in order to explore a settlement plan by the Respondent No. 1 and the
Appellant, for OTS /Restructuring Scheme for dues of the creditors.
Management of Corporate Debtor was taken over by Appellant and Sh. M.L.
Gupta was appointed as CMD of Corporate Debtor, by the Appellant and on
06.08.2019, invoked shares were returned by the Respondent No. 2 to the
Appellant which is recorded in the letter dated 05.03.2020 issued by the Sh.
M.L. Gupta, who also requested Appellant to create pledge on the said shares in
favour of Respondent No. 2. Further, conversion of debt into equity done by
Respondent No. 2, was also reversed & accepted by the Board of the Corporate
Debtor.
-40-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
79. The Respondent No. 2 submitted that the MoU, is not relevant for the
Section 7 proceeding as the scope of the Section 7 proceeding is narrow & the
Adjudicating Authority is not a civil court where disputes relating to MoU can
be agitated or specific performance thereof can be sought. The Respondent No.
2 submitted that MoU was executed in order to give an opportunity to Appellant
and Respondent No. 1 to settle the dues of the creditors, however, Appellant and
Respondent No. 1 failed even to come up with a concrete proposal for
settlement of the dues of the lenders, much less paying/settling the same. Thus,
the MoU clearly stipulated repayment of loan granted under, the Additional
Loan Agreement dated 27.04.2017 as well as the DPG liability, apart from the
previous loans.
80. The Respondent No. 2 stated that on 03.12.2019, the nominee director of
Respondent No. 2 on the board of the Respondent No. 1 resigned and thereafter
on 11.12.2019, vide its letter addressed to the Respondent No. 1 and Appellant,
PFC highlighted non-compliance of the provisions of the MoU by the Appellant
and Respondent No. 1. The Respondent No. 2 submitted that the MoU was
entered into pursuant to this Appellate Tribunal Order and the recommendation
of STF, however, as the MoU was not implemented by the Promoter himself,
Respondent No. 2 had no option but to take recourse to the Section 7 Petition
and thus, the contention of the Appellant that Section 7 Petition was not to be -41- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
pursued in light of the MoU, are meaningless in as much as the terms of the
MoU were not even implemented by the Appellant.
81. Concluding his pleadings, the Respondent No. 2 requested to dismiss the
appeal with exemplary cost.
Our Analysis
82. Since, the case has chequered history, it will be important for us to note
down the basic facts of the case before going into the merit of the pleadings by
the Appellants and the Respondents.
History of the Project and Case
83. The history of the project and case has been captured from the pleadings
and submissions made by the parties before us and are summarized as under :-
84. In 1993, Government of Madhya Pradesh ('GoMP') entrusted the
construction and implementation of 400 MW hydroelectric power project
('Project') at Mandaleshwar, Madhya Pradesh ('Project') to the Appellant on
'Build Own Operate and Maintain' basis, Pursuant to which the Respondent No.
1 was incorporated as a Special Purpose Vehicle ('SPV') on 11.05.1993.
85. On 11.11.1994, a Power Purchase Agreement ('PPA') was signed
between the Respondent No. 1 and Madhya Pradesh State Electricity Board
(now Madhya Pradesh Power Management Company Ltd ('MPPMCL') for
purchase of 100% power from the Project. We note that to execute project, the -42- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Respondent No. 1 approached various banks and Financial Institutions for grant
of various credit facilities on 10.10.1997. The Respondent No. 2 sanctioned a
Rupee Term Loan ('RTL') of Rs. 100 Crores ('RTL 1') and Foreign Currency
Loan of USD 34 Million ('FCL 1 ') additional standby loan of USD 18.9
Million ('FCL 2'). Other lenders also extended financial assistance to the
Respondent No. 1 for the Project.
86. We note that the Promoters could not infuse required equity contribution
between 1998 to 2000, resulting in gap of Rs. 330 Crores in equity funding of
the Project. The Respondent No. 1 approached the GoMP for participation in the
Project equity, to bridge the aforesaid gap. GoMP accorded its approval for a
Stand-By Guarantee Facility of Rs 400 crores so as to enable the Respondent
No. 1 to raise optionally fully convertible debentures ('OFCDs') to the extent of
Rs 400 Crores. The Respondent No. 1 also approached the Respondent No. 2 to
provide a Default Payment Guarantee of Rs. 400 crores ('DPG'), who agreed to
same.
87. We note that despite these developments, the financial closure could not
be achieved by the Respondent No. 1. We also note that the Project cost
escalated from Rs 1565 Crores to Rs 1818 Crores (till 1998) with corresponding
equity required from promoters also increases to Rs 582 Crores till 2005. The
Promoter along with foreign investors could infuse equity of Rs 144 Crores
only.
-43-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
88. We also take note of the fact that on 02.03.2005, on request of the
Respondent No. 1, the Respondent No. 2 revalidated its financial support of Rs.
325 Crores and the DPG for the OFCDs and sanction letter dated 02.03.2005
was issued. It is significant to note that in terms of the sanction letter dated
02.03.2005, it 'was stipulated that the Respondent No. 2 in consultation with
other lenders will approve the appointments of Chairman, Managing Director
and Director (Finance) on the Board of the Corporate Debtor and accordingly,
AoA of the Respondent No. 1 was amended.
89. The Respondent No. 1 requested the Lenders to disburse more money to
complete the Project and Lenders agreed to convert defaulted portion of interest
in their respective accounts into Zero Coupon Bonds ('ZCB') redeemable over a
period of 20 years after a moratorium of 1 (one) year from the commercial
operation date ('COD') of the Project.
90. We also note that on 16.09.2005, an Amendatory and Restated Agreement
(A&RA) was signed amongst the GoMP, MPSEB, the Respondent No. 2, the
Respondent No. 1 and Appellant and as per Clause 3.3 of the A&RA, it was the
responsibility of the Promoter to achieve financial closure within 180 days of
the signing of the A&RA i.e. by 15.03.2006 and the COD was as defined in the
PPA or 4 years from the effective of GoMP's Counter Guarantee for the
optionally fully convertible debentures.
-44-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
91. We understand that in September, 2005 Ministry of Power ('MoP')
constituted a task force to revive project. During review meeting held on
24.10.2005 by the Secretary (Power), GoI, it was noted that the restructuring
was based on the starting point of the Promoter bringing in Rs 310 Crores as
Project equity which the Promoter could not be arrange. It was also decided that
the Respondent No. 1, its Promoters and the Lenders should make all out efforts
to restart the Project by 01.11.2005. In this background, the Respondent No. 2
further disbursed Rs 70 Crores till August 2006, however, the Respondent No. 1
could not achieve the financial closure due to non- infusion of equity/funds and
due to such non-achievement of financial closure, the Respondent No. 2 on the
request of the Respondent No. 1 had to sanction additional Rs 375 Crores in the
nature of subordinate loan to facilitate financial closure to ensure
implementation of the Project. Pursuant to this on 29.09.2006, Respondent No.
2 and the Respondent No. 1 executed a Subordinate Loan Agreement ('SLA')
for subordinate loan of Rs. 375 Crores.
92. We note that a Common Loan ('CLA') Agreement was also executed
between the Respondent No. 2, Rural Electrification Ltd., Housing & Urban
Development Corporation Ltd. and the Respondent No. 1 for a loan aggregating
to Rs 834 Crores. Thus, financial closure was achieved with the execution of the
CLA and the SLA and in accordance to the terms of the SLA, the Respondent -45- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
No. 2 had the right to convert a part or full of the subordinate loan into fully
paid up equity shares of the Corporate Debtor at par.
93. We also note that on 30.11.2006, in accordance with the requirements of
the CLA, a Deed of Pledge (Pledge Deed), was also executed in favour of
Respondent No. 2, whereby the Promoter pledged its 29,17,20,330 fully paid up
equity shares of aggregate face value of Rs.291,72,03,300/- held in the
Respondent No. 1, for the benefit of the lenders (including Respondent No. 2),
with a second charge on the said shares in favour of GoMP.
94. We note that due to involvement of multiple lenders and their standalone
financing and security documents led to a requirement of bringing all the
lenders on a common platform in order to achieve uniformity of terms and
conditions amongst all the lenders in relation to the administration and
disbursement of the Credit Facilities and creation of additional Security and its
enforcement, the Respondent No. 1 and the lenders (Respondent No. 2,
HUDCO, REC, Central Bank of India, State Bank of India, Life Insurance
Corporation Ltd., IFCI, Dena Bank, GIC, NIC, IDBI, UIICL, OIC & NIA (14
lenders) entered into Master Restructuring and Loan Agreement (MRLA) on
22.06.2010.
95. We note that since inception of project during 1993 to 2010, the lenders
distributed Rs. 1817 Crores, whereas Promoters could infuse only Rs. 497
Crores out of requirement on their part of Rs. 749 Crores. It is also a fact that -46- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
project was stalled between 2010-2016 and loan accounts of Respondent No. 1
were declared NPA on 31.03.2012.
96. We observe that since the project was not moving forward, a High Level
Committee (HLC) headed by Additional Chief Secretary (Finance), GoMP, was
constituted to suggest the way forward for the Project which included
Respondent No. 1, Appellant, Respondent No. 2, other lenders and promoters
and the HLC's report dated 02.05.2015 was submitted giving three likely
Scenarios to complete project. At this stage, it is important to understand these
three scenarios which reads as under :-
(A) Scenario-I: "Implementation by the present promoter - 90 days' time
allowed till 02.08.2015. Existing promoter will have to arrange additional
equity of Rs. 600 Crore as well as debt of Rs. 1100 Crore at concessional
rates to achieve the MPPMCL stipulated tariff of Rs. 5.32 per unit shall
be applicable."
(B) Scenario-II: "Government companies acquiring/ having majority equity
in project with management control. Project could be taken over by
NHPC Limited, NHDC Limited and that PFC would be amenable to
infusing equity or additional debt as well as lowering of interest rate for
existing debt and with commensurate support from lenders, tariff could
be reduced to Rs. 5.32 per unit which is acceptable to MPPMCL."
-47- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
(C) Scenario-III: "Cancellation of PPA. If scenario I & II above do not
fructify, the last option will be that MPPMCL cancels the existing Power
Purchase Agreement. GoMP and MPPMCL would be burdened on
account of GoMP's counter guarantee of Rs. 400 Crore issued to PFC."
97. Thus, as per the Scenario-I, the Promoter was given 90 days' time till
02.08.2015 to submit a firm and binding proposal regarding arrangement
including, additional equity of Rs. 600 Crores and debt of Rs. 1100 Crores. We
note that the Promoter could not infuse necessary equity and/or arrange the fund
and consequently Scenario-II was initiated.
98. We understand that in order to move forward as per HLC to implement
Scenario II the meeting was called on 22.03.2016 to bring NHPC/NHDC as new
Promoters but NHPC declined the offer. As interim measure, the Respondent
No. 2 along with other lenders agreed to finance more. The Scenario II also
involved invocation of pledged shares of promoters in favour of lenders and
exercise right to partially convert subordinate loan to equity. Accordingly, on
19.05.2016 notice was issued to invoke pledged shares and on 27.06.2016, the
notice was issued to convert subordinate loan of Rs. 66.10 Crores into equity.
By these acts, the Respondent No. 2 became 23.32% equity shareholder of
Respondent No. 1 and Lenders i.e., REC, HUDCO, CBI, Dena Bank, NICL and
Respondent No. 2 cumulatively acquired 51% shares of Respondent No. 1 in
accordance with HLC. We note that this was as per done decision of all -48- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
stakeholder including GoMP, GoI, Lenders and Promoters and not on unilateral
part of the Lenders alone.
99. We note that on 05.11.2016, the Respondent No. 2, on behalf of himself
and other Lenders, issued a Loan Recall Notice to the Respondent No. 1
demanding payment of the outstanding dues but no repayment was made to the
Lenders. In such financial conditions, in order to meet the immediate fund
requirements as part of revival measure of the Project, Respondent No. 2 in
principle agreed to increase the Project cost from Rs. 2760 Crores to Rs. 8121
Cores and requirement of additional debt of Rs. 3022 Crores ('Additional Debt")
for the Project. Subsequently, at the request of the Respondent No. 1, an
Additional Loan Agreement dated 27.04.2017 was executed between
Respondent No. 2 and the Respondent No. 1 for an additional term loan of Rs.
600 Crores and the Respondent No. 2 disbursed Rs. 384.59 Crores. The said
Additional Loan Agreement was entered into by Respondent No. 2 in the
capacity of Lender's Agent, Security Agent and Lender and the terms and
conditions including security creation, for this additional loan was approved in
the extra ordinary general meeting('EGM') of the Respondent No. 1 held on
31.07.2017.
100. We note one contentious issue w.r.t. interest amount of Rs. 10 Crores due
to be payable by the Respondent No. 2 and not paid, whereas remaining amount
was disbursed by Lenders to the Respondent No. 1.
-49-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
101. We note that NCLT vide order dated 15.06.2017 held that invocation of
pledged share and conversion of debt into equity was not in accordance the
procedures prescribed under the law. The same was confirmed by this
Appellate Tribunal and Hon'ble Supreme Court of India hence the Respondent
No. 2 cancelled these acquired shares and returned to the Respondent No. 1
later.
102. We note that as per SLA, first interest payment became due on
15.07.2017 in terms of Article 7.1 (b) of SLA r/w definition of "Interest
Payment date" which Respondent No. 1 failed to pay. It is the case of
Respondent No. 2 that he issued three demand letters on 06.07.2017, 01.10.2017
and 05.01.2018. On the other hand, it is case of Appellant that this "Interest"
was created by Respondent No. 2 for CIRP only as Respondent No. 1 issue
"Draw Due Notice (DDN) dated 02.05.2017 for Rs. 435 Crores including Rs. 10
Crores but Respondent No. 2 did not pay interest Rs. 10 Crores deliberately.
103. We observe that the Respondent No. 2 issued Recall Notice on
17.01.2018 to Respondent No. 1 recalling outstanding dues of Rs. 2139.20
Crores and pursuant to the same, the Lenders filed application under Section 7
of Code on 16.02.2018. We note that the Respondent No. 1 also defaulted on
Rs. 318.49 Crores for default Payment Guarantor (DPG) and further defaulted to
meet liability of Rs. 103.87 Crores towards ZCB.
-50-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
104. We have already noted that NCLT vide order dated 15.06.2017 held that
invocation of pledged shares and conversion of partial debt into equity by
Lenders was not in accordance with law. This was upheld by this Appellate
Tribunal vide order dated 12.03.2018 and also directed GoMP & GoI to
urgently consider the way forward. This Appellate Tribunal recorded the
following :-
"the Promoter do not appear to be enthusiastic to get status quo ante restored in the Articles not inspire confidence that if we strike down these amendments made on 25.11.2005 (and subsequently) they can take charge and complete the project which attracts public interest. Promoters have not brought to our attention that at any time they opposed, or stood up to the gradual takeover."
(Emphasis Supplied)
105. In terms of this Appellate Tribunal order dated 12.03.2018, a meeting was
convened of all stakeholder on 24.03.2018 which was attended by Respondent
No. 1, Respondent No. 2, Appellant, GoMP, GoI, Lenders and in Para 17, it was
decided that resolution of the Respondent No. 1 under IBC is best solution
GoMP also supported admission of Section 7 application of the Respondent No.
2 in an Affidavit filed on 03.08.2018 in Section 7 application of the Respondent
No. 2 filed on 16.02.2018. On 11.04.2019, the Respondent No. 1 through MD
filed an affidavit before NCLT that resolution need to be found of Respondent
No. 1.
-51-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
106. During the pendency of Section 7 application before NCLT, GoMP
formed a Task Force, which decided on 25.05.2019 that Promoter and Lenders
should try to find a way forward and accordingly an MoU was signed amongst
Lenders, Respondent No. 1 and Appellant on 22.07.2019 to explore a settlement
plan by the Appellant for OTS. Accordingly, Respondent No. 2 returned equity
shares due to invocation of pledged shares and partial conversion of debt into
equity bank to the Appellant pursuant to NCLT/this Appellate Tribunal/
Hon'ble Supreme Court of India judgment that these acts of Respondent No. 2
were not in accordance with procedures prescribed under the law.
107. We note that the management of Respondent No. 1 was taken over by the
Appellant and Mr. ML Gupta as nominee of the Appellant was appointed CMD
on 06.08.2019, thereafter, the Respondent No. 2 and Lenders quit management
of Respondent No. 1. This MoU stipulated that the Appellant would bring in an
upfront amount of Rs. 10 Crores within three weeks of appointment of CMD
i.e., dated 27.08.2019, but admittedly the Appellant could bring only Rs. 1 Crore
and could not bring balance of Rs. 9 Crores to Respondent No. 1. This MoU
also provided that loan granted under SLA dated 24.07.2017, DPG liability and
previous loan will be provided in settlement. Further, as per Clause 11 of MoU
i.e., Automatic termination of MoU was to take place if not implemented in 12
months from execution of MoU.
-52-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
108. As per Clause 19 of MoU, Respondent No. 2 requested Adjudicating
Authority to defer the proceeding under Section 7 of his application. However,
since MoU could not fructify, the Respondent No. 2 proceeded with application
and Adjudicating Authority during hearing on 05.12.2019 recorded the
following :-
"Learned Counsels appeared for both sides have submitted
that "Special Task Force Committee" has been constituted by the State Government (Madhya Pradesh) which is still under consideration. However, we are of the view that, the matter pertains to the year 2018 and the time is essence of the Code no further time can be granted on this aspect, the parties are hereby advised to come prepare with the final argument on the main CP(IB) 111 of 2018 as well as CP(IB) 389 of 2018 along with all pending Interlocutory Application(s)."
(Emphasis Supplied)
109. We note that the final hearing by the Adjudicating Authority was held on
28.02.2020 and order was reserved. However, the same could not be
pronounced as both members of NCLT were transferred to other benches in
May, 2020. The Appellant filed an application under Section 65 of the Code
before the Adjudicating Authority on 27.03.2020 vide IA No. 60 of 2020 i.e.,
after order in Section 7 application was reserved on 28.02.2020. -53-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
110. We observe that on 20.07.2020, MoU also got automatically terminated
in terms of Clause 22 of MoU.
111. Finally, the Adjudicating Authority gave its verdict in two separate order
wherein the Member (Technical) rejected Section 7 application of the
Respondent No. 2, however, Member (Judicial) admitted Section 7 application
and being split verdict, the matter was referred to the President NCLT who
made reference to Member (Judicial), Kolkata, Mr. Rohit Kapoor on 21.03.2022
under Section 419 (5) of the Companies Act, 2013 who pronounced the
Impugned Order i.e., his judgement on 27.09.2022.
112. We were informed that additional loan of Rs. 600 Crores was supported
by the Promoters i.e., Mukul Kasliwal as recorded in BoD minutes dated
02.03.2017, where it was recorded the following.
"Shri Mukul Kasliwal specifically requested the Board to record that, the sanctioning of additional loan to complete the project is a welcome step apart from all the issues and concerns going on between the Lenders and Promoters and Lenders will receive support from the promoters as well in view to complete the project."
(Emphasis Supplied)
113. We also note that Schedule II of SLA dated 27.04.2017, the existing debts
of Rs. 1750.93 Crores were acknowledged. Further as per Article 2.3 and
Article 4.1 (ii) (a) of SLA provides :-
-54-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
"Article 2.3
"The Drawdown under this Agreement shall be subject to the satisfaction of each condition precedent set forth in Article IV hereof. Further, the obligation of the Additional Lender to make disbursement under this Agreement shall be subject to the Borrower performing its obligation and undertakings under this Agreement and the Borrower's compliance with the disbursement procedure stipulated hereunder, including, the submissions by the Borrower of all necessary information, documents, etc. to the satisfaction of the Additional Lender."
Article 4.1(ii)(a) provides that "validity of the Additional Facility as well as its terms and conditions shall be subject to Government Companies/Lenders holding majority equity in the Project.............."
(Emphasis Supplied)
114. We consciously note that this SLA and its conditions were agreed to by
all including Promoters and signed on 27.04.2017, much prior to judgments of
NCLT on 15.06.2017 and this Appellate Tribunal's judgment on 12.03.2018 on
an application of Appellant under Section 241 & 242 of the Companies Act,
2013. We are noting these dates as one of the contentions of Appellant is that
the SLA is in violation of NCLT/NCLAT orders. We will discuss the same at
later stage at appropriate place, but suffice to note that the SLA happened much -55- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
prior to NCLT/NCLAT's judgment under Section 241 & 242 of the Companies
Act, 2013.
Findings
115. We note that the differences between the Members of NCLT,
Ahmedabad Bench were framed in their respective split orders which were
referred by the President NCLT to Member (Judicial) NCLT, Kolkata Bench
under Section 419(5) of the Companies Act, 2013.
116. Issue framed by Member (Technical)
"I. Whether, in the facts and circumstances of the case, notice dated 17.01.2018 recalling the loan is bad in law as debt is neither due nor payable as on that date?
II. Whether, in the facts and circumstances of the case, application filed under Section 7 of IBC, 2016 is an instance of malicious initiation of insolvency proceedings in particular for the reason that event of default for non payment of interest during construction period has been created by the Respondent No. 2 itself and, therefore, liable to be rejected under Section 65 of IBC, 2016?
III. Whether, in the facts and circumstances of the case, M/s. Entegra Ltd., being the original promoter and M/s. Power Infrastructure India Ltd. as strategic investor have got locus to intervene in the matter on behalf of the Corporate Debtor?
-56-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
IV. If point no. I and II above are in affirmative then whether the application U/s of IB Code ought to be rejected?"
(Emphasis Supplied)
Issues framed by the Member (Judicial) :-
"(I) Whether M/s. Entegra Ltd., the original promoter and M/s. Power Infrastructure India as strategic investors, have any locus to intervene in the matter on behalf of the corporate debtor?
(II) Whether, notice dated 17.01.2018 recalling the loan is bad in law.
(III) Whether, present application filed under Section 7 of IBC, 2016 is an instance of fraud/malicious initiation of insolvency proceedings U/s 65 of the Code? (IV) If point No. III above is affirmative then whether the application U/s 7 of the IB Code ought to be rejected on that ground?"
(Emphasis Supplied)
117. From above issues framed by Judicial Member and Technical Member,
the common threads of issues pertains to validity of Recall Notice dated
17.01.2018; whether Section 7 application of Respondent No. 2 is malicious and
fabricated insolvency petition or otherwise, locus of the Appellant and finally
whether Section 7 ought to be rejected or otherwise.
118. Following issues emerges in the present appeal :- -57-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
(i) Whether there was a debt and default which entitled the Respondent
No. 2 to initiate Section 7 application under the Code and whether
such debt and default was within the period of limitation.
(ii) (a) Whether, the Lenders especially the Respondent No. 2 who was the
Financial Creditor and also allegedly in control of the Respondent No.
1 since, 2005 to 2018, could have initiated present Section 7
application or should have initiated application under Section 10 of the
Code.
(b) Whether the invocation of pledge shares and partial conversion of
debt into equity by the Respondent No. 2 has adverse impact in the
present appeal.
(c) Whether, the Lenders especially the Respondent No. 2 assumed
the role of owners in addition to role of the Lenders after invocation
of pledged shares and partial conversion of debts into equity or the
Lenders were involved in management with limited roles to protect
their loan advanced to the Respondent No. 1.
(iii) Whether, the additional loan agreement dated 27.04.2017 was
fabricated or forced upon the Respondent No. 1 to initiate Section 7
application by the Respondent No. 2 and whether the Recall Notice
dated 17.01.2018 was legal or not.
-58-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
(iv) Whether, Section 241 and 242 Companies Act, 2013 application filed
by the Appellant who got reliefs from NCLT/ NCLAT and the
Hon'ble Supreme Court of India has any bearing on present Section 7
application.
Since, all these issues are inter-related, inter-connected and inter-dependent,
we shall deal with these issues in conjoint manner in subsequent discussions.
119. Issue (I) Whether there was a debt and default which entitled the
Respondent No. 2 to initiate Section 7 application under the Code and
whether such debt and default was within the period of limitation.
➢ We note that various financial debts i.e., loan was granted from time to
time from 1998 to 2017 by the Respondent No. 2 to the Respondent No. 1
and following are the relevant agreements:-
S.No. Date Documents
1. 04.12.1998 Loan Agreement
2. 16.09.2005 Amendatory and Restated Agreement
3. 29.09.2006 Common Loan Agreement
4. 29.09.2006 Subordinate Loan Agreement
5. 22.06.2010 Master Restructuring and Loan Agreement
6. 27.04.2017 Additional Loan Agreement
➢ We have noted that the Respondent No. 2 sanctioned Rs. 100 Crores
(RTL - 1) and foreign currency loan of Rs. 34 million USD (FCL-1) on
10.10.1997. The Respondent No. 2 further sanctioned additional foreign -59- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
currency loan of USD 18.9 Million to the Respondent No. 1 (FCL-II) on
24.11.1998 and the authorized loan facilities were entered into loan
agreement which was executed between the Respondent No. 1 and
Respondent No. 2 on 04.12.1998.
➢ We have already noted that due to lack of financial arrangements from
Promoters side regarding equity infusion and funds, the financial closure
could not be achieved and as a result of which the project did not see any
progress up to October, 2005.
➢ Subsequently, after intervention of GoMP and GoI and other
stakeholders, the Respondent No. 2 revalidated the loan on 02.03.2005 for
OFCDs which was sanctioned somewhere in March, 2001.
➢ We have already noted earlier the facts regarding amendatory and restated
agreement dated 16.09.2005 and common loan agreement amongst the
lender on 29.09.2006.
➢ We have also recorded that at the request of the Respondent No. 1, the
Lenders also agreed to convert defaulted portion of interest in their
respective accounts into ZCB which was redeemable period 20 years after
mandatory moratorium of one year by the Master Restructuring and Loan
Agreement was executed on 22.06.2010.
➢ It is a significant to note that subsequent to meeting held by Secretary,
Ministry of Power, Government of India on 24.10.2005, it was decided -60- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
that the Promoters will bring in project equity and to achieve financial
closure, Respondent No. 1 at the request of Respondent No. 2 had
sanctioned Rs. 375 Crores in the nature of subordinate loan for which the
subordinate loan agreement was signed on 29.09.2006.
➢ At the request of Respondent No. 1, the Respondent No. 2 sanctioned yet
another additional loan of Rs. 600 Crores, signed additional loan
agreement on 27.04.2017 and against which Rs. 384.59 Crores was
disbursed.
➢ We note that at this stage, the project cost was revised from Rs. 2760
Crores to Rs., 8121 Crores and requirement of additional debt of Rs. 3022
Crores was also factored into.
➢ We note that the Respondent No. 1 could not pay and meet his financial
obligations towards various loan facilities as elaborated in preceding
discussions and as a result of which, the additional financial facilities
granted by the Lenders including the Respondent No. 2 to the Respondent
No. 1, were sanctioned to revive the project.
➢ The disbursal of the loan by the Respondent No. 2 and receipt of the same
by the Respondent No. 1 is undisputed fact. However, what is disputed
by the Appellant as Promoters of Respondent No. 1 is that even though
the financial debt might have been due and payable but there was no
default on account of the Respondent No. 1 for several reasons. It is the -61- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
case of the Appellant that there was no default since the Respondent No.
2 himself was responsible for non-payment of interest amount under
additional financial loan agreement which was not disbursed by the
Respondent No. 2 as such, there was no default by the Respondent No. 1
of any debt due and payable.
➢ The Appellant has been emphasizing mainly on the additional loan
account wherein amount of Rs. 435 Crores was sought based on draw
down notice, out of which Rs. 10 Crores was meant for interest which
was not disbursed by the Respondent No. 2.
➢ It is further the case of the Appellant that the past loan agreement by the
Lenders have deemed to become illegal since subordinate loan agreement
dated 29.09.2006 was sanctioned by BoD in violation of provision of
63(3) of the Companies Act, 2013.
➢ We note the plea of the Appellant that any illegality in the subsequent
loan agreement would completely invalidate of past transactions and past
loan agreements and thus all these previous loan agreements tantamount
to sham agreements.
➢ It is further the case of the Appellant that the additional loan agreement
dated 27.04.2017 entered into Respondent No. 2, despite their knowing
that the said agreement was void-ab-intio and illegal and therefore there -62- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
was no financial debt due and payable under such illegal loan agreements
and therefore there is no question of any default by the Respondent No. 1.
➢ The Appellants another argument is that, since the Respondent No. 2 was
wearing the hats of both as Financial Creditor as well as allegedly in the
management of the Respondent No. 1, there could not be any valid loan
agreement between the Respondent No. 1 & Respondent No. 2.
➢ Further, we have noted the contention of the Appellant that the
Respondent No. 2 kept on entering into further loan agreements only to
utilize such proceeds for service of interest due on loan for previous loans
and not for the project.
➢ Finally, the Appellant argues that the earlier loan agreements are
completely barred by the limitation since the Lenders declared
Respondent No. 1 as NPA on 31.03.2012 qua these loans.
➢ We have perused Section 7 application filed by the Respondent No. 2
before the Adjudicating Authority (NCLT Ahmedabad) bearing CP (IB)
111/2018 on 16.02.2018 along with various annexures forming Part IV of
the Section 7 application. We note that the total amount claimed to be
defaulted has been stipulated as Rs. 2789.42 Crores including outstanding
interest amount payable and other charges as on 15.01.2018.
➢ We have also noted that the working of computation of these total dues
have been indicated in tabular form in computation sheet dated -63- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
15.01.2018 which was annexed as Annexure A-5 of Section 7 application
along with Loan Recall Notice dated 17.01.2018 as Annexure A-6 with
the original Section 7 application.
➢ From Annexure A-5, we note the following.
➢ We further note that details of these amount have been further elaborated
in other pages of the above Annexure A-5, which we have perused but not
repeating herein.
➢ Thus, the Part IV is categorially clear regarding the default amount of
Rs. 2789.42 Crores.
-64-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
➢ In contrast, the main plea of the Appellant is that the various agreements
are sham agreements. He has taken one specific technical point that Rs.
10 Crores was to be disbursed by the Respondent No. 2 as part of
additional loan agreement which the Respondent No. 2 did not disburse
and hence, the loan recall notice dated 17.01.2018 was allegedly itself
created and fabricated document by the Respondent No. 2 just to create
default on the part of the Respondent No. 1.
➢ On the other hand, we have already noted from the various pleadings of
both the parties specially the Respondent No. 2 that the financial creditors
specially the Respondent No. 2 , kept on pumping the money from time to
time only for revival of the project in so much so that even for financial
closure, which could not be achieved by the Promoters due to non
infusion of equity and fund amount, the Respondent No. 2 had sanctioned
money through the additional loan agreement just to facilitate the
financial closure to be done by the promoters of the Respondent No. 1.
➢ We have already noted that both the GoI and GoMP even tried their best
to revive the project and have been actively involved in consultation with
various stakeholders including the Respondent No. 2 and Promoters and
under these persuasive efforts of both Central and State Governments, the
Respondent No. 2 kept on sanctioning the loans the Respondent No. 1. As
regard the point raised by the Appellant regarding non disbursal of Rs. 10 -65- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Crores as interest/ IDC, we do not find any merit that this was
deliberately done by the Respondent No. 2 only to initiate Section 7
application. We wonder, if the Respondent No. 2 and other Lenders have
pumped in thousands of Crores of loans to the Respondent No. 1, why
would they hesitate to give additional loan of mere Rs. 10 Crores but for
any legal hurdle as brought out before us w.r.t., judicial orders whereby
the Lenders ceased to be shareholder and therefore, the conditions
precedent of Scenario II of HLC could not have been met and
consequently the Lenders were not obliged to release any more funds to
the Respondent No. 1 including Rs. 10 Crores interest to Respondent
No. 1. We do not find any merit in the arguments of the Appellant on this
ground.
➢ We have taken note that the judicial fora declared the conversions of
pledged shares into equity, as well as partial conversion of debts into
technically not valid due to non following the legal procedure laid down
in the Companies Act, 2013. We do not find that any legal fora treated
the money disbursed or Loan Agreement by Lenders and the Respondent
No. 2 as sham or fabricated as loans which were due and payable and for
which default were committed by the Respondent No. 1.
➢ We note that the project was conceived way back in the year 1993 and
various facilities were granted since 1997 onward by the Respondent No. -66- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
2. The Respondent No. 1 clearly failed to meet his obligation and there
was a clear debt and default by any stretch of imagination. We are not in
a position to accept the plea of the Appellant that the loan agreement was
sham agreement and the Loan Recall Notice dated 17.01.2018 was
fabricated and created documents by Respondent No. 2 just to take the
Respondent No. 1 into insolvency.
➢ We note that the Respondent No. 2 has been funding from time to time by
way of original RTL-I, FCL-I and FCL-II, which Respondent No. 1 failed
to service its obligations. We also note that even later the Respondent
No. 2 sanctioned subsequent loans and finally additional loans of Rs. 600
Crore which the Respondent No. 1 failed to pay. In view of the above
details discussions, we hold that the verdict of Member (Judicial),
Ahmedabad Bench and Member (Judicial), Kolkata Bench to be correct
holding default committed by the Respondent No. 1.
➢ We have also gone through the verdict of Member (Technical) of
Ahmedabad Bench who has noted that Rs. 600 Crores additional loan was
sanctioned in April 2017 and noted however that only Rs. 384 Crores was
disbursed till 05.01.2018 by the Respondent No. 2 and the Respondent
No. 1 was not having any commercial operations during this period as the
project was under construction.
-67-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
➢ The Member (Technical) of Ahmedabad Bench also noted that the first
installment was due for payment of interest on 15.07.2017 which was not
paid by the Respondent No. 1 and next installment of interests fell due on
15.10.2017 and 15.01.2018 which were also not paid by the Respondent
No. 1.
➢ The Member (Technical ) of Ahmedabad Bench further notes that
"22. ....However, even first instalment of such interest which fell due for payment on 15.07.2017 has not been paid. Further, next two instalments of interest due on 15.10.2017 and 15.01.2018 have also not been paid. The crucial fact is to be noted that disbursement of loan was undergoing till 05.01.2018 and balance loan amount (600 crores minus 384 crores) has not been disbursed at all and, therefore, responsibility for non-completion of project squarely lies on the shoulders of the lenders, who were in complete control of the project at that point of time, It is also noted that the applicant-financial creditor asked the corporate debtor to pay existing debt of Rs. 2139 crores plus interest on the additional loan within 15 days from the date of such recall notice knowing fully well that the corporate debtor was not in a position to do so and such position of the corporate debtor was substantially attributable to the conduct of the applicant-financial creditor itself. This factual position speaks for itself. Further, in our view, a situation of default has been created with the malicious intent to file application under Section 7 of IBC, 2016 so that the petition filed by the -68- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
M/s. Entegra Ltd., being intervener under Section 241-242 of the Companies Act, 2013 can be brought the under moratorium.
25. .....in our opinion, are more than sufficient to hold that application filed under Section 7 is an instance of abuse of process of law. Thus, we are not dealing with their other contentions for the sake of brevity, although, in our opinion, such pleas lend further credence to their claims made in this regard. We may further add that if we dive deep into the sea of controversies only more and more skeletons would came out and which may create further issues for lenders."
29..... In the present case, it further pains us that applicant- financial creditor as is one of the prominent central public sector undertakings and other financial creditors are institutional lenders. Hence, there cannot be any justification for such entities to act in this fashion and a serious introspection is required in their approach to promote the entrepreneurship, make availability of credit and for future growth of the economy. These objects are defined in the preamble to the CODE also. Thus, a person, in a dominant position like this, needs to correct itself. Thus, if all the parties Involved with a view to find an amicable solution as if it was required yesterday would have to act in a positive manner, forgetting the past and relinquishing their egoistic approach. We may further observe that, in the facts and circumstances of the case, even it would not be in the interests of the lenders as well as they may have to take -69- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
substantial hair-cuts and also it may hurt the interests of various other stakeholders.
32. ... In the result, TP 258 of 2019 in CP (IB) 111 of 2018 stands dismissed, being an instance of malicious initiation of insolvency proceedings and also on account of debt not being due and payable as on the date of issue of notice of recall.
(Emphasis Supplied)
➢ We would like to point out that the reasoning of Member (Technical) in
above paras are on perceived issues and presumed facts rather than on any
legal issues. We do not find any meaningful discussion regarding
applicability of Section 7 of the Code in the facts of the case and also do
no find any discussions on any judgment of the Hon'ble Supreme Court
of India's (out of catena of the judgments) on the subject where it has
been held again that the role of the Adjudicating Authority is limited to
find existence of debt for which default has taken place, meeting the
stipulated minimum threshold limit and take action to accept Section 7
application else reject the same. The Hon'ble Supreme Court of India
again and again held limited role of Adjudicating Authority in such case
except where non-compliance to provision of the Code is noted.
➢ The Adjudicating Authority is required to work as per the mandate of the
Code and regulations and in accordance with the ratio decided by the -70- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Hon'ble Supreme Court of India and this Appellate Tribunal, rather than
presumption and assumptions in quoting few facts here and there out of
context, and therefore, we do not support the rational of the Member
(Technical) Ahmedabad Bench as contained in his order dated
08.10.2021.
➢ We find that all the parameters of Section 7 application has been met and
correctly pointed out in the Impugned Order by both the Judicial
Members of Ahmedabad and Kolkata in their judicial orders.
➢ We also further record that the case is squarely covered under the various
judgments of Hon'ble Supreme Court of India including Innoventive
Industries Ltd. v. ICICI Bank and Anr, (2018) 1 SCC 407], ES
Krishnamurthy v. M/s Bharath Hi Tech Builders [(2022) 3 SCC 161]
and Vistra ITCL (India) Limited & Ors. Vs. Dinkar
Venkatasubramanian and Anr. [(2023) 7 SCC 324], in addition to
catena of judgments of the Hon'ble Supreme Court of India and this
Appellate Tribunal.
➢ We note that there was no dispute on aspect of limitation between the
Member (Technical) and Member (Judicial) of NCLT Ahmedabad Bench
as seen from order dated 18.10.2021 passed by both the Members through
their different judgements and we also find that no question was framed
on this account by any of the Members.
-71-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
➢ However, we find that the Member (Judicial), Ahmedabad Bench has
held that Section 7 application is not barred by limitation after recording
its detailed reasoning for the same.
➢ We find that the pleadings of the Respondent No. 2 that the issue of
limitation has attained finality on 08.10.2021 and the present appeal in so
far it challenged the said order on limitation itself is barred by limitation.
We also note that the Respondent No. 2 has taken this specific objection
in the Reply to appeal to which there was no rebuttal/ rejoinder.
➢ We have also noted the contention that disbursement of debt of
Rs. 384.59 Crores was made under additional loan agreement dated
27.04.2017, whereas for Section 7 application was filed on 16.02.2018
which is within the limitation period. As regard the previous loan
agreements, the same have been acknowledged from time to time in the
various documents and Balance Sheets. One Chart along with brief
compilation of relevant documents on record was presented before us and
handed over to us and the Appellant during the course of hearing in
present appeal on 19.09.2024. The same has also been filed in Written
Submissions by the Respondent No. 2. This also confirm the same.
➢ Based on above detailed discussions, we hold that there was a debt and
default on part of the Respondent No. 1 which entitled the Respondent -72- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
No. 2 to initiate Section 7 application of the Code and the same was not
barred by limitation.
120. Issue (II) (a) Whether, the Lenders especially the Respondent No. 2
who was the Financial Creditor and also allegedly in control of the
Respondent No. 1 since, 2005 to 2018, could have initiated present Section 7
application or should have initiated application under Section 10 of the
Code.
(b) Whether the invocation of pledge shares and partial conversion of debt
into equity by the Respondent No. 2 has adverse impact in the present
appeal.
(c) Whether, the Lenders especially the Respondent No. 2 assumed the role
of owners in addition to role of the Lenders after invocation of pledged
shares and partial conversion of debts into equity or the Lenders were
involved in management with limited roles to protect their loan advanced to
the Respondent No. 1.
➢ We have already noted the various facts regarding the failure of the
Corporate Debtor to complete the project and also their failure to make
the payment from time to time to the Lenders. We also note that even the
financial closure could not take place on account of non infusion of equity
and other funds by the promoters within the stipulated time period. -73-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
➢ It is the case of the Appellant that this happened due to external factors
which were not under the control of the Promoters or the Respondent
No. 1 like Narmada Bachao Andolan and other legal issues. Be that as it
may, we have noted that the project cost which was 1565 Crores became
Rs. 1818 Crores in 1998 and further increased to Rs. 8121 Crores in
2016-17. The present day cost of project, if at all still viable, has not been
quantified by anyone and may be very steep at this stage.
➢ We observed from pleadings of both the parties that the project came to
grinding halt between the period 2001-2005 and only after the
government interventions, the Lenders and other stakeholders were
persuaded to infuse additional money into the project and in this
background the Respondent No. 2 revalidated his financial support of
Rs. 325 Crores and DPG for OFCDs and sanction letter was issued on
02.03.2005 by the Respondent No. 2 to Respondent No. 1. It is necessary
to understand that in this background, it was stipulated that the
Respondent No. 2 in consultation with other Lenders would be involved
in process of appointment of Chairman, MD, Director Finance on the
BoD of Respondent No. 1 and accordingly the AoA of Respondent No. 1
was amended.
➢ We need to take note of the fact that the Respondent No. 1 was
incorporated as a SPV on 11.05.1993 and since 1997 the money was -74- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
being sanctioned by Lenders including Respondent No. 2 to Respondent
No. 1 and despite of these financial facilities including additional loan
agreement, Default Payment Guarantee ('DPG') for Optionally Fully
Convertible Debentures ('OFCD'), the financial position of the
Respondent No. 1 could not improve.
➢ The project could not proceed further mainly due to lack of financial
arrangements on the part of the Promoters by way of equity and other
fund infusion. Even the managerial aspect of the Promoters could also
have been contributory factors leading to the crises in affairs of the
Respondent No. 1.
➢ The fact remains that the task force was constituted in September 2005 by
Ministry of power, GoI consisting of all the stakeholders including
Lenders and in pursuant to this task force, the DPG in favour of the
trustee of OFCD was issued which was secured by counter guarantee of
GoMP.
➢ It is the case of the Appellant that by the amendments in AoA especially
regarding process of approval of Chairman, MD, DF, the management
control of Respondent No. 1 effectively got transferred from the
Appellant to Lenders especially Respondent No. 2. Hence, the
Respondent No. 2 became the shareholder and could not have initiated
Section 7 application. In this connection, we note that these amendments -75- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
were done with the consent and approval of shareholders including the
Promoters. We note that GoMP fully consented to the said process.
➢ In this background, we note that the Respondent No. 1 requested the
Lenders to disburse further amount to complete the project and then
existing lender also agreed to convert default portion of interest by the
Respondent No. 1 in their respective books into ZCB, details of same, we
noted in our earlier discussions. We have already noted that Master
Restructuring and loan agreement was executed subsequently on
22.06.2020. We also note that the amendatory and restructuring
agreement (A&RA) was also signed amongst GoMP, Financial Creditors,
Respondent No. 1 and the Appellant and according to Part 3.3 of A&RA,
it was responsibility of the Promoters to achieve financial closure within
180 days of signing of A&RA dated 15.03.2016.
➢ However, the financial closure could not take place due to non infusion of
equity by the Promoters and therefore the Respondent No. 2 had to
sanction additional loan of Rs. 375 Crores and additional loan agreement
was signed on 29.09.2006 along with common loan agreement between
other lenders for Rs. 834 Crores.
➢ We note that as per terms of Subordinate Loan Agreement ('SLA'), it was
right of Respondent No. 2 to convert a part or full loan into equity shares
of the Corporate Debtor. At this stage, we would like to note that it was -76- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
right and not obligation on the part of the Respondent No. 2 to do so and
that too it could have been done in part or full.
➢ We observe that in terms of common loan agreement amongst the
Lenders, the Deed of pledge was also executed (pledge deed) on
30.11.2006 in favour of the Respondent No. 2 acting as security agent,
further addendum was done thereto in the year 2010-11, whereby the
Promoter's Rs. 29,17,20,330/- fully paid up shares were pledged for the
benefit of lenders including Respondent No. 2 with the secondary charge
in favour of the GoMP.
➢ We take note that the events of lack of financial closure due to non
infusion of equity and funds from the Promoters and due to persuasive
efforts of the Government, the Lenders especially the Respondent No. 2
was obligated to further sanction various financial facilities including
subordinate loan and additional loans to Respondent No. 1, detail of
which we have already noted earlier. Thus, it was not done as desire of
the Lenders for conversion of debts into equity or for that matter for
invocation of pledged shares, but was done as per then prevailing
financial condition of Respondent No. 1 and this was conscious decision
taken by all stakeholders.
➢ In any case, this was done, of course, only on the failure of the
Respondent No. 1 to make repayments to the Lenders. In the present -77- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
case, these rights were duly approved by the Stakeholders and the
Promoters to secure the huge amount of loans by the banks which is
normal commercial policy of Lenders.
➢ We do not subscribe to the pleadings of the Appellant that the Respondent
No. 2 wanted to take over the control of the Respondent No. 1 to service
his own interest and effectively took over the control of the management
of the Respondent No. 1 from the Appellant.
➢ It is required to be understood that if the Promoters would have kept his
promise to infuse the stipulated equity and funds, similarly if the
Respondent No. 1 would have paid back the amount due on the stipulated
time to the Lenders, there would not have been any occasion to make
such decision by the Lenders including changes under AoA or creating
pledged deed. Further, if the Appellant and the Respondent No. 1 would
have done their acts properly, there was no need for Respondent No. 2 to
invoke the pledged shares and partially convert the subordinate loan into
equity shares. In fact, there is no need for any banker to do so. After all
the bankers are involved in granting loans and getting interest, which is
their normal business and only to protect their financial interest, Lenders
make such provisions like partial conversion of debt into equity or
invocation of pledged shares in case of default by borrowers. Hence, in
this background, it need to be appreciated that the allegation that deemed -78- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
control of the Respondent No. 1 got transferred from the Appellant to
Respondent No. 2 with ulterior motives of Lenders is not correct.
➢ We also note that the Promoters Mr. Manoj Kasliwal continued to remain
on BoD of the Respondent No. 1. We further note that the MD, DF of the
Respondent No. 1 were approved by the following due process, with the
consent of the Lenders, and again on this aspect, we do not find any merit
in the allegation of the Appellant.
➢ At this stage, it would be important to understand the impact of
invocation of pledged shares by which the Lender became the
shareholders w.r.t. their rights in filing Section 7 application.
➢ We find that there is a direct judgment of this Appellate Tribunal which
support, prima-facie, the case of the Appellant i.e., case of PTC India
Financial Services Ltd. vs. Mr. Venkateswarlu Kari & Anr. passed in
Company Appeal (AT) (Ins.) No. 450 of 2018. The relevant paras of this
judgment are read as under :-
"2. The question arises for consideration is whether the Appellant can be held to be a 'Financial Creditor', who claimed to be a 'Financial Creditor' for accepting its claim.
3. The case of the Appellant is as follows.
The 'Bridge Loan Agreement' was reached on 10th March, 2014 between 'NSL Nagapatnam Power and Infratech Limited' (Corporate Debtor) and the Appellant - 'PTC India Financial Services Limited' pursuant to which a sum -79- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
of Rs. 125 Crores was disbursed to the 'Corporate Debtor' on the terms and conditions as set out in the agreement, for setting up a 1320 MW coal based thermal power project (super-critical) at Tentulei Village, Talcher Taluk, District Angul, Odisha.
4. The aforesaid 'debt' was secured by a 'Deed of Pledge' of shares dated 10th March, 2014 owned by 'Mandava Holdings Private Limited ('MHPL' for short) in 'NSL Energy Ventures Private Limited' ('NEVPL', for short).
13. The 'Interim Resolution Professional' (1st Respondent) issued email on 19th February, 2018 to the Appellant rejecting the financial claim of the Appellant on the purported ground that the claim had been satisfied as on the insolvency commencement date by invocation of pledge.
28. In view of the aforesaid position, as we held that the Appellant became the shareholder in terms of Clause 6 of the 'Pledge Deed' dated 10th March, 2014, the Appellant cannot take the advantage of Section 176 of the Contract Act. Section 176 of the Contract Act also cannot be taken into consideration for the purpose of collating the claim of any claimant (creditor) by the 'Resolution Professional' under Section 18 of the I&B Code."
(Emphasis Supplied)
➢ Thus, this Appellate Tribunal held that by invocation of pledged shares,
the Lenders became Shareholder and could not press for their claims
under Code.
-80-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
➢ At this stage, we would like to refer to the Hon'ble Supreme Court of
India judgment dismissing this Appellate Tribunal's above quoted
judgment in the case of PTC India Financial Services Limited vs.
Venkateswarlu Kari and Anr. in Civil Appeal No. 5443 of 2019.
➢ We are conscious of facts that issue before the Hon'ble Supreme Court of
India was on few legal issues i.e., is whether the Depositories Act, 1996
read with the Regulation 58 of the Securities and Exchange Board of
India (Depositories and Participants) Regulations, 1996 has the legal
effect of overriding the provisions relating to the contracts of pledge
under the Indian Contract Act, 1872 and the common law as applicable in
India.
➢ We note that the aspect of invocation of pledged shares resulting Lenders
to became management shareholder v/s his right to file Section 7
application came up again to this Appellate Tribunal and it was decided
comprehensively, hence we will take benefit of this Appellate Tribunal
judgment. This Appellate Tribunal gave its judgment in the matter of
India Power Corporate Ltd. Vs. Meenakshi Energy Ltd. & Anr., passed
in Company Appeal (AT) (Ins.) No. 1220 of 2019 vide order dated
10.09.2020. The relevant paras of this judgment read as under :-
" 2.1 Brief facts of the case is that Meenakshi Energy Ltd. Respondent No. 1 (referred as Corporate Debtor) had availed term loan and working Capital facilities from time -81- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
to time from a consortium of lenders including State Bank of India, State Bank of Hyderabad, State Bank of Bikaner and Jaipur, State Bank of Mysore and State Bank of Travancore (SBI and the Associate Banks) Respondent No. 2 (referred as Financial Creditor) in two different phases to set up a 300 MW coal based power project (phase I) and 700 MW coal based thermal power project (phase II) respectively, in terms of Common Loan Agreement dated 10.07.2009 and 01.10.2010 respectively, at Thamminapatnam village, Nellore District (Andhra Pradesh).
2.4. The Corporate Debtor is unable to pay its debts. Therefore, Financial Creditor filed an Application under Section 7 of I&B Code, for initiating CIRP. The Application was filed by the SBI on behalf of the SBI and the Associate Banks as the Associate Banks have merged into SBI with effect from 01.04.2017.
3. The Corporate Debtor resisted the Application on various grounds. The amount claimed by the Financial Creditor was secured by pledge of valuable security in the form of shares of the Corporate Debtor. The Financial Creditor has suppressed material fact that the shares of the Corporate Debtor have already been invoked and transferred by the Financial Creditor to the Demat Account of SBI CAP Trustee. Thus, the Financial Creditor became owner of 95.2% shares of the Corporate Debtor and the entire debt of the Corporate Debtor stood discharged. The Financial Creditor being a majority Shareholder of the Corporate Debtor, cannot maintain this Application as a Financial -82- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Creditor. The Financial Creditor has also mis-led the Ld. Adjudicating Authority by failing to disclose the pending legal proceedings before various forums. The Financial Creditor has filed this Application as a counter blast to the proceedings initiated by the Corporate Debtor and IPCL against the Financial Creditor in various forums. The Application is barred by Limitation. There does not exist any debt as on date, thus, there is no question of default in respect of the Financial Creditor....
5. Learned Senior Counsel for the Appellants submitted that the debt owed by Corporate Debtor was secured by pledge of shares of the Corporate Debtor held by the IPCL. The Financial Creditor after invocation of pledge and subsequent transfer of shares in the name of SBI CAP Trustee Company Ltd, now holds 95.2% of shares in the Corporate Debtor. The Financial Creditor admitted in form No. 1 the value of the pledged shares is Rs. 5,475 Crores and thus, the entire debt of the Financial Creditor stood discharged and there is no default. This Appellate Tribunal in the case of PTC India Financial Services Ltd. (in short PFS) Vs. Mr. Venkateshwaralu Kari and Mandava Holdings Pvt. Ltd. Company Appeal (AT) (Ins) No. 450 of 2018 held that once shares are transferred to the Financial Creditor, the Financial Creditor becomes the owner of the shares and in such a situation there is no debt due to the Financial Creditor as the dues stand satisfied by way of shares. Ld. Adjudicating Authority erroneously held that the Judgment of this Appellate Tribunal in PFS (Supra) has been stayed -83- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
by the Hon'ble Supreme Court, in fact further proceedings are stayed. Thus, as per the Judgment in PFS the entire debt of the Financial Creditor stood discharged
8. It is also submitted on behalf of the Appellants that after invocation of pledge and transfer of shares. The Financial Creditor in collusion and connivance with all the erstwhile lenders have been siphoning of the funds from the Corporate Debtor. Therefore, the Appellant (IPCL) had filed an Application under Section 241 & 242 of the Companies Act, against the Financial Creditor. However, Learned Adjudicating Authority has erroneously admitted the Application under Section 7 of I&B Code. Hence, the order deserves to be set aside.
9. On the other hand, Learned Counsel for the Financial Creditor (Respondent No. 2) submitted that the Appellants have wrongly contended that the invocation of pledge amounted to transfer of shares or discharge of debt. The Pawnee's rights are governed by the Section 176 of Indian Contract Act, 1872, when Pawnor makes default the Pawnee does not have a right to appropriate and transfer ownership to itself of the pledged goods. The Pawnee's remedies are limited to sue for debt and retain the pledged goods or sell the pledged goods on giving the Pawnor reasonable notice of the sale and appropriate the proceeds.
For this preposition, place reliance on the Judgment of Hon'ble Supreme Court in the case of Balkrishna Gupta Vs. Swadesi Polytex Ltd. (1985) 2 SCC 167. Wherein Hon'ble Supreme Court has held that even after the pledge is -84- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
enforced, the legal title in the shares pledged would not vest in the pledgee and the pledgee has only a special interest/property to retain the shares as a collateral or sell them in accordance with Section 176 of the Indian Contract Act. Hon'ble Bombay High Court in the case of United Breweries (Holdings) Ltd. & Ors. Vs. State Bank of India & Ors. (order dated 02.04.2013) in notice of Motion (L) No. 718 of 2013 in Suit (L) NO. 263 of 2013 held that invocation of pledge and transfer of pledged securities to the pledgee's Demat Account did not violate the Section 176 of the Indian Contract Act and did not result in the pledgor being divested of their rights to the pledged shares. The same view has been taken by this Appellate Tribunal in MAIF investments India Pvt. Ltd. Vs. M/s Ind. Bharath Energy (Utkal) Ltd., (Company Appeal (AT) (Ins) No. 597 of 2018). Thus, the invocation of pledge in itself does not amount to transfer of shares or discharge of debt. This Appellate Tribunal in the case of PFS held that invocation of pledged of shares amounts to discharge of debt. However, Hon'ble Supreme Court has stayed the proceedings. Therefore, this Judgment does not help the Appellants.
14. After hearing Learned Counsel for the parties, we have perused the record.
15. The following two issues are crop up in these Appeals.
(a) Whether the Application under Section 7 of I&B Code, filed pursuant to the RBI Circular dated 12.02.2018? -85-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
(b) Whether the liability of the Corporate Debtor stood discharged in view of the invocation of the pledged shares by the Financial Creditor.
Issue No. 2
18. According to the Appellants after invocation of the pledged shares the Financial Creditor became 95.2% shareholder of the Corporate Debtor and the entire dues of Corporate Debtor stood discharged. In support of this submissions Learned Counsel for the Appellants cited two Judgments one of this Appellate Tribunal in the case of PTC India Financial Services Ltd. (Supra) in which it is held that once shares are transferred to the Financial Creditor, the Financial Creditor became the owner of the shares. The another Judgment of Hon'ble High Court of Delhi in the case of Tendril Financial Services Pvt. Ltd. (Supra) in this Judgment it is held that as per the Regulation 58 of Security Exchange Board of India (Depositors and Participants) Regulations, 1996, the moment the shares are transferred to the Demat Account of the beneficiary after invocation of pledge shares, such transfer amounts to sale and transferee became the beneficial owner of the shares.
19. Learned Counsel for the Respondent No. 2 (Financial Creditor) submits that Regulation 58(8) of the Debentures Regulations is subject to the terms of Share Pledge Agreement and the pledge is governed by the Indian Contract Act.
20 In the present case the whole controversy arises when SBI CAP Trustee Company Ltd. issued a notice of -86- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
invocation of pledge shares dated 20.12.2017. (Annexure 8 Page 240 of Reply of Respondent No. 2 (Financial Creditor)). In such a situation we are considering the effect of invocation of pledge shares.
26. In the light of the Judgement of Hon'ble High Court of Delhi in Tendril Financial Services Pvt. Ltd. (Supra). We are convinced with the arguments of Learned Counsel for the Appellants that the moment the shares transferred to the Demat Account of the SBI CAP Trustee Company Ltd. it became the beneficial owner of the shares as also held by this Appellate Tribunal in the case of PTC India Financial Services Ltd (Supra). Learned Counsel for the Appellants tried to impress that pursuant to invocation of pledged shares the Financial Creditor became the shareholder of the Corporate Debtor. We are unable to convince with this argument and held that after invocation of pledged shares the SBI CAP Trustee Company Ltd. became the shareholder of the Corporate Debtor, as per the Clause 2.6.2 of the Share Pledge Agreement dated 23.09.2016. The Financial Creditor is not party in the above referred agreement. In the notice dated 20.12.2017 it is mentioned that invocation of pledged shares shall not prejudice the rights and remedies available to the Financial Creditor under the Financing Documents. Therefore, it cannot be said that after invocation of the pledged shares by the SBI CAP Trustee Company Ltd., the Financial Creditor cannot maintain the Application under Section 7 of I&B Code, or the entire dues of the Corporate Debtor stood discharged.
-87-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
27. It is argued on behalf of the Appellant that after invocation of pledge and subsequent transfer of shares the Financial Creditor held 95.2% shares of the Corporate Debtor. Thus, the entire debt of the Financial Creditor stood discharged. If this is the position, then why the Corporate Debtor after receiving the notice of invocation of pledged shares dated 20.12.2017 sent an acknowledgement of debt on 16.02.2017 (See Annexure 20 of Page 313 Reply of Financial Creditor Vol. II) and after transfer of shares sent letters dated 25.05.2018 and 11.06.2018 for settlement. It shows that even after transfer of shares in the Demat Account of SBI CAP Trustee Company Ltd., there exist a debt of more than Rs. 1 lakh and there is a default on the part of the Corporate Debtor.
29. Thus, we are unable to convince with the arguments of Learned Counsel for the Appellants that after invocation of the pledged shares by the SBI CAP Trustee Company Ltd. liability of the Corporate Debtor stood discharged.
30. It is true that after invocation of the pledge, Shares were transferred in dematerialised form in the DP Account of SBI CAP Trustee Company Ltd. and it became the beneficial owner of the shares it does not mean that the Financial Creditor became the beneficial owner of the shares and it losses the status of Financial Creditor.
31. With the aforesaid, we hold that the Financial Creditor has not filed the Application under Section 7 of I&B Code, in pursuant to the RBI Circular dated 12.02.2018 and even after invocation of the pledged shares by SBI CAP Trustee -88- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Company Ltd., the financial Creditor can maintain the Application. Learned Adjudicating Authority has rightly admitted the Application under Section 7 of I&B Code. It is undisputed fact that the Corporate Debtor has committed default in repayment of debt and the amount of debt is more than 1 Lakh. Thus, we found no ground to interfere in these Appeals.
Thus, the Appeals are hereby dismissed. No order as to costs.
(Emphasis Supplied) ➢ We note that the present appeal before us is squarely covered in the
judgment of this Appellate Tribunal in the case of India Power (Supra)
and the same has not been challenged before the Hon'ble Supreme Court
of India, thus attained finality. We are duty bound to follow the same. ➢ We note that in the case of India Power (Supra), this Appellate Tribunal
has categorically held that the Lenders (like Respondent No. 2 herein)
have independent right to file Section 7 application, despite becoming
shareholder due to events like invocation of pledged shares.
➢ Thus, it becomes clear that Lender have independent rights under the
Code despite invocation of pledged shares which can make them
shareholder of the Corporate Debtor.
➢ In view of above detailed discussions, we find that the Lenders despite
might be in alleged control of Respondent No. 1 for intervening period
have independent rights to file Section 7 application under the Code and -89- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
as such there was no need or reason or occasion for the Respondent No. 2
to initiate application under Section 10 of the Code.
➢ Thus, we hold that based on above discussion including discussed
judgements above, that although the Respondent No. 2 might has become
the shareholder of Respondent No. 1 for intervening period due to partial
conversion of debt into equity and due to invocation of pledged shares,
(which were returned back to the Appellant based on judgement of
judicial fora as already discussed earlier), the Respondent No. 2 does not
lose his right to initiate Section 7 application.
➢ Similarly, we hold that invocation of pledge share and partial conversion
of debt into equity by Respondent No. 2 has no adverse impact in the
present appeal.
121. Issue No. (III) Whether, the additional loan agreement dated
27.04.2017 was fabricated or forced upon the Respondent No. 1 to initiate
Section 7 application by the Respondent No. 2 and whether the Recall
Notice dated 17.01.2018 was legal or not.
➢ It is the case of the Appellant that the additional loan agreement dated
27.04.2017 was fabricated and created by the Respondent No. 2 only with
dubious intentions of initiating Section 7 application against the
Respondent No. 1 and similarly additional loan agreement dated
27.04.2017 was also illegal and therefore, the present Section 7 -90- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
application of the Code could not have been initiated at all by the
Respondent No. 2. In this connection, we note that the additional loan
agreement was signed on 27.04.2017 between the Respondent No. 1 &
Respondent No. 2 and few important part of the agreement reads as
under:-
-91-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022 -92- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022 -93- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022 -94- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022 -95- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
➢ Similarly, we take note of loan recall notice dated 17.01.2018 and we
would like to take note of some of important point of the same which
reads as under :-
-96- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022 -97- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022 -98- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022 -99- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
➢ We note that Member (Technical) of Ahmedabad Bench has held that
Recall Notice dated 17.01.2018 was not valid as Respondent No. 2 was in
management control of the Respondent No. 1.
➢ We would like to take into all relevant para of Member (Technical)
judgement which reads as under :-
"22. ... Now, coming to the validity of recall notice dated 17.01.2018 given by the lender when they were in the management and control of the Corporate Debtor. It is noted that Rs.600 crores additional loan was sanctioned in April, 2017. However, only Rs. 384 crores were disbursed till 05.01.2018 and no further amount is disbursed thereafter....
23. Another important aspect which, at the very outset, may make the notice of recall dated 17.01.2018 premature as far as it concerns to the repayment of existing debts including the additional loan amount disbursed under loan agreement dated 27.04.2017. As per Clause 5.1.1.(B)(a) r.w. Schedule-
V, Schedule- X-A, Schedule-X-B (refer pages 709, 710, 741 and 750 of Volume-III of application), the repayment starts from 15.07.2020 and 15.01.2020. Further, there is reschedulement of all existing outstanding debts of the applicant-financial creditor in addition to fresh loans given in 2017. ...
-100-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Hence, on date of issue of recall notice, such debts are not payable at all and, therefore, the application filed for the so-called default is premature. Further, as far as interest during construction period is concerned, it has also been observed that it was to be paid out of loan amount disbursed by the applicant-financial creditor only and which was in the hands of the applicant-financial creditor and, therefore, the loan recall notice to this extent is illegal, malafide and impossible to perform as there is no source of funds available with the corporate debtor to repay the same other than the loan being disbursed or to be disbursed by the applicant-financial creditor for this purpose.
(Emphasis Supplied)
➢ We would like to take into all relevant para of judgment passed by
Member (Judicial) vide order dated 27.09.2022 in NCLT, Kolkata Bench
which reads as under :-
"Analysis and Findings:
II. Whether, notice dated 17.01.2018 recalling the loan is bad in law?
70. While adverting to answer the question/issue no. (II) as referred above, it is relevant to refer to the three reply affidavits filed by the Corporate Debtor:...
74. A clear picture that emerges from the above position on record is concluded as under.
-101- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
i. First reply by the Corporate Debtor dated 13.04.2018 was filed on 16.04.2018.
ii. Second reply affidavit was filed on 15.04.2019.
iii. Third reply affidavit by the Corporate Debtor was filed on 28.02.2020.
iv. The time gap between each of these reply affidavits is around between 8 to 12 months. Therefore, it was after a huge gap of 22 months from the date of filing the first affidavit, Corporate Debtor has come up with a completely new plea in the third reply that the first and second reply affidavits were filed in collusion and without any decision by the Board of Directors. It is stated in third reply affidavit that the Company Secretary who filed the 1st affidavit was acting at the behest of the applicant and the 2nd affidavit was filed by the managing director and the CEO and not the director as contended by the Corporate Debtor in 3rd affidavit. This is clear from minutes of 156 meeting placed on record along with the 2nd affidavit which has been reproduced above.
v. Corporate Debtor in its 3rd reply affidavit has wrongly described Mr. P.C Pankaj as the Director who was not only the managing director but also the CEO of the Corporate Debtor.
vi. On 27 September, 2018 the Corporate Debtor was merely asked to file a better affidavit by the Adjudicating Authority and in compliance of the said direction, the 2nd -102- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
affidavit was filed on 11th of April, 2019 on behalf of the Corporate Debtor, extract of contents has been reproduced above.
78. Besides the clear admission by Corporate Debtor of its debt and dues and also its inability to repay, as referred in preceding paragraphs/ record and documents furnished before this AA:
a. Plea raised by Financial Creditor vis-a-vis Additional loan agreement dated 27.04.2017 that;
i. In order to meet the immediate fund requirements as part of revival measure of the Project, the Financial Creditor in principle agreed to the increase in the Project cost from Rs. 2760,00,00,000/- to Rs. 8121,00,00,000/- and requirement of additional debt of Rs. 3022,00,00,000/- ('Additional Debt") for the Project. Subsequently, at the request of the Corporate Debtor, a Loan Agreement dated 27.04.2017 was executed between the Financial Creditor and the Corporate Debtor ('Additional Loan Agreement') for an additional term loan of Rs. 600 crores in order to meet the immediate fund requirements as a part of revival measure of the Project.
ii. Pursuant to the said Additional Loan Agreement, the Financial Creditor had disbursed an amount of Rs. 384,59,00,000. The said Additional Loan Agreement was entered into by the Financial Creditor in the capacity of Lender's Agent, Security Agent and Lender.
-103- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
iii. The aforesaid loan was supported by the Promoter Sh. Mukul Kasliwal in the board meeting dated 02.03.2017, as recorded in the minutes of meeting as under, wherein it is recorded that "Shri Mukul Kasliwal specifically requested the Board to record that, the sanctioning of additional loan to complete the project is a welcome step apart from all the issues and concerns going on between the Lenders and Promoters and Lenders will receive support from the promoters as well in view to complete the project.
iv. Entegra is thus estopped from questioning the said Loan Agreement and any argument to the contrary is hit by doctrine of approbate and reprobate.
v. Schedule II of the Additional Loan Agreement dated 27.04.2017 acknowledges the already existing debt of Rs.
1750.93 crore including the aforesaid amount due to the Financial Creditor (Pg. No. 736/758). Further, the Recitals to the Loan Agreement (Pg. Nos. 685/707) also acknowledge the previous liabilities of the Corporate Debtor; when seen and examined on the basis of record referred therein is found to be correct.
79. Debt was also acknowledged in the Annual Report/Balance Sheet of the Corporate Debtor for the FY 2013-14 signed by Sh. Mukul Kasliwal (Promoter) as one of Directors of the Corporate Debtor on 17.11.2014. The Annual Report was filed with the RoC & is part of public record. The Annual Report is also filed by Entegra Ltd. as Annexure-QQ with CP No. 175/2017.
-104-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
80. Debt is again acknowledged in the Balance Sheet of the Corporate Debtor for FY 2016-17 signed on 28.08.2017.
81. The Corporate Debtor again acknowledged its liability/debt in the meeting of the Board of Directors of the Corporate Debtor held on 29.09.2015 duly attended by the Promoter Sh. Mukul Kasliwal.
82. Reliance has been placed on behalf of Corporate Debtor to the judgement in case of Vidarbha (supra.) but it is clear that the Corporate Debtor is not in a position to repay its debt and hence, the Corporate Debtor's reliance on Vidarbha (supra.) is totally misplaced.
83. Suffice it to say for the foregoing reasons, it is held in response to Point number (II), the Financial Creditor was well within its right to issue a recall notice dated 17.01.2018 demanding the Corporate Debtor to make payment of the total outstanding amount of Rs. 2139.20 crores including outstanding interest amounts payable as on 16.01.2018 within 15 (fifteen) days of the receipt of the said notice.
(Emphasis Supplied)
➢ From above, it is seen that the Member (Technical) of Ahmedabad Bench
has basically tried to analyse overall eco-system of the case and recorded
in his rational requiring of another chance was to be given to the
Respondent No. 1 and also holding that the Respondent No. 2 was in
control and management of the Respondent No. 1 and as such Recall -105- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Notice was malicious and fabricated with only intent to take Respondent
No. 1 into insolvency.
➢ The Member (Technical) has not analysed as how recall notice dated
17.08.2018 was bad in law and how it was in violation of the Code or the
Regulations. On the other hand the Member (Judicial) of Kolkata vide
the Impugned Order dated 27.09.2022 has analysed in details the various
aspects of debt and default and has also gone into the various replies and
affidavits filed by the Respondent No. 1, various admission of debt, due
and inability to pay by the Respondent No. 1 recorded by the
Adjudicating Authority himself and finally the various acknowledgments
of debts in their Annual Report/ Balance Sheets which have also been
filed before ROC and are in public record especially for the year 2013-14
and 2016-17.
➢ The Member (Judicial) has also recorded Vidarbha Judgment is not
applicable in the present facts of the case.
➢ We note that the ingredients Section 7 of the Code does not prescribe any
formal demand notice to be issued by the financial creditors to the
Respondent No. 1 in contrast to Section 8, where it is mandatory on the
part of any operational creditor to issue demand notice to the Corporate
Debtor. However, the commercial practice and also for the principal of
natural justice, the financial creditors and the bankers issue loan recall -106- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
notice whereby they give all the details and also certain time line within
which the loan and interest along with other charges, if any, are recalled
by the bankers and the Corporate Debtor is called upon to repay. In the
present case, the Respondent No. 2 issued loan recall notice on
17.01.2018, which we have already noted earlier and highlighted the
significant portion.
➢ From this loan recall notice dated 17.01.2018, it becomes clear that the
Respondent No. 2 reminded Respondent No. 1 of his continuous failure to
service of financial facilities and based on which the account of the
Respondent No. 1 was declared as NPA as on 31.03.2012.
➢ This recall notice dated 17.01.2018 also mentioned about earlier recall
notice dated 05.01.2016 demanding payment of Rs. 1817 Crores as
outstanding amount as on 31.12.2015 along with additional payment of
Rs. 342.68 Crores towards ZCB.
➢ We also note that the recall notice has mentioned the event which
required Lenders to revoke pledged shares and convert partial subordinate
loan into equity and acquiring 51% stake in shareholding of Respondent
No. 1 by all Lenders collectively.
➢ The Recall notice dated 17.01.2018 categorically stipulated that the
project cost has seen abnormal increase to Rs. 8121 Crores and their
sanction of additional loan of Rs. 600 Crores and also mentioned facts -107- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
about their disbursement of 381.59 Crores till 02.01.2018 out of this
additional loan agreement of Rs. 600 Crores. We note that the Respondent
No. 2 specifically pointed out that despite partial disbursement of
Rs. 381.59 Crores, the Respondent No. 1 could not comply with
mandatory conditions precedent and failed to make quarterly interest on
additional loan from time to time being on 15.07.2017, failed further to
pay despite demand letter dated 06.07.2017, 01.10.2017, 05.01.2018
which has resulted in default in payment of interest and additional facility
as an event of default under Clause 17.1 (b) of additional loan agreement
and further defaulted under Clause 7.1 (c) by no repaying the credit
facilities granted under financing agreement. After summarising the
events, the Respondent No. 2 called upon Respondent No. 1 to make
payment of total outstanding of Rs. 2139.20 Crores within 15 days of
receipt of recall notice dated 17.01.2018 and on failure of which the
Respondent No. 2 would take necessary legal recourse.
➢ We do not find anything illegal or contrary to the law in issuing such
recall notice which is issued of details including of failures on the part of
Respondent No. 1 and contained details required proof of debt and default
along with various acknowledgements by the Promoters and the
Respondent No. 1.
➢ Thus, we hold that the Recall Notice dated 17.01.2018 was valid. -108-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
➢ We have already noticed the details of additional loan agreement dated
27.04.2017 along with the reason for lenders to agree to such additional
loan and we do not wish to repeat the same. We hold that the additional
loan agreement dated 27.04.2017 was a genuine intent of Respondent No.
2 to help the Respondent No. 1 to survive and sustain and by no way it
can be treated as fabricated or forced upon the Respondent No. 1. We
note that this additional loan agreement was supported by Promoters of
the Respondent No. 1 Mukul Kasliwal in the board meeting dated
02.03.2017, as recorded in the minutes of meeting that "Shri Mukul
Kasliwal specifically requested the Board to record that, the sanctioning
of additional loan to complete the project is a welcome step apart from all
the issues and concerns going on between the Lenders and Promoters and
Lenders will receive support from the promoters as well in view to
complete the project".
➢ Thus, this issue goes in favour of the Respondent No. 2.
122. Issue (IV) Whether, Section 241 and 242 Companies Act, 2013
application filed by the Appellant who got reliefs from NCLT/ NCLAT and
the Hon'ble Supreme Court of India has any bearing on present Section 7
application.
➢ As regard, Section 241 & 242 of the Companies Act, 2013 and the
decision of the NCLT, this Appellate Tribunal and the Hon'ble Supreme -109- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
Court of India, which we have discussed earlier, we find that this was
done w.r.t. invocation of pledged shares and partial conversion of debt
into equity which was done in particular facts and circumstances of the
case. We also find that this Appellate Tribunal while dismissing the
appeal of the Respondent No. 2, held that the process was invalid due to
non following the procedure as laid down in the Companies Act, 2013.
➢ At this juncture, we would like to take into account the fact that this
Appellate Tribunal has categorically recorded about lack of enthusiasm
on the part of Promoters to take the project forward and even the
amendment back to AoA would have been restored, there was no
possibility on the part of the promoters to complete the project. We note
that this Appellate Tribunal has given direction to GoI and GoMP to find
way forward and HLC was constituted giving three scenarios noted
earlier.
➢ We have already noted that Scenario I failed due to non infusion of
Rs. 600 Crores as equity by the Promoters and non infusion of Rs. 1100
Cr as additional funds by Promoters. The Scenario II of HLC, happened
in the present case envisaged that government undertaking shall take over
the majority equity holding in the Respondent No. 1 and accordingly the
Lenders of Respondent No. 1, including the Respondent No. 2 had to
invoke the pledged shares and also convert the partial subordinate loan -110- Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
into equity. These invocation were held not in accordance with law and
nowhere judicial fora held that the Respondent No. 2 do not have any
right to initiate Section 7 application under the Code. Incidentally, we
note that the GoMP has filed the affidavit before the Adjudicating
Authority that they do not find any hope for the project and only logical
course of action could be resolution of the Corporate Debtor i.e.
Respondent No. 1.
➢ In view of above, we do not find that Section 241 & 242 application
which came in favour of the Appellant has any adverse bearing under
Section 7 application filed by the Respondent No. 2 and consequently in
the present appeal.
123. In view of above detailed discussion, we find that the Adjudicating
Authority i.e., both Member (Judicial) of Ahmedabad and Kolkata Bench have
correctly passed the Impugned Order admitting Section 7 application of the
Respondent No. 2 and ordering initiation of the CIRP against the Respondent
No. 1. We are not satisfied with the rational contained in the judgment of
Member (Technical) of Ahmedabad Bench and do not agree to his finding in
rejecting Section 7 application of the Respondent No. 2. -111-
Comp. App. (AT) (Ins.) No. 1287 & 1291 of 2022
124. In fine the appeal devoid of any merit, fails and stands rejected. No cost.
IA, if any, are closed.
[Justice Rakesh Kumar Jain] Member (Judicial)
[Mr. Barun Mitra] Member (Technical)
[Mr. Naresh Salecha] Member (Technical) Sim
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free