Engin Nasiroglu & Anr vs Rvr Projects Pvt Ltd

National Company Law Appellate Tribunal19 December 2018

Ratio decidendi

The rule this decision rests on

Where a corporate debtor, by writing, consciously admits a subsisting liability to pay an operational creditor's claim and keeps the matter open by deferring reconciliation and refusing to finalise the reconciliation statement, there is a continuing cause of action, and the operational creditor's claim is not barred by limitation. A writing relied on as an acknowledgement of liability must admit a subsisting jural relationship and a conscious affirmation of an intention to continue that relationship in respect of an existing liability; the admission need not be as to a precise amount or in express words, but a mere admission of past liability, or a statement that the claim is under examination without admitting liability, does not suffice. A corporate debtor which issues job completion certificates recording the value of work executed by the operational creditor, and which responds to a demand by stating that the bills are under reconciliation and seeking joint signing of a reconciliation statement without disputing the claim, has acknowledged the debt; an operational creditor's demand notice under Section 8(1) that is not denied by the corporate debtor is then not defeated by limitation, and the debt is one payable in law for the purposes of Section 9.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

NATIONAL COMPANY LAW APPELLATE TRIBUNAL, NEW DELHICompany Appeal (AT) (Insolvency) No. 566 of 2018

[Arising out of Order dated 09th July, 2018 passed by the Adjudicating Authority (National Company Law Tribunal), New Delhi Bench-III in CP-IB-158/ND/2018]

IN THE MATTER OF:

1. MR. ENGIN NASIROGLU, Ex-Director & Nominee Shareholder Fernas Construction India Pvt. Ltd., Son of Necat Nasiroglu Space No. S19, Second Floor, Malhan Falcon, Plaza, Plot No.4, Pocket-7, Dwarka New Delhi - 110075. Also At: D-Bakir Mahallesi, Nasiroglu Is MerkeziSokak EV No. 103, Batman 72050, Turkey Through its Constituted Attorney - Mr. Mazlum Dogan

2. FERNAS INSAAT A S Holding Company Fernas Construction India Pvt. Ltd. India Project office at: Space No. S19, Second Floor, Malhan Falcon Plaza, Plot No. 4, Pocket-7, Dwarka, New Delhi- 110075. Also at: Elci Sokak No. 21 06550Y, Ayranci Ankara, Turkey, Through its Authorised Representative- Mr. Mazlum Dogan ...Appellants Vs RVR Projects Pvt. Ltd. # 9-16-29, CBM Compound, Vishakhapatnam - 530003. Also at: A-1/38, 3rd Floor, Safdurjung Enclave, New Delhi-110029. ....Respondent Present:

For Appellants: Mr. Arun Kathpalia, Sr. Advocate with Mr. N. Prashant Kumar Nair and Mr. Samaksh Goyal, Advocates For Respondent: Mr. Akshay Sharma, Advocate -2-

J U D G M E N T

SUDHANSU JYOTI MUKHOPADHAYA, J.

This appeal has been preferred by shareholder and Director of 'Fernas

Construction India Pvt. Ltd.' (Corporate Debtor) against order dated

09.07.2018 passed by the Adjudicating Authority (National Company Law

Tribunal) New Delhi Bench-III wherein application under Section 9 of the

Insolvency and Bankruptcy Code, 2016 (hereinafter referred to as 'I&B Code')

has been admitted.

2. Learned counsel appearing on behalf of the appellant submitted that

the amount due or payable as claimed by the operational creditor being

barred by limitation, there is no debt payable in law and therefore the

question of default does not arise.

3. According to appellant - 'Fernas Construction India Pvt. Ltd.'

(Corporate Debtor) had obtained and undertaken projects worth Rs. 2,400

Crore for companies like ONGC Petro Additions Ltd., Indian Oil Corporation

Ltd. extensively working in the Oil & Gas Sector and engaged in constructing

Cross Country Pipeline, Refineries, Petrochemicals, Roads and

Infrastructure etc.

Company Appeal (AT) (Insolvency) No. 566 of 2018 -3-

4. The Corporate Debtor had obtained high value projects from Indian

Oil Corporation Ltd. to the tune of Rs. 272 crore at Paradip, Orissa on

15.02.2011 and ONGC Petro Additions Limited to the tune of Rs. 1800 crore

at Dahej, Gujarat sometime thereafter within a gap of couple of months.

5. Fernas Turkey had appointed managerial persons from India to run

the operations in India. Undertaking the said project and managing all work

related to the said project the Appellant had been using data storage and

processing system for the entire work being carried out at the two project

sites. The Corporate Debtor had engaged around 250 to 350 sub-contractors

for the projects.

6. 'Fernas Construction India Pvt. Ltd.' approached the 'RVR Projects

Pvt. Ltd.' to avail its services of piling works for integrated utilities and off-

site package for a Petrochemical Complex situated at Dahej Gujarat and

entrusted to it the first work order for the contract amount of

Rs.10,25,10,275/- on 04.08.2011. The 'RVR Projects Pvt. Ltd.' started

executing the works and raised invoices.

7. It appears that 'Fernas Construction India Pvt. Ltd.' (Corporate

Debtor) released part payment of bills raised. On 09.05.2012 'Fernas

Construction India Pvt. Ltd.' (Corporate Debtor) foreclosed the works and by

that time a sum of Rs. 4,22,20,877/- for which bill was raised was paid.

Company Appeal (AT) (Insolvency) No. 566 of 2018 -4-

8. Case of 'RVR Projects Pvt. Ltd.' is that the 'Fernas Construction India

Pvt. Ltd.' issued another work order for an amount of Rs.2,05,02,500/- to

the 'RVR Projects Pvt. Ltd.' (Operational Creditor). The said order was also

foreclosed midway and by that time total amount of work done was

Rs.1,48,00,184/-. The case of 'RVR Projects Pvt. Ltd.' is that the 'Fernas

Construction India Pvt. Ltd.' admitted a debt of Rs.1,45,28,508/- for both

the above work orders on 17.06.2013 and made some past payment

amounting to Rs.42,35,000/- leaving a balance of Rs.1,02,93,508/-

remaining unpaid.

9. The demand notice under Section 8 (1) was issued by 'RVR Projects

Pvt. Ltd.' (Operational Creditor) to the 'Fernas Construction India Pvt. Ltd.'

(Corporate Debtor) on 01.12.2017, which were served on 04.12.2017 and

05.12.2017 by courier and speed post, respectively. Thereafter, having

received no reply, the application under Section 9 was filed by 'RVR Projects

Pvt. Ltd.', which has been admitted.

10. Learned Senior Counsel appearing on behalf of the appellant while

referring to application under Section 9 (Form-5) particularly Part IV & V

submitted that the Operational Creditor has accepted that the cause of

action had taken place in August 2013 when Corporate debtor defaulted to

pay. Therefore, it was submitted that the claim is barred by limitation in

Company Appeal (AT) (Insolvency) No. 566 of 2018 -5-

absence of any subsequent cause of action. Reliance has also been placed

on decision(s) of Hon'ble Supreme Court which we will discuss at

appropriate stage.

11. Learned Counsel appearing on behalf of the respondent - 'RVR

Projects Pvt. Ltd.' (Operational Creditor) referred to the communication

made between the parties and submitted that there is a continuous cause of

action and therefore the claim cannot be said to be barred by limitation.

12. According to him, pursuant to letter dated 17.06.2013 of 'RVR

Projects Pvt. Ltd.' (Operational Creditor), the 'Fernas Construction India Pvt.

Ltd.' (Corporate Debtor) confirming the balance as on 31.03.2013 and

balance credit paying according to books of accounts was shown to be

Rs.1,45,28,508/-. 'RVR Projects Pvt. Ltd.' asked to file under the Micro,

Small and Medium Enterprises Development Act, 2006 and request its

confirmation to Auditor of the Corporate Debtor within 10 days considered

the balance as confirmed.

13. 'Fernas Construction India Pvt. Ltd.' (Corporate Debtor) issued a

completion certificate on 07.08.2013 wherein actual value of work executed

was shown to be Rs.1,48,00,184.00. The certificate was so issued for the

purpose of billing by 'RVR Projects Pvt. Ltd.' for forthcoming opportunities.

Company Appeal (AT) (Insolvency) No. 566 of 2018 -6-

Another (2nd) job completion certificate was issued on 07.08.2013 wherein

actual value of work executed was shown as Rs.4,21,83,810.00.

14. Operational Creditor by registered post on 31.12.2013 intimated the

Corporate Debtor about the work done and amount payable showing total

amount payable to the operational creditor. It was followed by letter dated

03.02.2013.

15. 'Fernas Construction India Pvt. Ltd.' by letter dated 13.12.2013 while

intimated Operational Creditor that it was well within the rights of Corporate

Debtor to allocate work to the Operational Creditor - 'RVR Projects Pvt. Ltd.'

it said that the same shall be commensurate with their capabilities. It was

specifically mentioned that 'Fernas Construction India Pvt. Ltd.' (Corporate

Debtor) is in process of reconciliation of all bills along with supporting

documents and as soon as reconciliation is complete, the true and correct

status of outstanding balance will be communicated to RVR Projects Pvt.

Ltd. (Operational Creditor) and recommended to the Management. RVR

Projects Pvt. Ltd. was requested to depute the concerned personnel from

their accounts department for reconciliation purpose and jointly signing

reconciliation statement, as proved from the copy of the letter dated

13.12.2013, as under.

Company Appeal (AT) (Insolvency) No. 566 of 2018 -7-

Company Appeal (AT) (Insolvency) No. 566 of 2018 -8-

16. Thus we find that the Corporate Debtor has taken time for

reconciliation and signing the reconciliation statement but not having

completed it the demand notice was issued by the Operational Creditor

under section 8(1), which was not denied by the Corporate debtor.

17. In 'Valliamma Champaka Pillai V/s Sivathanu Pillai and Others

(1979) 4 SCC', the Hon'ble Supreme Court held that under section 18 of

Limitation Act, one of the essential requirements for a valid

'acknowledgement' under Section 18, is that the writing concerned must

contain an admission of a subsisting liability. A mere admission of past

liability is not sufficient to constitute such an 'acknowledgement'.

18. In 'J.C. Budhraja V/s Chairman, Orissa Mining Corporation Ltd.

and Anr., 2008 2 SCC', the Hon'ble Supreme Court observed:-

"It is now well settled that a writing to be an

acknowledgement of liability must involve an

admission of a subsisting jural relationship between

the parties and a conscious affirmation of an

intention of continuing such relationship in regard to

an existing liability. The admission need not be in

regard to any precise amount nor by expressed

words. If a defendant writes to the plaintiff

requesting him to send his claim for verification and

Company Appeal (AT) (Insolvency) No. 566 of 2018 -9-

payment, it amounts to an acknowledgment. But if

the defendant merely says, without admitting

liability, it would like to examine the claim or the

accounts, it may not amount to acknowledgement. In

other words, a writing, to be treated as an

acknowledgement of liability should consciously

admit his liability to pay or admit his intention to pay

the debt."

19. In the present case we find that the 'Fernas Construction India Pvt.

Ltd.' (Corporate Debtor) in its job completion certificate has shown the

actual value of work executed by the Operational Creditor. In reply to the

demand the Corporate debtor intimated the Operational creditor that all the

bills along with supporting documents are in process. It has not disputed

the claim. On the other hand by letter dated 13.12.2013 accepted that as

soon as reconciliation process will be completed the same will be

communicated to the 'RVR Projects Pvt. Ltd.' (Operational Creditor) and

management will be recommended. Corporate Debtor also requested the

Operational creditor to depute personnel for reconcile purpose and to sign

jointly reconcile statement.

20. Till date the 'Fernas Construction India Pvt. Ltd.' (Corporate debtor)

has not completed reconciliation of all the bills and not signed reconcile

Company Appeal (AT) (Insolvency) No. 566 of 2018 -10-

statement and kept matter pending. The matter having kept open by the

Corporate Debtor we hold that there is a continuous cause of action in

absence of completion of reconcile statement jointly signed by the parties.

Substantial liability having been already accepted by the Corporate Debtor

in writing and intention of continuing with relationship in the record, we

hold that the Corporate Debtor has treated and acknowledged the liability

consciously and admitted liability to pay on reconciliation.

21. In view of aforesaid position of law and the facts we hold that the

claim of the Operational Creditor is not barred by limitation, there being

continuous cause of action and the Corporate Debtor cannot take plea that

there is no debt payable to Operational Creditor in law. We find no merit in

this appeal. It is dismissed. No cost.

[Justice S.J. Mukhopadhaya] Chairperson

[Justice Bansi Lal Bhat] Member (Judicial)

NEW DELHI 19th December, 2018

SA

Company Appeal (AT) (Insolvency) No. 566 of 2018

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.