The appeal is dismissed on a ground of procedure: an appeal under Section 61 of the Insolvency and Bankruptcy Code, 2016 filed beyond the thirty-day limitation period cannot be entertained unless sufficient cause for the delay is shown, and the court closing for vacation or a registry being closed does not by itself supply such cause. On the merits, the rejection of an application under Section 9 of the Code is upheld where the adjudicating authority has found, on the material before it, that a dispute existed between the parties before the issuance of the demand notice under Section 8(1), such that the operational creditor's claim is not an undisputed debt and the application cannot succeed.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

NATIONAL COMPANY LAW APPELLATE TRIBUNALNEW DELHII.A. No. 29 of 2018ANDCompany Appeal (AT) (Insolvency) No. 14 of 2018IN THE MATTER OF:

Elecon Engineering Co. Ltd. ...Appellant

Versus

Ducon Technologies (I) Pvt. Ltd. ...Respondent

Present:

For Appellant : Shri Priyam Shah, Advocate

For Respondent : Shri Rakesh Sinha and Shri Arjun Harkauli, Aadvocates

ORDER

12.01.2018 The appeal under Section 61 of the Insolvency and

Bankruptcy Code, 2016 (hereinafter referred to as the 'I & B Code') has been

preferred by the appellant (Operational Creditor) against the order dated 2nd

November, 2017 passed by the Adjudicating Authority (National Company Law

Tribunal), Mumbai Bench in C.P. No. 1317/I&BP/NCLT/MAH/2017 whereby

and whereunder the application preferred by the appellant under Section 9 of

the I & B Code has been rejected.

2. An application for condonation of delay has also been filed and stated that

there is a delay of 15 days delay in preferring this appeal. Learned counsel

appearing on behalf of the respondent submitted that the delay is more than 15 2

days, which cannot be condoned and appropriate ground has not been shown to

condone the delay.

3. We have heard the learned counsel for the appellant and the respondent

both on the question of condonation of delay and on merit.

4. From the record we find that free certified copy of the impugned order

dated 2nd November, 2017 was supplied to the appellant on 15th November, 2017

who was required to file the appeal within 30 days i.e. by 15th December, 2017.

However, the appeal has been filed on 2nd January, 2018.

Learned counsel for the appellant submits that this Appellate Tribunal was

closed during Winter Vacation but we notice that the Court was closed from 23rd

December, 2017 but the Registry was open which closed from 28th December,

2017. However, even if we accept the submission made on behalf of the appellant

that re-opening of 2nd January, 2018 as the last date of filing the appeal, we find

no good and convincing ground has been shown to condone the delay.

5. Apart from the aforesaid fact, we find that there is an 'existence of dispute'

pending even before the issuance of demand notice under sub-section (1) of

Section 8 of the I & B Code, as noticed by the Adjudicating Authority and quoted

below:

"In another email dated 8.7.2015 come from the corporate debtor to the petitioner discloses that a statement of accounts has been furnished to the petitioner incorporating the actual cost incurred by the debtor due to the delay in replacing the pipe conveyor belts at Mahan site and inviting commercial person from the petitioner

Company Appeal (AT) (Insolvency) No. 14 of 2018 3

side to understand the details of debit notes and the cost incurred by the corporate debtor. To which the answer from the petitioner in email dated 7.7.2015 is that the petitioner also incurred losses, meaning thereby the corporate debtor already incurred losses. In a letter dated July 3, 2015, written by the debtor to Aditya reflects that the debtor forwarded statement of Account along with a final payment to be made to the petitioner was Rs. 18,18,369 subject to confirmation of receipt of PBG (Performance Bank Guarantee)."

6. In view of 'existence of dispute', we are not inclined to interfere with the

impugned order. In absence of any merit also, the appeal is dismissed. No cost.

[Justice S.J. Mukhopadhaya] Chairperson

[ Justice Bansi Lal Bhat ] Member (Judicial)

/ns/uk

Company Appeal (AT) (Insolvency) No. 14 of 2018

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free