Dezire Group Through Harmanjeet Singh ... vs Indamer Mjets Airport Services ...
- CitationCompany Appeal (AT) (Ins) No. 578 of 2024
Ratio decidendi
The rule this decision rests on
The Operational Creditor's Section 9 application fails where the final bill is not unconditionally accepted by the Corporate Debtor, so that the existence of the debt and the time for its payment are in doubt. Where the Corporate Debtor's endorsements on the bill qualify its acceptance of liability, that question requires further evidence and cannot be decided in summary proceedings under Section 9 of the Insolvency and Bankruptcy Code. A claim under Section 9 must establish a debt of at least the threshold amount. Where the amount claimed in the final bill is inconsistent with the amount stated in the demand notice, and the increase is not adequately explained, the Operational Creditor fails to establish that the debt due exceeds the threshold, and the threshold cannot be met by adding a separate bill that is not itself shown to be due. Where the Corporate Debtor has raised a counter-claim for liquidated damages or penalty under the contract (for delay in completion), which is a claim arising from the same contract and not disputed as to its existence, a pre-existing dispute exists that the Operational Creditor's Section 9 application cannot overcome in summary proceedings, and the Section 9 petition is liable to be dismissed.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
Dezire Group ...Appellant Through Mr. Harmanjeet Singh Bedi, Partner
Vs
M/s Indamer Mjets Airport Service Pvt. Ltd. ...Respondent
(Arising out of Impugned Order dated 20.11.2023 passed by the Adjudicating Authority (National Company Law Tribunal, Mumbai Bench, Court - III) in C.P.(IB)-1033(MB)/C-III/2022)
For Appellant: Mr. Palash S. Singhai and Mr. Harshal Sareen, Advocates
For Respondent: Mr. Hemant Phalpher and Mr. Kunal Sinha, Advocates
JUDGEMENT
Per Justice N. Seshasayee, Member (Judicial)
An Operational creditor, whose application for initiating a CIRP under Sec 9
of IBC was dismissed by the Adjudicating Authority on the ground of existence
of a pre-existing dispute between the parties, has preferred this appeal. 2
The Facts
2. The material facts that provide a backdrop to this case are as below:
a) The appellant is a partnership firm and is involved in the business of
construction. While so, on 01.03.2021 it entered into a Construction
Contract with the respondent for the execution of certain civil work and
allied interior work associated with the lounge near Terminal 3 of Delhi
International Airport. Alongside this contract, both the parties entered
into what is known as 'Workshop Contract' (the copy of this second
mentioned contract is not made part of the record, and the debt involved
in this case does not relate to this contract but to the Construction
Contract).
b) The Construction Contract stipulated three months' time for completing
the work. Clause 15 of the said contract provides that the contractor
could submit the running bill fortnightly upon receiving which the
respondent would release payment within 5 days there from. And, the
contractor is required to submit its final bill within 30 days from the
date of completion the contracted work duly certified by the respondent,
and the payment there under would be finalised within 30 days from
the date of the bill.
c) Be that as it may, the appellant had raised four Running Account bills
(referred to as Running Bills in the Clause 5 of the Contract), the details 3
whereof are as below:
Sl.No Date Amount (in Rs.) 1. 10.03.2021 66,17,293
2. 10.06.2021 36,25,358
3. 08.12.2021 1,11,04,433
4. 15.02.2022 86,64,411
d) Besides the above bills, the appellant claims another Rs.17.0 lakhs
towards glass and aluminium vide Annexure 5, which was said to have
been raised sometime in February, 2022.
e) While the contract work was in focus, on 21.03.2022 the respondent
abruptly terminated the contract. And on 11.04.2022, the appellant
raised its final bill. In all, the total value of the work which the appellant
had done is Rs.4,66,89,639/-, out of which the respondent had paid
Rs.3,09,70,026/- leaving a balance of Rs.1,57,19,613.00 to be paid.
f) According to the appellant, despite due verification of all these bills, the
respondent showed no intention to honour its liability under the bills.
It is in these circumstances, on 03.07.2022, the appellant had issued a
demand notice as required under Sec. 8 IBC, but despite receiving it,
the respondent showed no interest to pay the same.
The respondent has thus committed default in paying the debt, which in turn
had given the appellant a cause for filing its petition under Sec.9 of IBC for
commencing a insolvency resolution process against the respondent. 4
3. In its Reply, the respondent contended:
a) That the construction contract which the appellant had entered into
with the respondent commenced on 01.03.2021, and it stipulated that
the entire work must be completed in three months. However, the
appellant did not complete the work within the time stipulated, and
since the contract-period had fallen within the pandemic days due to
Covid - 19, time was periodically extended and finally up to 31.01.2022.
The work still was not complete. Hence the respondent was constrained
to terminate the Construction Contract.
b) In terms of the contract dated 01.03.2021, if the appellant delayed in
completing the work, it is liable to pay a penalty of Rs.25,000/- a day.
c) This apart vide e-mails dated 02.12.2021, 24.12.2021 and 09.01.2022,
complaints were raised on the aspect of delay, on the invoice, and also
on the quality of work done. In effect, the respondents have raised
certain dispute even prior to the commencement of CIRP.
d) IBC is not a recovery mechanism, and if at all the appellant feels
aggrieved, it should resort to arbitration in terms of the contract.
4. After considering the rival submissions, the Adjudicating Authority had
concluded vide its Order dated 20.11.2023 that the appellant's Petition under
Section 9 of IBC is liable to be dismissed since there exists a pre-existing
dispute between parties which included delay in performance of the
contractual obligation by the appellant. This Order is now under challenge. 5
Arguments
5. The learned counsel for the appellant submitted: that on 11.04.2022
(however, in the notes of arguments provided by the appellant it is mentioned
as 14.04.2022) the appellant raised the final bill and it was verified by the
respondent. When once the final bill amount was verified by the respondent,
the latter's obligation to pay the amount so verified commences. Admittedly,
this amount has not been paid, and it completes the debt-default equation
necessary to invoke Sec.9 IBC. Reliance was placed on the ratio of this
tribunal in R.R.Gopaljee Vs I.O.B. & Others [Comp. A (AT)(Ins) 748 of 2019].
The tribunal however, relied on an e-mail of the respondent dated 25.04.2022
for concluding that there existed a dispute which originated even prior to the
issuance of notice under Sec.8 IBC, but this e-mail relates to what is styled
as 'Workshop Contract', and does not relate to the contract vis-à-vis the final
bill whose non-payment has given rise to the cause of action for invoking Sec.9
IBC.
6. Per contra, the learned counsel for the respondent submitted that the main
plank of the respondent's defence was that the appellant had not completed
the contracted work despite multiple extension and it forced the respondent
to terminate the contract. Now for belated payment the respondent is entitled
to claim penalty @ Rs.25,000/- for every day of delay. Secondly, the purported
claim in the final bill is only for Rs.81,76,767/- and it does not meet the
threshold limit of Rs.1.0 crore to invoke the IBC. Thirdly, that the claim of the
appellant was not free of dispute is established by: (i) in the final bill, an
endorsement has been made on behalf of the respondent that it is not 6
accepted; (ii) that vide e-mail dated 26.11.2022, the appellant had listed its
difficulties in executing the work and in the respondent's mail dated
02.12.2021, the respondent had alleged the appellant of its negligence in
executing the work; (iii) in its e-mail dated 09.01.2022, the respondent had
raised quality-issue in the work executed by the appellant which relates to
leakage due to rain. Indeed, the respondent had expressed its displeasure
both regarding the pace of execution of the work and quality of the work done
vide e-mails dated 01.02.2022 and 14.02.2022, and eventually the
respondent was constrained to terminate the contract. In effect, the appellant
attempts to brand a solvent company as insolvent when the fault lies with it.
Reliance was placed on the ratio in Kay Bouvet Engineering Ltd., Vs
Overseas Infrastructure Alliance (India) (P) Ltd., [(2021)10 SCC 483].
Discussion & Decision
7. After carefully evaluating rival submissions we consider that this appeal is
liable to be dismissed, and the reasons are:
a) That the final bill dated 11.04.2022 is not seen approved for payment
by the respondent, nor its correctness acknowledged by it. On the
contrary, the respondent's representative has made two endorsements.
The first endorsement runs into two sentences and commences with the
phrase: 'Not accepting...'. The learned counsel for the appellant
contended that it related to releasing the security deposit, but on a plain
observation of the final bill it is not adequately evident that the phrase
'not accepting' must be read only in relation to the security deposit, even 7
though the endorsement also refers to security deposit. And there is a
second endorsement as well. Taking both these endorsements together,
it does not establish that the respondent had accepted the liability
under the final bill unconditionally and without any qualification. This
requires further evidence and it cannot be decided in a summary
proceeding.
b) In terms of the final bill (Annexure 6), the net amount payable was
mentioned as Rs.81,76,767/-. However, in the statutory demand notice
dated 03.07.2022, it is mentioned as Rs.1,02,87,004/-. To this was
added another Rs.17.0 lakhs as bill for glass and aluminium. It is not
adequately explained how Rs.81.76,767/- has enlarged to Rs.1.02 crore
and odd. Now, unless the justification for a claim of Rs.1.02 crore has
been established, even the inclusion of the bill for Rs.17.0 glass and
aluminium will not help in crossing the threshold limit of Rs.1.0 crore.
In effect, the appellant has not been able to establish the exact debt due
from the respondent, and at any rate that it is at least more than the
threshold limit of Rs.1.0 crore. When the entire case of the appellant is
spun around the final bill dated 11.04.2022, it is not adequately
explained how it hits the threshold limit for invoking the IBC.
c) There are two e-mails, of which one is from the respondent to the
appellant dated 09.01.2022 (Annexure D to the respondent's reply filed
before the tribunal below) in which it had pointedly raised an issue of
quality of the work done. The other e-mail is dated 31.05.2022 from
the appellant to the respondent wherein the representative of the 8
appellant writes: "My bills have been verified and submitted, barring a
few discrepancies, which have to be sorted out....". There is no reference
as to when exactly this discrepancy was and if it was sorted out. This
apart, Clause 15 of the Construction Contract stipulates that the
payment of the final bill would be done but after due certification of the
completion of the work. To sum up, the final bill is not unqualified. This
apart, the respondent himself has admitted to some discrepancies in
the bill. Given the setting, there is a doubt if the time for payment of the
alleged debt has arrived. In other words, both the debt and the default
in paying the same which are sine qua non for invoking Sec.9 are in
doubt.
d) That the work was not executed in time, that it was not completed
despite extension of time granted by the respondent, that the
respondent had terminated the contract etc., are not disputed, nor is
the contractual term enabling the respondent to claim Rs.25,000/-
from the appellant for every day's delay. Whether the respondent will
be entitled to claim damages at Rs.25,000/- per day might have to be
tested in a separate proceeding, but nothing prevents the respondent
from making the claim based on this term. And, the respondent had
raised this point in its defence, and if this is telescoped into the case of
the appellant, it leaves the appellant's claim shaky.
8. It is very apparent that the case of the appellant is not free of factors which
the IBC regime does not accommodate. Consequently, this tribunal does not
find any material to interfere with the Order of the Adjudicating Authority 9
dated 20.11.2021 in C.P. (IB) 1033 of 2022. This appeal is accordingly
dismissed.
(Justice N. Seshasayee) Member (Judicial)
(Barun Mitra) Member (Technical)
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free