Miss Lucy
← All judgments

Deepak Gupta vs Ved Contracts Pvt. Ltd. & Ors

National Company Law Appellate Tribunal19 November 2019

Ratio decidendi

The rule this decision rests on

The delay of five days in preferring the appeal is condoned on the appellant's showing of sufficient cause. Where the corporate debtor's accounts show a sum payable to it and there are claims and counter-claims between the parties, that dispute over claims and counter-claims cannot be determined by the Adjudicating Authority in proceedings on an application under Section 9 of the Insolvency and Bankruptcy Code, 2016. An application under Section 9 is to be admitted even where the operational debt is disputed or said to be payable, provided the amount is found to be more than Rs. 1,00,000 and there is no pre-existing dispute between the parties.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

NATIONAL COMPANY LAW APPELLATE TRIBUNAL, NEW DELHICompany Appeal (AT) (Insolvency) Nos. 1262 of 2019IN THE MATTER OF:

Deepak Gupta .... Appellant

Vs

Ved Contracts Pvt. Ltd. & Ors. .... Respondent

Present: For Appellant: Mr. Sandeep Bhurasia and Mr. Allam, Advocates.

ORDER

19.11.2019 Having heard learned counsel for the appellant and being satisfied with the grounds, the delay of five days in preferring the appeal is condoned. Interlocutory Application No.3652 of 2019 stands disposed of.

2. M/s. Ved Contracts Pvt. Ltd. ('Operational Creditor') filed an application under Section 9 of the Insolvency and Bankruptcy Code, 2016 (hereinafter referred to as the 'I&B Code') for initiation of 'Corporate Insolvency Resolution Process' against M/s RG Infra Build Pvt. Ltd. ('Corporate Debtor'). The Adjudicating Authority (National Company Law Tribunal), New Delhi Bench by impugned order dated 25th September, 2019 admitted the application.

3. Learned Counsel for the Appellant submits that in the accounts of three consecutive years, it is shown that the amount is payable to the 'Corporate Debtor' and there are claims and counter claims, which has not been adjudicated by the Adjudicating Authority. However, such ground cannot be accepted as the disputed question relating to claims and counter claims cannot be determined by Adjudicating Authority in an application under Section 9 of the I&B Code. In view of the judgment of the Hon'ble

Page 1 of 2 Supreme Court in "Innoventive Industries Ltd. Vs. ICICI Bank and Anr.

- (2018) 1 SCC 407", even if amount is disputed or payable and is found to be more than Rs.1,00,000/-, the application under Section 9 is to be admitted. In the present case, there is no pre-existing dispute pending before the parties. Therefore, the Appellant cannot take any advantage relating to disputed bills, the question of joint inspection of contract etc. does not arise. In absence of any merit, the Appeal is dismissed.

[Justice S. J. Mukhopadhaya] Chairperson

[Justice Bansi Lal Bhat] Member (Judicial)

[Justice Venugopal M.] Member (Judicial)

Ash/GC Company Appeal (AT) (Insolvency) Nos. 1262 of 2019 Page 2 of 2

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free