Once a resolution plan has been approved by the Adjudicating Authority under Section 31(1) of the Insolvency and Bankruptcy Code, 2016, the claims provided for in the plan stand frozen and bind the corporate debtor and all its stakeholders, and every claim not part of the approved plan stands extinguished, so that no proceedings may be initiated or continued in respect of it. Statutory dues owed to the Central Government, a State Government or a local authority, if not provided for in the approved resolution plan, are likewise extinguished, and no proceedings for such dues relating to the period before approval may be continued. A creditor who fails to file its claim when invited by the resolution professional under Sections 13 and 15 of the Code, and does not file even before the Committee of Creditors approves the plan, cannot obtain relief against an approved plan on the ground of its unfiled claim; the earlier decision relied upon on the filing of late claims is distinguished because there the claim had been asserted before the resolution professional and the attachment predated the insolvency process.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
NATIONAL COMPANY LAW APPELLATE TRIBUNAL, PRINCIPAL BENCH, NEW DELHI Company Appeal (AT) (Ins) No.891 of 2021
IN THE MATTER OF: Commissioner of Customs & Excise - Jaipur-I (Now known as "Principle Commissioner, Central Goods & Service Tax") NCR Building, Statute Circle, C-Scheme, Jaipur (Raj.)-302 005 ...Appellant
Vs.
1.M/s. Ashika Commercial Pvt. Ltd. Through the Resolution Applicant Registered office at 1,Grasting Place, Orbit, 4th floor, Kolkata - 700 001 ...Respondent No.1
2.M/s.Siddha Domicile Company Pvt. Ltd. 12, Park Lane, Kolkata - 700 016 ...Respondent No.2
3. M/s. Himavanta Investors Pvt. Ltd. 12, Park Lane, Kolkata - 700 016 ...Respondent No.3
4.Mr. Rajesh Kumar Agarwal, Resolution Professional 1,GC Avenue, Kolkata - 700 013 ...Respondent No.4
Present: For Appellant : Mr Sandeep Pathak, Mr. Avnish Dave, Advocates. For Respondents : Mr. Vikrant Pachnanda, Ms.Shruti Swaika, Advocate for R1. Mr. Rituraj Choudhary, Mr. Chandan Kumar Advocate for R4
Company Appeal (AT) (Ins) No. 891 of 2021 Page 1 of 13
J U D G M E N T
( 16th December, 2022)
DR. ASHOK KUMAR MISHRA, TECHNICAL MEMBER
1. The Appellant has filed the present appeal under Section 61 of the
'Insolvency and Bankruptcy Code 2016' (hereinafter referred as to 'the
Code') against the impugned order dated 12.08.2020 passed by the
'National Company Law Tribunal, Kolkata Bench (hereinafter referred as
to 'the Adjudicating Authority') in IA (IB) No. 600/KB/2020 in CP(IB) No.
503/KB/2018.
2. The Appellant /Commissioner of Custom and Excise, Jaipur -I now known
as Principal Commissioner Central Goods and Service Tax Jaipur has
prayed for setting aside the impugned order dated 12.08.2020 passed by
the Adjudicating Authority as also non-provisioning for outstanding
statutory dues of the Corporate Debtor (CD) amounting to
Rs.2,88,53,538/-plus interest at applicable rate in the Resolution Plan etc.
3. The CD/Ashika Commercial Pvt. Ltd had failed to pay excise duty on
manufactured goods in respect of which Cenvat Credit had been availed
by the CD and which had been rejected and returned by the buyer.
4. The ld. Counsel for the Appellant has stated that under the Central Excise
Act, 1944, Central Excise Rules, 2002 and the Cenvat Credit Rules, 2004,
Company Appeal (AT) (Ins) No. 891 of 2021 Page 2 of 13 a manufacturer of excisable goods is entitled to seek Cenvat Credit on
inputs used in the manufacturing of certain goods manufactured and
supplied by such manufacturer. However, in cases where such goods are
rejected or returned by the buyer and are disposed without going through
any manufacturing process, such manufacturer is required to pay excise
duty equal to the amount of Cenvat credit claimed. Since the CD had failed
to pay such excise duty for the period of 2011-12, a show cause notice was
issued to the CD to show cause as to why Central Excise Duty amounting
to Rs. 8,01,407/- along with applicable penalty and interest not be
recovered from the CD. The show cause notice so issued to the CD was
adjudicated vide order in Original dated 30.10.2015 passed by the Joint
Commissioner, Central Excise Department, Jaipur, whereby the demand
of Rs. 8,01,407/- and penalty amount to Rs. 4,31,213/- alongwith interest
at applicable rate was confirmed against the CD. The CD preferred
statutory appeal before the Ld. Commissioner (Appeals) against the OIIO
dated 30.10.2015, which came to be dismissed vide order in appeal dated
07.03.2018. The order in appeal dated 07.03.2018 was challenged by the
CD before the Custom, Excise and Service Tax Tribunal, New Delhi
(CESTAT) which was dismissed by the CESTAT vide its final order dated
28.11.2019. In the meanwhile, during the course of audit of the records of
the CD for the period of 2011-12 to 2015-16 by the officers of the Appellant
Company Appeal (AT) (Ins) No. 891 of 2021 Page 3 of 13 Department, it was discovered that the CD was engaged in clandestine
clearance of finished goods without payment of central excise duty on such
goods in violation of the provision of Central Excise Act, 1944. A show
cause notice dated 03.05.2018 was issued to the CD to show cause as to
why such central excise duty amounting to Rs. 1,38,10,459/- be not
recovered from the CD along with applicable interest and penalty. The
show cause notice dated 03.05.2018 was adjudicated vide order in original
dated 28.02.2019 whereby the Adjudicating Authority was pleased to
confirm the demand of Rs. 1,38,10,459/- and penalty of Rs. 1,38,10,459/-
alongwith interest at applicable rate.
5. The CD was required to pay accordingly, an amount of Rs. 2,88,53,538/-
for violation of various provisions of Central Excise Act, 1944 and relevant
rules made thereunder. It was stated by the Ld. Counsel for the Appellant
that the Adjudicating Authority initiated Corporate Insolvency Resolution
Process (CIRP) vide its order dated 22.08.2019 on an application preferred
under Section 7 of the Code before the Adjudicating Authority by the
Financial Creditors. Mr. Rajesh Kumar Agarwal was appointed as
Resolution Professional (RP) in the first Committee of Creditors (CoC)
meeting. The Ld. Counsel has also stated that the RP invited Expression
of Interest (EoI) and received four EoI from the Resolution Applicant. The
CoC by 100% vote approved the Resolution Plan submitted by Mr.
Company Appeal (AT) (Ins) No. 891 of 2021 Page 4 of 13 Sanwarmal Jain and the same was approved by the Adjudicating Authority
vide impugned order dated 12.08.2020.
6. It was also stated by the Ld. Counsel that in a hearing before ld.
Commissioner (Appeals) on 12.08.2020, the RP of the CD didn't mention
that Resolution Plan has been approved by the Adjudicating Authority.
Similarly, in earlier appearances also before the Departmental Officer, the
RP didn't provide any information regarding CIRP.
7. What has been accepted by the Ld. Counsel of the appellant that they have
not filed the claim when it was invited by the RP and accordingly, there is
no provision of statutory dues of Rs.2,88,53,538/- plus interest anywhere
in the resolution plan and non-provision of statutory debt is a loss to the
public exchequer and hence they have filed the appeal against the
impugned order approving the Resolution Plan.
8. The ld. Counsel for the Respondent no.4/ RP on query from the Bench
that whether any contingent provision exist in the plan. It was informed
by her that plan has already been implemented and no residual is available
in the plan. Hence, nothing can be done. She also stated that only a
vigilant creditor is entitle for payment, however, when the claim was
invited, the agency had not filed its claim and now it simply desires that
its job be done based on correspondence/case file by the RP which is not
the requirement of law so far.
Company Appeal (AT) (Ins) No. 891 of 2021 Page 5 of 13
9. The Respondent No.1/Resolution Applicant/CD has stated in its pleading
that the appeal so filed involves abuse of process of law and not
maintainable. The ld. Counsel for the R1 also stated that the Resolution
plan so approved by the Adjudicating Authority under Section 31 of the
Code warrants no interference. Now the law is settled that the commercial
wisdom rest with the CoC and once the resolution plan is approved
virtually it becomes untouchable. The Appellant has failed to file its claim
when it was invited. The law provides for relief only for those who are
diligent. Through elaborate pleadings, he has tried to justify that nothing
can be done at this stage as they have even not filed its claim even at the
belated stage and now only coming at the stage after the approval of the
Resolution plan not only by the CoC but also by Adjudicating Authority.
10. The ld. Counsel for the R1 also stated that the CD had issued a letter
dated 10.02.2020 to the Superintendent, CGST and Central Excise Range
L1 opposite Central Bank of India, Ajmer road, KishanGarh, which is
depicted as below to supplements its stand that the Appellant was aware
of that CD is under CIRP even in February, 2020 whereas Resolution Plan
by Adjudicating Authority has been approved in August, 2020:
Company Appeal (AT) (Ins) No. 891 of 2021 Page 6 of 13 Company Appeal (AT) (Ins) No. 891 of 2021 Page 7 of 13
11. We heard at length the parties and have carefully gone through the
pleadings of the parties, available material on record, the order of the
Adjudicating Authority and we are having the following observations:
a. It is not in dispute that the Appellant/ Commissioner of Custom and
Excise, Jaipur -I has not filed the claim while it was so notified by the
RP. Even the claim has not been filed at the belated stage prior to
approval of Resolution Plan by the CoC. The Appeal has been filed after
the plan has been approved by the Adjudicating Authority. As a result
of which the Appellant has not complied with the provisions of Section
13 & 15 of the Code.
b. At this belated stage no fund is available out of the kitty of the
Resolution Plan which can be earmarked to the Appellant as informed
by the RP and the Resolution Applicant also. Both Resolution Applicant
and RP has confirmed implementation of the plan and nothing remains
to be adjudicated.
c. It is very much clear that Section 238 of the Code provides very clearly
that provisions of this Code to override other laws as also section 14 of
the Code provides for moratorium during CIRP.
d. We are not in a position even to accede to the request of the Appellant
based on Hon'ble Apex Court Judgment in Civil Appeal No. 1661 of
2020 with Civil Appeal No. 2568 of 2020 State Tax Officer (1) Vs.
Company Appeal (AT) (Ins) No. 891 of 2021 Page 8 of 13 Rainbow Papers Limited1 para 4-10. Even this Judgment has
elaborately dealt with the filing of claims and submission of proof etc.
However, in this case the property of the CD was attached by the
Sales Tax Department prior to initiation of CIRP and as also in this
case Sales Tax Department had already filed a claim before the RP
in the requisite format. Para 4-10 as stated supra is depicted below:
"4.The appellant has, from time to time, been assessed
for Value Added Tax (VAT) and Central Sales Tax (CST)
under the GVAT Act. It is stated that an amount of
Rs.53,71,65,489/- is due from the Respondent to the
Sales Tax authorities towards CST and VAT, as per the
statement enclosed at Page 44 of the Paper Book.
5. On or about 8th July, 2016, recovery proceedings
were initiated against the respondent, in respect of its
dues for the year 2011-2012, and the appellant
attached the property of the respondent being land at
Survey No.2379 and 2381 situated at Rajpur, Taluka
Kadi on 8th October, 2018.
6. One Neeraj Papers Private Limited, as operational
creditor of the respondent, filed Company Petition (IB)
1 2022 Livelaw (SC)743
Company Appeal (AT) (Ins) No. 891 of 2021 Page 9 of 13 No.88 of 2017 under Section 9 of the IBC before
Ahmedabad Bench of the National Company Law
Tribunal (NCLT), for initiation of the Corporate
Insolvency Resolution Process (CIRP) against the
respondent.
7. By an order dated 12th September, 2017, the said
Company Petition [Company Petition (IB) No. 88 of
2017] filed by the said Neeraj Papers Private Limited
was admitted. One George Samuel was appointed
Interim Resolution Professional (IRP) on 22 nd
September, 2017.
8. After appointment of the said George Samuel as IRP,
claims were invited from Creditors under Section 15 of
the IBC by issuance of newspaper publications. The
last date for submission of claims was 5th October
2017.
9. After receipt of claims, a Committee of Creditors (CoC)
was constituted on 10th October 2017. At its first
meeting, the CoC passed a resolution to replace the IRP.
Accordingly, Ramachandra D. Choudhary, a Chartered
Accountant, was appointed as Resolution Professional
Company Appeal (AT) (Ins) No. 891 of 2021 Page 10 of 13 (RP). The appointment of Mr. Choudhary was approved
by the NCLT by an order dated 6th November 2017.
10. The appellant filed a claim before the RP in the
requisite Form B, claiming that Rs.47.36 crores
(approximately), was due and payable by the
respondent to the appellant, towards its dues under the
GVAT Act. The claim was filed beyond time."
Hence this judgment is not in a position to help the Appellant herein
as they have not filed their claim even at belated stage.
e. However, in this context we may also refer to the judgment of
Ghanashyam Mishra and sons Pvt. Ltd. Vs. Edelweiss Reconstruction
company Limited2 held at para 102.1:
"102. In the result, we answer the questions framed by
us as under:
102.1 That once a resolution plan is duly approved by
the Adjudicating Authority under sub section (1)
of Section 31, the claims as provided in the resolution
plan shall stand frozen and will be binding on the
2 (2021) 9 SCC 657
Company Appeal (AT) (Ins) No. 891 of 2021 Page 11 of 13 Corporate Debtor and its employees, members, creditors,
including the Central Government, any State Government
or any local authority, guarantors and other
stakeholders. On the date of approval of resolution plan
by the Adjudicating Authority, all such claims, which are
not a part of resolution plan, shall stand extinguished
and no person will be entitled to initiate or continue any
proceedings in respect to a claim, which is not part of the
resolution plan
102.2. 2019 amendment to Section 31 of the I&B Code is
clarificatory and declaratory in nature and therefore will
be effective from the date on which I&B Code has come
into effect;
102.3Consequently all the dues including the statutory
dues owed to the Central Government, any State
Government or any local authority, if not part of the
resolution plan, shall stand extinguished and no
proceedings in respect of such dues for the period prior
to the date on which the Adjudicating Authority grants its
approval under Section 31 could be continued."
Company Appeal (AT) (Ins) No. 891 of 2021 Page 12 of 13 f. In view of the above stated position of law, we are not in a position to
accede to the prayer of the Appellant and accordingly, the Appeal is
dismissed. No order as to costs.
Pending application, if any, stands disposed of.
[Justice Rakesh Kumar] Member(Judicial)
[Dr. Ashok Kumar Mishra] Member (Technical)
Raushan
Company Appeal (AT) (Ins) No. 891 of 2021 Page 13 of 13
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free