Miss Lucy
← All judgments

Chintan Jhunjhunwala vs Avani Towers Private Limited

National Company Law Appellate Tribunal29 August 2025Ashok Bhushan

Ratio decidendi

The rule this decision rests on

The Tribunal's decision rests on the following rules, each stated in the order the court takes them. A resolution plan approved under the Insolvency and Bankruptcy Code is not invalid merely because some of its clauses address rights or obligations under pre-insolvency agreements, where those clauses reproduce, track or are expressly subject to the terms of those agreements, and where the plan itself provides that the corporate debtor's obligations under those agreements are to be performed in accordance with them, subject to the preconditions stated in those agreements; such clauses do not thereby take away the ownership rights of a non-debtor landowner nor contravene the agreements. A mere contractual right of a corporate debtor as developer under a joint development agreement, including the right to create a charge or mortgage on the project land for project finance, is recognised by the agreement itself where it so provides, and a resolution plan clause reflecting such a right does not require any further consent of the landowner to be valid. A person who was executed a power of attorney solely as nominee of the corporate debtor to facilitate its development, and who holds no individual right in the property, has no right affected by a resolution plan clause that replaces or cancels that power of attorney on approval of the plan, and cannot challenge such a clause. A decision of this Tribunal which turns on the particular facts there, where the plan purported to transfer title to land under an unregistered development agreement to which the objector was not a party, is not authority for invalidating a plan whose clauses are consistent with the parties' registered development agreement and do not transfer ownership to the corporate debtor. A resolution plan is not rendered contingent or conditional, and so contrary to section 30(2)(e) of the Code, merely because it refers to infusion of funds dependent on approvals under the underlying agreement, where the plan fixes payment timelines and binds the successful resolution applicant to implement it without any exit right. A successful resolution applicant satisfies the eligibility criteria for a resolution applicant where the financial statements and the resolution professional's affidavit, filed on the record, show net worth above the prescribed minimum and funds deployed meeting the prescribed threshold for the immediately preceding completed financial year.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

NATIONAL COMPANY LAW APPELLATE TRIBUNAL, PRINCIPAL BENCH, NEW DELHI Company Appeal (AT) (Insolvency) No. 326 of 2025 (Arising out of Order dated 03.01.2025 passed by the Adjudicating Authority (National Company Law Tribunal), Division Bench, Court No.II, Kolkata in I.A. (IB) No.1332/KB/2024 in Company Petition (IB) No.372/KB/2019)

IN THE MATTER OF: Chintan Jhunjhunwala ...Appellant Versus Avani Towers Pvt. Ltd. Through Its RP, Jitendra Lohia & Ors. ...Respondents

Present:

For Appellant : Mr. Krishnendu Datta, Sr. Advocate with Mr. Kumarjit Banerjee, Mr. Shashank Agarwal, Mr. Sahil Sharma, Mr. Abhishek Taneja, Mr. Yash Tandon, Advocates. For Respondent : Mr. Abhijeet Sinha, Sr. Advocate with Mr. Saikat Sarkar, Ms. Swati Sinha, Ms. Safura Ahmed, Ms. Neha Sinha, Mr. Nitin Kant Setia, Advocates with Mr. Jitendra Lohia, RP for R-1. Mr. Nirmalya Dasgupta, Advocate for CoC Mr. Sandeep Bajaj and Ms. Suparna Sardar and Mr. Mayank Bijani, Advocates for SRA. Mr. R.R. Modi, Advocate for R4. Mr. K.K. Modi, Advocate for Energy- RP.

JUDGMENT

ASHOK BHUSHAN, J.

This Appeal has been filed by the Appellant challenging the order

dated 03.01.2025 passed by National Company Law Tribunal, Division

Bench, Court No.II, Kolkata in IA (IB) No.1332/KB/2024 filed by the

Appellant. By the impugned order, IA (IB) No.1332/KB/2024 has been

dismissed by the Adjudicating Authority. Aggrieved by which order, this

Appeal has been filed.

Company Appeal (AT) (Ins.) No.326 of 2025 1

2. Brief facts of the case necessary to be noticed for deciding the

Appeal are:

(i) The Appellant - Chintan Jhunjhunwala is Suspended

Director of Energy Properties Private Limited (hereinafter

referred to as the "Energy") and a shareholder of Corporate

Debtor ("CD") - Avani Towers Private Limited (hereinafter

referred to as the "Avani").

(ii) Energy entered into a Memorandum of Understanding

("MoU") with Avani for acquisition of subject land comprising

10.19 acres situated at Ramrajatalla, Near Ramrajatalla

Station Road, District - Howrah from UCO Bank in a sale

under Section 13, sub-section (4) of the SARFAESI Act, 2002.

Under the MoU, the Avani was to give accommodation

amount of Rs.2.7 crores to the Energy for buying the land

from UCO Bank for acquiring the property. On 24.01.2008, A

Shareholders' Agreement was executed between Energy and

Avani, where 40% shareholding of Energy was transferred to

Avani - CD. On 29.01.2008, Sale Certificate was issued by

UCO Bank in favour of Energy for consideration of

Rs.2,97,03,484.

(iii) MoU dated 24.01.2008, contemplated a Joint Development

Agreement ("JDA") to be executed between Energy and Avani,

Energy as owner and Avani as Developer for developing the

Company Appeal (AT) (Ins.) No.326 of 2025 2 land of 10.19 acres. The JDA dated 16.06.2008 was entered

between Energy (as owner) and Avani (as developer), where

Avani - CD was offered exclusive development rights on the

subject land. Under the JDA, Avani had to pay security

deposit of Rs.12 crores, which was not to carry interest, any

amount in addition to Rs.12 crores, subject to maximum of

Rs.3 crores was to carry 18% interest per annum. The JDA

provided for allocation of 60% constructed area to the

developer and 40% to the owner - Energy. The JDA also

contemplated for return of security deposit paid by Avani.

One Victory Iron Works Ltd. ("Victory") was given a Leave

and License on 10000 sq. ft. on 19.08.2011 for a period of 11

months

(iv) On Section 7 application filed by one - Sesa International

Ltd., the Corporate Insolvency Resolution Process ("CIRP")

commenced against the Avani vide order dated 15.10.2019.

The Resolution Professional ("RP") of the CD filed an

application before the Adjudicating Authority for taking

possession of land of CD (in which the CD has development

rights), which was allowed by the 12.02.2020 by the

Adjudicating Authority.

(v) Both Energy and Victory filed Appeals before this Tribunal,

which was dismissed on 08.04.2021. Victory and Energy

filed Civil Appeals before the Hon'ble Supreme Court, which

Company Appeal (AT) (Ins.) No.326 of 2025 3 Appeals were dismissed by Hon'ble Supreme Court on

14.03.2023, upholding the order of the RP for taking

possession of the land. The Hon'ble Supreme Court held that

by virtue of MoU dated 24.01.2008, Shareholder Agreement

dated 24.01.2008 and JDA dated 16.06.2008, Avani has the

development rights in 10.19 acres of land owned by Energy.

(vi) In the CIRP of the CD, Energy filed various IAs seeking

several directions including participation in the Committee of

Creditors ("CoC") of the Avani. There was certain issues

regarding the constitution of the CoC, which are not relevant

for deciding this Appeal.

(vii) The CoC of the CD passed a resolution on 31.10.2023

approving the Resolution Plan submitted by Respondent No.3

- Cheminare Tradecomm Pvt. Ltd. The RP filed an application

before the Adjudicating Authority for approval of the

Resolution Plan being IA No.1892/KB/2023. The Appellant

filed an application - IA No.200 of 2024 seeking dismissal of

IA No.1892 of 2023 filed by the RP for approval of Resolution

Plan.

(viii) CIRP against Energy commenced by an order dated

20.03.2024 on an Application filed by Avani, through RP,

claiming to be a Financial Creditor, in which proceedings,

Respondent No.4 - Mahesh Chand Gupta was appointed as

the RP of Energy.

Company Appeal (AT) (Ins.) No.326 of 2025 4

(ix) The RP of Energy on the basis of Minutes of the CoC, decided

to withdraw IA No.200 of 2024, which was filed by Energy,

objecting to the Resolution Plan. On 25.06.2024, the RP of

Energy withdrew IA No.200 of 2024.

(x) The Appellant on 27.06.2024 filed an IA No.1332 of 2024

objection to the Resolution Plan as Member of Suspended

Board of Energy and shareholder of the Avani. The

Adjudicating Authority heard IA No.1332 of 2024 filed by the

Appellant along with other applications, including IA No.1892

of 2023 filed by the RP for approval of the Resolution Plan.

The Adjudicating Authority by the impugned order dated

03.01.2025, rejected IA No.1332 of 2024 filed by the

Appellant. The Adjudicating Authority while rejecting the IA

No.1332 of 2024 has held that the Appellant (Applicant)

neither has locus nor has succeeded to make out a case

meriting interference with the Plan submitted by the

Successful Resolution Applicant ("SRA"). The Adjudicating

Authority by the same order has also allowed application - IA

No.1892 of 2023 approving the Resolution Plan. The

Appellant in the Appeal has challenged the order passed by

Adjudicating Authority dated 03.01.2025 in IA No.1332 of

2024 filed in CP(IB) No.372/KB/2019

3. We have heard Shri Krishnendu Datta, learned Senior Counsel

appearing for the Appellant; Shri Abhijeet Sinha, learned Senior Counsel

Company Appeal (AT) (Ins.) No.326 of 2025 5 has appeared for the RP/ Respondent No.1; Shri Nirmalya Dasgupta,

learned Counsel appearing for the CoC; Shri K.K. Modi, learned Counsel

has appeared for Respondent No.4 - RP of the Energy; and Shri Sandeep

Bajaj, learned Counsel appearing for SRA.

4. Shri Krishnendu Datta, learned Senior Counsel appearing for the

Appellant challenging the impugned order submits that the Appellant had

locus to file the IA No.1332 of 2024, objecting to the Resolution Plan

approved by the CoC of the CD on 31.10.2023. It is submitted that

Energy, who is the owner of the land, of which the Appellant is

shareholder, had filed IA No.200 of 2024 objecting to the application filed

by the RP for approval of Resolution Plan. Various grounds were raised in

IA No.200 of 2024, objecting to the Resolution Plan approved by the CoC

of the Avani. It is submitted that the said application - IA No.200 of 2024

was withdrawn by the RP of the Energy after Energy was put into CIRP,

vide order dated 20.03.2024. It is submitted that RP of Energy has joined

hands with RP of Avani to get the Resolution Plan of Avani passed by

Adjudicating Authority and he withdrew IA No.200 of 2024. It is

submitted that it was thereafter the Appellant has filed IA No.1332 of

2024 objecting to the Resolution Plan. It is submitted that Appellant who

was shareholder of the Energy, the owner of the land as well as the

Suspended Director of the Energy had every locus to object to the

Resolution Plan of the CD, who was developer of the land. The

Adjudicating Authority committed error in observing that Appellant has

no locus to file IA No.1332 of 2024. It is submitted that in the Resolution

Company Appeal (AT) (Ins.) No.326 of 2025 6 Plan, which has been filed by Respondent No.3 in the CIRP of the CD -

Avani, the ownership rights of Energy, who is owner of the land are being

taken away. The Resolution Plan by its various Clauses, specially Clause

5(c), 5(h), 5(j) and 5(l), takes away valuable right of the Energy, the owner

of land as protected in the MoU dated 24.01.2008 as well as JDA dated

16.06.2008. It is submitted that the impugned Clause 5(c) seeks to alter

the order of repayment provided in Part II of the Third Schedule of the

JDA, instead of rendering the security deposit repayable upon various

milestones up to and including completion of the Project, the said clause

seeks to appropriate the same upon approval of the Resolution Plan by

acquiring the owner's allocation of the constructed area @ of Rs.1400 per

sq. ft. Such Clause renders the entire security deposit to be due and

payable immediately upon approval of the Resolution Plan, which is in

complete departure of Part II of the Third Schedule of the JDA. Similarly,

under Clause 5(h) the SRA with the approval of Resolution Plan is entitled

without any involvement of the landowner to raise finance by

encumbering the land, which is clear departure from the obligation of the

parties under Clause 20.8 of the JDA. Similarly, it is contended that by

Clause 5(l), SRA is permitted to bring in new investors by creating an SPV

to hold the shares of Energy. Further, Clause 5(j) envisages the RP of

Avani to be appointed as an independent Director/ Chairman of the

Energy by giving the entire control of the Board of Energy. Resolution

Plan is nothing but a oblique and purported effort towards usurpation of

the subject land and denude Energy from all ownership rights over the

Company Appeal (AT) (Ins.) No.326 of 2025 7 subject land. Alteration of terms of the contract is impermissible under

the Resolution Plan. Shri Datta further submits that Avani does not

become owner of the land, nor the judgment of Supreme Court dated

14.03.2023 holds the Avani as owner of the land. What was held by the

Supreme Court by judgment dated 14.03.2023 is that Avani by JDA has

development rights. The JDA clearly contemplates that owner of the land

is Energy, who shall continue to be the owner. The submission of the

Respondent that alteration of terms of the contract is permissible under

the IBC and there is nothing illegal in the Resolution Plan, is incorrect. It

is submitted that while alteration of terms of contract is permitted under

Regulation 37 of IBBI (Insolvency Resolution Process for Corporate

Persons) Regulations, 2016 ("CIRP Regulations"), alteration and dilution

of the owner's rights or interests in the subject land is not permissible

and it is distinct from mere alteration of contractual terms. Learned

Counsel for the Appellant referring to the judgment of this Tribunal dated

30.01.2023 in Greater Noida Industrial Development Authority vs.

Roma Unicon Designex Consortium - Company Appeal (AT) (Ins.)

No.180 of 2022 - submits that this Tribunal has held that without the

consent of owner of the land, the property can never be subject matter of

the CIRP, since the land is not the asset of the CD, who has only

development rights. It is further submitted that Resolution Plan is a

conditional Resolution Plan. The implementation of the Resolution Plan is

uncertain. The Resolution Plan contemplates that infusion of

Rs.17,94,27,647/- is entirely conditional and uncertain, it being

Company Appeal (AT) (Ins.) No.326 of 2025 8 contingent upon obtaining of certain approvals and permissions,

including conversion of land usage, which makes the Plan unworkable

and in contravention of Regulation 38(2)(a) and 38(3)(d) of the CIRP

Regulations. The RP of Energy and the CD have joined hands to harm the

interest of Energy, who is the owner of land.

5. Learned Counsel for the RP refuting the submission of learned

Counsel for the Appellant submits that the Appellant has not challenged

the order allowing IA No.1892 of 2023 approving the Resolution Plan. It

is submitted that although the Adjudicating Authority has taken the view

that Appellant has no locus to file the application, being IA No.1332 of

2024, but the RP proceeds to counter the submissions raised by the

Appellant on merits, accepting, for arguments sake, that Appellant has

locus to file the application. The submission of the Appellant that

Resolution Plan seeks to completely depart from the terms and conditions

of JDA, is incorrect. The submission is also incorrect that Resolution

Plan is attempting to dilute the rights of Energy contained in the JDA.

The submission of the Appellant that Resolution Plan is contrary to

Section 30(2)(e), is not correct. It is submitted that some of the Clauses in

the Resolution Plan specially Clause 5(c), (h), (i), (g) and (l) as relied by

learned Counsel for the Appellant in no manner alter the Clauses of JDA.

Referring to Clause 5(c), it is submitted that repayment of Rs.12 crores as

envisaged in the Resolution Plan is identical with the JDA and amount is

to be refunded in the phased manner as contemplated in Part-II, Third

Schedule of the JDA without any deviation. Learned Counsel for the

Company Appeal (AT) (Ins.) No.326 of 2025 9 Respondent has referred to Clause 5(m), which categorically provides for

Resolution Plan to comply with MoU dated 24.01.2008, Shareholding

Agreement dated 24.01.2008 and JDA dated 16.06.2008. It is submitted

that Clauses of Resolution Plan neither prejudice any of the Clauses of

the JDA, nor any of the rights of the Appellant have been diluted.

Regarding appropriation of owners' allocation @ 14000 sq. ft. as

contemplated in the JDA and the Clauses provided for such

appropriation, it is in accordance with the JDA. So far as, the Project's

finance is concerned, the JDA itself provided to create a charge or

mortgage, hence, no further consent is required from the Energy. The

right is given to Avani to create charge on the land to secure its interest.

The Plan rightly provided the name of the attorney holder to substitute

with the name of Directors of the Applicant as per the JDA. Under

shareholding, the Applicant - Avani has right to nominate its Director in

the Board of Energy. The Resolution Plan only contemplates to continue

with the aforesaid understanding. The Resolution Plan clearly states that

SRA envisages to implement the terms of JDA and Clauses as submitted

by the Appellant, which is not in contravention of any law or any

Agreement. The allegation that RP of Avani and RP of Energy has hands

in glove, is wholly incorrect.

6. Learned Counsel for the SRA submits that SRA was fully eligible to

submit the Resolution Plan. The Clauses of the Resolution Plan in no

manner contravene any Clauses of the JDA and MoU. It is submitted

that Resolution Plan has been approved with 100% vote share of the CoC.

Company Appeal (AT) (Ins.) No.326 of 2025 10 In reply to the submission that the Plan is conditional, it is submitted

that Resolution Plan adopts the various Clauses of JDA. The Resolution

Plan nowhere provides for the exit route/ option to withdraw the

Resolution Plan. The Resolution Plan is binding upon all the

stakeholders, including Respondent No.3. The submission that

Resolution Plan is contingent is incorrect.

7. Learned Counsel appearing for Respondent No.4 submits that

allegation that Respondent No.4 has colluded with RP of Avani is incorrect

and baseless. After the CIRP of the Energy commenced, the RP of Energy

convened the 4th CoC Meeting and RP has independently looked into the

Resolution Plan and found that Resolution Plan in no manner harm the

interest of Energy. Hence, a decision was taken to withdraw IA No.200 of

2024 in the interest of Energy and said was bonafide decision taken by

the RP of Energy. Respondent No.4 has acted in the interest of Energy.

8. Learned Counsel for the parties have placed reliance on judgment of

the Hon'ble Supreme Court and this Tribunal, which we shall refer to

while considering submissions in detail.

9. From the submissions of learned Counsel for the parties, following

are the questions, which arose for consideration in this Appeal:

(I) Whether Resolution Plan submitted by Respondent No.3,

specially Clauses 5(c), (h), (i), (j) and (l), take away ownership

rights of the Energy and the aforesaid Clauses contravene the

provisions of MoU dated 24.01.2008 and JDA dated

16.06.2008?

Company Appeal (AT) (Ins.) No.326 of 2025 11 (II) Whether ownership rights of the Energy in the land of 10.19

acres are being taken away by the Resolution Applicant,

under the approved Resolution Plan?

(III) Whether Resolution Plan submitted by SRA is contingent and

conditional Resolution Plan, which could not have been

approved?

(IV) Whether the SRA has not fulfilled necessary eligibility.

10. Before we proceed to consider the above submissions, it is relevant

to notice certain Clauses of MoU dated 24.01.2008; JDA dated

16.06.2008 and the judgment of the Hon'ble Supreme Court, which was

delivered in respect of CIRP of the CD dated 14.03.2023, where nature of

rights possessed by Avani has been considered and decided.

11. The facts on the record reveal that land of 10.19 acres of land was

owned by M/s Shree Gobinddeo Glass Works Ltd. There being default

committed in payment of facilities extended by UCO Bank, proceedings

under Section 13 of the SARFAESI Act were initiated by the UCO Bank, in

which proceedings the said land was sold for consideration of

Rs.2,97,03,484/- in favour of Energy. A MoU dated 24.01.2008 was

entered between Energy and Avani, where Avani agreed to provide

accommodation amount of Rs.2.7 crores to the Energy. The said

accommodation amount was to be paid by Avani to UCO bank directly on

behalf of the Energy for obtaining the sale and transfer of property.

Clause 14.1 of the MoU provides as follows:

Company Appeal (AT) (Ins.) No.326 of 2025 12

"14.1. The said Accommodation Amount agreed to be disbursed and/or made available by Avani, a sum of Rs. 2.7 Crores will be paid to the said Bank directly by Avani for and on behalf of Energy for obtaining the sale and transfer of the said property in favour of the Company and further sum of Rs. 9.3 Crores will be disbursed before and after the Definitive Agreement being entered into detailing out all the terms and conditions agreed upon being the subject of development of the said Property to enable Avani undertake Development of the said."

12. The MoU further contemplates that the amount of Rs.9.3 crores will

be disbursed by the Avani after Definitive Agreement is entered into,

detailing terms and conditions for development of the property. Clause

14.2 provides as follows:

"14.2. The said balance sum of Rs. 9.3 Crores will be utilized by the Company for liquidation of all liabilities and for obtaining vacant possession of the portions of the property presently in occupation of the said workmen and/or staff and/or occupants."

13. One more Clause, which is relevant to notice is Clause 15.3, which

provides that Avani shall be entitled to create a charge and mortgage in

respect of the premises by deposit of the original title deeds for the

purpose of obtaining construction loan. Clause 15.3 is as follows:

"15.3 It is hereby expressly agreed and declared that Avani shall be entitled to create a charge and/or mortgage over and in respect of the said Premises and/or. Avani's Area by deposit of the original title deeds for the purpose of obtaining construction loan for undertaking development of the said Premises after sanction of the Plan for which Energy with join as co applicant/co-borrower."

Company Appeal (AT) (Ins.) No.326 of 2025 13 14. The MoU further provides that for protecting the interest of Avani

including repayment of Rs.12 crores, it was agreed that Jhunjhunwala

Group Shareholders shall transfer 40% of the shares in favour of the

Avani. Clause 16.2 provides as follows:

"16.2 For the purpose of protecting the interest of Avani including repayment of the said sum of Rs. 12,00,00,000/- (Rupees twelve crores only) it has been agreed that the Jhunjhunwala Group Shareholders out of the shares presently held by them will transfer 40% of the shares at face value unto and in favour of Avani of Avani or affiliated and/or nominees."

15. Clause 18 of the MoU provides for 'Essential terms of the

Development Agreement', which included allocation of 60% to the

developer and 40% to the Energy.

16. A Shareholder Agreement was also executed on 24.01.2008

transferring 40% of the shares to the Avani and further 20% shares were

transferred to one Mr. R.L. Gaggar.

17. After the aforesaid MoU, Avani paid the amount to the UCO Bank

and a Sale Certificate dated 29.01.2008 was issued by the UCO Bank in

favour of the Energy. After issuance of Sale Certificate on 29.01.2008,

Joint Development Agreement was entered on 16.06.2008. The JDA,

clearly provided that Energy is the owner of land in possession. Clause

6.1 provides for appointment of developer, who has to make construction

and to cause marketing/ sale of both developers allocation and owners

allocation. Clause 6.1 provides as follows:

Company Appeal (AT) (Ins.) No.326 of 2025 14

"6.1 Appointment and Acceptance: The Owner hereby appoints the Developer as the developer of the Said Land and the Developer hereby accepts such appointment. By virtue of such-appointment, the Owner hereby grants and assigns exclusive right to the Developer to build upon and exploit commercially the Said Land by (1) demolishing the existing structures, if any (2) constructing the Housing Complex and (3) causing marketing/sale of both Developers Allocation and Owners Allocation."

18. Clause 7 provides for 'Allocation in the Project'. Clause 7.1 is as

follows:

"7. Allocation: 60% of the total constructed area together with the undivided proportionate share in all common parts portions areas, roof, can parks and facilities and together with the undivided proportionate share in the land comprised in the said property attributable thereto shall belong to the Developer (hereinafter referred to as the Developer's Allocation) and the remaining 40% of the total constructed area together with the undivided proportionate share in all common parts portions areas, roof, can parks and facilities and together with the undivided proportionate share in the land comprised in the said property attributable thereto shall belong to Owner (hereinafter referred to as the Owner's Allocation).

19. Clause 8 provides for 'Security Deposit and Refund'. Clauses 8.1,

8.2 and 8.3, which are relevant, are as follows:

"8.1 Refundable Deposit The Developer will keep in deposit with Owner a sum of Rs.12,00,00,000/- (Rupees twelve crore) (hereinafter referred to as the Security Deposit) which will not carry interest and will be payable & refundable in the manner as would appear from the Fart-1 of the Third Schedule hereunder written. The 'Developer as on date has

Company Appeal (AT) (Ins.) No.326 of 2025 15 already paid Rs.7,86,83,108/- (Rupees seven crores eighty six lác eighty three thousand one hundred eight). The said sum of Rs.12,00,00,000/-1 (Rupees twelve crore) agreed to be paid by the Developer will be treated as the Security Deposit. However any further sum, subject: to a maximum of Rs.3,00,00,000/- (Rupees three crore), if advanced by.

Developer to Owner, shall form part of Security Deposit and shall carry interest at agreed rate of 18% per annum compounded and payable quarterly.

8.2 Refund of Refundable Deposit: The Security. Deposit shall be refunded by the Owner to the Developer in the manner provided in the Part-II of the Third Schedule, The Owner agrees to ensure timely repayment of the said Refundable Deposit in the manner as hereinbefore stated and in the event of failure to refund an interest 18%ipa. compounded quarterly shall become payable calculated from the due date of refund.

8.3 Recovery of Security Deposit: In event the Owner fails to refund the said Security Deposit within 7 (seven) days of the same becoming due then and in that event Developer shall be entitled to acquire arid/or buy back such portion of the Owner's Allocation for repayment of the said Security Deposit at a agreed rate of Rs.1,400/- (Rupees fourteen hundred) per sq. ft. The Owner's Allocation shall stand reduced by such square feet as may be derived by dividing the outstanding refund amount with the rate of 1,400/- (Rupees fourteen hundred) per square feet."

20. Clause 10 deals with 'Powers and Authorities'. General Power of

Attorney was to be granted to the Developer and/or its nominees. Clause

10.1 provides as follows:

"10.1 General Power of Attorney: The Owner shall grant to the Developer and/ or its nominees a General Power of

Company Appeal (AT) (Ins.) No.326 of 2025 16 Attorney for causing construction of the Housing Complex further a separate power of Attorney for Sale shall be executed in favour of the Developer and the Owner shall also execute a separate Power of Attorney in favour of the Developer for the purpose of sanction."

21. The Development Agreement captures the Owners Obligation.

Clause 16.1 deals with Owners Obligation, which is as follows:

"16.1 To fulfill all Conditions Precedents: The Owner shall obtain all clearances/ permissions as provided in the Fourth Schedule before the Developer proceeds to perform its part of obligations: Out of the aforesaid Conditions Precedents upon failure by the Owner, which ever is carried out by the Developer on behalf of the Owner and any amount which may be incurred on such account by Developer shall be reimbursed by Owner and/or adjusted and appropriated by sale of the Owner's Allocation as hereinafter appearing at best market rate achievable and the Owner shall sign and execute all affidavits papers deeds documents and Instruments as may be necessary and/or required."

22. Clause 17 deals with 'Developer's Obligations'. Clause 17.1 is as

follows:

"7.1 Time of Completion: The Developer hereby agrees and covenants with the Owner that subject to the Owner meeting all its obligations and those provided, in Fourth Schedule including those mentioned in the various sub-clauses of Clause 16 above and subject further to Force Majeure (defined in, Clause 22 below): and reasons beyond the control of the Developer, the Developer shall complete. the construction of the Housing Complex within the Stipulated Period mentioned in Clause 11:5 above."

Company Appeal (AT) (Ins.) No.326 of 2025 17 23. Third Schedule of the Part-II deal with 'Manner of Refund of

Deposit'. Third Schedule Part-II is as follows:

"Part-II (Manner of Refund of Deposit)

1. The said Refundable Deposit shall become refundable in the following manner:

a) Rs.3,00,00,000/- (Rupees three crore) simultaneously upon completion of foundation of the blocks and certified so by the Architect.

b) Rs.3,00,00,000/- (Rupees three crore) simultaneously upon completion of 50% of the super structure and certified so by the Architect

c) Rs.3,00,00,000/- (Rupees three crore), simultaneously upon completion of the total super structure and brickwork as certified by the Architect.

d) Balance sum of Rs.3,00,00,000/- (Rupees three crore) upon completion of the project and certified so by the Architect."

24. The MoU dated 24.01.2008 and JDA dated 16.06.2008 created

development rights in favour of the Avani - the CD in the present

proceedings. After initiation of CIRP against the Avani by order dated

15.10.2019, the RP had filed an application for taking possession of the

subject land, which was allowed by the Adjudicating Authority on

12.02.2020, which order was challenged both by Energy as well as

Victory, who was granted Leave and License for 10000 sq. ft. in the

subject land. The Appeal filed by Energy as well as Victory were

dismissed by this Tribunal on 08.04.2021 against which a Civil Appeal

No.1782 of 2021 by the Energy and Civil Appeal No.1743 of 2021 by the

Company Appeal (AT) (Ins.) No.326 of 2025 18 Victory, were filed before the Hon'ble Supreme Court. Both the Appeals

came for consideration before the Hon'ble Supreme Court and the Hon'ble

Supreme Court vide its judgment dated 14.03.2023 dismissed both the

Appeals and in the said judgment the Hon'ble Supreme Court noticed in

detail the MoU dated 24.01.2008, JDA dated 16.06.2008 and after

noticing the MoU as well as JDA and Sale Certificate, held that bundle of

rights and interests were created in favour of the CD - Avani, over the

immovable property in question. It was held that development rights

created in favour of the CD constitute "property" within the meaning of

the expression under Section 3(27) of the IBC, which are "asset" within

the meaning of Section 18(f) and Section 25(2)(a) of the IBC. Following

was held by Hon'ble Supreme Court in paragraph 35 of the judgment:

"35. From the sequence of events narrated above and the terms and conditions contained in the Agreements entered into by the parties, it is more clear than a crystal that a bundle of rights and interests were created in favour of the Corporate Debtor, over the immovable property in question. The creation of these bundle of rights and interests was actually for a valid consideration. But for the payment of such consideration, Energy Properties would not even have become the owner of the property in dispute. Therefore, the development rights created in favour of the Corporate Debtor constitute "property" within the meaning of the expression under Section 3(27) of IBC. At the cost of repetition, it must be recapitulated that the definition of the expression "property" under Section 3(27) includes "every description of interest, including present or future or vested or contingent interest arising out of or incidental to property". Since the expression "asset" in common parlance denotes "property of any kind", the bundle

Company Appeal (AT) (Ins.) No.326 of 2025 19 of rights that the Corporate Debtor has over the property in question would constitute "asset" within the meaning of Section 18(f) and Section 25(2)(a) of IBC"

25. In IA No.1332 of 2024, which was filed by the Appellant before the

Adjudicating Authority, following prayers were made:

"a. Direction to be passed for dismissal of the lA (IBC) 1892 of 2023 filed by the RP before this Hon'ble Tribunal for approval of the Resolution Plan of the SRA.

b. Direction to be passed for rejection of the Resolution Plan of the SRA which was approved on October 31, 2023 at the 29th meeting of the CoC by the CoC, since the CIRP of the CD culminating into the approval of the Resolution Plan is vitiated with fraud and non- joinder of the EPPL being the necessary party;

c. Direction to be passed declaring the approval of the Resolution Plan of the SRA by the CoC as bad in law;

d. Such further or other order or orders as to this Hon'ble Tribunal may deem fit and proper;

e. Interim order in terms of prayer (a) and (b);

f. Ad interim orders in terms of prayer (a) and (b);

g. Receiver.

h. Costs."

Question Nos.(I) and (II)

Both the above questions being inter-related are being taken

together.

26. We have already noticed the relevant Clauses of JDA. Learned

Counsel for the Appellant has relied on various Clauses of the Resolution

Company Appeal (AT) (Ins.) No.326 of 2025 20 Plan to contend that the above Clauses take away the ownership rights of

the Energy and contravene the rights of the Energy, which are protected

under the JDA. Various Clauses of the Resolution Plan have been referred

to and challenged by the Appellant in support of its submission.

27. We now proceed to notice the relevant Clauses, which according to

the Appellant take away the ownership rights of the Energy. The first

Clause which has been attacked by the Appellant is Clause 5(c) of the

Resolution Plan. The copy of the Resolution Plan is brought on the record

as Annexure-P to the Appeal. The Resolution Plan dated 20.10.2023

Clause 5(c) provides as follows:

"5(c) JDA further envisages repayment of Security Deposit of Rs. 12 Crores which is to be paid back to the CD in phases after commencement of the project, as detailed under third schedule in the JDA.

Further in terms of the clause 8.1 and as per the information made available to the RA, additional loan advances were given to EPPL for Rs.3.50 Crores, which would also form part of the Security Deposits, and as such the entire amount of Rs.3.50 Crores in terms of the JDA would become payable in the manner as provided under Third Schedule, Part II. Being the additional advance, it is envisaged that the entire amount would become payable upon completion of foundation of the block and certified so by the architect.

As per the clause 8 (Security Deposits & Refunds) on failure of such payments (Rs.12 Crores & Rs.3.5 Crores) and within the due dates, developer shall automatically with approval of this plan & in terms of the JDA, be entitled to appropriate the outstanding amount relating to such security deposits becoming due by acquiring the owners allocation of the

Company Appeal (AT) (Ins.) No.326 of 2025 21 constructed area @1400/- per sqft, derived by dividing the outstanding refund amount with the rate of Rs 1400/- per Sqft, as per clause 8.3 of the JDA."

28. The submission of the Appellant is that Resolution Plan by virtue

of Clause (c), seeks to alter the order of repayment provided in Part-II

Third Schedule of JDA. Instead of rendering the security deposit

repayable upon various milestones up to and including completion of the

Project, the said Clause seeks to appropriate the same upon approval of

the Resolution Plan by acquiring the owner's allocation of the constructed

area @ Rs.1400 per sq. ft. Learned Counsel for the RP has submitted that

submission of the Appellant questioning Clause 5(c), is not correct.

Clause 5(c) captures the terms of JDA and repayment as provided in Part-

II of Third Schedule. The said appropriation is on failure of payment

within the due dates. Learned Counsel for the RP submitted that the said

Clause 5(c) does not contemplate that Plan does not deviate from the JDA

nor does it state that the adjustment would be made immediately after

approval of the Plan. The amount to be refunded in the manner as

contemplated in Part-II of Third Schedule is without any deviation.

Learned Counsel for the RP has relied on Clause 5(m), which clearly

provides that the Resolution Plan envisages to carry out all the terms of

the MoU, Shareholding Agreement and JDA on approval of Resolution

Plan by the Adjudicating Authority subject to fulfillment of the pre-

condition in terms of Fourt Schedule of the JDA. Clause 5(m) of the Plan

is as follows:

Company Appeal (AT) (Ins.) No.326 of 2025 22

"5(m) Resolution Applicant envisages to carry out all the terms of the Memorandum of Understanding, Shareholding Agreement and Joint Development. Agreement on approval of the Resolution Plan by the Adjudicating Authority, subject to fulfillment of the pre-condition in terms of Fourth Schedule of the Joint Development Agreement by EPPL for commencement of construction, including obligation by the owner for making the clear marketable title, permission & clearances, owners indemnity and other obligation by the owner as contained in the JDA including but not limited to as more fully mentioned in the clauses, 16.7, 16.8, 21.2, 18.1 and in the fourth schedule of the JDA."

29. We, thus, find that apprehension of Appellant is misplaced that on

approval of Resolution Plan, immediately the owner's shares shall be

appropriated towards the repayment of the security deposit. The

submission of the Appellant that ownership rights of the Energy is being

taken away by the above Clause, also cannot be accepted. Appropriation

@ Rs.1400/- per sq. ft. on account of non-refund of the amount by Energy

was contemplated in the JDA, relevant Clause of the JDA 8.3 has been

noted above, which provided for agreed rate of Rs.1400/- per sq. ft.

Hence, neither the ownership right of the Energy was taken away by the

aforesaid Clause nor Clause 5(c) contravenes the provisions of JDA. More

so, in view of the clear stipulation in Clause 5(m), the Resolution

Applicant is obliged to act in accordance with the various Clauses of JDA

and Clauses of Resolution Plan are to be implemented, subject to

fulfillment of pre-condition as contemplated in the JDA.

30. Shri Krishnendu Datta, Learned Senior Counsel has placed reliance

on the judgment of this Tribunal in "Greater Noida Industrial

Company Appeal (AT) (Ins.) No.326 of 2025 23 Development Authority (GNIDA) vs. Roma Unicon Designex

Consortium- Company Appeal (AT) (Insolvency) No.180 of 2022"

decided on 30.01.2023 to support his submission that the assessment of

a third party cannot be made subject matter of the Resolution Plan. In the

above case, Greater Noida Industrial Development Authority was owner of

the land which was allotted to one M/s. Earth Towne Infrastructures Pvt.

Ltd. which gave development rights to Earth Infrastructures Limited.

Roma Unicon Designex Consortium has submitted a Resolution Plan. One

of the questions framed was as to whether assets of the subsidiary i.e.

lease land could have been dealt with in the Resolution Plan and could

have contained a clause for transfer of lease hold rights. This Tribunal

found the Resolution Plan does not confine to the development rights

which were granted by the land owing company but also contemplates

transfer of title of land in favour of the Successful Resolution Applicant.

Following was observed in paragraph 51 of the judgment:-

"51. The Resolution Plan does not confine itself to the development rights, which were granted by the land owning company in favour of the Corporate Debtor on an unregistered Agreement, but also contemplates transfer of title of land in favour of Successful Resolution Applicant/ Special Purpose Company as contemplated in the Resolution Plan, which is an impermissible. The Development Agreement, which was unregistered document, could not have dealt with any right in the Project land and the lease hold right as per Development Agreement continued with the Lessee. Hence, the Resolution Plan could not have provided for transfer of the lease land in favour of Successful Resolution Applicant/ Special Purpose Company.

Company Appeal (AT) (Ins.) No.326 of 2025 24 Admittedly, the Appellant was not party to the Development Agreement, which was executed between land holding Company of the Corporate Debtor. The Appellant not being the creditor of the Corporate Debtor nor stakeholder in the CIRP Resolution Plan could not bind the Appellant in any manner. It is also relevant to notice that development agreement dated 09.09.2010 being an unregistered agreement could not have transferred any right in the lease land in favour of the developer. The Appellant not being party to such development agreement, the same is not binding on Appellant."

31. The judgment of this Tribunal in Roma Unicon Designex (supra)

was thus on its own facts. Present is a case where the Resolution Plan

and its clauses are in accord with the Development Agreement between

the parties dated 16.06.2008 and present is not a case where any

ownership is being transferred to the Corporate Debtor. We thus, are of

the view that the said judgment does not help the Appellant in the present

case.

32. The next Clause, which is questioned by the Appellant is Clause

5(h). Clause 5(h) is as follows:

"5h) JDA further envisages under clause 20.8, project finance that can be availed by the developer, it is hereby clarified that on approval of the resolution plan, the developer may avail such project finance facility and create such charge or equitable mortgage on the property owned by EEPL or on the proposed contracted area, without requiring any further clearances or no-objection certificate from the owners. Any such mortgage or charge created, shall be valid and subsist, till the project is completed. All the stakeholders including owners & escrow agent shall on approval of the resolution plan provide all the necessary co-

operation or assistance, including handover of such original title deeds, documents etc, as may be required towards such loans."

Company Appeal (AT) (Ins.) No.326 of 2025 25

33. In response to Clause 5(h), the RP has contended that right to

create charge/ mortgage by Avani was recognized in the JDA. Clause

20.8 of the JDA has been referred to by the Appellant, which deals with

Project finance. We, further notice that even the MoU dated 24.01.2008,

Clause 15.3 provides that Avani shall be entitled to create a charge and/

or mortgage over and in respect of the premises by deposit of the original

title deeds for obtaining construction loan. Thus, Clause 5(h) of the

Resolution Plan in no manner contravenes the provisions of JDA or MoU.

34. Next Clause which has been questioned by the Appellant is Clause

5(i), which provides as follows:

"i) As per the information made available, the owner has executed two (2) power of attorney in the name of directors of the suspended board, dated 16.06.2008 & 23.06.2008 towards development including sale, sanction and all such action that may be required in completion of the project. It is envisaged that on approval of the resolution plan, the name of such power of attorney holder would deemed to be substituted with the new directors of the resolution applicant, for which no further registration or agreement would be required.

In terms of the said Power of Attorney, executed pursuant to the Joint Development Agreement (JDA) and as contained in clause 12.3 of the said JDA, the developer shall have all the exclusive rights to receive advances including for the purpose of raising finance, sale, transfer or execute all deeds & agreements in terms of the JDA and that the owner shall have no rights to claim in the proceeds or advance money, except for in the manner as contained in the resolution plan and/or JDA."

35. The above Clause itself indicates that owner had executed two

Power of Attorney in the name of Directors of the Suspended Board

towards development including sale, sanction and all actions, which are

required for completion of the Project. On approval of Plan, it was

envisaged that name of such Power of Attorney holders would be deemed

Company Appeal (AT) (Ins.) No.326 of 2025 26 to be substituted with the new Directors of the Resolution Applicant. The

JDA has contemplated for execution of the Power of Attorney by the

owner. Clause 10.1 provided for grant of power of attorney. Clause 10.1

is as follows:

"10.1 General Power of Attorney: the Owner shall grant to the Developer and/ or its nominees a General Power of Attorney for causing construction of the Housing Complex further a separate power of Attorney for Sale shall be executed in favour of the Developer and the Owner shall also execute a separate Power of Attorney in favour of the Developer for the purpose of sanction."

36. Learned Counsel for the Respondent in support of his submission

has relied on judgment of this Tribunal in Dharmesh Jain vs. Jayesh

Sanghrajka & Ors. - Company Appeal (AT) (Ins.) No.825 of 2024

decided on 29.10.2024. In the above case, the Appellant who was given

power of attorney under the registered Development Agreement had

questioned the Clause of the Resolution Plan, which contemplated that

the said power of attorney shall stand cancelled. The challenge was made

by filing an application by the Appellant, which was rejected by the

Adjudicating Authority. The Appeal filed against the said order was

dismissed by this Tribunal. This Tribunal in paragraphs 17, 20 and 21

laid down following:

"17. We having noticed the relevant clauses of the Development Agreement and the Power of Attorney executed in favour of the Appellant, it is amply clear that the Appellant in the PoA was nothing but nominee of the corporate debtor and Appellant being suspended director of the corporate debtor was treated as nominee of the corporate debtor for the purpose of facilitating the developers. The developers being corporate debtor, PoA was not executed in an individual capacity of the appellant nor gave any right to the subject land. When the Resolution Plan submitted by the SRA is approved and the corporate debtor is being taken over by the SRA, the development of property and all other

Company Appeal (AT) (Ins.) No.326 of 2025 27 steps as per the Resolution Plan has to be taken by the SRA. The PoA dated 06.08.2005 which was executed in favour of the Appellant served its purpose and cannot be relied for any right which can be claimed by the Appellant in the process. Appellant who was contemplated to extend its co-operation as nominee of the corporate debtor in developing the property is now taken a stand to create obstacles in revival of the corporate debtor to carry out function by the SRA who now takes over the corporate debtor after approval of the Resolution Plan.

20. When PoA which was given for a particular purpose to the Appellant as nominee of the corporate debtor and Resolution Plan is approved by the CoC of the corporate debtor, the approval of the Resolution Plan is in commercial wisdom of the CoC and in event, the Resolution Plan declare the PoA which was given in favour of the Appellant as nominee of the corporate debtor as cancelled, the said clause of the Resolution Plan cannot be allowed to be challenged by the Appellant nor Appellant was given any rights in the subject property so as to assert any right. The endeavour of the Appellant is nothing but creating obstacles in revival of the corporate debtor in which he was suspended director. We also affirm the findings and imposition of cost of Rs.1 lakh that application was filed by the Appellant is nothing but a vexatious and dishonest attempt.

21. Counsel for the Appellant has also relied on the judgment of the Hon'ble Supreme Court in "Suraj Lamp and Industries Pvt. Ltd. vs. State of Haryana and Anr.- (2012) 1 SCC 656" for the proposition that mere execution of the Development Agreement could not have the effect of divesting Ralliwolf of all title, rights and interest in the subject property. There can be no dispute to the proposition laid down by the Hon'ble Supreme Court in the above case.

Corporate Debtor had development rights to develop the property on consideration of Rs.7 Crores. It is no more resintegra that the development rights can be claimed by the corporate debtor. The basis of the application filed by the Appellant was PoA dated 06.08.2005 and whether on the basis of the said PoA, clause of the Resolution Plan can be impugned by the Appellant was the question to be answered. As held by us, the PoA was executed in favour of the Appellant who was a nominee of the corporate debtor, only to facilitate the developers in carrying out the development and no rights were given to the Appellant in their individual capacity on the property. None of the rights of the Appellant, thus, can be said to be affected by approval of the Resolution Plan. PoA has out lived its purpose and has rightly held to be cancelled in the clause 7.33. We thus, do not find any error in the order of the Adjudicating Authority rejecting IA No.3689 of 2022.

Company Appeal (AT) (Ins.) No.326 of 2025 28

37. The above judgment fully supports the submission of the

Respondent that the Resolution Plan providing for execution of Power of

Attorney in favour of Resolution Applicant is correct. Further, with regard

to Developer's right to receive finances, the said was contemplated in

Clause 12.3. We, thus, do not find any contravention of the JDA by

Clause 5(i) of the Resolution Plan.

38. Next Clause 5(j) has been questioned by the Appellant, which is as

follows:

"5j) That on approval of the Resolution Plan by the Adjudicating Authority, CD shall continue to hold the shares/ directorship in EPPL in terms of various agreement executed with the CD, as on the CIRP commencement date.

The share of 20% however held by the Mr. Gaggar shall be kept in an escrow account and remain so till the completion of the project. It is further envisaged that the Resolution Professional shall be appointed as the Independent Director/ Chairman of EPPL and monitor the implementation of the Resolution Plan.

After the approval of the Resolution Plan, the said terms and conditions would continue to be governed strictly as per the executed documents between the Corporate Debtor and Energy Properties Pvt. Ltd or any other party. Upon approval of the Resolution Plan the said parties are required to comply with the said terms: For any breach on the part of any party, the Resolution Applicant shall have the right to seek for additional compensation, damages, loss for delay in the project, etc."

39. The MoU dated 24.01.2008 as well as Share Purchase Agreement

dated 24.01.2008 had clearly provided for transfer of 40% of shares to

Avani and 20% shares to Mr. R.L. Gaggar. Under the Share Purchase

Agreement, the Avani was entitled to nominate Director in the Energy and

nominating RP of the Avani as Independent Director was only for the

implementation of the Resolution Plan. Hence, we do not find Clause 5(j),

to be violative of any provision of the JDG.

Company Appeal (AT) (Ins.) No.326 of 2025 29

40. Last Clause, which has been questioned is Clause 5(l), which is as

follows:

"5(l) On approval of the Resolution Plan, the Corporate Debtor shall have the sole & exclusive right to bring in Joint Venture partner, raise funds or bring in investors by creating an SPV, which would hold the share of EEPL or the Corporate Debtor, as may be required towards implementation of the Resolution Plan and/or completion of the project."

41. The above Clause is also in accordance with the rights given to the

Developer in MoU and JDA. The above Clause in no manner contravenes

the provisions of JDA.

42. In view of the foregoing discussions, we answer Question Nos.(I) and

(II) in following manner:

Answer to Question No.(I) Clause 5(c), (h), (i), (j) and (l) of the Resolution Plan neither take away ownership right of the Energy, nor contravene any provisions of MoU dated 24.01.2008 and JDA dated 16.06.2008.

Answer to Question No.(II) Ownership of the Energy in the land of 10.19 acres, is not taken away under the approved Resolution Plan.

Question No.(III)

43. The submission of the Appellant is that payment as envisaged in

the Resolution Plan indicates that Resolution Plan is a contingent Plan.

Learned Counsel for the Appellant submits that significant part of the

Resolution Plan viz. Rs.17,94,27,647/- out of the proposed amount of

Company Appeal (AT) (Ins.) No.326 of 2025 30 Rs.25,11,70,194/-, are conditional and contingent upon obtaining

approvals under Fourth Schedule of the JDA, which have not been

obtained for last 17 years of the subsistence of the JDA, such contingency

in infusion of the significant funds, renders the Resolution Plan as

uncertain and does not give any concrete timeline for the implementation

of the Resolution Plan. The Resolution Plan provides for details of

amount to be provided to each stakeholders. Schedule-A of the letter

dated 20.10.2023 at page 834 of the paper book, which provides for

payment, the payment of Rs.5,24,67,647 and Rs.12,69,60,000/- have

been referred to at Item Nos.3 and 4 of the Schedule-A. The timeline for

payment is clearly mentioned. The above timeline for payments cannot be

said to be contingent or conditional. Further, in the Resolution Plan, there

is no Clause, which provides for exit of the Resolution Applicant. The

Resolution Applicant and all stakeholders are fully bound to implement

the Resolution Plan by taking substantial steps. We, thus, do not find

any such contingency in the Resolution Plan, which makes the Plan

violative of any provisions of Section 30, sub-section (2) (e) of the IBC. No

fault can be found with the Resolution Plan. Question No.(III) is answered

accordingly.

Question No.(IV)

44. With regard to eligibility of SRA, learned Counsel for the Appellant

has submitted that SRA did not fulfill the criteria of net worth, which was

necessary pre-condition to be fulfilled by a Resolution Applicant. It is

submitted that Financial Statements of the SRA for the Financial Year

Company Appeal (AT) (Ins.) No.326 of 2025 31 ended on 31.03.2023, the funds deployed by the Company was meagre

Rs.25,38,800/-. Neither, does the SRA had available cash and cash

equivalent nor it has Rs.5 crores, on its book available for deployment for

investment. Both RP and SRA have refuted the above submission and

contend that SRA fulfills the eligibility. It is submitted by Respondent

No.3 that in the Appeal, the relevant Financial Statements are there,

which were filed along with the affidavit of RP, where the RP has referred

to the eligibility criteria. It is useful to notice paragraphs 4, 5 and 6 of the

affidavit, which are as follows:

"4. I state that as per the Invitation for Expression of Interest a 'corporate applicant' having a Net Worth of Rs. 3 crores (Rupees Three Crores Only) or above can participate in the bidding process. Moreso, for a corporate applicant being an NBFC would also be eligible as per the additional criterion that had also been laid in the Invitation of EOI, which ahs been stated below:

For Financial Institutions/ Investment Companies/ Fund Houses/ PE Investors/NBFCs/ ARC or any other applicant: Minimum Asset Under Management (AUM) or funds deployed of Rs.5 Crores in the immediately preceding completed financial year or Committed funds available for investment/ deployment in Indian companies or Indian assets of Rs.5 Crore in the immediately preceding completed financial year.

A copy of the Invitation for expression of interest has already been annexed to the Rejoinder filed by the Applicant at pages14-39 marked as Annexure A.

5. It will be evident from the audited financial statement of Chiminare Tradecomm Private Limited for the financial year ended at 31st March, 2023 that the Net Worth of Chiminare as on 31st March.2022 is Rs.4,64,64,176/- and as on 31st

Company Appeal (AT) (Ins.) No.326 of 2025 32 March, 2023 is Rs. 4,74,56,200/-, which is over and above the minimum criteria of Rs. 3 crores stipulated for a 'corporate applicant.' A copy of the financial statement of Chiminare has already been annexed to the Rejoinder filed by the Applicant at pages 40-61 marked as Annexure B and the Balance Sheet is annexed at page 46 of the Rejoinder.

6. Moreover, considering that Chiminare is a Non-banking Financial Institution, it also fulfils the additional criteria of having committed funds available for investment/ deployment in Indian companies or Indian assets of Rs. 5 Crore in the immediately preceding completed financial year."

45. The affidavit was filed by the RP, justifying the eligibility criteria,

where referring to the balance sheet, the RP has stated that SRA meet the

criteria of funds deployed of Rs.5 crores in the immediately preceding

completed financial year. In paragraph-7 of the affidavit, following has

been stated:

"7. Additionally, Chiminare also meets the criteria of funds deployed of Rs.5 Crores in the immediately completed financial year and the same would be evident from the Balance Sheet of Chimmare for the financial-year 2022-23 [@ pg. 46 of the Rejoinder Affidavit] wherein the funds deployed (only considering current assets) is Rs.11,17,570,00 for the Financial year ending 31.03.2022 and Rs.11,47,923,00/- for the Financial year ending 31.03.2023."

46. The Financial Statements of the SRA were on the record before the

Adjudicating Authority and RP referring to the Financial Statements has

filed the affidavit, giving relevant figures to support the contention that

the SRA fulfilled the eligibility criteria.

Company Appeal (AT) (Ins.) No.326 of 2025 33

47. In view of the foregoing discussions, we answer Question No.(IV)

holding that SRA has fulfilled the eligibility criteria for a Resolution

Applicant.

48. In view of our foregoing discussions and conclusions, we do not find

any error in the order of the Adjudicating Authority dated 03.01.2025

rejecting I.A. (IB) No.1332/KB/2024, which was filed by the Appellant.

There is no merit in the Appeal. The Appeal is dismissed. There shall be

no order as to costs.

[Justice Ashok Bhushan] Chairperson

[Barun Mitra] Member (Technical)

NEW DELHI

29th August, 2025

Ashwani

Company Appeal (AT) (Ins.) No.326 of 2025 34

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free