Battula Anjaneyulu vs Dbm Geotechnics & Construction Pvt Ltd
- CitationCompany Appeal (AT) (Insolvency)No. 261 of 2019
Ratio decidendi
The rule this decision rests on
Where a corporate debtor, in response to a demand notice under section 8 of the Insolvency and Bankruptcy Code, has notice before the demand notice issues of a dispute concerning the work for which payment is claimed, including the imposition of penalties and adverse action taken under the principal contract, a pre-existing dispute exists within the meaning of the Code, and an application under section 9 is liable to be rejected on that ground.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
[Arising out of Order dated 20th December, 2018 passed by the Adjudicating Authority (National Company Law Tribunal) Mumbai Bench in the Company Petition (Insolvency & Bankruptcy) No. 1282 of 2017].
IN THE MATTER OF: Mr. Battula Anjaneyulu .....Appellant Vs. DBM Geotechnics & Constructions Pvt. Ltd. ......Respondent
Present : For Appellant: Mr. Gautam Ankhad, Mr. Murtaza Kachwalla, Mr. Ashdin Chivalwala, Mr. B. Anjaneyulu, Ms. Amrita Sarkar, Ms. Nimita Kaul and Ms. Ekta Bhasin, Advocates For Respondents: Mr. Aditya, Advocate
J U D G M E N T
SUDHANSU JYOTI MUKHOPADHAYA, J.
1. The present Appeal challenges the impugned order dated 20th December,
2018 passed by the Adjudicating Authority, Mumbai rejecting the petition filed
by Appellant under section 9 of the Insolvency and Bankruptcy Code by the
Appellant against the Respondent.
....contd./
2. Learned Counsel for the Appellant submitted that the Impugned Order
ought to be set aside as it has erroneously held that there were pre-existing
disputes between the parties. On the contrary, the facts demonstrate no such
pre-existing dispute and the Respondent sought to raise a false bogey only after
service of the demand notices dated 10th May, 2017 on them.
3. The case of the Appellant is that the Respondent issued various work
orders to the Appellant for carrying out different kinds of work such as marine
piling, labour supply, anchor-wall chipping, cage fabrication, etc. The Appellant
raised R.A. bills and invoices. Part payments were made from time to time by
the Respondent for the work carried out. Out of the total amount of about Rs.
43 crores worth of work done, approximately Rs. 28 crores were paid over a
period of time and there remained a pending amount of Rs. 14,62,18,995/-.
4. He further stated that the Respondent from time to time reassured the
Appellant that the payments would be released. The Respondent by emails
dated 8th May, 2012 and 26th December, 2014 admitted that they are in
financial difficulty and that amounts are due and payable to the Appellant. The
relevant portion of the emails dated 8th May, 2012 and 25th December, 2014 are
quoted below respectively.
E.mail dated 8th May, 2012 : -
"Dear Anjaneyulu,
Company Appeal (AT) (Insolvency)No. 261 of 2019 2 We really regret the delay in your payment..
We could not pay you last week due to cash flow problem..
But We are trying to pay you this week.."
Email dated 25th December, 2014:
"We are aware with the situation of
Agardanda as you have not received
the committed payment from DPL. We
wish to inform you we trying our best
to release the part payment to you".
5. It is stated that repeated reminders were sent by the Appellant to
the Respondent on 8th January, 2013, 8th April, 2013, 18th June, 2013 and
8th July 2013. There was no denial of liability nor did the Respondent raise
any dispute on quality or quantity.
6. It is stated that as no payment was forthcoming 13 demand notices
(Form 3) were issued to the Respondent on 10th May, 2017. Out of the total
13 demand notices issued, the present petition was filed for 6 demand
notices for a total amount of Rs. 14,62,18,995/-. The said demand notices
were duly received by the Respondent on 12th May, 2017.
Company Appeal (AT) (Insolvency)No. 261 of 2019 3
7. It is alleged that as a counter blast, the Respondent after receipt of
the demand notices on 12th May, 2017, with the sole intention to defeat and
dislodge the legitimate claim of the Appellant, filed Summary Suit No. 297 of
2017 on 17th May, 2017 before the Hon'ble High Court at Bombay and
thereafter responded to the demand notices vide their Advocates letter dated
22nd May, 2017 disputing the amounts demanded on false, frivolous and
baseless grounds. Vide order dated 10th October, 2017 unconditional leave
to defend was granted to the Appellant by the Hon'ble High Court at Bombay.
8. He further stated that the Respondent has acknowledged the work
of the Appellant and has issued work completion certificates. The
Respondent has made part payments as late as 17th March, 2015 and has
deducted TDS @ 1% for the entire amounts billed. The claim is therefore
within limitation.
9. According to Learned Counsel, the following facts shows that there
is no dispute about the work of the Appellant.
a. Admitted financial difficulties in its emails
dated 8th May, 2012 and 25th December, 2014
and that amounts are due and payable to the
Appellant (Ground Z);
b. Made part payments from time to time;
Company Appeal (AT) (Insolvency)No. 261 of 2019 4 c. Issued work completion certificates (See Ground
EE);
d. Deducted 1% TDS on the amounts billed by the
Appellant (Ground AA);
e. Gave additional contracts to the Appellant
every year from time to time;
f. Has never communicated any grievances
contemporaneously until the issuance of the
demand notices (Ground CC & KK).
10. The case of the Respondent is that it awarded the sub-contract
mainly for the labour works (for pilling work, deck structure work, etc.) to the
Appellant, on back to back basis. The terms of the Principal Contracts, inter
alia including specifications, time frames, penalties and liquidated damages
were applicable to the Sub Contracts.
11. It is also submitted that the Appellant while executing the works
under the Sub-Contracts, consistently failed to maintain the desired progress
of the works. The predominant reasons of its failures of the Appellant were (a)
inadequate deployment of the resources, (b) unsatisfactory and faulty quality
of the resources (i.e. equipment and manpower), (c) deployment of
inappropriate and improper methods for execution of the work, and (d)
abandoning the Sub Contract works.
Company Appeal (AT) (Insolvency)No. 261 of 2019 5
12. It is submitted that as a result of the failures by the Appellant, the
completion periods of the projects were prolonged, which attracted the
imposition of the liquidated damages, termination, forfeiture of security
deposits, earnest money, balance payments, invocation of the bank
guarantees, blacklisting, banning etc.
13. It is further submitted that the Respondent brought to the notices
of the Appellant the adverse actions being taken by the Clients from time to
time. The Appellant was therefore fully aware of the imposition of penalty
and damages by the Client and liability of the Appellant towards the same.
14. It is also submitted that the termination of the main / principal
contact led to automatic terminations of the sub-contact which were back to
back to the main contract.
15. Learned counsel for the Respondent submitted that the Respondent
called upon the appellant to make good the losses suffered by it for the
reasons attributable to the Appellant; the Appellant was not forthcoming for
making good the losses despite various request and reminders; therefore, the
Respondent contemplated filing a suit before Bombay High Court and thus
instructed their solicitors. The various emails including emails dated
Company Appeal (AT) (Insolvency)No. 261 of 2019 6 03.04.2017, 05.05.2017 and 9.05.2017 exchanged in this regards which are
prior to issuance of Demand Notice dated 10.05.2017.
16. Therefore, it is stated, it can be concluded that though the
Respondent filed the Summary suit before the Hon'ble Bombay High Court
on 16.05.2017, the preparation for the legal suit was commenced much prior
to issuance of Demand Notices and the disputes were in existence much
prior to the filing of the suit.
17. It is further contended that the Respondent also categorically
conveyed in its reply dated 22.05.2017 that the Respondent has already filed
the Summary Suit on 16.05.2017 before the Hon'ble Bombay High Court.
18. Learned counsel appearing on behalf of the Respondent referring to
the Demand Notice also submitted that the claim is barred by limitation,
therefore, no debt is payable. However, we are not deciding such issue as the
Suit is pending before the Bombay High Court.
19. From the submission made by the parties, emails and
communications, we find that there is a pre-existing dispute about the work
which were brought to the notice of the Appellant prior to the Demand Notice
dated 10.05.2017. The emails dated 03.04.2017, 05.05.2017 and 09.05.2017
Company Appeal (AT) (Insolvency)No. 261 of 2019 7 is by the Respondent taking step for award for imposition of penalty for
damage and having taken adverse action has also not been disputed. We
find, no merit in this appeal. It is accordingly dismissed. No costs.
[Justice S. J. Mukhopadhaya] Chairperson
[Justice A. I. S. Cheema] Member (Judicial)
[Kanthi Narahari] Member (Technical)
New Delhi
2nd July, 2019
ss
Company Appeal (AT) (Insolvency)No. 261 of 2019 8
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free