Asgi Properties Private Limited vs Rajesh Ramnani& Anr
- CitationCompany Appeal (AT) (Insolvency) No. 1921 of 2024
Ratio decidendi
The rule this decision rests on
The Adjudicating Authority does not err in rejecting an application seeking directions to renew an expired building map approval and to complete external infrastructure work where the approval has already lapsed and renewal proceedings before the municipal authority remain pending; in such circumstances the relief sought is not available from the Adjudicating Authority at this stage. Where a Resolution Plan has been submitted and approved and is pending consideration before the Adjudicating Authority, the appellant's remedy in respect of any subsequent renewal or revalidation of the plans by the development authority lies in the liberty to pursue such remedy as is available in law, and no direction on that question is given at this stage.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
IN THE MATTER OF: ASGI Properties Pvt. Ltd. ...Appellant Versus Rajesh Ramani & Anr. ...Respondents
Present: For Appellant : Mr. P. Nagesh, Sr. Advocate with Mr. Akshay Sharma, Advocates.
For Respondents : Mr. Shivanshu Kumar and Mr. Rajesh Ramani, Advocates for RP.
Ms. Anuja Pethia, Ms. Noor Shergill and Mr. Rishabh Govila, Advocates for SRA.
ORDER
(Hybrid Mode)
11.12.2024 : This Appeal has been filed challenging the Order dated
07.08.2024, by which I.A. filed by the Appellant being I.A. 6586/2023 has
been rejected.
2. In the IA, Appellant has made prayers, which has been quoted by the
Adjudicating Authority in Para 1 of the Impugned Order. Para 1 of the
Impugned Order is as follows:
"i. To allow the present application. ii. To direct the Respondent to take steps to renew the expired map approval of the "Sushant Aquapolis"
Project of Corporate Debtor;
iii. To direct the Respondent to complete the external infrastructure work of the Tower S2A & S2B OR iv. Alternatively, to allow the Applicant to complete the external infrastructure work of the Tower S2A & S2B under supervision of RP subject to adjustment of cost against the pending dues.
v. Pass any other direction/order which this Hon'ble Tribunal may deem fit in the larger interest of justice."
3. The prayers which has been made by the Appellant itself indicates that
the approval of the map has already expired and the renewal is sought.
4. Counsel for the Resolution Professional (RP) submits that the
proceedings before the Ghaziabad Development Authority (GDA) in pursuance
of the Order 22.04.2024 passed by this Tribunal are still pending
consideration and map has not yet been renewed.
5. We are of the view that no error has been committed by the Adjudicating
Authority in rejecting the Application in the facts and situation. Adjudicating
Authority has also noted that Resolution Plan submitted by SRA has been
approved and it is pending consideration before the Adjudicating Authority.
We only observe that in event, the Plans are renewed by the GDA or
revalidated, Appellant shall be at liberty to take such remedy as available in
law.
With these observations, we dismiss the Appeal.
Learned Counsel for the RP submits that Appellants are bound by the
terms of the Memorandum of Understanding (MoU).
[Justice Ashok Bhushan] Chairperson
[Barun Mitra] Member (Technical)
[Arun Baroka] Member (Technical) himanshu/nn
Comp. App. (AT) (Ins.) No. 1921 of 2024 & I.A. No. 7107 of 2024 2 of 2
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.