Approval of Resolution Plan - Sandwoods Infratech Projects Pvt. Ltd.
- CitationIA-2414-2022 in Company Petition No. IB-292(ND)-2021
Ratio decidendi
The rule this decision rests on
The Adjudicating Authority's scrutiny of a resolution plan under Section 31 read with Section 30(2) of the Insolvency and Bankruptcy Code is confined to the matters specified in Section 30(2): whether the plan provides for payment of insolvency resolution process costs in priority to other debts, for repayment of operational creditors in the prescribed manner, for management of the corporate debtor's affairs and for implementation and supervision of the plan, whether it contravenes any law for the time being in force, and whether it conforms to such other requirements as the Board may specify. The Authority has no jurisdiction to examine the commercial wisdom of the Committee of Creditors in approving a plan, which lies within the domain of the financial creditors voting under Section 30(4), and it cannot venture into the commercial aspects of those decisions. Where a resolution plan purports to waive statutory obligations or liabilities, such a waiver does not operate by the approval of the plan alone; it is subject to approval by the concerned statutory authorities, and the statutory dues are to be dealt with in accordance with the relevant laws.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
Order pronounced in open court vide separate sheets. IA-2414/2022 in IB-292(ND)/2021is allowed.
Sd/- Sd/- (ATUL CHATURVEDI) (BACHU VENKAT BALARAM DAS) MEMBER (TECHNICAL) MEMBER (JUDICIAL)
IN THE NATIONAL COMPANY LAW TRIBUNAL NEW DELHI (COURT III) IA-2414/2022 In Company Petition No. IB-292(ND)/2021 Under Section 30(6) & 31 of IBC r/w Regulation 39(4) of CIRP Regulations 2016. IN THE MATTER OF:- Mr. Balaji Durobuild Pvt. Ltd …….Applicant/Operational Creditor Versus Sandwoods Infratech Projects Pvt. Ltd. …….Respondent/Corporate Debtor AND IN THE MATTER OF:- Mr. Ravinder Kumar Goel …….Resolution Professional/Applicant
Pronounced on 10.08.2023 CORAM:- SHRI ATUL CHATURVEDI SHRI BACHU VENKAT BALARAM DAS MEMBER (TECHNICAL) MEMBER (JUDICIAL) PRESENT:- For the Applicant : Mr. Sourabh Kalia, Advocate for RP For the Respondent : ORDER Per Shri BachuVenkat Balaram Das, Member (J) 1. This application has been filed by the Resolution Professional of the Corporate Debtor seeking approval of the Resolution Plan submitted by D Konda (Successful Resolution Applicant) under Section 30(6) r/w 31(1) of IBC 2016 r/w Regulation 39(4) of CIRP Regulations, 2016. The facts of the case are as under:- (a) The Company Petition i.e. IB-292/ND/ 2021 was filed by M/s Balaji Durobuild Private Limited, the Operational Creditor seeking initiation of IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023
CIRP against M/s Sandwoods Infratech Projects Private Limited, the Corporate Debtor herein. (b) This Adjudicating Authority vide order dated 25.10.2021 initiated CIRP of the Corporate Debtor and appointed Mr. Ravinder Kumar Goyal, as Interim Resolution Professional. (c) Mr. Ravindra Kumar Goyal, the Interim Resolution Professional (hereinafter after referred to as IRP) took necessary steps as provided in the Code for publication of “Form A” calling for submission of claims from the creditors, workers and employee and other stakeholders of the Corporate Debtor. Pursuant to the public announcement, the IRP received several claims from various stakeholders of the Corporate Debtor. (d) Accordingly, the Resolution Professional constituted the Committee of Creditors as envisaged under Section 21 of the Code. The list of CoC members along with their respective voting share as on the date of filing of this application is as under:
(e) The 1st meeting of Committee of Creditors was held on 24.11.2021 and Shri Ravinder Kumar Goyal, the IRP was confirmed as the Resolution Professional and the same was approved by this Tribunal vide order dated 16.12.2021.
IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023 (f) The 3rd meeting of the Committee of Creditors was held on 01.01.2022, the Resolution with respect to publication of Form G, Information Memorandum (IM), eligibility criteria of Resolution Applicant, evaluation matrix and performance security of Resolution Applicant were finalized and approved by the members of CoC. (g) The Applicant published Form G as per Regulation 36A (1) of the Insolvency and Bankruptcy (Insolvency Resolution Process for Corporate Persons) Regulations, 2016 on 07.01.2022 and the last date of submission of Expression of Interest was 13.03.2022 which was subsequently extended to 27.03.2022 by CoC. (h) The total number of Expression of Interest (EoIs) received was 5 and the IRP finalized the list of Prospective Resolution Applicants who had submitted their eligibility documents along with their respective EOIs. (i) On 13.03.2022, D Konda submitted its Resolution Plan within the timeline of RFRP and on 12.03.2022, the Resolution Professional received a request from Mr. Sumit Kumar Khanna one of the PRA (s) to extend the time for submission of plan by two weeks. (j) The CoC in its 4th meeting held on 17.03.2022 extended the last date for submission of Resolution Plan to 27.03.2022. (k) In view of the extension of the last date for submission of the Resolution Plan a proposal for extension of CIRP period by 90 days was moved by the Resolution Professional which was granted by the CoC with 100% voting shares. Subsequently, an application seeking extension of CIRP was filed before this Adjudicating Authority and the extension was granted vide order dated 24.05.2022. (l) In the 5th meeting of the Committee of Creditors discussion on Resolution Plan submitted by D Konda was held and the fair and Liquidation value was shared with all members of CoC subject to furnishing of confidentiality undertaking. (m) In the 6th meeting of the CoC which was held on 04.05.2022, the RP placed before the CoC Resolution Plan as submitted by D Konda. IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023
Subsequently, the Resolution Plan was presented for voting and was approved by the members of CoC by 71.75% voting shares. One of the Financial Creditors i.e. Punjab National Bank holding 17.80% shares abstained from voting. (n) The Applicant/Resolution Professional has stated that a total of Six (6) COC meetings were held as on the date of filing of the present application which are as under:
(o) That 6 valuers (two valuers for each class of asset) were appointed as per the provisions of Regulation 27 of CIRP Regulations, 2016 to determine the Fair Value and Liquidation Value of the Corporate Debtor in accordance with Regulation 35 of CIRP Regulations, 2016. (p) The average of two estimates each of Land and Building, Securities or Financial Assets and Plant & Machinery are as under:
IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023 (q) The Resolution Professional further submitted that M/s. AKG & Associates, Chartered Accountants was appointed as transaction/forensic auditor to identify the transactions, if any under the following;- (a) Preferential transactions under section 43; (b) Undervalued transactions under section 45; (c) Extortionate credit transactions under section 50; and (d) Fraudulent transactions under section 66. The transaction auditor in his report has not reported any transaction covered under Section 43, 45, 50, 66 of IBC, 2016. (r) The Successful Resolution Applicant i.e., D Konda submitted an affidavit of eligibility under Section 29A of the Code. (s) The Resolution Professional has submitted that the Resolution Plan complaint in terms of Section 30(2) IBC and Regulation 37 and Regulation 38 of the CIRP Regulations, 2016. CONTENT OF RESOLUTION PLAN
Particulars of Payments under Resolution Plan- Rs. In Lacs
S. Particular Claim Proposed % of Payment No Admitted Amount in Claim Term Resolution Admitted Plan 1. Insolvency N/a 1,10,00,000 100% 100% within Resolution (Approx.) 30 days Process Cost However if this figure increase, then RA will also IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023 pay. 2. Workmen/ 9,31,344.22 9,31,344.22 100% Payment Term Employees * 100 % within 30 days of completion of both the project 3. Financial 40,89,27,52 1,50,00,000 3.67% Payment Term Creditors 4.74 * 100 % within (secured) 3 month of completion of both the project. Payment to dissenting creditor is more than their share of liquidation value under section 53 of IBC. 4. Financial 108642792 NA NA (RA proposing Creditors 8.21 (RA to complete (Unsecured)(Ho proposing both the me Buyers) to complete projects at both the Mohali projects at (Landran) & Mohali Kasauli within (Landran) & 9 month of IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023
Kasauli as approval of per the Plan by AA as approved per the Plans) approved without any Plans) without escalation any escalation.(Par a 13 of Plan) 5. Financial 157494870. 3200000 2.03% Payment Term Creditors 74 * 100 % within (Unsecured 90 days Related party) 6. Operational 35255433.7 710000 2.01% Payment Term Creditors 0 * 100 % within 30 days of completion of both the project 7. Operational 0 0 NA Creditor- Government Dues 8. Other 0 0 NA Payment Term Creditors * 100 % within 90 days
Implementation of Projects of the Corporate Debtor
The Corporate Debtor has 2 projects:
IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023 a) Mohali (Landran) Project- It is a residential project consisting of 10(Ten) Towers consisting of 394 flats & 5 shops out of which 7 towers are completed in all respects & construction work is going on with respect to balance 3 towers. Around 200 families are residing.
b) Kasauli Project- It is a residential project consisting of Flats(40 in number) & Villas(10 in numbers). Construction of villas are completed and for flats only internal work pending. As per IM, out of total 449 owners of Flats, Shops and Villas at both the projects, only 269 homebuyers have filled their claims with RP. However, the RA is proposing to complete both the projects at Mohali (Landran) & Kasauli within 9 month from the date of approval of Plan by AA for all the homebuyers whether they have filled their claims or not. Both the projects would be completed out of amount receivable from all Homebuyers and from sale proceeds of unsold flats of the project without any cost escalation.(Para 13 of Plan at page 137 of Application). No amount would be payable to any homebuyer as specified below:
(i) As per the agreement to sell executed by corporate debtor with various homebuyers, there is a clause for payment of penalty amount @ Rs. 5 per square feet per month for delayed period after 36 month plus grace period of 6 month. (ii) The Corporate debtor may have made some other commitments to some Homebuyers to compensate them for delay in project like assured return, pre-EMI interest or assured rent etc. The RA has proposed that no such penalties/compensation for delayed construction would be paid to any homebuyers since the RA is proposing to complete both the project as per approved plan which would be a very herculean task considering substantial increase during last 5 years in prices of various inputs/materials required for completion of the projects. All facilities as IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023 proposed in approved plan would be provided in both the projects. Further as the projects have to be completed out of the funds received from the Homebuyers, so it is pre-requisite that these funds should be paid by the Homebuyers in agreed timelines. In case of default RA shall be at liberty to cancel the allotment of the defaulter and forfeit 25% of the BSP amount and to allot the flat to a new buyer. The balance due if any of the existing homebuyers shall be repaid after the completion of the project along with the Financial Creditors. Any and all rights and entitlements of any actual or potential unsecured financial creditors of the Corporate Debtor not addressed in Clause 6.7, whether admitted or not, due or contingent, asserted or un-asserted, crystallised or un-crystallised, known or unknown, disputed or undisputed, present or future, in relation to any period prior to the acquisition of control by the Resolution Applicant over the Corporate Debtor pursuant to this Resolution Plan or arising on account of the acquisition of control by the Resolution Applicant over the Corporate Debtor pursuant to this Resolution Plan, shall stand permanently extinguished and the Corporate Debtor or the Resolution Applicant shall at no point of time, directly or indirectly, have any obligation, liability or duty in relation thereto.
Mohali (Landran) Project:
As per the information gathered during site visits and discussion with RP, as per the approved plan and brochure of project, CD has to provide facilities of modular kitchen, Geyser in all bathrooms, one RO and one Chimney in kitchen. Since the projects is to be completed in a time bound period and also due to varied preferences of homebuyers for these appliances, RA has proposed to deduct Rs. 80000/- (Rupees Eighty thousand only ) in lieu of these facilities, from the sale price of flat at the time of full and final payment. IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023
Kasauli Project:
As per IM, the owner of land of this project is Mrs. Uma Bagolia and all licences/permissions are in her name as, she being Himachali and CD was working as developer of this project. The Resolution Applicant will also be completing this project as developer and all legal requirements like obtaining permission from State Government under section 118 of HP Tenancy and Land Reforms Act, 1972, execution of sale deeds in favour of homebuyers, will be done by Mrs. Uma Bagolia. As per the due diligence by RA and information in IM, the total approximate expense to be incurred for completion of this project would be about Rs. 5 Crore and balance funds to be received from homebuyers of Villas and Flats is also about Rs. 5 Crore. Though no tangible gain is expected by working on this project, the RA want to complete this project also in order to full fill all the liabilities and commitments of the CD.
Supervision & Management- Para-14 of Resolution Plan provides a committee consisting of 3 members namely, the Resolution Professional (Subject to consent by Resolution Professional) or any other experienced professional, One nominee of Homebuyers and Resolution Applicant or nominees of the Resolution Applicant (“Monitoring Committee”) which will supervise the Corporate Debtor during the Interim Period. The Monitoring Committee will oversee the effective implementation of the Resolution Plan under its supervision, until the completion date
Mandatory Content of Resolution Plan
Claus e. No. Description/Requirement Details/how Dealt within the Resolution Plan IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023
As set out in Section 30 (2) of the Code, 2016 a) Plan must provide for Para 6.1 at page payment of CIRP cost in No.19 of the priority to repayment of Resolution Plan( other debts of CD in the Page 114 of App) manner specified by the Board. b) i) Plan must provide for i) Para 6.3 at page repayment of debts of OCs No.20 of the in such manner as may be Resolution Plan. ( specified by the Board Page 115 of App) which shall not be less than the amount payable to them in the event of liquidation u/s 53; or ii) Plan must provide for repayment of debts of OCs ii) Para 6.3 at page in such manner as may be No.20 of the specified by the Board Resolution Plan. ( which shall not be not less Page 115 of App) than amount that would have been paid to such creditors, if the amount to be distributed under the resolution plan had been distributed in accordance with the order of priority in sub-section (1) of section 53, whichever is higher
IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023 and iii) Provides for payment of iii) Payment of debts of financial creditors financial creditor who do not vote in favour shall be made within of the resolution plan, in 3 month of such manner as may be competition of both specified by the Board. the projects. Payment to dissenting creditor is more than their share of liquidation value under section 53 of IBC. c) Management of the affairs Para 15 at page No. of the Corporate Debtor 43 of the Resolution after approval of the Plan. ( Resolution Plan. App) d) Implementation and Para 14 at page No. Supervision 42 of the Resolution Plan. ( App) e) Plan does not contravene Para 29(i)(6) at page any of the Provisions of the No. 56 of the law for the time being in Resolution Plan.( force. Page 151 of App) (Undertaking at page 184 of App) f) Conforms to such other Para 29(i)(7) at page requirements as maybe No. 56 of the IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023 specified by the Board. Resolution Plan. (Page 151 of App) Mandatory contents of Resolution Plan in terms of Regulation 38 of CIRP Regulations 38(1) The amount due to the Para 6.3 at page operational creditors under No.20 of the a resolution plan shall be Resolution Plan. ( given priority in payment Page 115 of App) over financial creditors 38(1A) A resolution plan shall Para 7 at page No. include a Statement as to 34 of the Resolution how it has dealt with the Plan. ( interests of all App) stakeholders, including financial creditors and operational creditors of the corporate debtor. 38(1B) A resolution plan shall Declaration in include a statement giving Appendix-8 of the details if the resolution Resolution Plan( applicant or any of its Page 184 of App) related parties has failed to implement or contributed to the failure of Implementation of any other resolution plan approved by the Adjudicating Authority at any time in the past. 38(2) A resolution plan shall Para 16 at page No.
IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023 provide: 43 of the Resolution (a) the term of the plan and Plan. ( its implementation App) schedule; (b) the management and Para 15 at page No. control of the business of 43 of the Resolution the corporate debtor Plan. ( during its term; and App) c) adequate means for Para 14 at page No. supervising its 42 of the Resolution implementation. Plan. ( App) 38(3) A resolution plan shall Clause-13 & demonstrate that: Schedule 4, Cause of (a) it addresses the Default-Clause 13 & cause of default; 14 ( (b) it is feasible and App) viable; (c) it has provisions for No specific approval its effective has been sought in implementation; the plan. However (d) it has provisions for licenses required in approvals required the normal course of and the timeline for business is the same; and (e) mentioned in the Resolution Schedule 5 Schedule Applicant has the 2, 3 & 4 capability to implement Measures required for implementation of the Resolution Plan in IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023 terms of regulation 37 of CIRP Regulations: The Resolution Plan provides for the measures, as may be necessary, for insolvency resolution of the Company for maximization of value of its assets, including but not limited to the following: i. Any proposal on Regulation-37(a) Not proposed by transfer of all or of CIRP SRA part of the assets Regulations of the corporate debtor to one or more persons. ii. Any proposed Regulation 37 (b) Not proposed by sale of all or part of CIRP SRA of the assets Regulations whether subject to any security interest or not. iii. Any proposed Regulation 37(c) Not proposed by substantial of CIRP SRA acquisition of Regulations shares of the corporate debtor or the merger or consolidation of the corporate debtor with one or more persons iv. Any proposed Regulation 37(ca) Not proposed by cancellation of of CIRP SRA any shares of the Regulations
IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023 corporate debtor, v. Any proposed Regulation37 (e) Not provided by curing or waiving of CIRP SRA of any breach of Regulations the terms of any debt due from the Corporate Debtor. v. Any proposed Regulation 37 (f) Amount paid to reduction in the of CIRP all stakeholders amount payable Regulations is given in to the creditors Clause-7 (Page 129 of App) vi. Any proposed Regulation 37 (g) Not proposed by extension of of CIRP SRA maturity date or Regulations a change in interest rate or other terms of a debt due from the corporate debtor; vii. Any proposed Regulation37 (h) Not proposed by amendment of of CIRP SRA the constitutional Regulations documents of the corporate debtor; viii. Any proposed Regulation 37 (i) Not proposed by issuance of of CIRP SRA securities of the Regulations
IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023
Company, for cash, property, securities, or in exchange for claims or interests, or other Appropriate purpose; ix. Any proposed Regulation 37 (j) Not proposed by change in of CIRP SRA portfolio of goods Regulations or services produced or rendered by the corporate Debtor x. Any proposed Regulation37 (k) Not proposed by change in of CIRP SRA technology used Regulations by the corporate debtor. xi. List and status of Regulation 37 (l) Schedule-5 & necessary of CIRP Schdule-6 of the approvals from Regulations Plan. (Page 166 the Central/State & 167 of App) Governments and other Authorities
2. In so far as the approval of the resolution plan is concerned, this Adjudicating Authority follows the judgement of the Hon’ble Supreme IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023
Court in the matter of K.Sashidhar v. Indian Overseas Bank (2019) 12 CC 150, wherein the scope and interference of the Adjudicating Authority in the process of the approval of the Resolution Plan is elaborated as follow:-
35. Whereas, the discretion of the adjudicating authority (NCLT) is circumscribed by Section 31 limited to scrutiny of the resolution plan “as approved” by the requisite percent of voting share of financial creditors. Even in that enquiry, the grounds on which the adjudicating authority can reject the resolution plan is in reference to matters specified in Section 30(2), when the resolution plan does not conform to the stated requirements. Reverting to Section 30(2), the enquiry to be done is in respect of whether the resolution plan provides : (i) the payment of insolvency resolution process costs in a specified manner in priority to the repayment of other debts of the corporate debtor, (ii) the repayment of the debts of operational creditors in prescribed manner, (iii) the management of the affairs of the corporate debtor, (iv) the implementation and supervision of the resolution plan, (v) does not contravene any of the provisions of the law for the time being in force, (vi) conforms to such other requirements as may be specified by the Board. The Board referred to is established under Section 188 of the I&B Code.
The powers and functions of the Board have been delineated in Section 196 of the I&B Code. None of the specified functions of the Board, directly or indirectly, pertain to regulating the manner in which the financial creditors ought to or ought not to exercise their commercial wisdom during the voting on the resolution plan under Section 30(4) of the I&B Code. The subjective satisfaction of the financial creditors at the time of voting is bound to be a mixed baggage of variety of factors. To wit, the feasibility and viability of the proposed resolution plan and including their perceptions about the general capability of the resolution applicant to translate the projected plan into a reality. The resolution applicant may have given projections backed by normative IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023 data but still in the opinion of the dissenting financial creditors, it would not be free from being speculative. These aspects are completely within the domain of the financial creditors who are called upon to vote on the resolution plan under Section 30(4) of the I&B Code.
3. Also the Hon’ble Supreme Court of India in the matter of Committee of Creditors of Essar Steel India Limited vs. Satish Kumar Gupta & Ors., Civil Appeal No. 8766-67 of 2019, vid its judgement dated 15.11.2019 has observed as follows: “38. This Regulation fleshes out Section 30(4) of the Code, making it clear that ultimately it is the commercial wisdom of the Committee of Creditors which operates to approve what is deemed by a majority of such creditors to be the best resolution plan, which is finally accepted after negotiation of its terms by such Committee with prospective resolution applicants.” 4. Thus, from the judgements cited supra, it is amply clear that only limited judicial review is available to the Adjudicating Authority under Section 30(2) read with Section 31 of the Code, 2016 and this Adjudicating Authority cannot venture into the commercial aspects of the decisions taken by the committee of the creditors. 5. Therefore, in our considered view, there is no impediment in giving approval to the Resolution Plan. Accordingly, we hereby approve the Resolution Plan, which shall be binding on the corporate debtor and its employees, shareholders of corporate debtor, creditors including the Central Government, any State Government or any local authority to whom statutory dues are owed, guarantors, successful resolution applicant and other stakeholders involved.
In view of the above, I.A. 2414/ND/2022 stands allowed. 6. It is declared that the moratorium order passed by this Adjudicating Authority under Section 14 of the Code shall cease to have effect from the date of pronouncement of this order. 7. However, the resolution plan shall not construe any waiver to any statutory obligations/liabilities arising out of the approved resolution plan and the IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023 same shall be dealt in accordance with the appropriate authoritiesconcerned as per relevant laws. We are of the considered view that if any waiver is sought in the resolution plan, the same shall be subject to approval by the concerned authorities. The same view has been held by the Hon’ble Supreme Court in Ghanshyam Mishra and Sons Private Limited vs. Edelweiss Asset Reconstruction Company Limited and Embassy Property Development case (supra). 8. Accordingly, MoA and AoA of the corporate debtor shall be amended and filed with the RoC for information and record as prescribed. While approving the ‘resolution plan’ as mentioned above, it is clarified that the resolution applicant shall pursuant to the resolution plan approved under section 31(1) of the Code, 2016, obtain all the necessary approvals as may be required under any law for the time being in force within the period as provided for such in law.
9. The Resolution Professional shall forward all records relating to the Corporate Insolvency Resolution Process of the corporate debtor and the Resolution Plan to IBBI to be recorded at its database in terms of Section 31(3)(b) of the Code. The Resolution Professional is further directed to handover all the records, premises, properties of the corporate debtor to the Successful Resolution Applicant to ensure a smooth implementation of the resolution plan. 10. The approved ‘Resolution Plan’ shall become effective from the date of passing of this order. The Approved Resolution Plan shall be part of this order. 11. Let the copy of the order be served to the parties.
Sd/- Sd/- (ATUL CHATURVEDI) (BACHU VENKAT BALARAM DAS) MEMBER (TECHNICAL) MEMBER (JUDICIAL)
IA-2414/2022 in IB-292(ND)/2021 Date of Order: 10.08:2023
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free