Amit Chaturvedi vs Stressed Assets Stabilization Fund
- CitationCOMPANY APPEAL (AT)(INSOLVENCY) NO.1715 OF 2024
Ratio decidendi
The rule this decision rests on
Where a scheme of arrangement under Sections 391–394 of the Companies Act, 1956 has been sanctioned by the High Court before a Section 7 petition under the Insolvency and Bankruptcy Code, 2016 is admitted, the Adjudicating Authority should not admit the petition on the strength of an alleged default while the sanctioned scheme subsists; a sanctioned scheme is binding on all creditors, including the financial creditor, and has the force of a judgment in rem, and a creditor who has consented to it cannot resile from it. Because the word "may" in Section 7 makes admission discretionary, the Adjudicating Authority, where a challenge to the sanctioned scheme or to the withdrawal of consent is pending before the High Court, should keep the admission in abeyance until that challenge is decided, and must consider afresh the petition in the light of that decision rather than admit it on the existing record. A petitioning creditor who relies on a Section 7 petition must disclose the existence of a sanctioned scheme of arrangement to the Adjudicating Authority; non-disclosure is a factor weighing against admission.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
(Arising out of judgement and order dated 02.07.2024 passed by National Company Law Tribunal, Chandigarh in Company Petition No. CP(IB) No.365/ChD/PB/2024 titled SASF Vs Dwarikadhish Spinners Ltd)
In the matter of:
Mr Amit Chaturvedi Ex Director of Dwarikadhish Spinners Ltd 98 Eastern Avenue, Sainik Farm, New Delhi 110062 Appellant
Vs
1. Stressed Assets Stabilization Fund, Though its Manager Smt Shreshtha Paul, 3rd Floor, IDBI tower, WTC Complex, Cuffe Parade Mumbai 400005
2. Ms Dwarikadhish Spinners Ltd Th: Mr Prem Chand Goyal, IRP for Dwarikadhish Spinners Ltd 1, Village Kouli Majra, Tehsil Derabassi, Lalru Distt SAS Nagar 140501
Also at House No.1-F Adjoining Municipal House Model Town, Patiala Punjab 147001 Respondent
For Appellant: Ms. Purti Gupta, Ms. Heena George, Advocates
For Respondent: Mr. Anand Varma, Ms. Apoorva Pandey, Advocates 2
ORDER
JUSTICE YOGESH KHANNA, MEMBER (JUDICIAL)
The present appeal has been filed against an impugned order dated
02.07.2024 passed by the Ld. National Company Law Tribunal, Chandigarh
Bench in Company Petition No. IB-365/CHD/PB/2018 titled as Stressed
Assets Stabilization Fund Vs M/s Dwarikadhish Spinners Ltd. The Ld.
Adjudicating Authority has allowed a petition under Section 7 of IBC filed by
the Respondent No.1 herein, despite the fact on 23.07.2019 a scheme of
arrangement under Section 391-394 of the Companies Act, 1956 has been
approved by the High Court of Punjab & Haryana.
2.B Before proceeding further let us state few brief facts.
3. In the year 2008 a scheme of arrangement under Section 391-394 of
the Companies Act, 1956, being CP No. 51/2008 was initiated by the
Corporate Debtor which was approved by the 75% of the creditors of the
Corporate Debtor viz Dwarikadhish Spinners Ltd.
4. Qua the said scheme of arrangement the first motion application viz CP
No. 51/2008 was filed before the Punjab & Haryana High Court seeking
sanction of the scheme of arrangement between Corporate Debtor and its
creditors, including Respondent No.1.
5. Between March to June 2008, the Meeting of the Creditors of the
Corporate Debtor were convened as per due procedure laid down under the
Companies Act, 1956. On 20.06.2008 the Respondent No.1 sent a letter
showing its intention on agreeing to Option No. III for the scheme of
arrangement, whereby Respondent No.1 agreed to receive Rs. 459.36 lakhs
with certain terms and conditions.
3
6. On 21.06.2008 under the Chairmanship of Ms Ritu Singh, Advocate,
the meeting of the creditors was convened and thereafter on 25th July, 2008,
the first motion petition was approved by the Punjab & Haryana High Court.
7. On 30.07.2009 the second motion petition being CP No. 89/2009 was
filed in the High Court of Punjab & Haryana, but between 2009 to 2018 the
second motion petition remained pending for various reasons, including
disputes amongst several secured creditors, the corporate debtor and other
parties. Rather Respondent No.1 moved before the Ld. DRT for possession of
the property of corporate debtor under the SARFEASI Act. However, the said
application was stayed by the Punjab & Haryana High Court as the scheme
for arrangement was pending.
8. On 12.10.2018 the Respondent No.1 filed a petition under Section 7 of
IBC before the Ld. Adjudicating Authority while concealing the factum of
pendency of the Scheme for Arrangement before the Ld. Punjab & Haryana
High Court. On 23.07.2019 the second motion petition was allowed by the
Hon'ble Punjab & Haryana High Court approving the said scheme of
arrangement and with a direction the scheme shall be binding on the
appellant as well as all its stake holders, i.e. all creditors alongwith
Respondent No.1 herein.
9. On 23.09.2019 the copy of the order dated 23.07.2019 passed in CP
No. 89/2009 was sent to the Respondent No.1 by the appellant with a choice
to Respondent No.1 either to stick with Option No. III already opted for or any
other option provided in the scheme. However, on 02.08.2022 the
Respondent No.1 filed an application for recall of the order dated 23.07.2019
in CP No. 89/2009 which allowed the second motion petition and the said 4
order dated 2307.2019 was thus recalled by the Punjab & Haryana High
Court.
10 On 10.10.2022 the company appeal PP No. 14/2022 was filed before
the Hon'ble Division Bench of Punjab & Haryana High Court and while issuing
notice in the said appeal, the operation of recall order dated 2nd August, 2022
was stayed.
11. On 28.10.2022 the appellant filed an affidavit alongwith an order dated
10.10.2022 before Ld. NCLT but ultimately on 02.07.2024, the impugned
order was passed whereby the Ld. Adjudicating Authority allowed the CP
under Section 7 of the IBC 2016 filed by the Respondent No.1.
12. Thus the question before us is whether the Ld. NCLT ought to have
exercised jurisdiction under Section 7 of the Code, when a Scheme of
Arrangement was already in existence, as approved by the Ld. Single Judge
of the Punjab & Haryana High Court on 23.07.2019 itself.
13. It is the submission of the learned counsel for the Respondent No.1 that
in the present case the lenders have unanimously agreed to withdraw the
consent to the scheme of arrangement upon Corporate Debtor's failure to take
steps in filing of the second motion petition in time and the withdrawal of
such consent was communicated to the Corporate Debtor vide letter dated
03.07.2019 and that the lenders even filed objections before Hon'ble High
Court bringing to the notice of the High Court the consent of lenders stands
withdrawn as period for filing second motion had elapsed and only for this
reason, the scheme sanctioned order dated 23.07.2019 was recalled by the
Ld. Single Judge on an application filed by the lenders and though the said
order was stayed by the Ld. Division Bench of Punjab & Haryana vide its order 5
dated 10.10.2022 but it did not quash the order dated 2nd August, 2022
passed by the Ld. Single Judge and the same still exists.
14. Now admitted fact as they emerge are the order of recall dated 2nd
August, 2022 stands stayed in APP No.14/2022 by the Ld. Division Bench of
Punjab & Haryana High Court. The said appeal is still pending before the
Punjab & Haryana High Court and is now listed on 19th August, 2025.
15. The question is what we need to do till the pendency of the appeal before
the Ld. Division Bench of Punjab & Haryana High Court where the legality of
the scheme is being challenged. Admittedly an approved scheme has a
statutory force and is binding upon all its creditors and it operates as a
judgement in rem. Admittedly the scheme was initially accepted by the
requisite majority of creditors, including the Respondent No.1 (SASF).
Admittedly the Hon'ble High Court had sanctioned the scheme on 23.07.2019
i.e. much prior to the impugned admission order dated 02.07.2024. Thus
admittedly at the time of admission of the petition, a sanctioned scheme, as
approved, was already in existence. Section 391(3) of the Companies Act,
1956 makes an approved scheme binding on all the parties, including
Respondent No.1 and it cannot resile. Further Section 391(6) of the
Companies Act, 1956 provides for stay of all coercive action against the
sanction of the scheme of arrangement. Admittedly in its order dated
10.10.2022 in CPP 14/2022 the Hon'ble Division Bench noted there was a
consent of 75% of the creditors under the Scheme.
16. It was one of the submission of the appellant, consent once given could
not be withdrawn by lenders and their refusal to accept the payment upon
sanction of the scheme cannot be considered as a default on the part of the 6
Corporate Debtor. Now the withdrawal of the consent or default is an issue
pending before the Ld. Division Bench of High Court and it was not
appropriate for Ld. Adjudicating Authority to over-reach such jurisdiction. Per
force, as the scheme of arrangement was sanctioned on 23.07.2019 there
existed a novation of contract and the debt stood resolved per Suresh Kr
Reddy Vs Canara Bank and others 2023 (5) SCR 387.
17. Further Section 7 of the IBC uses the word "may", making admission of
a petition discretionary. Now the facts and circumstances so warrant, the
Adjudicating Authority should have kept the admission in abeyance till the
App No.14/2022 was decided.
18. The mandate of Section 7 of the Code is to explore a resolution for the
benefit of the company and it had already taken place under a sanctioned
scheme, when it stood sanctioned vide order dated 23.07.2019. Such a
rehabilitation was in line with the object of the Insolvency Code. Admittedly
the insolvency proceedings are not recovery proceedings and SASF, the
predecessor of M/s Omkar viz Respondent No.1 had admittedly settled at
Rs.459.36 lakhs under the scheme of arrangement and now in its insolvency
petition is claiming an inflated amount of Rs.154 crores.
19. In Lavkash Verma V M/s Vigneshwara Developers Pvt Ltd (IB)-
1076(ND)/2019, an admission order passed under Section 7 of the Code, was
kept in abeyance since a scheme of arrangement was approved by the High
Court of Delhi.
20. The learned counsel for the Respondent No.1 though referred to Grand
Developers V Nitin Batra, dated 15.05.2024 in CA (AT)(Ins) No.899/2024
wherein despite the scheme of arrangement pending between the parties the 7
petition under Section 7 of IBC was directed to be continued, but to our mind
the said judgment shall not be applicable to facts since in the cited case, the
scheme of arrangement was still pending, but whereas in the present case the
scheme has already been sanctioned prior to filing of Section 7 petition of the
IBC. Secondly the reliance of Respondent No.1 upon Forech India Ltd Vs
Edelweiss Assets Reconstruction Co (2019) SCC 549 is also not correct since
it was a case of winding up of the company and not a case of scheme of
arrangement.
21. In the light of the above circumstances we are of the considered view as
the objections to the scheme are still pending in APP No.14/2022 before the
Hon'ble Division Bench of Punjab & Haryana High Court and as the order of
recall in CP No. 89/2009 stands stayed in APP No. 14/2022 much prior to
the passing of the impugned order and as the Respondent No.1 ought to have
disclosed the factum of sanctioning of scheme before the Ld. NCLT; hence in
these circumstances the Ld. NCLT ought to have at least waited till disposal
of App No. 14/2022 pending before Ld. Division Bench of Punjab & Haryana
High Court, now listed for 19.08.2025. Thus in this case we set aside the
order of admission under Section 7 of IBC passed by Ld. NCLT, though
keeping the petition filed under Section 7 of IBC pending and only after the
APP No. 14/2022 is disposed of, the Ld. NCLT should have a fresh look in the
matter in the light of the order passed in APP No. 14/2022 (supra). 8
22. The appeal is disposed of in terms of the above.
23. Pending applications are also disposed of.
(Justice Yogesh Khanna) Member (Judicial)
(Mr. Ajai Das Mehrotra) Member (Technical) Dated: 18-08-2025 BM
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free