Alumilite Architecturals Limited vs Shrikant Studios Private Limited
- CitationCompany Appeal (AT) (Insolvency) No. 538 of 2023
Ratio decidendi
The rule this decision rests on
The pendency of a commercial suit filed by the operational creditor before the demand notice was issued, together with a bona fide dispute over the debt disclosed in the corporate debtor's reply to the Section 9 application (including the termination of the work order and the subsequent fresh work orders), constitutes a pre-existing dispute, and an application under Section 9 of the Insolvency and Bankruptcy Code, 2016 is liable to be rejected on that ground.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
Alumilite Architecturals Ltd. ...Appellant
Versus
Shikant Studio Pvt. Ltd. ...Respondents
Present: For Appellant: Advocate Asim Sood, Advocate Rachitta Rai, Advocate Kuber Bajaj, Advocate Shehan Ashraf, Advocate Shrey Sharma, Advocates For Respondent: Advocate Aparna Devkar, Advocate Shiva Krishna Murti.
ORDER
17.08.2023: Heard Learned Counsel for the Appellant.
2. This Appeal has been filed against the Order dated 03.02.2023 passed
by the Adjudicating Authority by which Section 9 Application filed by the
Appellant has been dismissed. The Adjudicating Authority has dismissed
Section 9 Application on the ground that there is a pre-existing dispute with
the Corporate Debtor.
3. The Adjudicating Authority has noticed that Commercial Suit No.
232/2017 was filed in the High Court of Bombay by the Appellant. Learned
Counsel for the Appellant challenging the Order contends that suit was filed
for the recovery of the dues and that cannot be treated to be any pre-existing
dispute. He has further referred to Letter dated 30th June, 2016 issued by the
Corporate Debtor to the Operational Creditor where it is submitted that there
is an acknowledgement of dues of the Appellant to the extent of Rs. 21 Lakhs. -2-
4. We have considered the submissions of Learned Counsel for the
Appellant and perused the record.
5. The Appellant had filed the Commercial Suit on 19.12.2016 in the
Bombay High Court and Demand Notice was issued on 22.10.2018. Demand
Notice was replied by the Corporate Debtor disputing the claim and when
Section 9 Application was filed, detail reply was filed by the Corporate Debtor.
Copy of the Reply filed by the Corporate Debtor in Section 9 Application has
been brought on record by the Appellant as Annexure A-3. In paragraph 7 of
the Reply under the heading "Pre-Existing Dispute prior to Demand Notice
dated 22.10.2018", the Corporate has given the sequence of the events and
details including the termination of work order and giving of the fresh work
orders. Further details of dispute between the parties have been mentioned
including the letter dated 30th June, 2016 which has been relied on by Learned
Counsel for the Appellant.
6. There being dispute between the parties as detailed in paragraph 7 of
the Reply and the Commercial Suit No. 232 of 2016 in the High Court of
Bombay, we are of the view that Adjudicating Authority did not commit any
error in rejecting Section 9 Application on the pre-existing dispute. No ground
is made out to entertain the appeal, the Appeal is dismissed.
[Justice Ashok Bhushan] Chairperson
[Mr. Barun Mitra] Member (Technical) Basant/nn Company Appeal (AT) (Insolvency) No.538/2023
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free