Miss Lucy
← All judgments

Ajay Kumar Nauriya And Anr vs Dream Procon Pvt Ltd Through Its ...

National Company Law Appellate Tribunal14 May 2025

Ratio decidendi

The rule this decision rests on

Where a homebuyer's claim is reflected in the Information Memorandum prepared by the Resolution Professional, the Resolution Professional must place the details of that claim before the resolution applicant, who must prepare an addendum to the resolution plan for consideration by the Committee of Creditors, notwithstanding that the claim was filed belatedly after the Committee of Creditors had approved the plan and the plan is pending before the Adjudicating Authority. The fact that a belated claim was filed after the Committee of Creditors' approval of the resolution plan does not by itself bar consideration of the claim where the liability is reflected in the records of the corporate debtor and the homebuyer is a non-commercial entity; the rule in the Supreme Court's decision in RPS Infrastructure, which precludes reopening an approved plan, does not apply to such a claim in the circumstances of this case.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

NATIONAL COMPANY LAW APPELLATE TRIBUNALPRINCIPAL BENCH, NEW DELHI

Company Appeal (AT) (Ins) No. 1391 of 2023 & I.A. No. 4972 of 2023 IN THE MATTER OF: Ajay Kumar Nauriya & Anr. ...Appellant

Versus Dream Procon Pvt. Ltd. ...Respondents Through its'Resolution Professional Nilesh Sharma & Anr. Present: For Appellant: Mr. Sumant Batra, Mr. Sarthak Bhandari and Ms. Nidhi Yadav, Advocates. For Respondents: Mr. Varsha Banerjee and Mr. Akash Srivastava, Advocates for R-1. JUDGMENT

Per: Justice Rakesh Kumar Jain:

This appeal is directed against the order dated 11.08.2023 by which

an application filed by the Appellants bearing I.A No. 3764 of 2021 in I.B

No. 1771/ND/2018 for issuance of a direction to the RP to admit their

claim, has been rejected.

2. In brief, both the Appellants are husband and wife who have jointly

applied for allotment of a unit in the project of Dream Procon Pvt. Ltd.

(CD) by the name of 'Victory Ace' situated at Plot No. GH-02, Sector 143,

Noida. They were allotted unit B1-502 in the said project by the allotment

letter dated 20.08.2013. The allotment letter was revised and by an

allotment letter dated 29.08.2016, the unit of the Appellant was changed

to A-2 1003 in the said project for total base sale price of Rs. 68,11,550/-

which was to be paid as per construction linked plan. -2-

3. The Appellants availed the loan of Rs. 42,83,640/- from ICICI Bank

for the said unit and paid a total sum of Rs. 55,31,705/- to the CD till

2016. The construction of the unit was not completed in time but the

Appellant had to regularly pay the EMIs to ICICI Bank.

4. The CD was pushed into CIRP vide order dated 06.09.2019. The IRP

made public announcement in Form A on 17.10.2019 but the Appellant

missed the advertisement. No communication was made by the IRP and

after few weeks Covid 19 hit the country and lockdown was ordered.

5. The Appellant No. 1 suffers from vision handicap in both eyes on

account of Covid-19 as a result of which he has been assessed to be 90%

visually handicapped.

6. As soon as, the appellant came to know that the CD is facing CIRP,

they submitted their claim in Form CA on 19.07.2021 for an amount of

Rs. 1,29,82,922.03 which included the principal and the interest but the

RP rejected their claim vide his email dated 06.08.2021 on the ground

that since the resolution plan submitted by R2 has been approved by the

CoC, therefore, their claim cannot be admitted.

7. It is pertinent to note that on the website of the CD, the name of the

Appellants and details of unit allotted to them was shown under the list of

creditors (allottees) who had not filed their claim and the list of creditors

is part of IM prepared by the RP.

8. The Appellants challenged the order in I.A No. 3764 of 2021 but the

Tribunal dismissed their application vide the impugned order dated Company Appeal (AT) (Ins.) No. 1391 of 2023 -3-

11.08.2023 relying upon a decision of this Court in the case of Puneet

Kaur Vs. K V Developers Pvt. Ltd. & Ors. on the ground that the claim

submitted belatedly after the approval of the plan by the CoC cannot be

entertained.

9. Counsel for the Appellant has submitted that the Tribunal has

committed an error in misreading the decision in the case of Puneet Kaur

(Supra) because in the very same judgment in para 27, this court has held

that if the claim of the homebuyers is reflected in the record of the CD in

the IM then it ought to have been taken note of the said liability by the RP

and should have appropriately dealt with in the resolution plan.

10. He has further submitted that this court had issued direction in the

case of Puneet Kaur (Supra) to the RP to submit the details of the

homebuyers whose details are reflected in the records of the CD to the RA,

on the basis of which shall prepare the addendum to the resolution plan

and place before the CoC for consideration.

11. On the other hand, Counsel for the Respondent has admitted the

allotment of unit to the Appellants but it is submitted that the claim has

been filed belatedly after the approval of the resolution plan by the CoC

which cannot be considered. It is alleged that the insolvency proceedings

in this case had commenced on 06.09.2019 and the last date for

submission of claim was 29.10.2019. The resolution plan was presented

on 01.03.2021, whereinafter the plan was put to vote and approved during

the period 07.05.2021 to 15.05.2021. The Appellant has belatedly filed the Company Appeal (AT) (Ins.) No. 1391 of 2023 -4-

claim after the approval of plan by CoC on 16.07.2021 on Form CA which

has been rejected by the RP rightly on 06.08.2021 because it was filed

after the delay of 536 days from the issuance of Form A and 62 days after

the approval of the resolution plan by the CoC.

12. According to the Respondent, the case is covered by the decision of

this Court in the case of Pooja Mehra Vs. Nilesh Sharma, CA (AT) (Ins) No.

1511 of 2023 and the decision of the Hon'ble Supreme Court in the case of

RPS International Limited Vs. Mukul Kumar & Ors., (2023) 10 SCC 718 in

which the Hon'ble Supreme Court has held that after the plan is approved

by the CoC though pending before the AA for approval, the claim cannot

be admitted.

13. We have heard Counsel for the parties and perused the record.

14. There is no dispute that the liability of the CD towards the Appellant is

clearly reflected in the IM. The appellant has also filed the claim belatedly and

the CoC has approved the plan but the plan has not been approved by the

Adjudicating Authority so far as it is pending for its consideration. The

appellant has basically relied upon a decision in the case of Puneet Kaur

(Supra) in which this court has held that "in the preset case there is no denial

that details of the Appellant(s) and other homebuyers, who could not file their

claims has not been reflected in the IM. There being no detail of claims of the

appellant(s), the resolution applicant could not have been taken any

consideration of the claim of the appellant(s), hence, resolution plan as

submitted by resolution applicant cannot be faulted". However, at the same,

Company Appeal (AT) (Ins.) No. 1391 of 2023 -5-

in the case of Puneet Kaur (Supra) this court has held that "however, we are

of the view that the claim of those homebuyers, who could not file their

claims, but whose claims were reflected in the record of the CD, ought to have

been included in the IM and resolution applicant, ought to have been taken

note of the said labilities and should have appropriately dealt with them in

the resolution plan. Non-consideration of such claims, which are reflected

from the record, leads to inequitable and unfair resolution as is seen in the

present case. To mitigate the hardship of the Appellant, we thus, are of the

view that ends of justice would be met, if direction is issued to resolution

professional to submit the details of homebuyers, whose details are reflected

in the records of the CD including their claims, to the Resolution applicant,

on the basis of which resolution applicant shall prepare an addendum to the

resolution plan, which may be placed before the CoC for consideration."

15. The argument of the Respondent that since the CoC has already

approved the plan and the claim has been filed after the approval of the plan,

the decision in the case of M/s RPS Infrastructure Ltd. (Supra) would come in

the way of the Appellant because in that case it has been held that "the mere

fact that the AA has yet not approved the plan does not imply that the plan

can go back and forth, thereby making the CIRP an endless process. This

would result in the reopening of the whole issue, particularly as there may be

other similar persons who may jump onto the bandwagon."

16. In the aforesaid case, however, it has been observed by the Hon'ble

Court in para 18 that "if we analyse the aforesaid plea, it is quite obvious that

Company Appeal (AT) (Ins.) No. 1391 of 2023 -6-

respondent no. 1 did what could be done to procure the CD's records by even

moving an application under Section 19 of the Code. That it was not fruitful

is a consequence of the CD not making available the material. It is thus not

even known whether there was a reflection in the records on this aspect or

not."

17. Further, since the claim was filed after delay of 287 days and creditor

feigned ignorance about the CIRP about which the Hon'ble court has held

that the Appellant being a commercial entity and had been litigating against

the CD, therefore, it ought to have been vigilant enough to find out whether

the CD was undergoing CIRP and once a public announcement of the CIRP

has been made through newspapers, it would constitute deemed knowledge

on the Appellant and the plea of not being aware of newspaper

pronouncement is not the one which should be available to a commercial

entity.

18. However, the present case pertains to the non-commercial entity like a

homebuyer.

19. In the case of Pooja Mehra (Supra), relied upon by the Respondent,

which was also against the same CD this court had found that there was no

evidence/acceptable material on record of the actual payment of Rs.

50,00,000/- to the CD. In this regard, the observation made by this court in

the said case is captured in para 102 which is reproduced as under:-

"102. The claim of the Appellant is that since approval of Resolution Plan is pending before the Adjudicating Authority, its claim can be considered on merits. We have examined this issue in detail basis the facts of the case, wherein the Appellant Company Appeal (AT) (Ins.) No. 1391 of 2023 -7-

seeks condonation of 540 days and basis the current position of law. It becomes unsustainable to accede to his request to allow his belated claim to be considered, particularly in the background that there is no acceptable material on record to suggest actual disbursement of Rs.50 lakhs to the Corporate Debtor and more so when the Appellant itself has filed Form - C and not CA raising its claim. There is also inconsistency in the description of the alleged unit being D2-601 or D2-2002 in the buyback agreement and allotment letter."

20. In our considered opinion, the decision in the case of Pooja Mehra

(Supra) is not applicable because in that case it was not even proved that the

Appellant had disbursed the amount in question to the CD whereas in the

present there is no dispute that the Appellant had disbursed the amount after

taking loan from the Bank and the said factum is part of the IM.

21. Thus, keeping in view the totality of circumstances, we are of the

considered opinion that the controversy in hand is covered by the case of

Puneet Kaur (Supra) and therefore, while allowing the present appeal and

setting aside the impugned order, we direct the RP to submit the detail of the

appellant reflected in the record of the CD including their claim to the

resolution applicant on the basis of which the resolution applicant shall

prepare an addendum to the resolution plan which may be placed before the

CoC for consideration. The entire exercise should be completed within a

period of three months from today and the addendum and the minutes of the

CoC at the time of finalizing the resolution plan shall be considered by the AA

at the time of the approval of the resolution plan which is pending

consideration before the AA. The Resolution Professional may also bring to

Company Appeal (AT) (Ins.) No. 1391 of 2023 -8-

the notice of the AA, the order of this date, so that the AA may await the

addendum alongwith the minutes of the CoC which may be considered

alongwith the approval of the resolution plan.

Pending I.As, if any, are hereby closed.

[Justice Rakesh Kumar Jain] Member (Judicial)

[Mr. Naresh Salecha] Member (Technical)

[Mr. Indevar Pandey] Member (Technical)

New Delhi 14th May, 2025 Sheetal

Company Appeal (AT) (Ins.) No. 1391 of 2023

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free