Airtech Airconditioners vs Parnika Commercial And Estates ...
- CitationCompany Appeal (AT) (Insolvency) No. 502 of 2024
Ratio decidendi
The rule this decision rests on
Where an operational creditor's Section 9 application comprises invoices of more than one project, each invoice's date of default must be assessed separately for the purposes of the Section 10-A exclusion; invoices whose dates of default fall outside the Section 10-A period cannot be rejected on the ground that other invoices in the same application fall within it. Where the amount of operational debt arising from invoices whose dates of default fall outside the Section 10-A period exceeds the threshold under Section 4 of the Insolvency and Bankruptcy Code, 2016, the adjudicating authority must consider those invoices and cannot dismiss the application under Section 10-A by reference only to the excluded invoices.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
[Arising out of the Impugned Order dated 18.12.2023 passed by the Adjudicating Authority, National Company Law Tribunal, New Delhi Bench in C.P. (IB) No. 126/ND/2023] In the matter of: M/s Airtech Airconditioning Through Mr. Arshad Shah, Proprietor Ashiana Building, adjoining Daryacha Building, Hauz Khas Village, New Delhi- 110016 .... Appellant Versus
Parnika Commercial & Estate Private Limited Having its Registered Office at: D-64, 6TH Floor Himalaya House, 23 KG Marg New Delhi - 11 0001 .... Respondent Present:
For Appellant : Mr. Vipul Ganda, Ms. Avnika Mishra, Ms. Nitu Barik and Mr. Gyanesh Tiwary, Advocates.
For Respondent : Mr. Bhupesh Narula, Advocate.
JUDGMENT
(Hybrid Mode)
Per: Barun Mitra, Member (Technical)
The present appeal filed under Section 61 of Insolvency and Bankruptcy
Code 2016 ('IBC' in short) by the Appellant arises out of the Order dated
18.12.2023 (hereinafter referred to as 'Impugned Order') passed by the
Adjudicating Authority (National Company Law Tribunal, New Delhi Bench-III)
in C.P. (IB) No. 126/ND/2023. By the impugned order, the Adjudicating Authority has dismissed Section 9 application filed by the Appellant-M/s Airtech
Airconditioners. Aggrieved by the impugned order, the present appeal has been
preferred by the Appellant.
2. To summarily capture the factual matrix of the matter, we notice that the
Appellant-M/s Airtech Airconditioners-Operational Creditor was engaged by
Corporate Debtor-M/s Parnika Commercial & Estate Private Limited to provide
Heating, Ventilation and Air Conditioning services for three of its projects. These
three projects were located at Vanijya Bhawan, New Delhi; DRDO, Delhi and IIT,
Mumbai. Separate work orders had been issued for these projects for which
separate invoices had been raised as running account bills by the Appellant.
Since payments were not forthcoming, the Appellant on 21.10.2022 had issued
a demand notice under Section 8 for an amount of Rs 8.23 Cr. and interest
thereon @18%. In response to the Section 8 demand notice, the Respondent-
Corporate Debtor replied on 31.10.2022 denying any outstanding dues qua the
Operational Creditor besides raising several deficiencies in the performance of
the Operational Creditor with respect to the execution of work by them. The
Operational Creditor thereafter filed Section 9 application on 22.02.2023 which
was rejected by the Adjudicating Authority vide impugned order dated
23.10.2023. Aggrieved by the impugned order, the present appeal has been
preferred by the Appellant.
3. Making submissions on behalf of the Appellant, Shri Vipul Ganda, Ld.
Counsel submitted that the Adjudicating Authority while rejecting their Section
9 application had failed to appreciate the fact that though the Corporate Debtor
had defaulted in clearing the outstanding operational debt which had arisen Page 2 of 10 Company Appeal (AT) (Insolvency) No. 502 of 2024 beyond the Section 10-A prohibited period and that this amount crossed the
threshold limit of Rs 1 Cr. prescribed under Section 4 of the IBC. It was
contended that the Adjudicating Authority while deciding on the maintainability
of the Section 9 application should have kept in mind the fact that the invoices
of the various projects were separate and the dates of default were also separate.
Emphasis was laid on the fact that the default in respect of invoices pertaining
to DRDO and IIT Bombay projects admittedly fell within the Section 10-A period
but the relevant invoices in respect of Vanijya Bhawan Project fell outside the
Section 10-A period. It was contended that the amount due and payable from
the Vanijya Bhawan Project alone was Rs 2.36 Cr. The Adjudicating Authority
had erroneously rejected the Section 9 application without taking notice of the
invoices pertaining to Vanijya Bhawan Project.
4. Denying the issue of pre-existing disputes which had been raised by the
Corporate Debtor, it was contended that the Vanijya Bhawan Project was
completed in time and the building already inaugurated on 23.06.2022. It was
also submitted that all the defects pointed out in the Snag List Report in respect
of the Vanijya Bhawan Project had been remedied by them. They had issued a
handing-over note to the Corporate Debtor on 08.10.2022 which note had also
been acknowledged by the Corporate Debtor. Even NBCC which had contracted
out this work to the Corporate Debtor had also issued a completion certificate.
The Corporate Debtor has also availed Input Tax Credit which was reflected in
their ledger in respect of the Vanijya Bhawan Project. The invoices dated
09.03.2022 and 13.07.2022 of Vanijya Bhawan Project which reflected on the
GST Portal was sufficient proof of the Corporate Debtor having accepted the Page 3 of 10 Company Appeal (AT) (Insolvency) No. 502 of 2024 services rendered by the Operational Creditor. The Respondent did not raise any
dispute until the receipt of Section 8 demand notice. The letters issued by the
Corporate Debtor on 31.12.2020 and 10.02.2021 basis which Corporate Debtor
has raised the bogey of pre-existing dispute were with respect to services
provided in respect of the IIT, Bombay Project and not the Vanijya Bhawan
Project. The disputes which have been raised by the Corporate Debtor in reply
to the Section 9 application with respect to Vanijya Bhawan Project were raised
only after filing of the Section 9 application which goes to show that the dispute
was raised as an after-thought to overcome the Section 9 application. Hence, the
allegation of pre-existing dispute raised by the Corporate Debtor were not only
unfounded but an after-thought which ought not to have been taken cognizance
of by the Adjudicating Authority. Even the factum of initiation of arbitration
proceedings did not constitute a pre-existing dispute as these proceedings were
filed much after the Section 8 Demand Notice.
5. Refuting the contentions of the Appellant, Shri Bhupesh Narula, Ld.
Advocate on behalf of the Corporate Debtor-Respondent submitted that they had
issued a demand notice on 19.10.2022 which was prior to the Demand Notice
issued by the Appellant. It was emphatically asserted that when the Corporate
Debtor had themselves issued a demand notice to the Appellant before the issue
of Section 8 demand notice by the Appellant, this itself indicates pre-existing
dispute. It was asserted that in their Demand Notice, they had claimed refund of
excess payment made to the Operational Creditor to the tune of Rs 1.43 Cr. It
was further pointed out that though the Operational Creditor had over-billed
their invoices, instead of clarifying the issue of excess payment receipt, they Page 4 of 10 Company Appeal (AT) (Insolvency) No. 502 of 2024 issued a counter notice of demand on 21.10.2022 which was a frivolous notice
of demand. It was submitted that the tax invoices and Input Tax Credits relied
upon by the Appellant to substantiate their plea of outstanding debt did not
contain the signature of the Corporate Debtor and such manipulated documents
cannot be looked into. It was also mentioned that several communications were
exchanged with the Operational Creditor regarding unexplained delay on their
part in completing the work. The Operational Creditor had abandoned the
projects midway and not having completed the works undertaken by them
cannot rightfully claim any payment to be made to them. Since the Operational
Creditor had abandoned the work, the Corporate Debtor had to make alternative
arrangements to complete these works as these were time-bound works. The
works were executed through alternative contractor viz. Global Aircon at a much
higher rate because of which they had to suffer losses. It was added that Global
Aircon was paid directly by the Corporate Debtor but the Appellant has
mischievously raised invoices for the same works completed by Global Aircon. It
was submitted that details of the payments made to Global Aircon was reflected
by them in para 4 of their Reply to the present appeal at page 11. It was pointed
out that at para 5 of the same Reply at page 13 other disputes relating to the
invoices were also fleshed out. A reconciliation statement was also placed at para
7 of the same Reply at page 15-16 which statement shows that the Operational
Creditor was liable to refund Rs 3.40 Cr. alongwith interest to the Corporate
Debtor. It was further contended that the Appellant had no grounds to raise the
Section 9 application because the Respondent had already invoked the
Page 5 of 10 Company Appeal (AT) (Insolvency) No. 502 of 2024 Arbitration Clause in terms of the work order and since the arbitration petition
is pending, the continuance of the Section 9 application had become infructuous.
6. We have duly considered the arguments advanced by the Learned Counsel
for the parties and perused the records carefully.
7. The short question before us for consideration is whether the invoices
raised by the Appellant-Operational Creditor in respect of Vanijya Bhawan
Project in the Section 9 application fell within the excluded period of Section 10A
or not.
8. To arrive at our findings, we may advert our attention to the Section 9
application with reference to details of the Vanijya Bhawan invoices set out
therein along with invoice number, date of default and outstanding amount. The
relevant particulars are as reproduced below:
PART-IV PARTICULARS OF OPERATIONAL DEBT
1. Total amount of Total amount of Debt debt details of Rs. 8,23,72,560/- (Rupees Eight Crores Twenty-
transactions on Three Lakhs Seventy-Two Thousand Five Hundred account of which Sixty) along with 18% interest till the date of actual debt fell due, and realization.
the date from ....
which such debt ....
fell due. 3. That, the Operational Creditor provided firefighting and HVAC services to the Corporate Debtor and was associated in the following three different projects staring from the year 2019:
Page 6 of 10
Company Appeal (AT) (Insolvency) No. 502 of 2024 .... S. No. Name of Location .... the Project
1. Vanijya Delhi Bhavan
2. DRDO Delhi
3. IIT Mumbai Bombay
8. As per the invoices raised to the Corporate Debtor, the debt became due and payable became due and payable within 15 days of the receipt of the payment by the Corporate Debtor from their respective clients.
The details of the said uncleared invoices are as under:
Invoice No. Date of Amount (Rs.) Default Vanijya Bhawan, Delhi 25/2021- April 14, 1,41,82,896 2022 2022 04/2022- July 29, 1,07,29,601 2023 2022 Less: Partly 12,19,002 received amount for the invoice Total (A) 2,36,93,495 DRDO, Delhi .....
Page 7 of 10
Company Appeal (AT) (Insolvency) No. 502 of 2024
2. Amount claimed ....
to be in default ....
and the date on which the default Invoice No. Date of Invoice Date of occurred. Default VANIJYA BHAVAN, DELHI 25/2021-2022 March 29, 2022 April 14, 2022 4/2022-2023 July 13 , 2022 July 29, 2022 DRDO, DELHI 80/2020-2021 October 21,2020 November 6, 2020 108/2020- February 15, March 3, 2021 2021 2021 IIT BOMBAY 88/2020-2021 November 11, November 2020 27, 2020 87 /2020-2021 November 11, November 2020 27, 2020
9. From the Part-IV entries, it becomes clear that the Appellant had raised
claim against six invoices. Two out of six invoices related to the Vanijya Bhawan
Project were dated 29.03.2022 and 13.07.2022 whose dates of defaults were
14.04.2022 and 29.07.2022. The dates of defaults of these two invoices
undisputedly fall outside the Section 10-A period.
10. Having seen the Part-IV particulars, we now turn to the impugned order
to find out how the Vanijya Bhawan Project invoices have been treated. The
relevant excerpt of impugned order is as extracted below:
"7. Analysis and Findings
iii. As per Section l0A of the IBC, 2016 and the MCA Notifications dated 24.09.2020 and 22.12.2020, no application for CIRP may be filed for defaults occurring between 25.03.2020 to 24.03.2021. The
Page 8 of 10 Company Appeal (AT) (Insolvency) No. 502 of 2024 invoices based on which the present Application has been filed are dated 06.11.2020, 27.11.2020 and 03.03.2021. Therefore, the present Application is barred by Section l 0A of the IBC, 2016."
11. From the above extracts, it is unambiguously clear that only invoices dated
06.11.2020, 27.11.2020 (two invoices) and 03.03.2021 have been recorded in
the impugned order. These invoices undisputedly fall in the excluded period of
Section 10-A. We also find that the Adjudicating Authority held the present
Section 9 application to be not maintainable by taking notice of only three
invoices dated 06.11.2020, 27.11.2020 and 03.03.2021. Where the Adjudicating
Authority blundered was that it clearly failed to take note of the two invoices of
the Vanijya Bhawan Project, the date of which invoices and their date of defaults
unambiguously fell beyond the period covered by Section 10-A of IBC. Since the
date of default arising out of these two invoices fall beyond the Section 10-A
period, the Section 9 application could not have been dismissed by the
Adjudicating Authority on grounds of Section 10-A. We find that the amount
arising out of the two invoices in respect of Vanijya Bhawan Project which is
more than the amount of threshold provided under Section 4 of IBC of Rs 1 Cr.,
the Section 9 application could not have been dismissed by the Adjudicating
Authority without looking into these two invoices. It is pertinent to add here that
during the oral submissions made before this Tribunal, the Appellant has
categorically stated that they would like to confine their claims in the Section 9
application only with respect to these two invoices pertaining to Vanijya Bhawan
Project.
Page 9 of 10 Company Appeal (AT) (Insolvency) No. 502 of 2024
12. In sum, we have no hesitation in concluding that the impugned order is
unsustainable as it has failed to notice that the two invoices relating to Vanijya
Bhawan Project are not covered by Section 10-A of IBC. We therefore find merit
in the present Appeal. The appeal is hereby allowed and the impugned order is
set aside. The application bearing CP No. 126 of 2023 is hereby restored and the
matter is remanded back to the Adjudicating Authority to be considered again in
accordance with law with the caveat that the claim of operational debt shall
remain confined only to the two invoices relating to the Vanijya Bhawan Project
dated 29.03.2022 and 13.07.2022. We also add here that we have not expressed
any opinion on the contentions raised by both parties with respect to pre-existing
dispute qua the Vanijya Bhawan Project. No order as to costs.
[Justice Ashok Bhushan] Chairperson
[Barun Mitra] Member (Technical)
Place: New Delhi Date: 07.01.2026 Harleen
Page 10 of 10 Company Appeal (AT) (Insolvency) No. 502 of 2024
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.