Walchandnagar Industries Ltd. vs The State Of Maharashtra
- Neutral2022 INSC 146
- SCR[2022] 18 SCR 826
Ratio decidendi
The rule this decision rests on
1. For severance and injurious affection claims under clauses "thirdly" and "fourthly" of Section 23(1) of the Land Acquisition Act, 1894, the court must distinguish between damage to immovable property due to severance, damage to movable property, and loss or diminution of earnings; severance under clause "thirdly" relates only to the damage to unacquired land from being severed, while clause "fourthly" covers injurious affection to movable property and earnings, with such claims tested on the evidence of actual harm shown by credible evidence. 2. Where a part of a length-dependent infrastructure like a railway or trolley line is acquired and the unacquired portion is thereby rendered useless, the claimant is entitled to compensation for injurious affection to the movable property forming part of that infrastructure, provided credible evidence establishes the valuations; the fact that a claimant may have sought to mitigate harm through alternative arrangements does not disentitle them to such compensation when those arrangements were not feasible or were not the claimant's responsibility to procure. 3. A claim for injurious affection to earnings or increase in transportation costs cannot succeed merely on proof of increased costs if there is insufficient evidence that such costs were actually borne by the claimant and not passed on to customers; the absence of contemporaneous evidence linking increased costs to loss of profits, coupled with the commercial reality that transportation costs are generally factored into price and may be recovered through adjustment of contractual terms, requires rejection of such claims.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
CIVIL APPEAL NOS. 26712672 of 2016
WALCHANDNAGAR INDUSTRIES LTD. ... APPELLANT (S)
VERSUS
THE STATE OF MAHARASHTRA & ANR. ... RESPONDENT(S)
JUDGMENT
V. Ramasubramanian, J.
1. Challenging a common Judgment rendered by the High Court
of Judicature at Bombay in two appeals, modifying the award of
the Reference Court passed under Section 18 of the Land Signature Not Verified Digitally signed by Jayant Kumar Arora Date: 2022.02.04 Acquisition Act,1894, the claimantlandowner has come up with 16:25:42 IST Reason: 1 these civil appeals.
2. We have heard Mr. Gopal Sankaranarayanan, learned senior
advocate appearing for the appellant; Mr. Sachin Patil, learned
advocate appearing for the first respondentState and Mr. Deepak
Nargolkar, learned senior advocate appearing for the second
respondentbeneficiary.
3. The appellant is a company incorporated under the
Companies Act. It has established a township in a vast area
measuring about 16000 acres of land, located 136 kms. away from
Pune. The nearest railway station to the township is at Bhigwan,
located 36 kms. away from Walchandnagar Township.
4. For the purpose of transporting sugarcane and other goods,
the appellant had laid trolley lines covering a distance of 50 kms.
inside its estate. The appellant has also set up a 36 km. narrow
gauge trolley line from Walchandnagar to Bhigwan for
transportation of heavy engineering goods.
5. In the year 1967, the Government of Maharashtra approved
2 the BHIMA (Ujjani) Irrigation Project. As part of the project, a 18
feet height dam across the Bhima River was proposed to be
constructed at Ujjani about 1½ kms. upstream from Hingangaon
bridge on PuneSholapur National Highway. Before undertaking
the construction of the dam, a general survey was carried out,
which revealed that a section of the trolley line may get submerged.
Therefore, a spate of correspondence and personal discussions
ensued between the officials of the Government and the
representatives of the appellant for exploring the possibility of
diverting the trolley line.
6. It is the case of the appellant that they wanted the
Government to invoke the urgency clause for the acquisition of
some other land for diverting the trolley line. But it is the case of
the respondents that the appellant had by then abandoned
transportation through trolley line and switched over to road
transport.
7. Be that as it may, a notification under Section 4 of the Land
Acquisition Act, 1894 was published on 26.10.1972. The proposal
3 included the land on which a section of the trolley line passed. The
extent of land covered by the trolley line that was expected to be
submerged was measured to be 6 hectares 7 ares. Since the total
land acquired for the project, included the lands of the appellant,
which were located in different villages, a series of awards were
passed.
8. For our present purpose, it may be noted that the Land
Acquisition Officer passed an award on 9.12.1981. The claim of the
appellant in the Award Enquiry was not only for the market value
of the land, but also for: (i) compensation for the loss; and
(ii) compensation for the injurious affection due to the trolley line
becoming obsolete. The claim of the appellant also included a claim
for the loss sustained by the appellant on account of the
unacquired portion being rendered useless.
9. By his Award dated 9.12.1981, the Land Acquisition Officer
awarded :
(i) Rs.15,329 for the acquired portion of land;
(ii) Rs.39032.94 for embankments, rails, bullies, sleepers;
4 (iii) Rs.43,491.12 for C.D. works;
(iv) Rs.12,754.17 towards labour charges for removing rails and steel sleepers; and (v) Rs.16,591.08 for solatium.
10. In effect, the Land Acquisition Officer awarded total
compensation of Rs.1,27,198.31/ and rejected the claim of
Rs.1,49,85,251/ for the unacquired portion.
11. Not satisfied with the award, the appellant sought a reference
under Section 18 on 12.01.1982. It was referred to the District
Court, Pune, which took the same on file as Land Acquisition
Reference No.6 of 1982.
12. Before the Reference Court, the appellant claimed
enhancement of compensation for the land acquired. In addition,
the appellant also claimed compensation for severance and
compensation for injurious affection. The claim under different
heads was summarized by the Reference Court in paragraph 14 of
its award and it is reproduced for easy appreciation as follows:
SUMMARY OF CLAIM FOR COMPENSATION
5 I. Land in Acquisition in Kumbhargaon village
1 Lands acquired 50,32500 2 Embankment 63,85000 3 C.D. Works 68,20000 4 Trees 36000 1,82,73500 5 Solatium @ 15% 27,41000 Total 2,10,14500
6 SEVERANCE AND INJURIOUS AFFECTION
II. SEVERANCE
A Land 6,03,80000 B Diminution in value of lands in 8,64,00000 Walchandnagar Township C Embankment, C.D. Works and 18,85,20000 buildings D Trees 27,00000 Total 33,80,00000
III. INJURIOUS AFFECTION
E Rails Sleepers etc. 42,45,00000 F Girders (remove) Nil G Telephone line 16,00000 H Rolling Stocks 22,17,60000 I Increase in transportation costs 80,07,18000 J Remodeling of Bhigwan Yard 4,72,10000 K Loss of earnings (profits) 35,62,00000 L Retrenchment compensation 1,00,00000 Total for injurious affection 1,86,19,70000
Total for Severance and Injurious affection II + III (Rs.33,80,000 + 1,86,19,700 = 2,19,99,700)
IV. TOTAL COMPENSATION
I Land 2,10,14500 II Severance 33,80,00000 III Injurious Affection 1,86,19,70000 Total Rs.2,22,09,84500
IV Less : Compensation as 1,27,19800 awarded by S.L.A.O No.1, Pune on 9th December 1981 V Net amount of enhancement 2,20,82,64700 VI Interest on total compensation
7 from the date of possession to date of payment of compensation @ 4% per annum under Section 34 of L.A. Act is to be paid by Government to the Claimant
13. Eventually by a Judgment dated 14.03.1990, the Reference
Court, (i) enhanced the compensation for the acquired part of the
land to Rs.55,893.23; and (ii) fixed an amount of Rs.80,09,725 as
compensation on account of severance and injurious affection.
14. Aggrieved by such enhancement and fixation, the State of
Maharashtra filed an appeal in First Appeal No.653 of 1991. Not
satisfied with the quantum fixed, the appellant also filed an appeal
in First Appeal No.709 of 1991. Both the appeals were disposed of
by a Division Bench of the Bombay High Court by a Judgment
dated 19.11.2008. By this Judgment the High Court awarded:
(i) a compensation of Rs.20,62,006/ towards severance (unacquired trolley line) payable with solatium at 30% working out to Rs.6,18,601.80, thus totaling to Rs.26,80,607.80;
(ii) a compensation of Rs.7,39,280/ for injurious affection, payable together with solatium at 30% working out to
8 Rs.2,21,784/, thus, totaling to Rs.9,61,064/; and
(iii) a compensation of Rs.1,23,231.25 towards acquired trolley line together with solatium at 30% working out to Rs.36,969.37, thus, totaling to Rs.1,60,200.62. The High Court also held that the claimant company (appellant) will be entitled to interest under Section 28 as well as 34, on the entire amount of compensation as well as solatium from March1976 till the date of deposit.
15. It is against the aforesaid Judgment dated 19.11.2008 passed
in First appeal Nos.653 and 709 of 1991 that the claimant
(landowner) has come up with the above appeals. The State does
not appear to have filed any appeal.
16. As observed by the High Court, the award of the Reference
Court was in two parts. The first part dealt with the claim for
compensation on account of severance and injurious affection in
respect of the trolley line running across 28 kms. in the
unacquired portion of the land measuring abut 60.38 hectares.
The second part of the award was in respect of the trolley line
spread over about 7 kms. in the area submerged in water. For a
better understanding of the arithmetic, it will be useful to present in a
9 tabulation, the different heads of claim, the amount claimed by the appellant, the amount
awarded by the Reference Court and the amount to which the compensation was reduced by the
High Court:-
Heads of claim Amount Amount awarded Amount claimed by by Reference granted by appellant Court High Court Severance 1 Land 6,03,800 1,50,950 1,50,950 2 Diminution in 8,64,000 Nil Nil value 3 Embankments, 18,85,200 20,16,019 19,11,056 C.D. Works etc. 4 Trees 27,000 Nil Nil Injurious Affection 1 Rails Sleepers etc. 48,45,000 31,21,816 6,08,942 2 Telephone Line 16,000 Nil Nil 3 Rolling stocks 22,17,600 17,79,884 Nil 4 Increase in 80,07,180 8,00,718 Nil transportation costs 5 Remodelling of 4,72,100 1,30,338 1,30,338 Bhigwan Yard 6 Loss of earnings 35,62,000 Nil Nil (profits) 7 Retrenchment 1,00,000 10,000 Nil compensation
17. As could be seen from the above tabulation, the appellant
suffered a huge set back before the High Court, mainly under three
heads of claims, which relate to severance and injurious affection
in respect of the trolley line running in the unacquired portion of
land. These three items are (i) rails and sleepers; (ii) rolling stocks;
10 and (iii) increase in transportation cost. At the cost of repetition,
we will once again present in a tabulation, the amount claimed by
the appellant, the amount awarded by the Reference Court and the
amount to which the award was reduced by the High Court under
these three heads, so that we have a better focus.
Heads Amount claimed Awarded by Awarded by Reference High Court Court Rails & 48,45,000 31,21,816 6,08,942 Sleepers Rolling Stocks 22,17,600 17,79,884 Nil Increase in 80,07,180 8,00,718 Nil transportation cost Total 1,50,69,780 5,702,418 6,08,942
18. Insofar as rails and sleepers which became obsolete are
concerned, the claim of the appellant was that they could not be
sold as such, in view of the fact that the railways had switched
over to broad gauge. Though the appellant had to spend huge
money for the removal of the rails and sleepers, they had to be sold
only as scrap. According to the appellant, the Government turned
down the proposal for a new line and hence they were entitled to
be compensated to the extent of the value of the rails and sleepers
11 which became obsolete.
19. The Reference Court found as a matter of fact that the entire
track had become completely useless and that the rails and
sleepers had to be sold only as scrap. Though the appellant
examined a qualified valuer by name Shri Talim, as a witness to
show the loss sustained by them, the Reference Court could not go
entirely by his evidence, as he admitted to have no personal
knowledge, but went by the information supplied by the appellant.
The Reference Court found that the trolley line was laid in the year
1946 and the valuation was made as of the year 1976. The
Reference Court, therefore, applied depreciation @ 35% and arrived
at the figure of Rs.31,21,816.
20. The High Court set aside the compensation awarded in
respect of the rails and sleepers in the unacquired portion of the
land, but confirmed the compensation for the acquired portion of
the land on the ground that the appellant did not take effective
steps to lay an alternative trolley line. The High Court disbelieved
12 the case set up by the appellant that the Government was not
responsive to their demand for invocation of the urgency clause to
acquire the land needed for alternative trolley line. The High Court
found, from the balance sheets that the appellant had not suffered
any loss on account of being compelled to switch over to road
transportation.
21. Insofar as rolling stock is concerned, the Reference Court
accepted the evidence of Mr. Kamat, a qualified valuer examined as
PW13. The Reference Court took the life of locomotives to be 20
years and the life of wagons to be 35 years, on the basis of the
guidelines issued by National Council of Applied Economic
Research. After accepting the evidence of PW13 that the estimated
cost of the rolling stock would be Rs.48,49,618/, the Reference
Court applied an arithmetical formula with reference to the
residual life and the total life of the locomotives and three wagons
and arrived at the depreciated value as Rs.22,36,424.70. From
this amount the Reference Court deducted the scrap value and
arrived at the compensation of Rs.17,79,884/.
13
22. However, the High Court rejected the report of Mr. Kamat
(PW13), on the ground that he started valuation only after the
year 1983 and that his valuation was based on 1986 prices. The
High Court also found that the appellant continued to use the
rolling stocks for the trolley line to a length of 14 kms. till the year
1983 and that, therefore, the appellant was not entitled to any
compensation on this count.
23. As regards “increase in transportation cost”, the Reference
Court found:
(i) that the appellant was forced to discontinue the most convenient and economical mode of transport;
(ii) that even if the appellant had resorted to an alternative route for the trolley line, the same would have been longer by 12 kms, warranting an expenditure of Rs.1.50 crores;
(iii) that the Government could not have invoked the urgency clause, for acquiring land for alternative trolley line, as the acquisition could not have been considered as one for public purpose but rather for the benefit of a company.
(iv) that the appellant was able to prove through credible
14 evidence that the cost of transporting 35,000 tones of goods p.a. increased from Rs.0.20 per km. to Rs.0.80 per km.
(v) that, therefore, the appellant should be compensated for the increase in transportation cost.
24. The Reference Court agreed with the appellant that the loss of
earnings for the appellant, in this regard, was Rs.80,07,180/, but
awarded compensation only for one year as against the claim of the
appellant for a period of 10 years. The Reference Court awarded a
sum of Rs.8,00,718/.
25. The High Court set aside the amount awarded by the
Reference Court under this head on the ground that the appellant
did not suffer any loss of profit on account of the increase in the
transportation cost, as the same would have been passed on to the
customers. The High Court observed that the balance sheets for
the period 197278 did not show any loss. The High Court went by
the presumption that transportation cost is always factored into
the manufacturing cost of the goods.
26. In the light of the manner in which the High Court interfered
15 with the award of the Reference Court, it was contended by Mr.
Gopal Sankaranarayanan, learned senior counsel for the appellant:
(i) that the appellant cannot be blamed for not finding an alternative route to lay the trolley line and for not insisting on the Government to invoke the urgency clause for the acquisition of some other land for laying trolley line, as the provisions of Section 17 could not have been invoked for the benefit of a company;
(ii) that in any case an alternative trolley line would have admittedly cost Rs.1.50 cores and the same would have been 12 kms. longer than the existing line, resulting in an increase in the operational cost;
(iii) that the appellant was able to prove by cogent evidence that the cost of transportation by road was higher;
(iv) that the High Court failed to note that the profit of the appellant went down from Rs.96.07 lakhs in 197576 to Rs.40.80 lakhs in 197677;
(v) that there was neither any pleading nor evidence to show that the transportation cost was passed on to the customers;
(vi) that the High Court failed to note that the acquisition of land on which a trolley line to a distance of 6 kms.
passed, led to the investment on 28 kms. of trolley line
16 in the unacquired portion being rendered useless;
(vii) that about 3 diesel locomotives and over 100 wagons were rendered useless due to the acquisition;
(viii) that the High Court misread the evidence of PW13 as though he took the price as of the year 1986;
(ix) that despite best efforts, the appellant could sell only some of the locomotives, on account of there being no market for them; and
(x) that, therefore, the High Court was completely in error in rejecting the claim of the appellant and also reducing the amount awarded by the Reference Court.
27. In response, it is contended by Mr. Deepak Nargolkar, that
the appellant set up a bogey of a claim about the trolley line in the
unacquired portion of land becoming redundant and that having
admittedly switched over to road transportation way back in
September 1972, the appellant was not entitled to claim any
compensation for the purported increase in transportation cost.
Placing reliance upon the decision of this Court in Wazir vs. State
of Haryana1, it was contended by Mr. Deepak Nargolkar that the
1 (2019) 13 SCC 101
17 additional component of compensation in terms of clause “thirdly”
under Section 23(1) of the Act is to be granted only when the value
of the left over land is effectively diminished in terms of quality.
Therefore, it is his contention that severance charges in cases of
this nature cannot be allowed.
28. We have carefully considered the rival contentions. As the
dispute now stands confined only to three heads of claims, namely,
(i) rails and sleepers; (ii) rolling stocks; and (iii) increase in
transportation cost, we shall deal with them itemwise.
Law on compensation for severance and injurious affection
29. Before we consider the aforesaid three heads of claim item
wise, it may be useful to take note of the legal principles on the
basis of which these claims are to be tested.
30. Sections 23 and 24 of The Land Acquisition Act, 1894 provide
two lists of matters respectively, namely (i) matters to be
considered in determining compensation; and (ii) matters to be
neglected in determining compensation. Section 23(1), which alone
is relevant for our present purposes, is extracted as follows:
18 “23. Matters to be considered in determining compensation (1) In determining the amount of compensation to be awarded for land acquired under this Act, the Court shall take into consideration
first, the marketvalue of the land at the date of the publication of the notification under section 4, subsection (1);
secondly the damage sustained , by the person interested, by reason of the taking of any standing crops trees which may be on the land at the time of the Collector's taking possession thereof; thirdly, the damage (if any) sustained by the person interested, at the time of the Collector's taking possession of the land, by reason of severing such land from his other land; fourthly, the damage (if any) sustained by the person interested, at the time of the Collector's taking possession of the land, by reason of the acquisition injuriously affecting his other property, movable or immovable, in any other manner, or his earnings; fifthly, in consequence of the acquisition of the land
19 by the Collector, the person interested is compelled to change his residence or place of business, the reasonable expenses (if any) incidental to such change; and sixthly, the damage (if any) bona fide resulting from diminution of the profits of the land between the time of the publication of the declaration under section 6 and the time of the Collector's taking possession of the land.”
31. In simple terms, the six items covered by Section 23(1), which
are to be taken into consideration by the court in determining
compensation, can be summarised as follows:
(i) The market value of the land on the date of publication of notification under Section 4(1);
(ii) The damage to standing crops or trees, which are on the land at the time of the Collector taking possession;
(iii) The damage sustained by reason of severing such land from the unacquired land;
(iv) The damage sustained by reason of the acquisition injuriously affecting the other property, movable or immovable, in any other manner or the earnings, of the person interested;
20
(v) The reasonable expenses incurred by the person interested, in changing his residence or place of business, when he is compelled to do so in consequence of the acquisition;
(vi) The damage bona fide resulting from diminution of the profits of the land between the time of publication of the declaration under Section 6 and the time of the Collector’s taking possession.
32. The points arising for determination in these appeals revolve
around clauses “thirdly” and “fourthly” of Section 23(1). These
clauses are referred to in common parlance as clauses concerning
‘severance’ and ‘injurious affection’ respectively.
33. But clauses “thirdly” and “fourthly” of Section 23(1) cannot be
considered in isolation. They have to be read together with Section
49 which reads as follows: “49. Acquisition of part of house or building.
(1) The provisions of this Act shall not be put in force for the purpose of acquiring a part only of any house, manufactory or other building, if the owner desire that the whole of such house, manufactory or building shall be so acquired:
Provided that the owner may, at any time before the Collector has made his award under section 11, by no tice in writing, withdraw or modify his expressed de sire that the whole of such house, manufactory or building shall be so acquired:
21 Provided also that, if any question shall arise as to whether any land proposed to be taken under this Act does or does not form part of a house, manufactory or building within the meaning of this section, the Collec tor shall refer the determination of such question to the Court and shall not take possession of such land until after the question has been determined. In deciding on such a reference the Court shall have regard to the question whether the land proposed to be taken is reasonably required for the full and unim paired use of the house, manufactory or building. (2) if, in the case of any claim under section 23, sub section (1), thirdly, by a person interested, on account of the severing of the land to be acquired from his other land, the appropriate Government is of opinion that the claim is unreasonable or excessive, it may, at any time before the Collector has made his award, or der the acquisition of the whole of the land of which the land first sought to be acquired forms a part. (3) In the case last hereinbefore provided for, no fresh declaration or other proceedings under sections 6 to 10, both inclusive, shall be necessary; but the Collec tor shall without delay furnish a copy of the order of the appropriate Government to the person interested, and shall thereafter proceed to make his award under section 11.”
34. It may be noted that clause thirdly of Section 23(1) relates
only to land, as it speaks only about the severance of the acquired
land from the unacquired land and the damage sustained as a
consequence. In contrast, clause fourthly of Section 23(1) deals
with the damage sustained by the person interested, due to the
injurious affection, (i) of his other movable property; (ii) of his other
22 immovable property; and (iii) of his earnings. In other words what
is injuriously affected at the time of Collector’s taking possession of
the land, may either be the unacquired portion of the immovable
property or other movable property or even the earnings of the
person interested.
35. It may also be noted that the expression used in clause
fourthly is “earnings”, while the expression used in clause sixthly
is “profits”. But clause sixthly is confined only to diminution of the
profits of the land between the time of publication of the
declaration under Section 6 and the time of the Collector taking
possession.
36. Coming to Section 49, it deals with two contingencies. They
are, (i) cases where what is sought to be acquired is only a part of
any house, manufactory or other building; and (ii) cases where a
claim for compensation under the head ‘severance’ under clause
thirdly of Section 23(1) arises.
37. In so far as the 1st contingency is concerned there is a bar
under subsection(1) of Section 49 for the acquisition of a part only
23 of any house, manufactory or other building, if the owner desires
that the whole of such house, manufactory or building shall be so
acquired.
38. In so far as the 2nd contingency is concerned, there is a choice
given to the appropriate Government to order the acquisition of the
whole of the land, if the appropriate Government is of the opinion
that the claim for severance compensation is unreasonable or
excessive.
39. The distinction between the scope of subsection (1) and the
scope of subsection (2) of Section 49 was brought out by this
Court in M/s Harsook Das Bal Kishan Das vs. The First Land
Acquisition Collector and Others2 as follows:
“12. The object of Section 49(1) of the Act is to give to the owner the option whether he would like part to be acquired. The Government cannot take the other part under Section 49(1) of the Act unless the owner says so. Section 49(2) of the Act has nothing to do with Section 49(1) of the Act. Section 49(2) of the Act gives the option to the Government only where the claim under the third clause of Section 23(1) of the Act is excessive. Reference to the third clause of Section 23(1) of the Act makes it clear that the claim under the third clause of Section 23(1) is for severance. The Government in such a case of acquisition of the remaining portion of the land under Section 49(2) of 2 (1975) 2 SCC 256
24 the Act saves the public exchequer money which otherwise will be the subjectmatter of a claim for severance.”
40. In the case on hand, the provisions of Section 49(1) have no
application. This is due to the fact that the appellant never desired
that the whole of the manufactory shall be acquired by the
Government. In fact, the total extent of land owned by the
appellant was about 16000 acres, on which a township had come
up. Therefore, there was no occasion for the appellant to exercise
any option invoking Section 49(1). In any case, the appellant
actually requested the Government to acquire land from other
people, to divert the trolley line. Therefore, Section 49(1) has no
application to the case on hand.
41. Section 49(2) also may not have any application for the reason
that the appropriate Government did not think fit to seek
acquisition of the whole of the land on which the remaining portion
of the trolley line existed, on the ground that the claim for
severance compensation was unreasonable or excessive.
Therefore, it is enough for us to go back to clauses thirdly and
25 fourthly of Section 23(1) without the constraints of subsection (1)
or (2) of Section 49.
42. As we have indicated earlier, clause thirdly relates to the
damage sustained by the person interested, by reason of severance
of the acquired land from the unacquired land, at the time of
Collector’s taking possession of the land. In contrast, clause
fourthly of Section 23(1) deals with the damage sustained by
reason of the acquisition injuriously affecting, (i) the other
movable property; (ii) the other immovable property; and/or
(iii) the earnings of the person interested.
43. The claim of the appellant before the Reference Court under
clauses thirdly and fourthly of Section 23(1), presented a mixup,
with some items overlapping with others. This can be seen from
paragraph 22 of the award of the Reference Court, where the claim
of the appellant is extracted by the Reference Court as follows:
“22. The main grievance of the Claimant Company is that the Special Land Acquisition Officer has not considered at all the Claimant’ claim for damages suffered by the Claimant Company on account of severance and injurious affection. Although the opponent has acquired only 6 kilometers, i.e., about
26 20.74 Hectares of land under the trolley line, this acquisition has rendered the remaining portion of about 30 Kilometers, i.e., 60.38 Hectares of the land under the trolley line totally useless. In other words, the contention of the Claimant Company is that the acquisition of only 6 kilometers has not only deprived the Claimant Company of the use of the trolley line facility, but it has also rendered the remaining portion of the trolley line of 30 kilometers, i.e. 60.38 hectares of land, the rolling stock, three diesel engines, buildings, telephone line and all other items connected with the trolley line, such as, civil works, embankments, C.D. works, culverts, bridges, totally redundant and obsolete. The claim can be divided into two categories as follows:
i) Enhancement of compensation in respect of the acquired portion of the land; and
ii) The compensation for the damages suffered by the Claimant Company in respect of the unac quired portion of the trolley line on account of severance and injurious affection under the fol lowing head:
1) Unacquired portion of the land admeasur ing about 60.38 hectars.
2) The entire railway track of 36 kilometers comprising of rails, sleepers, girders, etc.
3) Rolling stocks, various types of wagons, tankers etc.
4) Diesel Engines three;
5) Telephone line and telephone poles, trees, wells, etc. Embankments, C.D. works, Bridges, Culverts building, nonoperation of nearly 30 kilometers; Diminution in the value of Walchandnagar Township, due to discontinu ance of the trolley line facility which was hith erto available to the said Industrial Complex, the Additional cost of transport for switching over from trolley line transport to road transport, the cost of remodeling the yard at Bhigwan Station in order to suit the transshipment of loading
27 and unloading by road transport; total retrench ment compensation for about 52 persons, spe cially trained and employed for the operation of trolley line, who had come to be absorbed by the Claimant Company on humanitarian grounds and loss of earnings.”
44. The second category of claim indicated in paragraph 22 of the
award of the Reference Court, extracted above, contains a mix of
claims that may fall under clauses thirdly, fourthly and sixthly of
section 23(1). But fortunately the rejection of some of those claims
are not taken up now by the appellant. In the appeals on hand, the
claim is restricted only to three items namely, (i) the value of rails
and sleepers; (ii) the value of rolling stock; and (iii) increase in
transportation costs. These items are covered only by clause
fourthly of Section 23(1) and they do not fall under clause thirdly.
45. Even within clause fourthly, what we are concerned in these
appeals is the injurious affection of, (i) movable property such as
rails and sleepers and rolling stock; and (ii) the loss of earnings
due to increase in transportation costs. But unfortunately what the
appellant did was to claim a sum of Rs.80,07,180/ towards in
crease in transportation costs and a separate amount of
28 Rs.35,62,000/ towards loss of earnings. Even under the heading
‘loss of earnings’, what was claimed was actually loss of profits.
The appellant did not realize that the diminution of profits fell un
der clause sixthly of Section 23(1) and the claim under this head is
restricted to the time between the date of publication of the decla
ration under Section 6 and the time of Collector taking possession.
Injurious affection to earnings is covered by clause fourthly and the
statute has made a distinction between, (i) injurious affec
tion to earnings; and (ii) diminution of the profits between the time
of publication of the declaration under Section 6 and the time of
taking possession.
46. The Reference Court rejected the claim for compensation of
Rs.35,62,000/ towards loss of earnings, on the ground that it
overlapped with the claim under the heading ‘increase in trans
portation costs’. It is perhaps after realizing such overlapping of
claim that the appellant has confined their claim in the present ap
peals only to injurious affection, (i) to rails and sleepers; (ii) to
29 rolling stock; and (iii) to earnings due to increase in transportation
costs, all of which fall under clause fourthly of Section 23(1).
47. One of the earliest cases to be decided on the question of inju
rious affection, was a Division Bench decision of the Calcutta High
Court in R.H. Wernickle and Ors. vs. The Secretary of the
State for India3 . The said case arose out of the acquisition of
land which included a tea estate. The purpose of the acquisition
was the extension of the rifle range of the Cantonment in the Vil
lages of Lebong and Pandan at Darjeeling. A claim for injurious af
fection was made by the owners of the tea estate on the ground
that they were forced to stop work in the unacquired portion of the
tea estate, during the time when firing was practiced in the rifle
range. Dealing with the claim, Doss, J. opined, “There can be no
doubt that it is extremely unsafe to work on land situate behind the
butts when firing is going on, and the consequent loss of time must
inevitably increase the cost of cultivation”. Therefore, Doss, J., held
that the owners of the tea estate were entitled to compensation for
the injurious affection of the 8 acres of tea land behind the butts.
3 2 Ind.Cas 562
30 Expressing concurrence with the view of Doss, J., Richardson, J.
observed: “ It is said that the rifle range will interfere with the work
ing of 8 acres of land behind the butts and I think that there can be
no doubt as to this. It will not be safe to put coolies on the land
when the range is being used”. An argument was advanced by the
Government that the contemplated injury was contingent and that
it could arise only from the negligent use of the range and that the
same would fall under the category of actionable nuisance. Reject
ing the said argument, Richardson, J., opined: “But it is not clear
that the injury which the claimants contemplate will amount to an
actionable nuisance. The Government will have the right to use the
land as a rifle range and no doubt it may be presumed that it will be
so used with the greatest care and circumspection. But even so, no
prudent owner would put his coolies on the land behind the butts
while firing was going on”.
48. In Balammal vs. State of Madras4, this Court was
concerned with a land acquisition under the provisions of the
4 AIR 1968 SC 1425
31 Madras City Improvement Trust Act, Section 71 of which
authorized the Board of Trustees to acquire land under the
provisions of The Land Acquisition Act, 1894 with the previous
sanction of the Government. When the dispute relating to
determination of compensation ultimately landed up before this
Court, the argument of one of the land owners was that a part of
the compound of a cinema theatre was acquired compulsorily and
that it deprived the owner of the land, of the facility of providing
additional amenities to the patrons of the theatre and also of
making constructions on the land expanding the business. The
claim was pitched in the alternative on clauses thirdly, fourthly
and sixthly of Section 23(1). While agreeing on principle about the
entitlement of a person interested to compensation under these
clauses, this Court rejected the claim in that case, on the ground
that there was no evidence either to show any loss by reason of
severance or to show that the remaining land was injuriously
affected by reason of acquisition or to show that the earnings of the
owners were affected.
32
49. Therefore, keeping in mind the above legal principles, let us
now take up for consideration, the claim of the appellant in these
appeals.
Rails and Sleepers
50. It was the claim of the appellant that Walchandnagar
Township is situate at a distance of 36 kms. from Bhigwan Railway
Station on the Central Railway line and that with a view to provide
a direct and rapid connection from Walchandnagar to Bhigwan, the
appellant had provided its own trolley line with a private telephone
line, goods yard with transshipment siding and other facilities. The
trolley line was laid in the year 1946. According to the appellant,
35,000 tonnes of material used to get transported through this
trolley line which included heavy machinery. Part of the trolley line
got submerged in the backwaters of Ujjani Dam and the remaining
portion of the trolley line situate in the unacquired part of the land
had become useless. According to the appellant, they had to spend
Rs.1,90,000/ for the removal and transport of the material
relating to trolley line. The proposal for acquisition of alternative
33 land to lay a new trolley line did not materialize due to various
problems, not attributable to the appellant. In any case, the cost
of such acquisition was estimated at Rs.1.5 crores even at that
time. The rails and sleepers forming part of the trolley line to a
length of 28 kms. had thus become useless. Therefore, the
appellant claimed a sum of Rs.50,08,328/ towards compensation
for rails and sleepers.
51. This claim was resisted by the respondents on the ground
that the trolley line was laid in the year 1946 for the purpose of
carrying material from the sugar industry and that the appellant
started manufacturing heavy machinery only from 1956. The
trolley line was actually a narrow gauge line, having a width of
2 feet 6 inches. Therefore, the respondents contended that no
compensation was payable towards rails and sleepers, especially
when the appellant had also claimed compensation towards
increase in transportation costs for switching over from rail
transport to road transport.
52. Before the Reference Court, the Chief Administrative Manager
34 of the appellant, who was a qualified Civil Engineer was examined
as PW1, and a retired Director of Town Planning was examined as
PW15. Both these witnesses referred to the quotations given by
Hindustan Steels Limited, towards estimated cost of laying the
trolley line. After allowing depreciation and the value for which the
material was sold and after adjusting transportation cost, these
witnesses estimated the cost of rails and sleepers at
Rs.50,08,288/.
53. Though the respondents examined one Shri Mahajan, who
also produced independent calculations, the Reference Court
rejected his evidence on the ground that it did not inspire
confidence. Interestingly the Reference Court did two things,
namely, (i) it agreed that the method or formula adopted by
Shri Mahajan was proper and recognized by the standard authors
and yet rejected his evidence; and (ii) it agreed with the
submissions of the Government Pleader as to why the evidence of
Shri Talim, retired Director of Town Planning should not be relied
upon, but eventually held that the evidence of Shri Talim cannot
35 be discarded totally. Thereafter, the Reference Court proceeded to
take the estimated cost of rails and sleepers at Rs.2,41,053/
per km., and applied a depreciation of 35% and arrived at the
depreciated value at Rs.1,56,650/ per km. Applying this rate for
the trolley line of a distance of 35 kms. and after deducting the
actual scrap value received by the appellant, the Reference Court
arrived at the compensation for rails and sleepers at
Rs.31,21,816/.
54. Both the appellant as well as the State Government were
aggrieved by the compensation so fixed by the Reference Court and
both of them were on appeal before the High Court. The High Court
held that the appellant was not entitled to any compensation for
rails and sleepers lying in the trolley line for a distance of 28 kms.,
since the appellant was at fault for not taking effective steps to lay
alternative trolley line to a distance of 6 to 7 kms. which got
submerged in the backwaters. The High Court held that in any
case, the appellant did not suffer any loss, as was evident from the
balance sheets placed on record upto the year 1978. The finding
36 recorded by the High Court in this regard may be usefully
extracted as follows:
“In our opinion, the company cannot be granted compensation for rails and sleepers covering 28 kms. of the trolley line. In the earlier part of this judgment we have held that the company was at fault in not taking due steps to lay the alternative trolley line for 6 to 7 kms. area submerged in the backwater. It gave up this proposal by its own choice and the reasons put forward before the Reference Court were false and fabricated. Even otherwise the company did not suffer any loss after the trolley line was discontinued in 1976, as was evident from the balance–sheets placed on record upto the year 1978. The increase in transport cost i.e. road transportation by trucks was offset by increasing the manufacturing cost which is so obvious from the fact that the company did not incur any losses after it resorted to road transportation. The company could not have prayed for injurious affection on account of discontinuation of the trolley line and claimed compensation for rails and sleepers spread over 28 kms. of the trolley line. We do not find any justification that the company should be allowed to go with this compensation amount and have the double benefit. It would be a premium for its inaction for laying the alternative trolley line.”
55. After rejecting the claim with regard to the rails and sleepers
of the trolley line for a distance of 28 kms., on the basis of the
reasons extracted above, the High Court proceeded to award
compensation for the rails and sleepers in the trolley line to a
distance of 7 kms. which got submerged in the backwaters. This
compensation, payable for the rails and sleepers in the trolley line
37 to a distance of 7 kms. which got submerged in the backwaters,
was worked out, by accepting the depreciated cost fixed by the
Reference Court at Rs.1,56,650/ per km. For a distance of 7 kms.,
it worked out to Rs.10,96,550/. From this amount the High Court
deducted the scrap value of Rs.4,87,608/ and arrived at the
compensation payable under this heading at Rs.6,08,942/
56. But as rightly contended by Shri Gopal Sankaranarayanan,
learned senior counsel for the appellant, the acquisition of land for
laying alternative trolley line was not an easy task, especially when
there were lot of land owners. The urgency clause under Section 17
of the Land Acquisition Act could not have been invoked, as the
appellant is a company.
57. The fundamental flaw in the reasoning of the High Court is
that the High Court presumed that it was enough if the land for
relocating 7 kms. of trolley line was acquired. If trolley line to a
distance of 7 kms., out of a total stretch of 35 kms. admittedly got
submerged in the backwaters, the trolley line relating to the entire
stretch would naturally become redundant. Railway line is not like
38 a roadway. Roads can take deviation easily, but not railway lines.
Therefore, if land had to be acquired for relocating the trolley line,
it should have been for the entire stretch of 35 kms. It is not
possible to retain 28 kms. of trolley line and relocate the remaining
7 kms. stretch alone. Therefore, we are of the considered view that
the High Court committed a gross error in reversing the finding of
the Reference Court under this heading.
Rolling Stocks
58. The claim of the appellant was that due to the entire trolley
line becoming useless, three diesel locomotives, about 100 four
wheeler wagons, few 8 wheeler wagons and a one way bridge
became redundant and that they are entitled to compensation
towards the loss of value/utility of these rolling stocks. The
appellant quantified the claim under this head at Rs.22,16,044/.
59. This claim was resisted by the Government on the ground
that the appellant was put on notice of the proposed acquisition
way back in 1967 and that after showing inclination to lay an
alternative trolley line at the initial stages, the appellant
39 abandoned the proposal in the year 1974 and that, therefore, the
claim for compensation under this head was liable to be rejected.
60. The appellant examined an Industrial Consultant and a
registered valuer by name Shri Kamat, in support of this claim. His
report containing the valuation of the rolling stock was filed as
Exhibit93. This witness testified that before preparing the
estimate, he obtained quotations from one Shahajhan Engineers
and Suyog Electricals.
61. Though the respondents relied upon the evidence of the
Executive Engineer, Mechanical Division, examined as DW5, the
Reference Court rejected his evidence on the ground that it was of
no assistance. This witness had admitted that he never had any
occasion to value any railway wagons or locomotives.
62. In the light of the oral and documentary evidence, the
Reference Court came to the conclusion that the life of the
locomotives can be taken as 20 years and the life of wagons can be
taken as 35 years. Applying depreciation on a straight line
formula, the Reference Court arrived at the depreciated value of
40 rolling stock as Rs.22,36,424.70/. After deducting the scrap
value of Rs.4,56,540/, the Reference Court fixed the
compensation payable for the rolling stock at Rs. 17,79,884.70/.
63. The High Court, on reappreciation of evidence found that the
appellant company did not bring before the Court, the book value
of the rolling stock. But the expert witness Shri Kamat examined
as PW13 admitted during crossexamination that as per the Asset
Register maintained by the appellant relating to the year 1986, the
value of the rolling stock was almost zero. By selling the rolling
stock as scrap, the company had actually earned a sum of
Rs.4,56,540/. Moreover the High Court found from the evidence
on record that within the company premises, the trolley line to a
distance of 14 kms. was in operation till the year 1983. This was a
clear indication that the rolling stock was used at least till the year
1983. Therefore, the High Court reversed the grant of
compensation made by the Reference Court in respect of the rolling
stock.
64. Though it is contended on behalf of the appellant that the
41 evidence of PW13 (Shri Kamat) was misread by the High Court
and that due to good maintenance, the life of the rolling stock had
increased, we do not think that the view taken by the High Court
was completely out of sync with the evidence on record. The High
Court has actually extracted one portion of the evidence of
Shri Kamat (PW13). He has clearly admitted that though he
inspected the Assets Register in 1986 before preparing the report
he did not record in his report, the book value of the asset. He
clearly stated “it is possible that in book value, the assets might
become zero value in the instant case.”
65. Therefore, no exception can be taken to the finding recorded
by the High Court insofar as rolling stock is concerned.
Increase in transportation cost
66. In simple terms, the claim of the appellant was that the cost
of transportation through trolley line was Rs.0.20 per km. per
tonne and that the cost of transportation by road was Rs.0.80 per
km. per tonne. Since a portion of the trolley line got submerged in
the backwaters and as a consequence, the entire stretch of trolley
42 line became unusable, the company had to switch over to road
transport, resulting in an increased cost of Rs.8,00,718/ per year.
Applying a multiplier of 10, the appellant made a claim for
Rs.80,07,180/ under this head.
67. The appellant examined the Chief Administrative Manager as
PW1, the Planning Manager as PW3 and a person working as a
clerk in the transport Section of the company as PW6. The Chief
Accountant of the company was examined as PW7 and a person
who was carrying on road transport business under the name and
style of Purohit Road Lines was examined as PW12.
68. The Reference Court accepted the evidence adduced on the
side of the appellant and came to a conclusion that the appellant
was transporting about 35,000 tonnes of goods per year through
the trolley line at the cost of Rs.0.20 per tonne per km and that the
cost of road transport for the same quantity of material was
Rs.0.80 per km. per tonne. The Reference Court thus arrived at the
increase in the cost of transportation per year at Rs.8,00,718/.
43 However, the Reference Court rejected the claim of the appellant in
this regard for a total period of 10 years, on the ground that there
is no basis for allowing such a claim for a total period of 10 years.
Therefore as against the claim of the appellant for a sum of
Rs.80,07,180/ (increase in cost for 10 years), the Reference Court
awarded only Rs.8,00,718/ (increase in cost for one year only).
69. The High Court reversed the finding of the Reference Court on
the short ground that the appellant had not demonstrated to have
suffered any loss of profits on account of the increase in the
transportation cost and that even the balancesheets for the years
1972 to 1978 did not disclose any loss of profit. Therefore, the High
Court opined that the increase in transportation cost, even if any,
would have been absorbed in the price charged to the customers
and that there was no case for allowing compensation under this
head even for one year, when the appellant had not suffered any
loss of profit. In fact, the appellant had made a claim separately for
a sum of Rs.35,62,000/ towards loss of profits, but the same was
turned down by the Reference Court. Therefore, the High Court
44 held that the Reference Court could not have granted any
compensation under this heading ‘increase in transportation cost’.
70. The objections of the appellant to the finding of the High
Court in this regard are twofold namely, (i) that the profits
actually went down from Rs.96.07 lakhs in 197576 to Rs.40.80
lakhs in 197677; and (ii) that without any evidence on record the
High Court presumed that the increase in transportation cost was
offset and recovered from the buyers of the goods manufactured
by the company.
71. Insofar as the first objection is concerned, we must point out
at the outset that the Notification for acquisition under Section 4
was published in the Government Gazette on 26.10.1972. The
declaration under Section 6 was published in the Government
Gazette on 01.08.1974. Notices under Sections 9(1) and 9(2) were
published in September1974 and Feburary1975. Though the
exact date on which possession was taken is not mentioned by
either of the parties, the appellant has stated in their synopsis that
the Government took possession of the land in 1976.
45
72. The appellant has produced before us the copy of the balance
sheets and profit & loss account for the years 197576 and 1976
77. From these balancesheets and profit & loss accounts, it is
sought to be highlighted that the appellant made a profit of
Rs.96.07 lakhs during the year 197576 and that the profit went
down to Rs.40.83 lakhs during the year 197677.
73. If this claim of the appellant is taken to be true, it would
mean that the appellant suffered a reduction in profit to the tune
of about Rs.55,00,000/in one year immediately after possession of
the land was taken. The balance sheets and profit & loss accounts
produced by the appellant before us are as on 30.09.1976 and
30.09.1977. Even according to the appellant, the reduction in the
profit to the extent of nearly Rs.55,00,000/ was not wholly
attributable to the increase in transportation cost. The appellant
claimed only a sum of Rs.8,00,718/ per year towards increase in
transportation cost. This constitutes only 15% of the total amount
of reduction in profits. It is seen from the profit & loss account for
the year ended 30.09.1977 that the sales turn over itself had come
46 down from Rs.22.09 crores to Rs.18.17 crores. Even the raw
material consumed had come down from 13.47 crores to Rs.9.32
crores. There had also been a substantial down slide in sub
contract and process charges. Therefore, the contention of the
appellant that the profits went down, may be a point in an answer
to the adverse inference drawn by the High Court with regard to
profits. But it cannot be used in support of the appellant’s case
that the increase in the transportation cost accounted at least in
part to a reduced margin of profit.
74. The impact of the increase in transportation cost, upon the
profit margin of a seller of goods, would depend upon the terms
and conditions of the contract. It may also vary from sea transport
to rail transport to road transport to air transport. Though in
shipping contracts there are standard covenants such as FOB
(Free on Board), CIF (Cost, Insurance and Freight) etc., there are
no such standard covenants in rail and road contracts. In any
case, the trolley line of the appellant covered only a distance of 35
kms upto Bhigwan. Delivery of material had to be effected by the
47 appellant to its customers through some method of transport from
Bhigwan. Nothing is on record to show that the goods were always
dispatched to all customers through goods carriage railway line of
the Indian Railways beyond Bhigwan. In the absence of any
evidence to show that the increase in the transportation cost due
to the submerging of a part of the trolley line, had always to be
absorbed only by the appellant, but could not have been passed on
to its customers due to specific terms and conditions of contract,
the Reference Court could not have accepted a claim in this regard.
48
75. Moreover there was a finding of fact in the Award passed on
09.12.1981 which was taken note of by the High Court. The
relevant portion of the Award reads as follows:
“Further as per local enquiry it is told that the Trolley line was constructed years back mainly for bringing heavy machinery at Walchandnagar. After this purpose was served, they were using it for movement of goods for some time. The process of moving the goods on the Trolley line became uneconomical. So they resorted to road and truck traffic which was quick and possibly economical. Thus the whole Trolley line was in disuse being uneconomical on the relevant date i.e. 27972. In these circumstances the claim for severance and injurious affection has been rejected.”
76. Therefore, the decision of the High Court with regard to
the claim for compensation towards increase in transportation
cost appears to be reasonable and hence cannot be interfered
with.
CONCLUSION
77. The upshot of the above discussion is that the refusal of the
High Court to award any compensation for the injurious affection
to one set of movable property, namely, rolling stock cannot be
found fault with, for the reasons stated above. Similarly, the
refusal of the High Court to award any compensation for increase
49 in transportation cost, falling under the category of “injurious
affection to earnings” cannot also be faulted, for the reasons
indicated separately. However, the refusal of the High Court to
grant compensation for the injurious affection sustained by the
appellant to one set of movable property, namely, rails and
sleepers forming the trolley line for a distance of 28 kms., is clearly
unsustainable especially when the grant of compensation for the
injurious affection to rails and sleepers to a stretch of 7 kms.
submerged in the backwaters, has been sustained by the High
Court. In fact, the State has not come up on appeal against the
grant of compensation for the injurious affection to the trolley line
to a distance of 7 kms which got submerged in back waters. That
the remaining portion of the trolley line to a distance of 28 kms has
been rendered useless after the acquisition, is not in dispute.
78. A question may arise as to whether the reasoning given by us
for rejecting the claim for loss of earnings in the form of increase in
transportation costs, will not apply ipso facto to the claim for
compensation for the rails and sleepers also, since the appellant
50 had switched over to road transport in the year 1972 itself. But our
answer would be that clause fourthly of Section 23(1), uses a
significant phrase viz., “injuriously affecting his other
property, movable or immovable, in any other manner, or his
earnings”. Therefore, injurious affection to property, in any other
manner, may stand on a different footing from injurious affection
to earnings. While there is no evidence on record to connect the
drop in the level of profits from 197576 to 197677, with the
increase in transportation costs, there is acceptable evidence to
show that movable property became useless after the acquisition.
Therefore, both stand on different footings.
79. Therefore, the appeals are partly allowed, setting aside that
portion of the findings and conclusions reached by the High Court
in the impugned judgment (para 22), whereby the award of the
Reference Court relating to compensation for injurious affection to
rails and sleepers, was reversed by the High Court. As a
consequence, the award of the Reference Court granting a sum of
Rs.31,21,860/ towards compensation for rails and sleepers shall
51 stand restored. In respect of all other claims, the impugned
judgment is not interfered with.
80. Before parting we are obliged to bring one important fact on
record. It appears that at the time of filing of the First Appeal
before the High Court of Judicature at Bombay, the respondents
deposited on 17.07.1992, the award amount of Rs.2,72,25,680/.
By virtue of an order passed subsequently, the appellant withdrew
the said amount apparently after furnishing bank guarantee. But
by the impugned judgment dated 19.11.2008, the High Court of
Bombay allowed the appeal of the respondents and reduced the
award amount. When the Special Leave Petitions out of which the
present appeals arise, came up for admission, this Court passed
an order dated 16.03.2009 which reads as follows:
“Issue notice.
If the petitioner has furnished any bank guarantee in regard to the amount already drawn, there shall be interim stay of enforcement of the guarantee by the respondent subject to the petitioner extending validity of the bank guarantee till disposal of this matter.”
We hope that the bank guarantee is kept alive as per the above
order of this Court dated 16.03.2009. Now that the judgment of
52 the Bombay High Court is modified by us, the appellant will be
entitled to retain so much of the amount as they would be entitled
to, by virtue of this judgment and the appellant shall pay the
respondents the excess amount, within four weeks. In case the
bank guarantee furnished by the appellant is alive, the Land
Acquisition Officer may prepare fresh calculations and enforce the
bank guarantee only to the extent of disallowed portion. There
will be no order to costs.
…..…………....................J. (Hemant Gupta)
.…..………......................J. (V. Ramasubramanian)
New Delhi February 4, 2022
53
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free