Uttar Haryana Bijli Vitran Nigam Ltd. and Dakshin Haryana Bijli Vitran Nigam Ltd. vs Adani Power (Mundra) Limited and Another
- Neutral2023 INSC 402
Ratio decidendi
The rule this decision rests on
1. The term "Law" as defined in the Power Project Agreement is sufficiently wide to encompass all rules, regulations, orders and notifications issued by governmental instrumentalities, including communications issued by Coal India Limited reflecting decisions of its Board, regardless of whether such communications are published in the official gazette. 2. A communication issued by Coal India Limited, an instrumentality of the Government of India, reflecting a decision taken at its Board meeting to permit inter-plant transfer of coal between power plants owned by the same purchaser, constitutes a "Change in Law" event under the contractual definition, notwithstanding that it is an administrative instruction addressed to subsidiaries rather than a statutory enactment. 3. When a "Change in Law" event affects multiple distribution companies who are not parties to the proceedings, the regulatory commission possesses the jurisdiction and competence to address the issue, and the fact that other distribution companies were not parties does not prevent the decision-maker from deciding whether the event constitutes a change in law. 4. Where a "Change in Law" permits cost-saving outcomes such as reduced railway transportation costs for coal, the benefit of such savings must be calculated and passed on to the affected distribution companies, which may further pass such benefits to consumers.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 2908 OF 2022
UTTAR HARYANA BIJLI VITRAN NIGAM LIMITED AND ANOTHER ...APPELLANT(S) VERSUS ADANI POWER (MUNDRA) LIMITED AND ANOTHER ...RESPONDENT(S)
JUDGMENT
B.R. GAVAI, J.
1. The present appeal challenges the judgment and order
dated 21st December 2021 passed by the Appellate Tribunal
for Electricity (hereinafter referred to as ‘APTEL’), in Appeal
No. 231 of 2021, filed by the appellants herein, thereby
challenging the order dated 8th July 2019, passed by Central
Electricity Regulatory Commission (hereinafter referred to as
‘CERC’) in Petition No. 269/MP/2018. The APTEL has held Signature Not Verified Digitally signed by the communication dated 19th June 2013, issued by Coal Narendra Prasad Date: 2023.04.20 11:59:44 IST Reason: 1 India Limited (for short, “CIL”) not to be a ‘Change in Law’
event.
2. The facts, in brief, giving rise to the present appeal are
as under:
The respondent No.1 – Adani Power (Mundra) Limited
(hereinafter referred to as “AP(M)L”) had set up a generating
station of capacity 4620 MW (Phase I & II – 4 x 330 MW,
Phase III – 2 x 660 MW and Phase IV – 3 x 660 MW) at
Mundra in the State of Gujarat. AP(M)L had entered into
Power Project Agreements (hereinafter referred to as “PPA”)
dated 7th August 2008 with Uttar Haryana Bijli Vitran Nigam
Limited and Dakshin Haryana Bijli Vidyut Nigam Limited
(hereinafter referred to as “Haryana Utilities”), the appellants
herein, for supply of 1424 MW power from Phase IV of the
generating station.
3. CERC, vide its order dated 6th February 2017, allowed
the compensation towards certain ‘Change in Law’ events
claimed by AP(M)L in Petition No. 156/MP/2014. AP(M)L has
submitted that Haryana Utilities were already making
payments in terms of the supplementary invoices raised by
2 AP(M)L. Subsequently, on account of the judgment of this
Court in the case of Energy Watchdog v. Central
Electricity Regulatory Commission and Others1, AP(M)L
filed another petition being Petition No. 97/MP/2017
claiming compensation on account of change in New Coal
Distribution Policy, 2007 (for short, “NCDP 2007”).
Subsequently, certain interim directions were issued by
CERC. Haryana Utilities, thereafter, filed I.A. No. 21 of 2018
in Petition No. 97/MP/2017, stating therein that the
compensation as claimed by AP(M)L was incorrect inasmuch
as AP(M)L had not taken into consideration the benefits
accruing to them on account of Inter Plant Transfer (for
short, “IPT”) permitted under the communication dated 19 th
June 2013 issued by CIL.
4. Per contra, it was claimed by AP(M)L that the Haryana
Utilities unilaterally revised a huge amount from the monthly
bills on the ground of IPT. It was submitted by AP(M)L that
the contention of the Haryana Utilities with regard to IPT has
already been rejected by CERC in its order dated 31 st May
2018.
1 (2017) 14 SCC 80
3
5. In this background, AP(M)L filed Petition No.
269/MP/2018 before CERC claiming the following reliefs:
“(a) Clarify and declare that the findings of this Ld. Commission at paragraph 61 of the Order of the Commission dated 31.05.2018 in Petition No. 97/MP/2017 and IA No. 21 of 2018, are applicable to the Change in Law compensation pertaining to taxes and duties approved under Order dated 06.02.2017 in Petition No. 156/MP/2014 as well; and
(b) Direct the Respondents to pay Rs. 895.41 Crores (Rs. 566.83 Crores related to Domestic Coal Shortfall + Rs. 328.58 Crores related to taxes and duties) unilaterally deducted from the monthly bills/supplementary invoices along with the applicable Late Payment Surcharge.”
6. CERC framed the following issues:
“Issue No.1: Whether the Petition is maintainable under Section 142 of the Act?
Issue No. 2: Whether our finding in respect of IPT coal at Para 61 of the order dated 31.5.2018 in Petition No. 97/MP/2017 is applicable for the compensation payable for various taxes and duties approved as change in law in the order dated 6.2.2017 in Petition No. 156/MP/2014?
Issue No. 3: What should be the treatment of Inter Plant Transfer of Coal, if it is considered as change in law?
4 Issue No. 4: What should be the basis for calculating shortfall of domestic coal?”
7. Insofar as Issue No. 1 is concerned, CERC held the
dispute to be maintainable.
8. Insofar as Issue No. 2 is concerned, CERC held that in
view of its order dated 6th February 2017 in Petition No.
156/MP/2014, the coal supply, under Fuel Supply
Agreement (for short, “FSA”) dated 9th June 2012, to other
plants has to be accounted for the generation and supply of
power to Haryana Utilities from Units 7, 8 and 9 of Mundra
TPP for all commercial purposes. It, therefore, rejected the
contention of Haryana Utilities that it was liable to pay taxes
and duties only for the coal that it has actually consumed
and not for IPT coal.
9. Insofar as Issue No. 3 is concerned, CERC held that the
transfer of coal by AP(M)L under IPT Policy also affects other
generating stations that are consuming IPT coal and other
distribution companies who are also supplied power by the
generating stations that have used IPT coal. Since other
distribution companies were not parties to the proceedings
5 before CERC, it did not find it appropriate to deal with the
issue.
10. Insofar as Issue No. 4 is concerned, CERC, in view of
the judgment of this Court in the case of Energy Watchdog
(supra), held that the quantum of shortfall has to be
calculated taking into consideration the Assured Coal
Quantity (for short, “ACQ”) and the quantity actually
supplied by the coal companies.
11. Being aggrieved thereby, Haryana Utilities filed an
appeal before APTEL.
12. Insofar as Issue No. 4 is concerned, APTEL, vide its
judgment and order dated 21st December 2021, relying on
the judgment of this Court in the case of Energy Watchdog
(supra), held that ‘Change in Law’ compensation needs to be
calculated as ACQ – actual supply.
13. Insofar as the issue with regard to communication
dated 19th June 2013 being ‘Change in Law’ is concerned,
APTEL held the same not to be ‘Change in Law’. Being
aggrieved thereby, the present appeal.
6
14. We have heard Shri Shubham Arya, learned counsel
appearing on behalf of the appellants and Dr. A.M. Singhvi,
learned Senior Counsel appearing on behalf of the
respondents.
15. Shri Arya submitted that, considering the definition of
“Law” given in the PPA, the communication dated 19 th June
2013 would squarely fall under the term “Law”. He
submitted that in any case, CERC had refused to answer the
said issue in the absence of other distributors. It is
submitted that APTEL has grossly erred in holding the same
not to be a ‘Change in Law’ event.
16. Dr. Singhvi, on the other hand, submitted that the
communication dated 19th June 2013 is an inter-
departmental communication and the same cannot be held
to be ‘Change in Law’.
17. When we heard this batch of Electricity appeals, it was
agreed between all the parties that this Court should first
decide Civil Appeal No. 684 of 2021 (Maharashtra State
Electricity Distribution Company Limited v. Adani Power
7 Maharashtra Limited and Others2) [“MSEDCL v. APML
and Others”, for short] and Civil Appeal No. 6927 of 2021
(Maharashtra State Electricity Distribution Company
Limited v. GMR Warora Energy Ltd. and Others)
inasmuch as three of the issues involved in all the appeals in
the batch were common. It was submitted that those two
appeals could be decided by deciding the three common
issues. However, insofar as the other appeals are concerned,
it was submitted that, in addition to the three common
issues, certain additional issues were also involved and it was
agreed that after those two appeals are decided, the other
appeals should be heard for considering these additional
issues.
18. The said three common issues are thus:
(i) Whether ‘Change in Law’ relief on account of NCDP
2013 should be on ‘actuals’ viz. as against 100% of
normative coal requirement assured in terms of
NCDP 2007 OR restricted to trigger levels in NCDP
2 2023 SCC OnLine SC 233
8 2013 viz. 65%, 65%, 67% and 75% of Assured Coal
Quantity (ACQ)?
(ii) Whether for computing ‘Change in Law’ relief, the
operating parameters be considered on ‘actuals’
OR as per technical information submitted in bid?
(iii) Whether ‘Change in Law’ relief compensation is to
be granted from 1st April 2013 (start of Financial
Year) or 31st July 2013 (date of NCDP 2013)?
19. After extensively hearing all the learned counsel for the
parties, vide the judgment and order dated 3 rd March 2023 in
the case of MSEDCL v. APML and Others (supra), this Court
decided those two appeals after considering the aforesaid
three issues.
20. The first issue was answered by this Court, holding that
the ‘Change in Law’ relief for domestic coal shortfall should
be on ‘actuals’ i.e. as against 100% of normative coal
requirement assured in terms of NCDP, 2007. Insofar as the
second issue is concerned, it was held that the Station Heat
Rate (“SHR” for short) and Auxiliary consumption should be
9 considered as per the Regulations or actuals, whichever is
lower. The third issue was answered holding that the Start
date for the ‘Change in Law’ event for the NCDP, 2013 is 1 st
April 2013.
21. As such, Issue No. 4 stands squarely covered by our
judgment dated 3rd March 2023 in the case of MSEDCL v.
APML and Others (supra) so also by the earlier judgment of
this Court in the case of Energy Watchdog (supra).
22. Insofar as Issue Nos. 2 and 3 are concerned, we find
that the said issues are interlinked and the same would
depend on the decision as to whether the communication
dated 19th June 2013 providing for IPT would amount to
‘Change in Law’ or not.
23. It will be relevant to refer to the definition of “Law” as
defined under the PPA, which reads thus:
“Law means, in relation to this Agreement, all taws including Electricity Laws in force in India and any statute, ordinance, regulation, notification or code; rule, or any interpretation of any of them by an Indian Governmental Instrumentality and having force of law and shall further include all applicable rules, regulations, orders, notifications by an Indian Governmental Instrumentality pursuant to or under any of them and shall include all rules,
10 regulations, decisions and orders of the Appropriate Commission.”
24. It can, thus, clearly be seen that the definition of “Law”
is wide enough to include all rules, regulations, orders,
notifications by the Governmental instrumentalities.
25. It will be relevant to refer to the communication dated
19th June 2013, which reads thus:
“Sub: Modification in Model FSA applicable for New Power plants in respect of “Interplant transfer of coal”
A proposal for allowing inter power plant transfer of coal from one Power Plant to another under the modified FSA applicable for New Power Plants (for both PSU/Govt. PUs and Private PUs ) was placed before the 298th CIL Board in its Meeting held on 27.5.13.
The CIL Board while approving to the proposal allowed such dispensation subject to the following conditions which stand as below after legal vetting.
a) Transfer of coal shall be allowed only between the power plants wholly owned by the Purchaser or its wholly owned subsidiary. No transfer of coal shall be allowed for a JV company of the Purchaser.
The supply of coal, shall for all commercial purpose under the FSA remain unchanged and on account of the original Power Plant.
b) Both the Power Plants should have executed FSA in the modified FSA Model applicable
11 for new power plants and not having any supplies linked to coal blocks. In case of IPPs both the plants must have valid long term PPAs with DISCOMS.
c) In no case the transferred quantity to a plant together with the quantity supplied under the applicable FSA shall exceed the ACQ of the Transferee Plant for a particular year which is proportional to the long term PPA with DISCOMS.
d) Transfer of coal will not be allowed to those plants who are allotted coal blocks under this arrangement.
e) In case of change in the ownership and no environmental clearance of the plant this facility shall stand withdrawn, and
f) Penalty/ incentive under this arrangement would be considered in terms of (a) above.
A statement showing the modification in the FSA models applicable for New Power plants (for both PSU/ Govt. PUs and Private PUs) is enclosed.”
26. It can thus be seen that the said communication refers
to the decision of the CIL taken in its meeting held on 27 th
May 2013. A perusal thereof would reveal that the transfer
of coal which was not allowed hitherto, has been allowed only
between the power plants owned by the purchaser or its
wholly owned subsidiary. It further provides that no transfer
of coal shall be allowed for a JV Company of the purchaser.
12 It further provides that the supply of coal shall, for all
commercial purpose under the FSA, remain unchanged and
on account of the original Power Plant. It further provides
that both the Power Plants should have executed FSA in the
modified FSA Model applicable for new power plants and not
having any supplies linked to coal blocks. It further provides
that in case of IPPs, both the plants must have valid long
term PPAs with DISCOMS. It further provides that in no
case the transferred quantity to a plant together with the
quantity supplied under the applicable FSA shall exceed the
ACQ of the Transferee Plant for a particular year which is
proportional to the long term PPA with DISCOMS. It further
provides that transfer of coal will not be allowed to those
plants who are allotted coal blocks under this arrangement.
It further provides that in case of change in the ownership
and no environmental clearance of the plant, this facility
shall stand withdrawn.
27. It could thus be seen that the said communication
reflects the decision of CIL. The CIL is an instrumentality of
the Government of India. As such, we find that APTEL erred
13 in holding the said communication dated 19 th June 2013 not
to amount to ‘Change in Law’.
28. APTEL has held that the said communication is an
administrative instruction addressed to all the subsidiaries.
It will be apposite to refer to the following findings of APTEL:
“109. There is no denial of the fact that the letter dated 19.06.2013 addressed by CIL intimating to all subsidiaries the decision taken at its 298th board meeting (27.05.2013), allowing IPT of coal was conditional upon transfer (of coal) to be allowed only between the power plants wholly owned by the purchaser or its wholly owned subsidiary and supply of coal for all commercial purpose under the FSAs to remain unchanged and on account of original power plant. In particular context of the first respondent, it follows as a sequitur that IPT of coal is allowable if Mundra TPS transfers its portion of linkage coal from MCL coal mine, Talcher to Tiroda TPS (both owned by Adani group) for utilization of such coal at Tiroda TPS and that even though linkage coal from MCL coal mine, Talcher of Mundra TPS (original power plant in terms of the FSA) was actually utilized at Tiroda TPS (transferee plant), it will be accounted as if it were consumed at Mundra TPS. To put it simply, the effect of IPT of coal is that IPT coal cost (linkage domestic coal) will continue to be booked in the account of Mundra TPS (original power plant in terms of the FSA/transferor plant under IPT scheme) and alternate coal cost (imported coal or market-based e-auction coal used in the absence of linkage coal) will continue to be booked on ‘attributed cost’
14 basis in the accounts of Tiroda TPS (transferee plant under IPT scheme).”
29. We find that APTEL has failed to take into consideration
that CERC had not decided the said issue, inasmuch as the
decision on the said issue would have affected the other two
DISCOMS, i.e., MSEDCL and Rajasthan DISCOMS. It will
further be relevant to note that the very same Tribunal,
immediately after three months, in the case of Rattan India
Power Limited v. Maharashtra Electricity Regulatory
Commission and Another3, has taken a totally contrary
view. In the said case, it was sought to be argued on behalf
of MSEDCL that the Evacuation Facility Charge (for short,
“EFC”) imposed by CIL vide its circular dated 19 th December
2017 did not constitute ‘Change in Law’. It will be apposite
to refer to the following observations:
“9. It is incorrect to argue that to be covered as a change in law event under such contractual clauses as quoted earlier, the instrument whereby the law is claimed to have undergone a change must have been published in official gazette to have the force of law. In Energy Watchdog & Ors. (supra), for illustration, even a letter of the Ministry of Power in
3 Appeal Nos. 118 of 2021 and 40 of 2022 dated 22nd March 2022
15 the Government of India was accepted as an instrument having the “force of law”. Similarly, in Kusum Ingots & Alloys v. Union of India (2004) 6 SCC 254 executive instructions without any statutory backing were also considered as “law”.
That Coal India is Government instrumentality and the notifications, circulars, etc. issued by it have a force of law under Regulation 77(3) of the Constitution of India was accepted by this tribunal in GMR Kamalanga Energy Ltd. (supra).”
30. Vide judgment of even date, in Civil Appeal Nos. 5005 of
2022 and 4089 of 2022, we have upheld the concurrent view
of Maharashtra Electricity Regulatory Commission (for short,
“MERC”) and APTEL holding the said EFC to be ‘Change in
Law’.
31. In that view of the matter, we are of the opinion that the
finding of APTEL that the communication dated 19th June
2013 permitting IPT is not a ‘Change in Law’ would not be
sustainable.
32. It is to be noted that, while submitting the bid, AP(M)L
must have factored in the cost of transportation of linkage
coal from MCL Coal Mine, Talcher to its plant at Mundra. As
per the details given in the PPA, the mode of transportation is
through railway. As such, prior to the IPT being permitted,
16 AP(M)L was bound to utilize the linkage coal from MCL Coal
Mine, Talcher, only for the purpose of its original power
plant, i.e., AP(M)L. Only on account of the IPT would it be in
a position to utilize the coal from MCL Coal Mine, Talcher
either for its plant in Maharashtra or in Rajasthan.
Similarly, it will be entitled to utilize the coal linkages for its
plant in Maharashtra or in Rajasthan for production of
energy in its other power plants. As such, there is bound to
be a variance in the cost of transportation by railways. For
example, if the coal is to be transported from MCL Coal Mine,
Talcher to AP(M)L, the cost of railway transportation would
be higher as compared to the cost of railway transportation
from MCL Coal Mine, Talcher to Tiroda TPS. We are only
giving this example as an illustration. We find that the
savings made in the cost of transportation, i.e., the cost
which would have been incurred for transporting the coal
from MCL Coal Mine, Talcher to ‘X’ plant minus the actual
cost of transportation has to be passed on to the DISCOMS,
which, in turn, has to be passed on to the end consumers.
For example, if the cost of transportation per ton from MCL
17 Coal Mine, Talcher to AP(M)L is Rs.100/- and from MCL Coal
Mine, Talcher to Tiroda TPS is Rs.50/- per ton, the benefit of
Rs.50/- per ton will have to be passed on.
33. We, however, find that the changes occurring on
account of permitting IPT would affect AP(M)L as well as the
appellants and two other DISCOMS, i.e., MSEDCL and
Rajasthan DISCOMS. This was also observed by the CERC in
its order dated 8th July 2019. We do not possess any
expertise for working out as to what benefit any of the parties
would be entitled to on account of the said ‘Change in Law’.
However, we are of the considered view that cost of saving in
the railway transportation on account of ‘Change in Law’ in
the light of our observation in the aforesaid paragraph needs
to be worked out and passed on to the appropriate
DISCOMS, which can further be passed on to the consumers.
CERC, which is a body of experts, is best suited to do so.
34. We, therefore, find that the present appeal deserves to
be partly allowed. Though the issue with regard to allowing
‘Change in Law’ compensation on the basis of ACQ – actual
18 supply deserves to be upheld, the issue with regard to IPT
not being ‘Change in Law’ deserves to be set aside.
35. In the result, we partly allow the appeal and pass the
following order:
(i) The finding of the APTEL to the effect that the
communication dated 19th June 2013 providing for
IPT does not amount to ‘Change in Law’ is set
aside;
(ii) We hold that IPT amounts to ‘Change in Law’.
36. In the light of our observations made in paragraphs 32
and 33, the matter is remitted to CERC for working out the
effect of the aforesaid ‘Change in Law’ after giving notice to
MSEDCL as well as Rajasthan DISCOMS and hearing all the
parties including the appellants and the respondents herein.
37. However, since the said issue has been pending since a
long time, we direct CERC to decide the said issue and
calculate the benefits that would be accruable to any of the
parties within a period of six months from today.
38. Pending application(s), if any, shall stand disposed. No
costs.
19 …..….......................J. [B.R. GAVAI]
…….........................J. [VIKRAM NATH]
NEW DELHI;
APRIL 20, 2023.
20
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free